The file contains Project Special Provisions for the City of Cripple Creek Skate Park Surfacing Project, prepared by the Colorado Department of Transportation. The document outlines detailed specifications for a skate park surfacing renovation, including requirements for pavement removal, excavation, aggregate base course, concrete pavement, construction surveying, and traffic control. The project is set to be completed within 120 working days, with time not being charged during the months of December, January, February, and March. The specifications incorporate standards from CDOT, ASTM F2334-18 for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 for In-Ground Concrete Skateparks.

The project includes several force account items with estimated budgets, such as $50,000 for minor contract revisions, $10,000 for utility adjustments, $10,000 for erosion control, $2,500 for landscaping, and $10,000 for fence repair. The contractor will be responsible for coordinating with utilities, implementing erosion control measures, and maintaining horizontal and vertical site control. Traffic control requirements are strict, with work prohibited between 7 a.m. and 7 p.m., and all construction equipment and materials must be kept out of traffic lanes unless specifically approved. The project emphasizes minimal disruption to existing traffic and requires the contractor to notify the owner at least one week before starting construction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Colorado Department of Transportation Project Special Provisions for

The City of Cripple Creek Skate Park Surfacing Project

The 2023 Standard Specifications for Road and Bridge Construction controls the construction of this project. The following special provisions supplement or modify the Standard Specifications and take precedence over the Standard Specifications and plans.

PROJECT SPECIAL PROVISIONS

Name Date Page Index Pages (Mar. 26, 2025) 1-2 Commencement and Completion of Work (Mar. 26, 2025) 3 Revision of Section 101 Definitions and Terms (Mar. 26, 2025) 4 Revision of Section 102 Project Plans and Other Data (Mar. 26, 2025) 5 Revision of Section 105 Conformity to the Contract of Portland

Cement Concrete Pavement (Mar. 26, 2025)

Revision of Section 106 Control of Materials (Mar. 26, 2025) 7 Revision of Section 202 Removal of Pavement (Mar. 26, 2025) 8 Revision of Section 203 Excavation and Embankment (Mar. 26, 2025) 9 Revision of Section 304 Aggregate Base Course (Mar. 26, 2025) 10 Revision of Section 412 Portland Cement Concrete Pavement (Mar. 26, 2025) 11 Revision of Section 625 Construction Surveying (Mar. 26, 2025) 12 Force Account Items (Mar. 26, 2025) 13 Traffic Control Plan General (Mar. 26, 2025) 14

Project No. MFT M275-001

PCN 25211

Colorado Department of Transportation Standard Special Revisions for The City of Cripple Skate Park

Surfacing Project

STANDARD SPECIAL REVISIONS

Name Date # of Pages Revision of Section 101 Definitions and Section 106 - Control of Materials

(Jan. 8, 2024) 2

Revision of Section 105 Control of Work (Oct. 1, 2023) 1 Revision of Section 105 Dispute Review Board and Claims for Unresolved Disputes

(Oct. 1, 2023) 9

Revision of Section 105 E-Signature (Jan. 8, 2024) 1 Revision of Section 107 Water Quality Control (May 16, 2024) 9 Revision of Section 107 Water Quality Control (Under One Acre of Disturbance)

(Oct. 1, 2023) 9

Revision of Section 208 Erosion Control (Under One Acre of Disturbance)

(Oct. 1, 2023) 38

Revision of Sections 208, 213, and 216 Construction Permit Water Quality

(May 16, 2024) 24

Revision of Section 601 Concrete Acceptance (April 9, 2024) 4

Commencement and Completion of Work (Working or Calendar Day)

The Contractor shall commence work under the Contract on or before the 15th day following Contract execution or the 30th day following the date of award, whichever comes later, unless such time for beginning the work is changed by the Chief Engineer in the "Notice to Proceed." The Contractor shall complete all work within 120 working days per the "Notice to Proceed."

Subsection 108.08 shall include the following:

Time will not be charged during the months of December, January, February or March. This time is defined as free time and work may continue if conditions permit.

Revision of Section 101 Definitions and Terms

Revise Section 101 of the Standard Specifications for this project as follows:

Subsection 101.02 shall replace the following:

City. Shall refer to the City of Cripple Creek located within Teller County in the State of Colorado.

Department. Shall refer to the City of Cripple Creek.

Engineer. Shall refer to the representative assigned by the City of Cripple Creek.

Owner. Shall refer to the City of Cripple Creek.

Project Engineer. Shall refer to the representative assigned by the City of Cripple Creek.

END OF SECTION REVISION

Revision of Section 102 Project Plans and Other Data

Revise Section 102 of the Standard Specifications for this project as follows:

Subsection 102.05 shall include the following:

Supplemental data available to the contractor from the Owner include the following:

i. Horizontal and Vertical Control Documentation

ii. City of Cripple Creek Skate Park Surfacing Project: Geotechnical Evaluation Report

iii. City of Cripple Creek Skate Park Surfacing Project: Feasibility Document

The Owner does not warrant the supplemental data and this information is not considered to be a part of the Contract. Suppose bidders use or modify the supplemental data in preparing a proposal or planning and prosecuting the work. In that case, all associated data is used at their own risk, and bidders are responsible for all conclusions, deductions, and inferences drawn from the original or modified supplemental data.

