2025 HVAC Bundle Specifications - 5-12-2025.pdf
PDF 2 MB Posted
- Attached to
- PANG HVAC Bundle
- Solicitation number
- S-24800-00013958
- Issued by
- Multnomah County, Oregon
About this file
This document is a comprehensive specification and contract file for an HVAC (Heating, Ventilation, and Air Conditioning) bundle project for the 142d Wing of the Oregon Air National Guard located at 6801 NE Cornfoot Road in Portland, Oregon. The project involves replacing the existing HVAC system with new Variable Refrigerant Flow (VRF) and infrared (IR) systems, along with associated modifications to fire detection systems and electrical infrastructure. The specification details extensive technical requirements across multiple divisions including general requirements, existing conditions, metals, special construction, HVAC systems, electrical systems, and electronic safety and security.
The project requires strict environmental and sustainability compliance, including obtaining necessary permits from Oregon Department of Environmental Quality (DEQ), managing stormwater runoff, controlling hazardous materials, and adhering to air quality and MS4 permit requirements. Specific environmental considerations include using energy-efficient equipment, water-conserving fixtures, low-VOC materials, and implementing comprehensive waste management and recycling protocols. The contractor must work closely with the base environmental manager, obtain multiple state and local permits, and provide detailed documentation throughout the project lifecycle, including a Sustainability Notebook demonstrating compliance with federal Guiding Principles for sustainable construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HVAC BUNDLE PRE-BID SIGN IN001.pdf | ||
| HVAC BUNDLE BID SHEET001.pdf | ||
| ITB - PANG HVAC BUNDLE.pdf | ||
| PANG 2025 HVAC Bundle RFI Responses.pdf | ||
| ITB - PANG HVAC BUNDLE - Amendment 1.pdf | ||
| 00013959 Bid Results.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
Statement of Work/Specifications 142d Wing
6801 NE Cornfoot Road Portland, OR 97218
PANG HVAC BUNDLE
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 50 REQUEST FOR INFORMATION
01 32 01.00 10 PROJECT SCHEDULE
01 32 16.00 20 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 40.00 20 ENVIRONMENTAL MANAGEMENT
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
DIVISION 05 - METALS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 01 30.41 HVAC SYSTEM CLEANING
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2011%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2011%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2011%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2011%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2014%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2014%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2014%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2014%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2030%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2030%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2030%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2030%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2031%2050.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2031%2050.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2031%2050.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2031%2050.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2001.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2001.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2001.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2001.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2001.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2016.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2016.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2016.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2016.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2032%2016.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2029.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2029.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2029.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2033%2029.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2035%2040.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2035%2040.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2035%2040.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2035%2040.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2035%2040.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2042%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2042%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2042%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2042%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2000.10%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2000.10%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2000.10%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2000.10%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2000.10%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2035.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2035.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2035.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2045%2035.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2050%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2050%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2050%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2050%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2020.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2020.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2020.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2020.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2020.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2057%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2074%2019.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2074%2019.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2074%2019.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2074%2019.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/01%2078%2023.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/02%2041%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/02%2041%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/05%2050%2013.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/05%2050%2013.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/06%2010%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/06%2010%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/07%2060%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/07%2060%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/07%2060%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/09%2022%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/09%2022%2000.pdf
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS
23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 31 13.00 40 METAL DUCTS
23 34 23.00 40 HVAC POWER VENTILATORS
23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS
23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS
23 82 00 VARIABLE REFRIGERANT FLOW SPLIT-SYSTEM HEAT PUMPS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.00 10 INSULATED WIRE AND CABLE
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 00.00 10 FIRE DETECTION AND ALARM SYSTEMP
-- End of Project Table of Contents --https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2005%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2005%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2005%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2005%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2007%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2007%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2007%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2007%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2008%2000.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2008%2000.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2008%2000.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2008%2000.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2009%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2009%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2009%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2009%2093.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2011%2025.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2011%2025.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2011%2025.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2011%2025.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2023%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2023%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2023%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2023%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2031%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2031%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2031%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2031%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2034%2023.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2034%2023.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2034%2023.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2034%2023.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2037%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2037%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2037%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2037%2013.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2054%2016.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2054%2016.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2054%2016.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2054%2016.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2082%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2082%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2082%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2082%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/23%2082%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2000%2000.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2000%2000.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2000%2000.00%2020.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2000.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2000.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2000.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2019.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2019.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2019.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2048.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2048.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2048.00%2010.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2071.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2071.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2005%2071.00%2040.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2020%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/26%2020%2000.pdf https://usaf.dps.mil/teams/142dCES_CEN/Shared%20Documents/State%20Contracts/_Appendix%2031-21%20State%20Projects/01%20-%20Current%20Projects/FY25%20Hvac%20Bundle/01%20-%20Working%20Documents/28%2031%2000.00%2010.pdf
PART 1 GENERAL
SECTION 01 11 00
SUMMARY OF WORK
08/11
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work consists of the following:
a. see scope in ITB
1.1.2 Location
The work shall be located at Portland Air National Guard Base. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.4 ON-SITE PERMITS
Notify the Contracting Officer at least 3 working days prior to starting excavation work. The Contractor must obtain from the Contracting Officer a completed AF 103 Form. A separate AF Form 103 is required for each discrete area to be disturbed. The Contractor must retain this form until completion of work.
Contractor is responsible for marking and verifying all utilities not marked. Once an area to be excavated has been marked, the contractor is solely responsible for maintaining all markings throughout the life of the contract as needed to facilitate his work. This permit may be issued daily or up to a week at the discretion of the Government.
The Contractor shall obtain an approved Welding, Cutting and Brazing Permit, AF Form 592, from the ANG Base Fire Department prior to welding or starting any open flames. This permit must be renewed daily.
Other Federal, State and local permits may be required as referenced in Contract Clause 52.236-7 entitled "Permits and Responsibilities."
1.5 LOCATION OF UNDERGROUND UTILITIES
The Contractor shall scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6 SALVAGE MATERIAL AND EQUIPMENT
Contractor to return all recovered refrigerant to CE/GOV. Contractor to coordinate with state inspector, Josh Mumm for procedures.
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the the Portland Air National Guard Base storage area.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. Permission to interrupt any roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Installation become familiar with and obey regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed.
1.2.1.3 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.2.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings except in designated smoking areas in accordance with Activity regulations. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours are between the hours of 7 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
The Contractor shall provide justification for this work outside of
SECTION 01 14 00 Page 2
Portland Air National Guard Base, Oregon Air National Guard (ORANG) regular working hours. Except for utility cutover work, the Government may require compensation for all additional personnel or services it must perform to accommodate such work. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress
1.2.4 Occupied Building
The Contractor shall be working in an existing building which is occupied. Do not enter the building without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the building during the construction period.
1.2.5 Utility Cutovers and Interruptions
a. Coordinate utility cutovers and interruptions with the Contracting Officer. This may require work after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 1
1.1 SUBMITTALS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/11
SECTION 01 30 00 Page 2
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Progress and completion pictures; G Project Schedule; CPM and AF3064 and AF 3065; G Demolition Plan; G AF66, Material Submittal Log with completion dates; G Requests for substitution; G List of subcontractors; G Schedule of Values; G Insurance and Performance Payment Bonds; G Quality Control Plan; G Waste Management Plan; G MSDS Sheets; G Initial Base Access List; G
SD-04 Samples
1.2 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views. Submit a view location sketch indicating points of view. Submit with the monthly invoice on a CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.3 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. SEE ITB
b. Others as required by the solicitation.
1.4 CONTRACTOR SPECIAL REQUIREMENTS
1.4.1 Space Temperature Control, HVAC TAB, and Apparatus Inspection
All contract requirements of Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC shall be accomplished directly by a first tier subcontractor, including the Commissioning Agent. No work required by Section 23 09 53.00 20 or 23 05 93 shall be accomplished by a second tier subcontractor.
SECTION 01 30 00 Page 3
1.5 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.6 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
At a minimum, the Contractor shall submit for government review and comment all of the preconstruction submittals noted above at the preconstruction conference, except for progress and completion photos (if required).
Initial base access list shall include the name, company, driver's license number and last four digits of social security number for those personnel that will initially require base access
1.7 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
SECTION 01 30 00 Page 4
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.
Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.
Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
SECTION 01 31 50 Page 1
1.1 RELATED DOCUMENTS
SECTION 01 31 50
REQUEST FOR INFORMATION
08/14
a. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 REQUIREMENTS INCLUDED
a. Provides procedures and guidelines for preparation, submittal and response to Contractor's Requests for Information (RFI's) during construction of project.
1.3 RFI DEFINITION
a. Request for Information (RFI): The formal Request for Information (RFI) process is one tool to be utilizied by the Contractor to request information from the Contracting Officer regarding the Contract. It should be used only when the Contractor:
(1) Discovers an unforeseen condition or constructability issue; or
(2) Has a question regarding information in the Contract Documents; or
(3) Requires information not found in the Contract Documents.
1.4 REQUESTS FOR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .