This file is a PowerPoint presentation containing SCIF communication diagrams and network infrastructure layouts for Building 10577 at what appears to be a military facility. The diagrams detail existing and planned communication infrastructure across three floors, including classified and unclassified network conveyance routes, network drop locations, and equipment cabinet specifications.
The diagrams show detailed specifications for network drops across multiple rooms, with each drop typically consisting of 2-4 LC fiber ports for classified networks and 2 LC fiber ports for unclassified networks, connecting to various communication panels (particularly C303 and C300E). The presentation includes floor plans showing conveyance routing both above false ceilings and below false floors, locations of communication cabinets, wall penetrations, and J-boxes. Specific details include requirements for a new full-size 22" wide 7' high equipment cabinet with fan in room B201, and various fiber distribution panels and PDS (Protected Distribution System) ducts. The diagrams indicate both existing infrastructure and new installations required for the SCIF IT infrastructure upgrade project referenced in the associated pre-solicitation notice.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_VSFB B10577 SCIF Comm Installation_20241216.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comm Entrance Facility Room (this is not a SCIF)
B104 B10577 1st Floor SCIF Diagram 1
Existing Comm Cabinet Existing Cable Tray Existing Wall Penetration Existing Ceiling Penetration
“LAUNCH AND TEST ABOVE THE REST”
B10577 2nd Floor SCIF Diagram 2 B201
SCIF Area The Scope of this SOW
B10577 3rd Floor SCIF Diagram 3
SCIF Area The Scope of this SOW
B10577 2nd Floor Diagram 4 Above False Ceiling Conveyance Routing
C201 C201A C201B C207C C207
B C207A C209
C209A C204 C202 201A
C202A C202B
Ceiling Conveyance Plan New Classified Conveyance Existing Classified Conveyance New Unclassified Conveyance Existing Unclassified Conveyance Existing Classified PDS Existing Wall or Ceiling Penetration New Wall (installed by others) Existing Comm Cabinet
Ceiling penetrations to C303
C202C
C207B
Floor & Ceiling penetrations
A B C301 C303 C305 C307 C309 C309A
C300D C300 C300C C300B C300A
B10577 3rd Floor Diagram 5 Below False Floor Conveyance Routing
Floor penetrations to C201
Floor Conveyance Plan
Existing Classified Conveyance New Unclassified Conveyance Existing Unclassified Conveyance Existing Classified PDS Existing Wall or Ceiling Penetration
Existing Comm Cabinets
C300E
Floor penetration
B C301 C303 C305 C307 C309 C309A
C300D C300 C300C
Existing Classified Conveyance New Unclassified Conveyance Existing Unclassified Conveyance Existing Classified PDS Existing Wall or Ceiling Penetration
Existing Comm Cabinets
B10577 3rd Floor Diagram 6 Above False Ceiling Conveyance Routing Very very tight location for conveyance
Locked J-box & Penetration
Locked J-box
This conveyance needs structure support repair Penetrations to 201A
Unclass Penetration UnLocked J-box for black and red
B10577 2nd Floor Diagram 7 New Network Drop Locations
C201 C201A C201B C207C C207
C207B C207A C209
C209A C204
201A
C202A C202B
For C201, C201A, C201B, C207, C207A Network Drop Each consists of:
2 each LC Fiber ports homed to CP to C303 (Classified) 2 each LC Fiber ports homed to CP to C300E (Classified) 2 each LC Fiber ports homed to CP to C207B (Classified) 2 each LC Fiber ports homed to CP C303 (Unclassified) C202C
For C202, C202A, C202B, C202C, C204, C209, C209A Network Drop Each consists of:
4 each LC Fiber ports homed to CP to C303 (Classified) 2 each LC Fiber ports homed to CP to C303 (Unclassified)
40 total drops 6 total drops 11 total drops
26 total drops
22 total drops
C202
37 total drops
B C301 C303
C307 C309 C309A
C300D C300 C300C
B10577 3rd Floor Diagram 8 New Network Drop Locations
For C305, C307, C309, C309A Network Drop Each consists of:
4each LC Fiber ports homed to CP to C303 (Classified) 2each LC Fiber ports homed to CP to C303 (Unclassified)
C305
14 total drops 11 total drops
27 total drops For C300, C300A, C300B, C300C, C300D Network Drop Each consists of:
4 each LC Fiber ports homed to CP to C303 (Classified) 2 each LC Fiber ports homed to CP to C300E (Classified) 2 each LC Fiber ports homed to CP to C303 (Unclassified)
3rd Floor C303 Diagram 11
Backup Charts
2nd Floor B201 Diagram 9 New Conveyance & Network Drop Locations
B201
For B201 rooms Network Drop Each consists of:
4each LC Fiber ports homed to CP to B201 new Comm Cabinet 2each Ethernet ports homed to 301A
Existing Wall Penetration
New Full Size 22” wide 7’ heigh equipment cabinet with fan
New Unclassified Conveyance Existing Unclassified Conveyance
CUI
Current Cabling Configuration (Cat5) 2nd Floor B201 Diagram 10 Reroute B-Wing Unlcass Network Drops New Cabling Configuration Cat6e for B209E, B209, B203 LC Fiber for B201
201A 201A
New fiber switch here
Empty JWICS/PPs JWICS/SIPR AutoPatch Encryption/SIPR Timing/DRSN/SDIN/PPs/SONET
SDIN
Empty Empty Empty Monitor Station Empty 18 Space Equipment
Monitor Station
Row 2 FPI 3R0X Row 3 FPI 3RXX Row 4 FPI 3RXX Row 5 FPI 3RXX Row 1 FPI 3BXX Row 6 Row 7 Row 8 Row 9
B10577 2nd Floor
B10577 2nd Floor
A: A201 Comm Rm Cab # 4: No Label (thick orange cable)—this goes to C207 NIPR Fiber Box.
A201 Comm Rm Cab # 4 Panel B1-72 Ceiling C201; 73-120 C207; 120-132 C209 (thick orange cable innerduct)—need to chase this cable down A201 Comm Rm Cab # 4 NIPR XUMU-AN-10577-2-C93G02 C: C201 Wall Mount FOP to C300E Cab # 6
CUI
CUI
A
NIPR
SIPR
JWICS
NIPR
SIPR
JWICS
201A Comm Room
Red=>?
Black=>?
B201 B201
NIPR/SIPR=>
FOP
2nd Floor 6-Strands 1-3 12-Strands 4-7 2nd Floor
HC-1 1-48
HC-2 49-96
HC-3 97-144
TS/SCI Fiber Dist Panel PPA C303.3R08.FDPe.L1/M12???
B10577 3rd Floor
B10577 3rd Floor
A: A301 Cab # 5 (SIPR cabinet) C300E orange 24MM; C300E yellow 12SM B: C300E Rack # (not labeled) but goes to A301 Cab #5 above cables C: C300E PDS duct to C303 to C201 to C205 Jbox.: includes 144MM thick orange cable; med size orange (maybe to C209 GSN); thin dark orange cable D: C300E PDS duct to C303 server room: includes thin light orange terminating in rack #6 JWICS; 2 blue cat 5 terminating into rack # 9; thin gray cable terminating into rack # 6 (goes to C303?)
CUI
CUI
A B C D
B10577 Additional SCIF Space
CUI
B201 SAP-F
Unclass Cat5 Penetration
TS/SCI Fiber Distribution Panel
PPA C303.3R08.FDP3.L1/M12
2.5” conduit 1” conduit 2” innerduct Confirm Secret?
What happens here?
Locked J-Box
Org Innerduct 2 org fiber pairs 3 org round fibers
Confirm these connect image1.jpg image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png