Revision of Section 105 Conformity to the Contract of Portland Cement Concrete Pavement

Revise Section 105 of the Standard Specifications for this project as follows:

Subsection 105.06 shall include the following:

105.06 Conformity to the Contract of Portland Cement Concrete Pavement. Concrete Pavement shall be in accordance with the requirements of CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

Revision of Section 106 Control of the Materials

Revise Section 106 of the Standard Specifications for this project as follows:

Subsection 106 shall include the following:

106.03 Samples, Tests, Cited Specifications. Concrete Pavement shall be in accordance with the requirements of CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

106.06 Sampling and Testing of Portland Cement Concrete Paving. Concrete Pavement shall be in accordance with the requirements of CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

REVISION OF SECTION 202

REMOVAL OF PAVEMENT

Section 202 of the Standard Specifications is hereby revised for this project to include the following:

DESCRIPTION

This work consists of full-depth saw cutting and removal of concrete and asphalt pavements within the project limits or as directed by the Owner.

CONSTRUCTION REQUIREMENTS

The areas of pavement to be removed shall be saw cut where required by the Owner to mitigate damage to adjacent facilities. Sawing shall be accomplished with the use of a diamond blade saw or approved equivalent. Sawing shall be done to a true line with a vertical face to provide a smooth, clean, and uniform removal line, unless otherwise specified.

The equipment for saw cutting shall have provisions for controlling dust and other particulate matter created by the cutting action. Slurry and residue resulting from diamond saw cutting shall not be allowed to flow across lanes occupied by the traffic or enter the storm system.

After sawing has been completed, the pavement designated to be removed shall be lifted vertically from its position unless otherwise approved by the engineer. Pavement breakers or jackhammers shall be used in the removal process where lifting is not possible. All loose materials shall be removed from the area. Removed concrete pavement shall become the property of the Contractor and shall be disposed of in accordance with subsection 202.07.

METHOD OF MEASUREMENT

Removal of Pavement will be measured by the area in square yards, completed to the required depth and accepted.

BASIS OF PAYMENT

Removal of Pavement will be paid for at the contract unit bid price per square yard. Payment will be considered full compensation for all labor, equipment, tools, water, and incidentals required to diamond saw cut and remove the pavement to the depth, width, grade, and cross slope shown on the plans or as directed by the Owner, debris handling, and disposal of materials.

Payment will be made under:

Pay Item Pay Unit Removal of Pavement Square Yard

Revision of Section 203 Excavation and Embankment

Revise Section 203 of the Standard Specifications for this project as follows:

Subsection 203.01 shall be revised as follows:

203.01 General. This work consists of excavation, hauling, disposal, placement, and compaction of all material encountered within the limits of the work, including the construction of dikes and excavation for ditches and channels necessary for the construction of the roadway per the Contract.

These activities shall be in accordance with the requirements of the CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

Revision of Section 304 Aggregate Base Course

Revise Section 304 of the Standard Specifications for this project as follows:

Subsection 304.02 shall be revised as follows:

304.02 Aggregate. The aggregates shall meet the requirements of subsection 703.03. Acceptance will be based on random samples taken from each lift.

These activities shall be in accordance with the requirements of the CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

Revision of Section 412 Portland Cement Concrete Pavement

Revise Section 412 of the Standard Specifications for this project as follows:

Subsection 412.01 shall be revised as follows:

412.01. This work consists of constructing a pavement composed of Portland Cement Concrete on a prepared subgrade or base course per these specifications and in conformity with the lines, grades, thicknesses, and typical cross sections shown on the plans or established.

Concrete Pavement shall be in accordance with the requirements of CDOT specifications, ASTM F2334-18 Standard Guide for Above Ground Public Use Skatepark Facilities, and ASTM F2480-06 (Reapproved 2012) Standard Guide for In-Ground Concrete Skateparks, and Cripple Creek Skate Park Surfacing Project Geotechnical Investigation unless otherwise authorized in writing by the Owner.

Revision of Section 625 Construction Surveying

Revise Section 625 of the Standard Specifications for this project as follows:

Subsection 625.03 shall add the following:

In the event Bid Alternate 1 is executed, the contractor shall be responsible for establishing and maintaining horizontal and vertical control of the site, to ensure adequate grade control through the duration of the project.

In the event Bid Alternate 1 is not executed, the City of Cripple Creek shall be responsible for establishing and maintaining horizontal and vertical control of the site. The Contractor shall be responsible for maintaining City‐ provided control throughout the duration of the project.

Force Account Items

Description

This special provision contains the Department's estimate for force account items included in the Contract. The estimated amounts marked with an asterisk will be added to the total bid to determine the amount of the performance and payment bonds. Force Account work shall be performed as directed by the Engineer.

Basis of Payment

Payment will be made in accordance with subsection 109.04. Payment will constitute full compensation for all work necessary to complete the item.

Force account work valued at $5,000 or less, that must be performed by a licensed journeyman in order to comply with federal, state, or local codes, may be paid for after receipt of an itemized statement endorsed by the Contractor.

Force Account Item Estimated Quantity Amount

F/A Minor Contract Revisions F.A. $ 50,000*

F/A Adjust Utilities F.A. $ 10,000*

F/A Erosion Control F.A. $ 10,000*

F/A Landscaping F.A. $ 2,500*

F/A Fence Repair F.A. $10,000*

Descriptions:

F/A Minor Contract Revisions – Consists of minor work authorized and approved by the owner, which is not included in the contract plans or specifications and is necessary to accomplish the scope of work of this contract.

F/A Erosion Control – Erosion control measures implemented by the Contractors Erosion Control Supervisor, in accordance with all erosion control and water quality requirements required by the City permitting process and sections 107 and 208 of CDOT specifications. All items and efforts shall be approved by the owner prior to installation, or they will be charged at no cost to the project.

F/A Utilities – Subsurface Utility Engineering (SUE) has not been provided for this project; the contractor shall be responsible for locating and coordinating with all adjacent and impacted utilities prior to construction. This force account is intended to address minor utility adjustments and potholes approved by the owner to mitigate utility conflicts not included in the contract plans or specifications, which are necessary to accomplish the scope of work of this contract. Coordination and locating efforts shall be incidental to the work and will not be measured or paid for separately.

F/A Landscape Restoration – Consists of efforts associated with clearing and grubbing in accordance with section 201 and landscape restoration in accordance with section 212 of CDOT specifications. It is anticipated that trees may require trimming, and minor landscaping will require restoration following the contractor's access to the site. The owner shall authorize and approve all efforts associated with this force account prior to construction; non-authorized work will be at no cost to the project.

F/A Fence Repair – Costists of repairs to the existing perimeter 120-inch chain link fence as directed by the City. Anticipated efforts include removal, resetting, and replacement in accordance with CDOT specifications 202, 210, and 607 or as directed by the owner. The owner shall authorize and approve all efforts associated with this force account prior to construction; all non-authorized work will be at no cost to the project.

Traffic Control Plan – General

The key elements of the Contractor's method of handling traffic (MHT) are outlined in subsection 630.10(a).

The components of the TCP for this project are included in the following:

(1) Subsection 104.04 and Section 630 of the specifications.

Unless otherwise approved by the Owner, the Contractor’s equipment shall follow normal and legal traffic movements. The Contractor’s ingress and egress of the work area shall be accomplished with as little disruption to traffic as possible. Traffic control devices shall be removed by picking up the devices in a reverse sequence to that used for installation. This may require moving backwards through the work zone. When located behind barrier or at other locations shown on approved traffic control plans, equipment may operate in a direction opposite to adjacent traffic.

The Owner may have entered into operating agreements with one or more law enforcement organizations for cooperative activities. Under such agreements, at the sole discretion of the Owner, law enforcement personnel may enter the work zone for enforcement purposes and may participate in the Contractor’s traffic control activities. The responsibility under the Contract for all traffic control resides with the Contractor and any such participation by law enforcement personnel in Contractor traffic control activities will be referenced in either the Special Provisions or General Notes of the plans depending on whether the Contractor is to hire local law enforcement or if Owner is contracting with Colorado State Patrol for uniformed traffic control. Nothing in this Contract is intended to create an entitlement, on the part of the Contractor, to the services or participation of the law enforcement organization.

Special Traffic Control Plan requirements for this project are as follows:

During the construction of this project, traffic shall use the present traveled roadway unless approved by the Owner.

The Contractor shall not have construction equipment or materials in the lanes open to traffic at any time, unless approved by the Owner.

Lanes of traffic may not be closed unless approved in writing by the Owner.

The Contractor shall not perform any work within the public Right-of-Way between 7 a.m. and 7 p.m. or as directed by the Owner.

At least one week before starting construction, the Contractor shall notify the Owner of the date the Contractor intends to start construction.

All costs incidental to the foregoing requirements shall be included in the original contract prices for the project.

a1 Index of Project Specials
a2 Index of Standard Specials
a4 Commencement and Completion of Work (Working or Calendar Day)
Revision of Section 101 Definitions and Terms
Revision of Section 102 Project Plans and Other Data
Revision of Section 105 Conformity to the Contract of Portland Cement Concrete Pavement
Revision of Section 106 Control of Materials
Revision of Section 202 Removal of Pavement
Revision of Section 203 Excavation and Embankment
Revision of Section 304 Aggregate Base Course
Revision of Section 412 Portland Cement Concerete Pavement
Revision of Section 625 Construction Surveying
z1 Force Account Items
z2 Traffic Control Plan General