This is a comprehensive state and local contract opportunity document for the City of Cripple Creek, Colorado, soliciting bids for the Cripple Creek Skate Park Surfacing Project. The project involves surfacing work at the Mountain View Skate Park located on Masonic Avenue between 1st and 2nd Streets, with a fenced enclosure measuring approximately 60 feet by 119 feet. The scope of work includes approximately 800 square yards of concrete sidewalk and pavement removal, replacement of concrete pavement sections, and repair of damaged chain link fence sections. Sealed bids are due on Tuesday, May 13, 2025, at 2:00 pm local time, with a non-mandatory pre-bid conference scheduled for Thursday, May 1, 2025, at 10:00 AM at Cripple Creek City Hall. The project will be completed within 100 days of the contract commencement, with final completion expected within 120 days.
The contract will be awarded on a unit price basis, with bidders required to submit both a base bid and an alternate bid for sidewalk and pavement removal. The estimated project cost includes various line items such as excavation, aggregate base course, concrete pavement, construction surveying, mobilization, and traffic control. Bidders must provide bid security of 5% of their maximum bid price and are subject to liquidated damages of $1,500 per day for delays in substantial completion or final completion. The City of Cripple Creek will fund the project, and no federal or state wage requirements are mandated. Bids will be evaluated based on the lowest responsive bid, with the owner reserving the right to reject any or all bids and to award the contract based on the lowest total base bid, bid alternatives, and bidder qualifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EJCDC® C-100, Specifications and Contract Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
AS-ADVERTISED
SPECIFICATIONS AND CONTRACT DOCUMENTS
for the
Cripple Creek Skate Park Surfacing Project
Cripple Creek, COLORADO
April 16, 2025
The City of Cripple Creek
337 East Bennett Avenue
Cripple Creek, CO 80813
Steve DiCamillo, Public Works Director
City of Cripple Creek, Colorado
Date
The work contained in the bidding documents have been reviewed and meet the Owner’s project requirements. All questions about the meaning or intent of these documents shall be submitted in writing to the Owner, as stated above.
EJCDC® C-100, Specifications and Contract Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
INDEX OF CONTRACT DOCUMENTS
Cripple Creek City Skate Park Surfacing Project
TABLE OF CONTENTS
TITLE PAGE
Specifications and Contract Documents………………..……..…..…………………………………………………….……C-100-1
Advertisement for Bids ....................................... …………………………………………………………………………..C-111-1
Instructions to Bidders ........................................ ……………………………………………………………………………C-200-1
Bid Form………………………………………………………………………………………………………………………………………..C-410-1
Bid Bond………………………………………………………………………………………………………………………………………..C-430-1
Qualifications Statement…………………………………………….…………………………………………………………………C-451-1
Notice of Award…………………………………………………………………………………………………….………………………C-510-1
Agreement Between Owner and Contractor for Construction (Stipulated Price)……..…………………...C-520-1
Notice to Proceed……………………………………………………………………………………………………….………….……..C-550-1
Performance Bond………………………………………………………………….………………………………………………………….PB-1
Labor and Materials Payment Bond ..........…………………………………………………………………………………….LBMP-1
Contractor’s Application for Payment…….………………………………………………..……………………………………C-620-1
Certificate of Substantial Completion………………………………..…………………………………………………………..C-625-1
Standard General Conditions of the Construction Contract ................................…………………………………GC-1
Supplementary Conditions………………………………………………………………………………………………………………..SC-1
Change Order ........................................................………………………………………………………………………… C-941-1
Field Order ..........................................................................................................................................C-942-1
PART II SPECIFICATIONS ......................... ……………………………………………………………….................Appendix
Project Special Revisions ........................................................................................................................... PSP
Standard Special Provisions ...................................................................................................................... SSP
PART III – CONTRACT FORMS .................... ………………………………………………………………...............Appendix
Contractor Performance Capability Statement…………………………………………………………………..CDOT Form 605
Anti Collusion Affidavit………………………………………………………………………………………………………CDOT Form 606
Assignment of Antitrust Claims………………………………………………………………………………………….CDOT Form 621
Commitment Confirmation……………………………………………………………………………………………..CDOT Form 1415
Good Faith Effort………………………………………………………………………………………………………..……CDOT Form 1416
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ADVERTISEMENT FOR BIDS
The City of Cripple Creek Cripple Creek, Colorado
Cripple Creek Skate Park Surfacing Project
The City of Cripple Creek (Owner) is requesting Bids for the construction of the Cripple Creek City Skate Park Surfacing Project. This Bid is submitted to: The City of Cripple Creek, 337 East Bennett Ave, Cripple Creek, CO 80813. Sealed Bids shall be received in person by the City Clerk at the City Hall no later than Tuesday, May 13, 2025, at 2:00pm local time. Please bring a sealed hard-copy version of all bid documents to the meeting. At that time the Bids received will be publicly opened and read aloud.
