2025-07-16 RFB 92-25 Lee_s Marina County Park Green Infrastructure Improvements - Technical Specifications.pdf

PDF 4 MB Posted

Attached to
Lee's Marina County Park: Green Infrastructure Improvements
Solicitation number
92-25
Issued by
Morris County, New Jersey

About this file

This document is a comprehensive technical specification for the Lee's County Park Marina Green Infrastructure Improvements project, prepared by the Morris County Park Commission and AKRF, Inc. The project involves constructing green stormwater infrastructure and accessibility upgrades at Lee's County Park Marina located at 443 Howard Boulevard in Mt. Arlington, New Jersey. The scope of work includes multiple elements such as site demolition, earthwork, excavation, stormwater management system installation, permeable pavement systems, lighting installations, landscaping, utility infrastructure improvements, and associated site work. The project will be constructed under a prime general construction contract with a total contract time of 180 calendar days.

The project is funded through the Morris County Park Commission and will involve several key infrastructure enhancements, including permeable pavement systems with subsurface stone storage, swales, underdrains, piping, drainage structures, and electrical service connections. The technical specifications detail precise requirements for materials, installation methods, quality control, and performance standards across multiple technical sections. The estimated project budget and specific funding sources are not explicitly stated in the document. Bidders will be required to provide comprehensive documentation, including detailed construction schedules, material certifications, shop drawings, and submit to a rigorous review and approval process throughout the project's implementation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATIONS

LEE'S COUNTY PARK MARINA

GREEN INFRASTRUCTURE STORMWATER IMPROVEMENTS

BLOCK 10, LOTS 1.67, 68, 69 & 70

BOROUGH OF MT. ARLINGTON, MORRIS COUNTY, NEW JERSEY

July 14, 2025

Prepared For:

Morris County Park Commission 300 Mendham Road

Morristown, NJ 07962

Prepared By:

530 Walnut Street, Suite 998

Philadelphia, PA 19106 tel: 267.585.4839 www.akrf.com

LEE'S COUNTY PARK MARINA - CONTRACT #92-25

BID DOCUMENTS SECTION 000007 - 1

JULY 14, 2025 TABLE OF CONTENTS

Division Page

TABLE OF CONTENTS

01 GENERAL REQUIREMENTS

Summary of Work 011100 Phasing of Work 011216 Maintenance and Protection of Traffic 011526 Project Coordination 013113 Project Meetings 013119 Construction Schedule 013213 Construction Facilities and Temporary Controls 015000 Product Requirements 016000 Cleaning Up 017400 Stormwater Pollution Control 017416 Contract Close Out 017700

02 EXISTING CONDITIONS

Site Demolition 024113

10 SPECIALTIES

Exterior Signage 101453

26 ELECTRICAL

Exterior Lighting 265600

31 EARTHWORK

Geosynthetics for Earthwork 310519 Site Preparation 311010 Earthwork 312000 Grading 312200

32 EXTERIOR IMPROVEMENTS

Concrete for Exterior Improvement 320523 Asphalt Paving 321216 Permeable Unit Paving 321443 Permeable Gravel Paving 321444 Metal Landscape Edging 321600 Stone Curbs and Edges 321640 Pavement Markings 321723

BID DOCUMENTS SECTION 000007 - 2

JULY 14, 2025 TABLE OF CONTENTS

Turf and Grasses 329200 Exterior Planting 329310

33 UTILITIES

Storm Drainage Utilities 334000

BID DOCUMENTS SECTION 011100 - 1

JULY 14, 2025 SUMMARY OF WORK

SECTION 011100

SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

B. NJDEP Land Use Approval (1426-15-0001.2 LUP220001), dated 12/13/22 and modification approval, dated 9/25/24

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. OWNER-furnished products.

4. Access to site.

5. Work restrictions.

6. Specification and drawing conventions.

B. Related Requirements:

1. Section 015000 "Construction Facilities and Temporary Controls" for limitations and procedures governing temporary use of OWNER's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: Lee’s County Marina Park.

1. Project Location: Block 10, Lots 67, 68, 69, 70, 443 Howard Blvd, Mount

Arlington, Morris County, New Jersey

B. OWNER: Morris County Park Commission, 300 Mendham Road, Morristown, New Jersey 07962

1. OWNER's Representative: Matthew Smith, LLA, ASLA, Directer of Park Planning &

BID DOCUMENTS SECTION 011100 - 2

JULY 14, 2025 SUMMARY OF WORK

Development, Engineering Services, MSmith@MorrisParks.net.

C. ENGINEER: AKRF, Inc. (AKRF) 530 Walnut Street, Suite 998, Philadelphia, PA 19106

(267) 585-4839

1. ENGINEER's Representative: Edward Confair, PLA, PE, EConfair@akrf.com

1.4 SITE INFORMATION

A. The site is located in at 443 Howard Boulevard (Block 10, Lots 67, 68, 69, 70) in Mt.

Arlington, NJ and is approximately 13.25 acres. The site is bounded by Howard Boulevard to the east, Lake Hopatcong to the north, and residential properties to the south and west.

B. The property contains regulated riparian zones and Flood Hazard Area associated with Lake Hopatcong.

1.5 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Salvage, removal and disposal of existing site features, as designated on the drawings, that include but are not necessarily limited to; clearing and grubbing, complete tree removal, excavation, asphalt pavement.

