About this file
The document is a detailed pricing response form for Horizontal Directional Drilling (HDD) services issued by Gainesville Regional Utilities (GRU) for a comprehensive infrastructure project in Alachua County, Florida. The solicitation, numbered 2025-103, seeks qualified vendors to perform underground utility installations across water distribution, wastewater collection, gas mains, communication conduits, and electric conduits. The contract term spans from October 1, 2025, to September 30, 2028, with potential renewal options for two additional one-year periods. Key procurement dates include a September 5, 2025 release, September 16, 2025 deadline for questions, and a September 30, 2025, 2:00 pm response deadline.
The pricing response form provides an extensive unit pricing schedule covering various pipe materials and sizes, including ductile iron, high-density polyethylene (HDPE), and polyethylene pipes ranging from 2" to 16" in diameter. The document includes line items for carrier pipes, casing pipes, conduits, and additional services such as premium work hours and mobilization. While no specific set-aside designations are mentioned, the solicitation requires comprehensive insurance coverage, including $2,000,000 in Commercial General Liability, $1,000,000 in Automobile Liability, and statutory Workers' Compensation. Vendors must submit detailed documentation, including business registration, experience modification rate documentation, OSHA forms, contractor references, and a 5% bid bond, reflecting GRU's emphasis on technical capabilities, safety records, and proven experience in complex underground utility installations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Horizontal_Directional_Drilling_(Addendum_#2_Revision).pdf | ||
| Horizontal_Directional_Drilling.pdf | ||
| Pricing_Form_Horizontal_Directional_Drilling_FINAL.xlsx | XLSX spreadsheet | |
| Horizontal_Directional_Drilling_Tech..docx | DOCX document | |
| Contract_Sample_Document.pdf | ||
| 2025_HorizontalDirectionalDrill_TechSpec_final.docx | DOCX document | |
| 2025HDDPricingResponseForm.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Bid Item Bid Item Description Unit Unit Price
| A | Water Distribution | GRU Furnish | Contractor Furnish | |
| Carrier Pipes | ||||
| A.1 | 2" CTS Blue or Purple, DR 9 | LF | ||
| A.2 | 4" DI Pipe | LF | ||
| A.3 | 6" DI Pipe | LF | ||
| A.4 | 8" DI Pipe | LF | ||
| A.6 | 12" DI Pipe | LF | ||
| A.7 | 16'' DI Pipe | LF | ||
| A.8 | 4" HDPE, DR 11 | LF | ||
| A.9 | 6" HDPE, DR 11 | LF | ||
| A.10 | 8" HDPE, DR 11 | LF | ||
| A.11 | 12" HDPE, DR 11 | LF | ||
| A.12 | 16'' HDPE, DR 11 | LF | ||
| Casing Pipes | ||||
| A.13 | 2" PE Tubing Casing, DR 13.5 | LF | ||
| A.14 | 4" PE Tubing Casing, DR 13.5 | LF | ||
| A.15 | 6'' PE Tubing Casing, DR 13.5 | LF | ||
| B | Wastewater Collection - Force Mains | GRU Furnish | Contractor Furnish | |
| B.1 | 2" HDPE (IPS), DR 11 | LF | ||
| B.1 | 4" HDPE, DR 11 | LF | ||
| B.2 | 6" HDPE, DR 11 | LF | ||
| B.3 | 8" HDPE, DR 11 | LF | ||
| B.5 | 12" HDPE, DR 11 | LF | ||
| B.6 | 16'' HDPE, DR 11 | LF | ||
| D | Gas Mains | GRU Furnish | ||
| D.1 | 2" and Smaller HDPE Carrier/Casing | LF | ||
| D.2 | 3" HDPE SDR 17 Carrier/Casing | LF | ||
| D.3 | 4" HDPE SDR 17 Carrier/Casing | LF | ||
| D.4 | 6" HDPE SDR 17 Carrier/Casing | LF | ||
| D.5 | 8" HDPE SDR 17 Carrier/Casing | LF | ||
| D.6 | 10" HDPE SDR 17 Carrier/Casing | LF | ||
| E | Communication Conduits | GRU Furnish | ||
| E.1 | 1.5" HDPE Single Conduit | LF | ||
| E.2 | 2" HDPE Single Conduit | LF | ||
| E.3 | 2.5" HDPE Single Conduit | LF | ||
| E.4 | 3" HDPE Single Conduit | LF | ||
| E.5 | 4" HDPE Single Conduit | LF | ||
| E.6 | 1" PVC Conduit | LF | ||
| E.7 | 1.5" PVC Conduit | LF | ||
| E.8 | 2" PVC Conduit | LF | ||
| E.9 | 2.5" PVC Conduit | LF | ||
| E.10 | 3" PVC Conduit | LF | ||
| E.11 | 4" PVC Conduit | LF | ||
| E.12 | 2" HDPE Parallel Conduits | LF | ||
| E.13 | 2.5" HDPE Parallel Conduits | LF | ||
| E.14 | 3" HDPE Parallel Conduits | LF | ||
| E.15 | 4" HDPE Parallel Conduits | LF | ||
| E.16 | Set 2' x 3' pedestal | EA | ||
| E.17 | Set 2' x 3' pedestal in concrete | EA | ||
| E.18 | Set underground junction box | EA | ||
| E.19 | Set underground junction box in concrete | EA | ||
| E.20 | Set 10" round pedestal | EA | ||
| E.21 | Set 10" round pedestal in concrete | EA | ||
| E.22 | Remove 2' x 3' pedestal | EA | ||
| E.23 | Remove 2' x 3' pedestal set in concrete | EA | ||
| E.24 | Remove underground junction box | EA | ||
| E.25 | Remove underground junction box set in concrete | EA | ||
| E.26 | Remove 10" round pedestal | EA | ||
| E.27 | Remove 10" round pedestal set in concrete | EA | ||
| E.28 | Change out 2' x 3' pedestal | EA | ||
| E.29 | Change out 2' x 3' pedestal set in concrete | EA | ||
| E.30 | Change out underground junction box | EA | ||
| E.31 | Change out underground junction box set in concrete | EA | ||
| E.32 | Change out 10" round pedestal | EA | ||
| E.33 | Change out 10" round pedestal set in concrete | EA | ||
| E.34 | Install Pull String | EA | ||
| E | Electric Conduits | GRU Furnish | ||
| F.1 | 1.5'' HDPE Conduit | LF | ||
| F.2 | 2'' HDPE Conduit | LF | ||
| F.3 | 2.5'' HDPE Conduit | LF | ||
| F.4 | 3'' HDPE Conduit | LF | ||
| F.5 | 4'' HDPE Conduit | LF | ||
| F.6 | 6'' HDPE Conduit | LF | ||
| F.7 | 2" HDPE Parallel Conduits | LF | ||
| F.8 | 2.5" HDPE Parallel Conduits | LF | ||
| F.9 | 3" HDPE Parallel Conduits | LF | ||
| F.10 | 4" HDPE Parallel Conduits | LF | ||
| F | Additional Pricing | Contractor Furnish | ||
| G.1 | Premium Work Hours | Per HR | ||
| G.2 | Mobilization – HDD (<$1,000 Work Order) | LS | ||
| G.3 | Emergency Mobilization | LS | ||
| HDPE Adapters | ||||
| G.4 | 4" HDPE MJ Adapter | EA | ||
| G.5 | 6" HDPE MJ Adapter | EA | ||
| G.6 | 8" HDPE MJ Adapter | EA | ||
| G.7 | 10" HDPE MJ Adapter | EA | ||
| G.8 | 12" HDPE MJ Adapter | EA | ||
| G.9 | 16'' HDPE MJ Adapter | EA | ||
| Fusing of Pipe for Customers per each | ||||
| G.10 | 4'' Pipe | EA | ||
| G.11 | 6'' Pipe | EA | ||
| G.12 | 8'' Pipe | EA | ||
| G.13 | 10'' Pipe | EA | ||
| G.14 | 12'' Pipe | EA | ||
| G.15 | 16'' Pipe | EA | ||
| Hydrostatic and Leakage Testing | ||||
| G.16 | Testing for 2"-4" Pipe | EA | ||
| G.17 | Testing for 6" - 8" Pipe | EA | ||
| G.18 | Testing for 10"-12" Pipe | EA | ||
| G.19 | Testing for 16'' Pipe | EA | ||
| Rock Removal | ||||
| G.20 | Rock Removal for 2"-4" Pipe | LF | ||
| G.21 | Rock Removal for 6" - 8" Pipe | LF | ||
| G.22 | Rock Removal for 10"-12" Pipe | LF | ||
| G.23 | Rock Removal for 16'' Pipe | LF | ||
| Traffic Control | ||||
| G.24 | Furnish Flagman | Per HR | ||
| G.25 | Furnish Single Lane Closure per FDOT Index 603 | LS | ||
| G.26 | Furnish Multilane Closure per FDOT Index 613 | LS |