This is a bid results tabulation document for ITB No. S-73000-00013959 issued by the State of Oregon on June 30, 2025, for the OR99: MP8.5-MP9.1 Bicycle Improvement project located in Medford, Oregon. The project involves roadway improvements including asphalt pavement removal and replacement, concrete work, inlet and manhole adjustments, pavement markings, and related traffic control and erosion management activities. The bid closing occurred on June 30, 2025, at 11:00 AM. The project scope encompasses 29 line items ranging from mobilization and temporary traffic protection to specialized work such as cold plane pavement removal (11,000 square yards), asphalt concrete pavement installation (1,300 tons), concrete islands (1,800 square feet), and thermoplastic pavement markings (12,500 linear feet).
Two contractors submitted bids for the project: LTM, Incorporated dba Knife River Materials, located in Central Point, Oregon, with a total bid of $598,246.00, and HP Civil Inc., located in Salem, Oregon, with a total bid of $682,883.88. The bid tabulation indicates significant pricing variations between bidders across multiple line items, with HP Civil Inc. bidding higher on the majority of items, particularly on pavement work (cold plane removal at $7.00 per square yard versus $5.00, and ACP mixture at $210.00 per ton versus $150.00). The document explicitly states that this tabulation is not an indicator of award and serves only as a compilation of submitted bids for consideration. The document does not specify contract duration, funding sources, or renewal options.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 6/30/25 | |||||
| ITB No. | S-73000-00013959 | BIDDER | ||||
| NAME: | LTM, Incorporated dba Knife River Materials | HP Civil Inc. | ||||
| Bid Closing: | 6/30/2025 at 11:00 am | CITY/STATE: | Central Point, OR | Salem, OR | ||
| Description: | OR99: MP8.5 -MP9.1 Bicycle Improvement (Medford) | CCB# | 56603 | 202060 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $89,000.00 | $ 89,000.00 | $68,288.38 | $ 68,288.38 | |
| 2 | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | 1 | LS | $70,300.00 | $ 70,300.00 | $80,000.00 | $ 80,000.00 | |
| 3 | TEMPORARY SIGNS | 560 | SQFT | $32.00 | $ 17,920.00 | $22.00 | $ 12,320.00 | |
| 4 | SEQUENTIAL ARROW SIGNS | 1 | EACH | $2,500.00 | $ 2,500.00 | $1,500.00 | $ 1,500.00 | |
| 5 | FLAGGERS | 240 | HOUR | $85.00 | $ 20,400.00 | $72.50 | $ 17,400.00 | |
| 6 | FLAGGER STATION LIGHTING | 240 | HOUR | $15.00 | $ 3,600.00 | $10.00 | $ 2,400.00 | |
| 7 | TEMPORARY BARRICADES, TYPE Ill | 3 | EACH | $170.00 | $ 510.00 | $180.00 | $ 540.00 | |
| 8 | EROSION CONTROL | 1 | LS | $500.00 | $ 500.00 | $2,000.00 | $ 2,000.00 | |
| 9 | INLET PROTECTION, TYPE 3 | 8 | EACH | $85.00 | $ 680.00 | $165.00 | $ 1,320.00 | |
| 10 | POLLUTION CONTROL PLAN | 1 | LS | $500.00 | $ 500.00 | $500.00 | $ 500.00 | |
| 11 | CONSTRUCTION SURVEY WORK | 1 | LS | $15,000.00 | $ 15,000.00 | $15,000.00 | $ 15,000.00 | |
| 12 | REMOVAL OF STRUCTURES AND | |||||||
| OBSTRUCTIONS | 1 | LS | $22,600.00 | $ 22,600.00 | $35,000.00 | $ 35,000.00 | ||
| 13 | CONCRETE SAW CUTTING, 6" DEEP | 500 | FOOT | $5.00 | $ 2,500.00 | $5.00 | $ 2,500.00 | |
| 14 | ASPHALT PAVEMENT SAW CUTTING, 10" DEEP | 100 | FOOT | $3.00 | $ 300.00 | $8.00 | $ 800.00 | |
| 15 | MAJOR ADJUSTMENT OF INLETS | 3 | EACH | $6,000.00 | $ 18,000.00 | $1,500.00 | $ 4,500.00 | |
| 16 | ADJUSTING BOXES | 1 | EACH | $800.00 | $ 800.00 | $700.00 | $ 700.00 | |
| 17 | ADJUSTING INLETS | 1 | EACH | $3,000.00 | $ 3,000.00 | $1,500.00 | $ 1,500.00 | |
| 18 | MINOR ADJUSTMENT OF MANHOLES | 2 | EACH | $3,000.00 | $ 6,000.00 | $1,500.00 | $ 3,000.00 | |
| 19 | COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 11000 | SQYD | $5.00 | $ 55,000.00 | $7.00 | $ 77,000.00 | |
| 20 | LEVEL 4, 1/2 INCH ACP MIXTURE (76- | |||||||
| 22ER oil) | 1300 | TON | $150.00 | $ 195,000.00 | $210.00 | $ 273,000.00 | ||
| 21 | 6 INCH ASPHALT CONCRETE | |||||||
| PAVEMENT REPAIR | 230 | SQYD | $22.00 | $ 5,060.00 | $60.00 | $ 13,800.00 | ||
| 22 | CONCRETE ISLANDS | 1800 | SQFT | $20.00 | $ 36,000.00 | $20.50 | $ 36,900.00 | |
| 23 | MONO-DIRECTIONAL WHITE TYPE IAR | |||||||
| MARKERS.RECESSED | 60 | EACH | $18.00 | $ 1,080.00 | $16.50 | $ 990.00 | ||
| 24 | Bl-DIRECTIONAL YELLOW TYPE IAR MARKERS.RECESSED | 47 | EACH | $18.00 | $ 846.00 | $16.50 | $ 775.50 | |
| 25 | PERMANENT SURFACE MOUNTED | |||||||
| TUBULAR MARKERS | 9 | EACH | $350.00 | $ 3,150.00 | $350.00 | $ 3,150.00 | ||
| 26 | THERMOPLASTIC, SPRAYED, SURFACE, NON-PROFILED | 12500 | FOOT | $1.65 | $ 20,625.00 | $1.65 | $ 20,625.00 | |
| 27 | PAVEMENT LEGEND, TYPE B-HS: ARROWS | 12 | EACH | $400.00 | $ 4,800.00 | $400.00 | $ 4,800.00 | |
| 28 | PAVEMENT LEGEND, TYPE B-HS: | |||||||
| BICYCLE LANE STENCIL | 3 | EACH | $400.00 | $ 1,200.00 | $400.00 | $ 1,200.00 | ||
| 29 | PAVEMENT BAR, TYPE B-HS | 55 | SQFT | $25.00 | $ 1,375.00 | $25.00 | $ 1,375.00 | |
| TOTAL | $ 598,246.00 | $ 682,883.88 |