2. Earthwork. Excavation for asphalt, stormwater management structures and pipes, and site grading.

3. Removal of rock if required to allow for necessary excavation.

4. Installation of security and soil erosion and sediment control measures, including but not limited to: stabilized construction entrance, silt fence, bale barriers, soil stockpile, inlet protection, erosion control matting, and tree protection.

5. Installation of asphalt pavement, concrete pavement, permeable unit paving, gravel paving, and curbs.

6. Installation of rope fence.

7. Installation of new traffic signage and striping as specified or as shown on the drawings.

8. Preparation and installation of specified landscaped items, including but not limited to: seeded lawn and swales, understory trees, and canopy trees.

BID DOCUMENTS SECTION 011100 - 3

JULY 14, 2025 SUMMARY OF WORK

9. Preparation and installation of stormwater management measures, including but not limited to: permeable pavement systems with subsurface stone storage, swales, underdrains, piping, drainage structures, cleanouts, impermeable liner, and geotextile fabric.

10. Installation of lighting fixtures, lighting fixture foundations, conduit and pull boxes, and electrical services and connection required to deliver fully operational systems (coordinate with utility provider).

11. Acquisition of all necessary permit(s) from various agencies having authority.

B. Type of Contract:

1. Project will be constructed under a prime general construction contract.

1.6 CONTRACTOR’S ACCESS TO SITE

A. General: CONTRACTOR shall have full use of Project site for construction operations during construction period. CONTRACTOR's use of Project site is limited only by OWNER's right to perform work or to retain other CONTRACTORs on portions of Project.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated.

1. Working before 7:00 A.M. or after 5:00 P.M. shall not be permitted except upon authorization by the OWNER.

2. No work other than maintenance work shall be performed on Saturdays, Sundays, or legal holidays, except in the case of emergency and then only to the extent necessary and with the written approval of the OWNER.

3. Should permission be obtained to perform night work, the CONTRACTOR shall provide, at his own expense, all lighting, safety and other facilities necessary for such work.

D. CONTRACTOR shall furnish, install, and maintain adequate supports, shoring, and bracing to preserve structural integrity and prevent collapse of existing improvements and/or Work modified and/or altered as part of the Work.

BID DOCUMENTS SECTION 011100 - 4

JULY 14, 2025 SUMMARY OF WORK

E. CONTRACTOR shall secure Work areas with locking devices.

F. CONTRACTOR assumes custody and control of OWNER property, both fixed and portable, remaining in existing facilities vacated during the Work.

G. CONTRACTOR shall protect areas adjacent to the Work to prevent soiling or damage from dust, dirt, water, and/or fumes. Prior to OWNER occupancy, CONTRACTOR shall clean all surfaces including OWNER property.

H. CONTRACTOR shall protect all surfaces, coverings, materials, and finished Work from damage. Mobile equipment shall be provided with pneumatic tires.

I. CONTRACTOR shall not permit the use of portable and/or fixed radios or other types of sound producing devices.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications.

The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by CONTRACTOR unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

END OF SECTION

BID DOCUMENTS SECTION 011216 - 1

JULY 14, 2025 PHASING OF THE WORK

SECTION 011216

PHASING OF THE WORK

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Requirements for phasing of Work include logistics, phasing, and completion of designated phases prior to commencement of subsequent phases.

1.02 RELATED REQUIREMENTS

A. Section 01 1100: Summary of Work.

PART 2 - PRODUCTS (Not used)

PART 3 - EXECUTION

3.01 SUBMITTALS

A. CONTRACTOR shall submit a Project site logistics plan in accordance with and as required by this Section. The OWNER reserves the right to request additional information in the Project Site Logistics Plan

3.02 LOGISTICS

A. Prior to commencement of Work, CONTRACTOR shall prepare and submit to the OWNER, a detailed Project site logistic plan, in same size and scale of Drawings, setting forth CONTRACTOR plan of Work relative to following, but not limited to, items:

1. Maintained access to the pavilion and circulation of off-season marina traffic and operations throughout construction. After Columbus Day Weekend, CONTRACTOR can utilize the project area east of the marina office and gatehouse. CONTRACTOR to coordinate with MCPC to facilitate schedul-ing of pavement demolition and construction of SWM system #6 at the west-ern end of the site with potential tournaments using Ramp #3 (the western-most ramp) at times during the off-season. Access will need to be maintained to the ramp, as well as temporarily relocation of any boats stored in the cur-rent paved/proposed gravel area.

2. Construction fencing and access gate locations. Temporary chain link fenc-ing shall separate construction activities from off-season marina traffic/ac-tivities. Orange plastic temporary construction fencing may be used where

BID DOCUMENTS SECTION 011216 - 2

JULY 14, 2025 PHASING OF THE WORK

construction activities abut the existing upslope hillside, as approved by the Owner.

3. Hauling route shall be in accordance with local ordinances a truck access route to and from Project site.

4. The identification of any overhead wire restrictions for power, street light-ing, signal or cable.

5. Local sidewalk access and street closure requirements.

6. Protection of sidewalk pedestrians and vehicular traffic.

7. Construction parking.

8. Material staging or delivery areas.

9. Material storage areas.

10. Temporary trailer locations.

11. Temporary service location and proposed routing of all temporary utilities.

12. Location of temporary or accessible fire protection.

13. Trash removal and location of dumpsters.

14. Concrete pumping locations.

15. Location of portable sanitary facilities.

16. Mixer truck wash out locations.

17. Traffic control signage.

18. Perimeter and site lighting.

19. Storm Water Pollution Prevention Plan – SWPPP.

20. Stockpile or lay down areas including those for materials delivered to the site or dismantled on site by Others.

21. Security lighting.

B. Revised Project site logistic plan may be required by the OWNER for separately identified phases of Work as set forth in this Section.

BID DOCUMENTS SECTION 011216 - 3

JULY 14, 2025 PHASING OF THE WORK

C. CONTRACTOR is responsible for securing and/or obtaining all approvals and per-mits from authorities having jurisdiction relative to any activities including but not limited to the Morris County Engineering & Transportation Department.

3.03 PHASING OF THE WORK

A. Project will be constructed as identified or as described in this Section or Contract Documents. Unless otherwise approved or directed by OWNER, each phase and/or component of work shall be completed according to approved Baseline Schedule prior to commencement of next subsequent phase. CONTRACTOR shall incorpo-rate and coordinate Work of Separate Work Contracts relative to this Project into the Phasing and Construction Schedule.

B. CONTRACTOR shall be aware that work by Others shall be performed and incor-porated, where required, during the project including but not limited to items pur-chased by OWNER and installed by CONTRACTOR or purchased by OWNER and installed by Others. CONTRACTOR shall incorporate and coordinate Work by Others relative to this project into the Phasing and Construction Schedule.

C. CONTRACTOR shall install all necessary Work for, but not limited to, power, lighting, signal, drainage, dewatering, shoring, and fencing in phased Work before completion of designated phase. All valves, pull boxes, stub outs, temporary cap-ping, and other Work necessary for phased completion and operation of all neces-sary systems shall be provided whether or not such Work is specifically identified in Contract Documents.

3.04 PHASING OF THE WORK

A. CONTRACTOR shall prepare Construction Schedule in order to complete Work and related activities. CONTRACTOR shall include all costs to complete all Work within Milestones or Contract Time.

B. OWNER will be seriously damaged by not having all Work completed within Mile-stones or Contract Time. It is mandatory Work be complete within Milestones or Contract Time.

C. The Contract Time shall be a total of 180 calendar days from date of commence-ment of Contract Time.

BID DOCUMENTS SECTION 01 1526-1

JULY 14, 2025 MAINTENANCE AND PROTECTION OF TRAFFIC

SECTION 011526

MAINTENANCE AND PROTECTION OF TRAFFIC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SECTION INCLUDES

A. Work of this Section shall include all labor, materials, equipment and services necessary to provide maintenance and protection of traffic work as shown on the drawings and/or specified herein.

1. 3 RELATED SECTIONS

A. Division 01 – General Requirements.

1.4 REFERENCES

A. Work shall be performed in accordance with the requirements of ANSI D6.1 - Manual on Uniform Traffic Control Devices and in accordance with the requirements of local and state authorities having jurisdiction.

1.5 SUBMITTALS

A. Whenever road closures are required to permit the execution of the work of this Contract, the Contractor shall prepare and submit to the OWNER and to the appropriate County or State authorities a comprehensive detour plan indicating all measures to be implemented in the plan and the duration of the plan. This detailed plan shall be submitted to the appropriate authority for review and approval at least 7 days prior to its implementation, and a 72 hour notice shall be given to the above-named authority prior to actual disruption of vehicular traffic patterns.

PART 2 - PRODUCTS

2.1 MATERIALS

The Contractor shall furnish, maintain and remove all temporary barricades, signs, lights, safety devices and facilities including the furnishing of traffic directors and/or flagmen as

BID DOCUMENTS SECTION 01 1526-2

JULY 14, 2025 MAINTENANCE AND PROTECTION OF TRAFFIC

required or directed by the OWNER. Traffic control devices shall conform to ANSI D6.1 - Manual on Uniform Traffic Control Devices Part VI-Traffic Controls for Street and Highway Construction and Maintenance Operations.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Work shall be conducted with the least possible obstruction, inconvenience and interruption to the public with maximum protection to persons and property.

B. Signs, barriers, etc. for the maintenance and protection of traffic shall be furnished, erected, maintained, and replaced, if necessary, at all necessary locations. The signs shall be maintained so as to provide maximum visibility and legibility at all times.

C. All maintenance and protection of traffic measures executed under this contract shall be maintained throughout working and non-working hours including holidays and weekends.

D. Flag person shall be utilized whenever the travel way is reduced to less than one half of available width along any affected roadway or as otherwise may be required.

E. Vehicles hauling materials shall have tight bodies and tailgates, with adequate freeboard and covers to prevent spillage for any reasons. All materials dropped or spilled on public roads or streets shall be removed daily or at such times as required or directed to preclude the creation of a traffic hazard.

PART 4 – PAYMENT

4.1 MAINTENANCE & PROTECTION OF TRAFFIC

A. No separate payment shall be made for this item. Include all costs for Maintenance & Protection of Traffic in the prices bid for the various related items of work as designated in the proposal. No separate payment shall be made for detour plans or traffic control plans if required by the County Engineer. All costs shall be under the lump sum cost for Mobilization & De-Mobilization Bid Item 01.01.

B. Where needed for work adjacent to the right-of-way, the cost for uniformed traffic control officers along Howard Boulevard shall be under the allowance in Bid Item 01.02.

BID DOCUMENTS SECTION 013113 - 1

JULY 14, 2025 PROJECT COORDINATION

SECTION 013113

PROJECT COORDINATION

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. This Section specifies administrative and procedural requirements necessary for coordinating Work operations including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

1.02 RELATED REQUIREMENTS

A. Section 01 1216: Phasing of the Work.

B. Section 01 3213: Construction Schedule.

C. Section 01 7700: Contract Closeout.

PART 2 - PRODUCTS (Not used)

PART 3 – EXECUTION

3.01 CONSTRUCTION MANAGEMENT SOFTWARE

A. CONTRACTOR shall utilize a computer-generated construction management soft-ware program for coordination and document management related to submittals, RFIs, and drawing. This would include implementing one of the following software programs: Procore, or approved equal

3.02 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

BID DOCUMENTS SECTION 013113 - 2

JULY 14, 2025 PROJECT COORDINATION

B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times.

3.03 COORDINATION

A. CONTRACTOR shall coordinate operations included in various sections of Con-tract Documents to assure efficient and orderly installation of each part of Work.

Coordinate Work operations included under related sections of Contract Docu-ments that depend on each other for proper installation, connection, and operation of Work, including but not limited to:

1. Schedule construction operations in sequence required where installation of one part of Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to assure maximum acces-sibility for required maintenance, service, and repair.

3. Provide provisions to accommodate items scheduled for later installation.

4. Prepare and administer provisions for coordination drawings.

B. Where necessary, prepare memoranda for distribution to each party involved, out-lining special procedures required for coordination. Include such items as required in notices, reports, attendance at meetings, and:

1. Prepare similar memoranda for OWNER and Separate Work Contract where coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required adminis-trative procedures with other construction activities to avoid conflicts and assure orderly progress of Work. Such administrative activities include, but are not lim-ited to, following:

1. Preparation of schedules.

2. Installation, relocation, and removal of temporary facilities.

3. Delivery and processing of submittals.

BID DOCUMENTS SECTION 013113 - 3

JULY 14, 2025 PROJECT COORDINATION

4. Progress meetings.

5. Project closeout activities.

D. Conservation: Coordinate Work operations to assure operations are carried out with consideration given to conservation of energy, water, materials, and:

1. Salvage materials and equipment involved in performance of, but not actu-ally incorporated into Work.

3.04 SUBMITTALS

A. Coordination Drawings: CONTRACTOR shall prepare coordination drawings to coordinate the installation of products and materials fabricated, furnished and in-stalled by separate entities, under different parts of the Contract. CONTRACTOR shall notify OWNER and ENGINEER of all major conflicts in writing in a timely manner so that the design team can respond without construction delays. Coordi-nation drawings shall address the following at a minimum:

1. Limitations in available space for installation or service. CONTRACTOR shall overlay plans of each trade and verify space requirements and conflicts between trades. Minor changes and adjustments that do not affect design intent shall be made by CONTRACTOR and shall be highlighted for ENGINEER’S review.

2. Incompatibility between items provided under different trades (such as dif-ference in voltage between equipment specified and electrical power pro-vided.)

3. Inconsistencies between drawings, specifications and codes (between trades and within each trade).

4. Additional items required for existing facilities construction projects shall be designed and prepared from available as-built drawings that are verified through non-invasive and non-destructive, visual observation only.

CONTRACTOR shall field verify actual existing conditions during and upon completion of demolition work and incorporate findings into prepara-tion of co-ordination drawings. Minor changes and adjustments that do not affect design intent shall be made by Sub-CONTRACTOR and shall be highlighted for OWNER and ENGINEER’S reviews.

B. Prepare coordination drawings with each trade, in specified color and scale.

CONTRACTOR and each Subcontractor shall provide and forward reproducible copies in the order described here:

1. Electrical and Low Voltage Subcontractors will indicate service and feeder conduit runs and other electrical equipment complete, including low voltage with installation and dimensioned service clearances, sizes, top or bottom

BID DOCUMENTS SECTION 013113 - 4

JULY 14, 2025 PROJECT COORDINATION

of conduit and rack elevations, distances of conduits and equipment from building reference points and hanger and support locations. Minor changes and adjustments that do not affect design intent shall be made by sub-CON- TRACTORs and shall be highlighted for OWNER and ENGINEER’S re-views. Upon completion drawings shall be forwarded to CONTRACTOR for further co-ordination. Electrical work shall be indicated in dark green lines. Low voltage work shall be indicated in light green lines.

2. CONTRACTOR will be responsible for the overall coordination review. As each coordination drawing is completed, CONTRACTOR will meet with OWNER to review and resolve all conflicts on coordination drawings.

3. Coordination meetings will be held in Project field office of CONTRACTOR. CONTRACTOR is required to distribute Shop Drawings, cut sheets and submittals to Subcontractors where appropriate. Reviewed coordination drawings will be maintained in Project field office of CONTRACTOR. Meeting minutes shall be developed by CONTRACTOR and submitted to OWNER within 5 days.

3.05 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or inter-pretation of the Contract Documents, CONTRACTOR shall prepare and submit an RFI in the form specified.

2. ENGINEER will return RFIs submitted to ENGINEER by other entities controlled by CONTRACTOR with no response.

3. Coordinate and submit RFIs in a prompt manner so as to avoid delays in CONTRACTOR's work or work of Subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following

1. Project name.

2. Project number.

3. Date.

4. Name of CONTRACTOR.

5. Name of ENGINEER.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. CONTRACTOR's suggested resolution. If CONTRACTOR's suggested resolution impacts the Contract Time or the Contract Sum, CONTRACTOR shall state impact in the RFI.

12. CONTRACTOR's signature.

BID DOCUMENTS SECTION 013113 - 5

JULY 14, 2025 PROJECT COORDINATION

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms:

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. ENGINEER's Action: ENGINEER will review each RFI, determine action required, and respond. Allow seven working days for ENGINEER's response for each RFI. RFIs received by ENGINEER after 1:00 p.m. will be considered as received the following working day.

1. The following CONTRACTOR-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of CONTRACTOR's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of ENGINEER's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. ENGINEER's action may include a request for additional information, in which case ENGINEER's time for response will date from time of receipt of additional information.

3. ENGINEER's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for CONTRACTOR to submit Change Proposal according to the provisions of the contract.

a. If CONTRACTOR believes the RFI response warrants change in the Contract Time or the Contract Sum, notify ENGINEER in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly.

1. Project name.

2. Name and address of CONTRACTOR.

3. Name and address of ENGINEER.

4. RFI number including RFIs that were returned without action or withdrawn.

BID DOCUMENTS SECTION 013113 - 6

JULY 14, 2025 PROJECT COORDINATION

5. RFI description.

6. Date the RFI was submitted.

7. Date ENGINEER's response was received.

F. On receipt of ENGINEER's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify ENGINEER seven days if CONTRACTOR disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

BID DOCUMENTS SECTION 013119 - 1

JULY 14, 2025 PROJECT MEETINGS

SECTION 013119

PROJECT MEETINGS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. This Section specifies administrative and procedural requirements for Project meet-ings, including but not limited to, the following:

1. Pre-construction conference.

2. Pre-installation conferences.

3. Project closeout conference.

4. Progress meetings.

5. Additional meetings.

6. Owner’s right to record

1.02 RELATED REQUIREMENTS

A. Section 01 1216: Phasing of the Work.

B. Section 01 3113: Project Coordination.

C. Section 01 3213: Construction Schedule.

PART 2 – PRODUCTS (Not used)

PART 3 - EXECUTION

3.01 PRE-CONSTRUCTION CONFERENCE

A. In accordance with General Conditions, OWNER will schedule a job start meeting before starting the Work, at a time and date determined by OWNER. Meeting shall be held at the Project site or another location as determined by OWNER. Meeting will be held in order to review responsibilities, procedures, and other administrative requirements contained within the Contract Documents.

B. Authorized representatives of OWNER, INSPECTOR, ENGINEER, CONTRACTOR and other parties shall attend the meeting. All participants at the

BID DOCUMENTS SECTION 013119 - 2

JULY 14, 2025 PROJECT MEETINGS

meeting shall be familiar with the Project and authorized to conclude matters relat-ing to the Work.

C. Agenda items shall include significant items which could affect progress of the Work, including, but not limited to the following:

1. Preliminary Construction Schedule.

2. Critical work sequencing.

3. Designation of responsible personnel.

4. Identification of OWNER.

5. Critical work sequencing and long-lead items.

6. Designation of key personnel and their duties.

7. Lines of communications.

8. Procedures for processing field decisions and Change Orders.

9. Procedures for RFIs.

10. Procedures for testing and inspecting.

11. Procedures for processing Applications for Payment.

12. Distribution of the Contract Documents.

13. Submittal procedures.

14. Prevailing wages.

15. Submittal and review of Shop Drawings, Product Data, material lists, and Samples.

16. Preparation of project record documents.

17. Use of the Project site and/or premises.

18. Work restrictions.

19. Working hours.

20. Responsibility for temporary facilities and controls.

21. Parking availability.

BID DOCUMENTS SECTION 013119 - 3

JULY 14, 2025 PROJECT MEETINGS

22. Office, work, and storage areas.

20. Equipment deliveries and priorities.

21. Safety procedures.

22. First Aid.

23. Security.

24. Housekeeping.

25. Contract Compliance Officer.

26. Insurance Services.

27. Environmental Health and Safety.

28. Substantial Completion, Administrative Closeout and Contract Completion requirements and procedures.

29. Procedures for Mandatory Dispute and Claim Resolution.

30. 31. NJDEP Compliance.

D. OWNER shall prepare and issue meeting minutes to attendees and interested parties no later than five calendar days after the meeting date.

3.02 PRE-INSTALLATION CONFERENCES

A. CONTRACTOR shall coordinate and conduct pre-installation conferences at the Project site as required by related Sections of the Contract Documents.

B. CONTRACTOR, manufacturers, and fabricators involved in or affected by the in-stallation and its coordination or integration with other preceding and/or subsequent installations of Work shall attend the meeting. CONTRACTOR shall advise OWNER, INSPECTOR, and ENGINEER of scheduled meeting dates in order to secure their attendance.

1. CONTRACTOR shall review the progress of construction activities and preparations for the particular activity under consideration at each pre-in-stallation conference, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related Construction Directives and Change Orders.

BID DOCUMENTS SECTION 013119 - 4

JULY 14, 2025 PROJECT MEETINGS

d. Purchases.

e. Deliveries.

f. Shop Drawings, Product Data, and quality-control samples.

g. Review of mockups.

h. Possible conflicts.

i. Compatibility problems.

j. Time schedules.

k. Weather limitations.

l. Manufacturer’s recommendations.

m. Warranty requirements.

n. Compatibility of materials.

o. Acceptability of substrates.

p. Temporary facilities.

q. Space and access limitations.

r. Governing regulations.

s. Safety.

t. Inspecting and testing requirements.

u. Required performance results.

v. Recording requirements.

w. Protection.

2. CONTRACTOR shall record significant discussions and directives re-ceived from each conference. CONTRACTOR shall, within three (3) cal-endar days after the meeting date, distribute the minutes of the meeting to all concerned parties, including but not limited to, OWNER, INSPECTOR, and ENGINEER.

BID DOCUMENTS SECTION 013119 - 5

JULY 14, 2025 PROJECT MEETINGS

3.03 PROGRESS MEETINGS

A. Progress meetings will be held at the Project site biweekly as determined by the

OWNER.

B. In addition to representatives of CONTRACTOR, OWNER, and ENGINEER, each Subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of the Work shall, if requested by OWNER, be represented at these meetings. All participants at the conference shall be familiar with the Project and authorized to conclude all matters relating to the Work.

C. Failure of CONTRACTOR to be so represented at any progress meeting which is held at a mutually agreed time or for which a written notice is given, shall not re-lieve CONTRACTOR from abiding by any and all OWNER determinations or di-rectives issued at such meeting.

D. OWNER will review and correct or approve minutes of the previous progress meet-ing and will review other significant items affecting progress. Topics for discussion as appropriate to the status of the Project include but are not limited to:

1. Interface requirements.

2. Construction Schedule.

3. Sequence and coordination.

4. Status of submittals / RFIs.

5. Deliveries.

6. Off-site fabrication.

7. Access.

8. Site utilization.

9. Temporary Construction Facilities and Controls.

10. Hours of work.

11. Hazards and risks.

12. Housekeeping.

13. Quality of materials, fabrication, and execution.

14. Unforeseen conditions.

BID DOCUMENTS SECTION 013119 - 6

JULY 14, 2025 PROJECT MEETINGS

15. Testing and Inspection.

16. Defective Work.

17. Construction Directive.

18. Request for Proposal.

19. Change Order Proposals and Change Orders.

20. Documentation of information for payment requests.

21. Application for Payment.

22. Other items as required or as brought forth.

23. Initial Notice of Start of Issue, Event, Condition, Circumstance, or Cause of Perceived Delay, Disruption, Interference, Hindrance, Acceleration.

24. Final Notice of End of Issue, Event, Condition, Circumstance, or Cause of Perceived Delay, Disruption, Interference, Hindrance, Acceleration

25. Storm Water Pollution Prevention.

E. No later than five (5) calendar days after each progress meeting, OWNER will pre-pare and distribute minutes of the meeting to each present and absent party. Include a brief summary, in narrative form, of progress, decisions, directives, actions taken, and all other issues since the previous meeting and report.

1. Schedule Updating: CONTRACTOR shall revise the Construction Sched-ule after each progress meeting where revisions to the schedule have been made or recognized, and issue the revised schedule at the next scheduled progress meeting.

3.04 PROJECT CLOSEOUT CONFERENCE

A. Schedule and conduct a project closeout conference, at a time convenient to OWNER and ENGINEER, but no later than 45 days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of OWNER, ENGINEER, and their consultants; CONTRACTOR and its superintendent; major Subcontractors;

suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

BID DOCUMENTS SECTION 013119 - 7

JULY 14, 2025 PROJECT MEETINGS

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Submittal of written warranties.

d. Requirements for preparing operations and maintenance data.

e. Requirements for delivery of material samples, attic stock, and spare parts.

f. Requirements for demonstration and training.

g. Preparation of CONTRACTOR's punch list.

h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

i. Submittal procedures.

j. Coordination of separate contracts.

k. OWNER's partial occupancy requirements.

l. Installation of OWNER's furniture, fixtures, and equipment.

m. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting will record and distribute meeting minutes.

3.05 ADDITIONAL MEETINGS

A. OWNER, upon giving notice to the intended parties and without further obligation, may require additional meetings to discuss Work and/or Project related activities.

3.06 OWNER’S RIGHT TO RECORD

A. CONTRACTOR agrees on behalf of itself and all its Subcontractors that the OWNER may audiotape or videotape any meetings, training and any work at any time during the Project.

BID DOCUMENTS SECTION 013213 - 1

JULY 14, 2025 CONSTRUCTION SCHEDULE

SECTION 013213

CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Required procedures for the development of the Baseline Construction Schedule, Monthly Schedule Update, Four-Week Rolling Schedule, Recovery Schedules, Fragnets and Time Extension requests.

1.02 RELATED REQUIREMENTS

A. Section 01 1100: Summary of Work.

B. Section 01 1216: Phasing of the Work.

C. Section: 01 3119: Project Meetings.

D. Section 01 7700: Contract Closeout.

1.03 SCHEDULER QUALIFICATIONS

A. CONTRACTOR shall have a scheduler with a minimum of 5 years direct experi-ence in the development and maintenance of schedules.

B. CONTRACTOR shall submit the resume of the construction scheduler to OWNER for review and approval. OWNER has the right to refuse to accept the Scheduler based upon a lack of experience as required by this Section or based on lack of on-site performance and timeliness of schedule submittals. If OWNER does not accept the proposed Scheduler, CONTRACTOR shall within one week of disapproval, propose another Scheduler who meets the experience requirements stated above.

1.04 SCHEDULING SOFTWARE

A. CONTRACTOR shall utilize a computer-generated schedule software program that will employ the Critical Path Method (CPM) in the development and maintenance of the construction schedule. This would include implementing one of the following software programs: Primavera P6, or approved equal.

B. All schedule calculation rules, auto cost rules and resource calculation rules shall be in a format acceptable to OWNER. When schedule calculations are performed, the “Retained Logic” setting shall be used. CONTRACTOR shall use the zero

BID DOCUMENTS SECTION 013213 - 2

JULY 14, 2025 CONSTRUCTION SCHEDULE

“Decimal Places” setting. Finish Milestones shall be constrained with either a “fin-ish on or before” date or a “late finish” type constraint. No “Mandatory Finish” type constraints, no “Zero Free Float” constraints, no special hidden lag time be-tween activities or other “float Suppression” techniques will be permitted. A sched-ule milestone constraint extending beyond Contract time or less than Contract time will not be acceptable. Rather, CONTRACTOR shall show any unused contract time as float (slack time) available to the project, except as required by coordination with utility authorities.

1.05 PRE-CONSTRUCTION SCHEDULING CONFERENCE

A. CONTRACTOR and CONTRACTOR Scheduler shall attend a pre-construction scheduling conference with OWNER. CONTRACTOR Scheduler shall develop a construction schedule in accordance with this Specification Section. Scheduler shall cooperate with OWNER and shall make themselves available for on-site meet-ings to develop, monitor, maintain and update the schedule in a timely manner.

B. CONTRACTOR and CONTRACTOR Scheduler shall work with the OWNER to create a project schedule that proposes project work during the Marina off-season to allow for unimpeded traffic circulation and construction.

1.06 SUBMITTALS

A. Within seven calendar days after the effective date of the Notice to Proceed, CONTRACTOR shall submit to OWNER for review, a detailed Baseline Construc-tion Schedule setting forth all requirements for complete execution of the Work.

Include individual activities for the preparation of specific submittals, activities for owner review periods, activities for the procurement / fabrication period, installa-tion activities, any applicable start-up & testing activities, and all contract mile-stones. With the exception of submittals and fabrication /procurement activities, each work activity shall range in duration from 1 workday minimum to a 10 work-day maximum. The Scheduling system shall indicate all inter-relationships (logic ties) between the activities and shall be logically tied to all relevant milestones listed in Section 01 1216 Phasing of the Work. CONTRACTOR shall cost load the activities with a “budgeted cost” that totals up to the Contract award value. All monthly schedule updates and baseline schedules shall be dated and initialed by the Contractor.

B. Duration and events indicated on schedule shall conform to phasing set forth in Section 01 1216 Phasing of the Work and shall show any area or building within a particular phase. Each activity description shall outline the specific work scope (by trade) and the location. Schedule shall indicate any and all Contract "milestone events" and other milestones agreed to by OWNER, but no other manually-imposed dates will be accepted unless approved by OWNER.

BID DOCUMENTS SECTION 013213 - 3

JULY 14, 2025 CONSTRUCTION SCHEDULE

C. CONTRACTOR shall allow for inclement weather in the Proposed Baseline Sched-ule by incorporating an activity titled “Rain Day Impact Allowance” as the last activity prior to the Substantial Completion Milestone. No other activities may be concurrent with it.

D. CONTRACTOR shall submit a color bar chart of all activities organized by Area (Location) and sorted by early start date in a graphically “left to right” manner. In addition, submit a Critical Path (Longest Path) color bar chart filter. Include the following column headings on the left hand side of both bar chart reports: activity ID, activity description, original duration, remaining duration, percent complete, start date, finish date, total float (slack time), and budgeted cost. CONTRACTOR shall also include an electronic copy of the Schedule in an acceptable format to the

OWNER.

E. Include a written schedule narrative sufficiently comprehensive to explain the basis of the CONTRACTOR'S approach to work. The written schedule narrative should include a paragraph of the project’s Critical Path, the anticipated crew sizes (by trade), any planned equipment needed, a discussion on any long lead procure-ment/fabrication items, and any site logistic challenges.

F. Seven calendar days after receipt of the OWNER'S review comments, CONTRACTOR shall revise and re-submit the Construction Schedule acceptable to OWNER. Once the Baseline Construction Schedule is approved, no changes will be allowed unless authorized by the OWNER.

G. Failure of CONTRACTOR to submit a Construction Schedule in full compliance with the Contract Documents will result in a delay in progress payment processing.

The Construction Schedule is to be used in evaluating progress and for monthly payment approval.

H. Subsequently with each Monthly Progress Payment Request, CONTRACTOR shall deliver to OWNER a Monthly Schedule Update reflecting Work progressed to the end of the Progress Payment Request period (set as the last day of the month).

Each such Monthly Schedule Update shall indicate actual progress to date in exe-cution of the Work, together with a projected schedule for completion of all the remaining Work. CONTRACTOR shall copy & re-name the schedule file each month, status the activities with actual start and/or finish dates, adjust remaining durations, add re-submittals (if applicable), calculate the schedule with a “data date” to the end of the pay period, and submit the required report to the OWNER.

Each Monthly Schedule Update shall be submitted con-currently with the Monthly Pay Application. In updating the Schedule, CONTRACTOR shall not modify Ac-tivity ID numbers, activity descriptions, original durations, logic, schedule calcula-tion rules/criteria, or the Activity Coding unless authorized by the OWNER. All monthly schedule updates and baseline schedules shall be dated and initialed by the Contractor.

BID DOCUMENTS SECTION 013213 - 4

JULY 14, 2025 CONSTRUCTION SCHEDULE

I. All Schedule submittals are subject to review and acceptance by OWNER.

OWNER retains the right to withhold progress payments in whole (or in part) until CONTRACTOR submits a Construction Schedule acceptable to OWNER.

1.07 FOUR-WEEK ROLLING SCHEDULE

A. At each Biweekly Progress Meeting, CONTRACTOR shall present a Four-Week Rolling Schedule in Bar Chart format. It shall show one (1) week of actual and three (3) weeks of forecasted progress. The Four-Week Rolling Schedule shall be used as a basis for discussing progress and work planned during the three (3) weeks.

1. The Four-Week Rolling Schedule shall be based on the most recent OWNER Accepted Monthly Schedule Update. It shall include weekly up-dates to all construction, submittal, fabrication and procurement, and sepa-rate work contract activities. CONTRACTOR shall ensure that it accurately reflects the current progress of the Work.

2. CONTRACTOR shall discuss at the Biweekly Progress meeting the actual dates and any variances to critical or near critical activities.

3. Upon request by OWNER, CONTRACTOR shall provide the Four-Week Rolling Schedule in electronic format.

4. If the Four-Week Rolling Schedule indicates activities are behind schedule, CONTRACTOR shall provide a Recovery Schedule in accordance with Ar-ticle 1.08 below.

5. If the CONTRACTOR chooses to provide a Four-Week Rolling Schedule in a greater level of detail (by trade/subcontractor) outside of the monthly schedule database, then upon CONTRACTOR REQUEST and OWNER written approval, the CONTRACTOR may proceed as long as the detailed activities roll-up to the contractual monthly schedule updates. These de-tailed activities will need to be linked to the overall Substantial Completion date as to properly forecast whether the project is ahead or behind schedule during the biweekly Progress Meetings. The Four-Week Rolling Schedule must accurately reflect the work that is going on during the current week and must accurately reflect what will happen in the next three weeks.

1.08 RECOVERY SCHEDULES

A. If a Monthly Schedule Update indicates negative float greater than ten (10) days on a critical path as result of events not predicated by the General Conditions, CONTRACTOR shall prepare a Proposed Recovery Schedule demonstrating CONTRACTOR’S plan to regain the time lost. The Recovery Schedule shall be submitted either in advance of or concurrent with the Monthly Schedule Update and CONTRACTOR progress request. Both the Monthly Schedule Update and the

BID DOCUMENTS SECTION 013213 - 5

JULY 14, 2025 CONSTRUCTION SCHEDULE

Proposed Recovery Schedule shall be based on the same percentages of completion and actual dates accepted by OWNER.

B. The Proposed Recovery Schedule shall be based on a copy of the Monthly Schedule Update for the calendar month during which the negative float first appears. The Proposed Recovery Schedule shall use a TIA (Time Impact Analysis) adjustment based on an up-to-date CPM.

C. The Proposed Recovery Schedule shall include a written narrative that identifies the causes of the negative float on the critical path and provides CONTRACTOR’S proposed corrective action to ensure timely completion of all Milestones and the Substantial Completion Date. CONTRACTOR’S corrective actions shall include but are not limited to increasing concurrent operations, increasing labor, adding multiple shifts in a 24-hour period, and adding overtime.

D. During any period of time when CONTRACTOR is found to be behind schedule by OWNER, the Monthly Schedule Update described above shall become a weekly requirement (at no additional cost to OWNER) to provide a greater degree of focus on the timely completion of the Work. These Updates shall be submitted to OWNER every Monday morning. When CONTRACTOR is deemed by OWNER to be back on schedule, CONTRACTOR may revert to submitting the schedule monthly.

E. CONTRACTOR’S progress payment may not be processed until OWNER accepts the Proposed Recovery Schedule. Following such an acceptance, the Proposed Re-covery Schedule will be known as the Recovery Schedule and future Work will be performed by CONTRACTOR in accordance with it.

1.09 FRAGNETS AND TIME EXTENSION REQUESTS

A. Float is not for exclusive use or benefit of either OWNER or CONTRACTOR but is an expiring resource available to both parties on a non-discriminatory basis. If required to meet specified Milestones, either party may utilize float. Adjustments to Milestones or Contract Time will only be authorized by Change Order and only to the extent the claimed adjustments exceed total float along the most critical path of the current Monthly Schedule Update in effect at the time of the claimed adjust-ments. The claimed adjustments to the Milestones and/or Contract Time must also cause the Substantial Completion Date to exceed that currently indicated in the Monthly Schedule Update.