This project is located at the City of Cripple Creek Mountain View Skate Park, also referred to as “Skate Park”, which is located on the northern portion of Masonic Avenue between 1st Street and 2nd Street.
The Skate park comprises a fenced enclosure measuring approximately sixty (60) feet by one‐hundred nineteen (119) feet, with an approximate one (1) foot wide concrete ribbon of foundation at its base.
The paved area within the skate park is comprised of a combination of concrete and asphalt pavements, measuring approximately fifty‐eight (58) feet by one‐hundred‐thirteen (113) feet with an average depth of two (2) inches. An existing sidewalk is located at the northernmost portion of the skate park, comprised of an area of approximately four (4) feet by fifty-eight (58) feet.
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Work associated with this project is comprised of approximately 800 square yards of removal of concrete sidewalks and pavements within the skatepark, replacement of a new concrete pavement section, and repair of damaged sections to the existing chain link fence enclosure. Removal of existing sidewalks and pavements has been tabulated as “Bid Alternate 1”, with all other activities provided within the “Base Bid”.
The proposed concrete pavement section is comprised of eight (8) inches of subgrade reconditioning, six
(6) inches of aggregate base course (class 6), and five (5) inches of concrete pavement in accordance with the Part II Technical Specifications based upon the City of Cripple Creek Skate Park Surfacing Project Feasibility Study and Geotechnical Evaluation Report.
Work identified in the bid tabulation(s) shall encompass the scope of work, with additional efforts to accomplish these activities being incidental to the work. Additionally, the contractor will be responsible for obtaining all necessary permits and documentation related to the work, including but not limited to traffic control, erosion control, utility coordination, and clearance.
Information and Bidding Documents for the Project can be found at bidnetdirect.com and cityofcripplecreek.com. The Owner is not responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.
A non-mandatory pre-bid conference will be held on Thursday, May 1, 2025, at 10:00 AM, at the Cripple Creek City Hall located at 337 East Bennett Avenue, Cripple Creek, CO 80813. Bids will be accepted only from pre-qualified bidders; attendance of the non-mandatory pre-bid conference will not be required.
Bidders shall submit questions through email to the Owner, Steve DiCamillo (sdicamillo@cripple-creek.co.us), and City Administrator Frank Salvato (fsalvato@cripple-creek.co.us). The last day for bidder questions will be Monday, May 5, 2025, at end of business. An addendum in response to questions will be posted no later than Thursday, May 8, 2025, by the close of business.
Bid security shall be furnished in accordance with the Instructions to Bidders.
For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
This Advertisement is issued by:
Owner: City of Cripple Creek By: Steve DiCamillo Title: Public Works Director Date: April 16, 2025 mailto:sdicamillo@cripple-creek.co.us mailto:sdicamillo@cripple-creek.co.us mailto:fsalvato@cripple-creek.co.us
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Qualifications of Bidders
Article 4— Pre-Bid Conference
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6— Bidder’s Representations and Certifications
Article 7— Interpretations and Addenda
Article 8— Bid Security
Article 9— Contract Times
Article 10— Substitute and “Or Equal” Items
Article 11— Subcontractors, Suppliers, and Others
Article 12— Preparation of Bid
Article 13— Basis of Bid
Article 14— Submittal of Bid
Article 15— Modification and Withdrawal of Bid
Article 16— Opening of Bids
Article 17— Bids to Remain Subject to Acceptance
Article 18— Evaluation of Bids and Award of Contract
Article 19— Bonds and Insurance
Article 20— Signing of Agreement
Article 21— Wage Rate Requirements
Article 22— Extended Payment Provision
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.
B. Project Special Provisions – Revision of Section 101 Definitions and Terms
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.
2.04 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version X or later. It is the intent of the Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 3 days of Owner’s request, Bidder must submit the following information:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
Other required information regarding qualifications
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference; however, attendance at this conference is not required to submit a Bid.
4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-related Documents
A. No other Site-related documents are available.
5.04 It is the responsibility of each Bidder before submitting a Bid to:
A. Examine and carefully study the Bidding Documents, and the other related data identified in the Bidding Documents;
B. Visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. Become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. Carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph 4.02 of the Supplementary Conditions as containing reliable "technical data," and
(2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in the Paragraph 4.06 of the Supplementary Conditions as containing reliable "technical data";
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
E. Consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;
F. Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. Promptly give the Owner written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by the Owners acceptable to Bidder; and
I. Determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
5.05 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.06 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to the Owner in writing. Interpretations or clarifications considered necessary by the Owner in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effecton.
7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
the Contractor to request that the Owner authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by the Owner until after the Effective Date of the Contract.
10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 If the Supplementary Conditions require the identity of certain Sub-contractors, Suppliers, individuals, or entities to be submitted to Owner in advance of Notice of Award, all Bidders so requested, will within seven days after the day of the Bid opening, submit to Owner a list of all sub-contractors and suppliers for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information as to similar projects and other evidence of qualification for each sub-contractor, person and organization if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, other person, or organization, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
11.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which the Owner makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to the Owner subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
11.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.
12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.06 A Bid by an individual must show the Bidder’s name and official address.
12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.08 All names must be printed in ink below the signatures.
12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Base Bid with Alternates
A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.
The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
13.02 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13.03 Allowances
A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 14—SUBMITTAL OF BID
14.01 The Bidding Documents include one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.
14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid.
14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.
15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.
15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 16—OPENING OF BIDS
16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to the Owner, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Base Bid. All bid alternatives will be evaluated and final award to be based on lowest total base bid, bid alternatives and bidder qualifications.
18.05 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 21—WAGE RATE REQUIREMENTS
21.01 Contractors, prime contractors and subcontractors will not be required to follow any federal or state mandated wage requirements being there is no federal or state funding for this project.
ARTICLE 22—EXTENDED PAYMENT PROVISION
22.01 This construction contract specifically provides for a payment later than twenty-one days after submission of an undisputed request for payment. Owner will make payment within forty-five days after submission of an undisputed request for payment.
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM FOR CONSTRUCTION CONTRACT
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1—OWNER AND BIDDER
This Bid is submitted to: The City of Cripple Creek, 337 East Bennett Ave, Cripple Creek, CO 80813.
Sealed Bids shall be received in person by the City Clerk at the City Hall no later than Tuesday, May 13, 2025, at 2:00pm local time. Please bring a sealed hard-copy version of all bid documents to the meeting. At that time the Bids received will be publicly opened and read aloud.
1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. List of Proposed Subcontractors;
C. List of Proposed Suppliers;
D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;
E. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;
F. Required Bidders Qualification Statement with supporting data;
G. Veterans Preference Certification;
H. Non-Collusion Affidavit;
I. Campaign Contribution Disclosure Form; and
J. Certification Regarding Debarment Suspension
ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES
3.01 Unit Price Bids
A. Bidder will complete the Bid Form attached to this document for the City of Cripple Skate Park Surfacing Project.
B. Bidder acknowledges that:
1. Each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
2. Estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
3.02 Bid Alternative
A. Bidder will complete each Bid Alternative of the Bid Form attached to this document for the City of Cripple Creek Skate Park Surfacing Project. Each bid alternative shall be negotiated and contracted at the discretion of the City of Cripple Creek.
1. The “base bid” includes all work required to complete the scope of work related to logistical and paving operations. Removal of concrete sidewalk and removal of pavement has been removed from the base bid and provided as “Bid Alternate 1” for which the Contractor Shall also submit a bid form.
B. Bid Alternatives are additions to the project scope and shall be decided by the City of Cripple Creek, based on available budget and pricing considerations.
C. Bidder acknowledges that:
1. Each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item.
2. Estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 4—BASIS OF BID—COST-PLUS FEE
4.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
BASE BID
CONTRACT
ITEM NO.
CONTRACT ITEM UNIT
TOTAL
QUANTITIES
BID UNIT PRICING BID TOTALS
202-01 Removal of Sidewalk (4 Inch Average) SY 0
202-02 Removal of Pavement (2 Inch Average) SY 0
203-01 Unclassified Excavation (9 Inch) CY 200
210-01 Reset Fence LF 0
210-02 Reset Gate EA 1
304-01 Aggregate Base Course (Class 6)(6 Inch) TON 240
306-01 Reconditioning (Subgrade)(8 Inch) SY 800
412-01 Concrete Pavement (5 Inch) SY 800
BASE BID SUB-TOTAL
625-01 Construction Surveying LS 0.85
626-01 Mobilization ** LS 0.85
630-01 Traffic Control LS 0.85
LUMP SUM SUB-TOTAL
700-01 F/A Minor Contract Revisions ** F/A 0.85 $50,000.00
700-02 F/A Erosion Control F/A 0.85 $10,000.00
700-03 F/A Utilities F/A 0.85 $10,000.00
700-04 F/A Landscape Restoration F/A 0.85 $2,500.00
700-05 F/A Fence Repair F/A 0.85 $10,000.00
FORCE ACCOUNT SUB-TOTAL
PROJECT TOTAL
TOTAL BID IN WRITTEN WORDS:
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID ALTERNATIVE 1
CONTRACT
ITEM NO.
CONTRACT ITEM UNIT
TOTAL
QUANTITIES
BID UNIT PRICING BID TOTALS
202-01 Removal of Sidewalk (4 Inch Average) SY 26
202-02 Removal of Pavement (2 Inch Average) SY 774
203-01 Unclassified Excavation (9 Inch) CY 0
210-01 Reset Fence LF 25
210-02 Reset Gate EA 0
304-01 Aggregate Base Course (Class 6)(6 Inch) TON 0
306-01 Reconditioning (Subgrade)(8 Inch) SY 0
412-01 Concrete Pavement (5 Inch) SY 0
BASE BID SUB-TOTAL
625-01 Construction Surveying LS 0.15
626-01 Mobilization ** LS 0.15
630-01 Traffic Control LS 0.15
LUMP SUM SUB-TOTAL
700-01 F/A Minor Contract Revisions ** F/A 0.15 $50,000.00
700-02 F/A Erosion Control F/A 0.15 $10,000.00
700-03 F/A Utilities F/A 0.15 $10,000.00
700-04 F/A Landscape Restoration F/A 0.15 $2,500.00
700-05 F/A Fence Repair F/A 0.15 $10,000.00
FORCE ACCOUNT SUB-TOTAL
PROJECT TOTAL
TOTAL BID IN WRITTEN WORDS:
Unit Prices have been computed in accordance with the General Conditions.
Estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities determined as provided in the Contract Documents.
Time of Completion
4.02 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
4.03 Bidder accepts the provisions of the Agreement as to liquidated damages.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
5.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
5.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
5.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda: [Add rows as needed. Bidder is to complete table.]
Addendum Number Addendum Date
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Bidder’s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
procedures of construction to be employed by Bidder, if selected as Contractor; and
(c) Bidder’s (Contractor’s) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given the Owner written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by the Owner is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
6.02 Bidder’s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .