2024.10.18_24-858-ADDENDUM 1 combined.pdf
PDF 576 KB Posted
- Solicitation number
- 446-2024-100
- Issued by
- Cabarrus County, Yanceyville Town, North Carolina
About this file
This document is an addendum for a state and local contract opportunity from the Town of Valdese, North Carolina for the Draughn Aquatic Center Structure project. The project consists of modifications to the exterior wall adjacent to the pool, installation of a pre-engineered membrane structure over the pool and pool deck, and installation of mechanical, electrical, and plumbing systems in the new structure. Sealed bids will be received until October 28, 2024 at 11:00 a.m. from invited general contractors. A pre-bid meeting will be held for all interested bidders and vendors. A bid bond equal to 5% of the base bid is required, as well as payment and performance bonds equal to 100% of the contract sum. The successful bidder must complete the project within a specified number of consecutive calendar days after the notice to proceed.
The bid form includes a base bid amount and a list of unit prices for additional work, but does not include state or local sales tax. The contract will be awarded to the lowest responsive, responsible bidder. Bidders must be properly licensed contractors in North Carolina. The owner reserves the right to accept or reject any or all bids and to waive informalities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MICHAEL GRAVES MichaelGraves.com
530 North Trade Street, Suite 301, Winston-Salem, NC 27101 | 336.725.1371 NJ | DC | MD | NY | NC
ADDENDUM NO. 2
PROJECT:
Town of Valdese Draughn Aquatic Center Structure
Valdese, North Carolina 24-858
TO: All Plan Holders
ADDENDUM DATE: 10/18/2024
This Addendum forms a part of and modifies the Contract Documents dated October 15, 2024, as described below, and consists of one
(1) pages. This Addendum is incorporated into the first issued printed set.
GENERAL:
ITEM SECTION DESCRIPTION
1. - Added Addendum 1 Cover Sheet
SPECIFICATIONS:
ITEM SECTION DESCRIPTION
2.
3.
4.
000020
000030 000060
Revised TABLE OF CONTENT
Revised ADVERTISEMENT FOR BIDS Revised BID FORM
DRAWINGS:
ITEM DRAWING DESCRIPTION
5. M1.01 Revised specifications
END OF ADDENDUM
TOC-1
24-858
ADDENDUM #1
TABLE OF CONTENTS
BIDDING REQUIREMENTS AND INFORMATION
Advertisement for Bids
Instruction to Bidders County Sales & Tax Report (NC) Bid Form
Bid Bond (A310)
SAMPLE CONTRACT FORMS AND PROJECT INFORMATION:
Performance Bond (A312) Payment Bond (A312) General Guarantee Roofing Warranty Asbestos Free Warranty
CONDITIONS OF THE CONTRACT:
General Conditions of the Contract for Construction (A201) Supplementary General Conditions (To A201 General Conditions)
SPECIFICATIONS:
DIVISION1 – GENERAL REQUIREMENTS
01 11 00 Summary of the Work 01 12 00 Owner Occupancy During Construction 01 20 00 Allowances & Unit Prices 01 31 00 Project Meetings 01 33 00 Submittals 01 35 50 Product Requirements 01 42 00 Reference Standards & Layout Work 01 50 00 Temporary Facilities 01 61 00 Materials and Equipment 01 63 00 Product Substitutions 01 73 00 Cutting and Patching 01 74 00 Cleaning Up 01 75 00 Documents at Project Site 01 78 00 Contract/ Project Close-Out 01 83 00 Equipment Maintenance and Operations Program
DIVISION 2 – EXISTING CONDITIONS
02 41 19 Selective Demolition
TOC-2
DIVISION 3 - CONCRETE
03 10 00 Concrete Formwork 03 20 00 Concrete Reinforcement 03 25 00 Adhesive Anchors 03 30 00 Cast in Place Concrete
DIVISION 4 - MASONRY
04 06 00 Masonry Mortar 04 20 00 Unit Masonry
DIVISION 5 - METALS
See Drawings for Structural Engineering specifications
05 50 00 Miscellaneous Metal Fabrications
DIVISION 6 - WOOD AND PLASTICS
06 10 00 Rough Carpentry
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07 14 00 Fluid Applied Waterproofing (Prosoco Fastflash) 07 20 00 Rigid Insulation 07 21 16 Flexible Insulation 07 53 00 Fully Adhered Thermoplastic Polyolefin (TPO) Roofing 07 62 00 Flashing and Sheet Metal 07 90 00 Sealants
DIVISION 8 - DOORS AND WINDOWS
08 11 00 Hollow Metal Doors and Frames 08 33 60 Overhead Rolling Doors 08 51 00 Steel Windows 08 80 00 Glass and Glazing
DIVISION 9 - FINISHES
09 29 00 Gypsum Drywall 09 91 00 Field Painting
DIVISION 10 – SPECIALTIES (not used)
DIVISION 11 – EQUIPMENT (not used)
DIVISION 12 – FURNISHINGS (not used)
TOC-3
DIVISION 13 - SPECIAL CONSTRUCTION
13 12 00 Pre-Engineered Structures
DIVISION 14 - CONVEYING SYSTEMS (not used)
DIVISION 21 – FIRE PROTECTION
See Drawings
DIVISION 22 - PLUMBING
DIVISION 23 - MECHANICAL
DIVISION 26 - ELECTRICAL
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
END OF TOC
ADV-1
ADVERTISEMENT FOR BIDS
Sealed Bids will be received by the Town of Valdese at 11:00 a.m., October 28, 2024, at the Town of Valdese Town Hall, in the Community Room, at 102 Massel Ave. SW, Valdese, NC 28690; at which time the Bids will be opened and read publicly for the construction of the following:
Town of Valdese – Draughn Aquatic Center Structure
Bids will be received from invited General Contractors only and their bids will include general construction, plumbing, HVAC, electrical, plumbing, civil, audio/visual and all work indicated by the Bidding Documents.
Digital copies of the Bidding Documents will be available from the Architect’s Office to invited General Contractors. General Contractors will be required to share the Bidding Documents with their sub-contractors.
Digital copies of the Bidding Documents will not be available to sub-contractors from the Architect’s Office.
Invited General Contractors may purchase printed, full sets of the Bidding Documents from The Sharpe Company, 800-688-0629.
The project consists of:
Modifications to the exterior wall adjacent to the pool, installation of pre-engineered membrane structure over pool and pool deck, installation of mechanical, electrical, and plumbing systems in new structure.
Bidders must be properly licensed Contractors in accordance with applicable North Carolina state law.
Bids must be on the standard form provided by the Architect and must be marked to identify the type of Prime Contract noted.
Bidders shall use complete sets of Bidding Documents in preparing Bids; neither the Owner nor Architect assumes responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
An open pre-bid meeting will be held for all interested bidders and vendors.
A Bid Bond will be required with each Bid. The Bond shall be in the sum equal to 5% of the gross Base Bid.
A Payment and Performance Bond will be required each in the sum equal to 100% of the Contract Sum.
No Bidder may withdraw his Bid within 30 days after the opening thereof.
The Owner reserves the right to accept or reject any or all Bids, and to waive informalities.
Owner:
BF-1
BID FORM
Name of Bidder
Business Address
N.C. License No.
Telephone Number
Email Address
PROJECT: Town of Valdese – Draughn Aquatic Center Structure
TO: _______________________________________________________
Gentlemen:
The undersigned, having carefully examined the Bidding Documents, Drawings and Specifications, and all subsequent Addenda as prepared by Walter Robbs Architects, a Michael Graves Company, has visited the site and being familiar with all conditions and requirements of the work, hereby agrees to furnish all labor, materials, equipment, services, and other requirements to complete the following construction:
All to be in accordance with the bidding documents for the following amounts:
BASE BID: Dollars ($ )
Base Bid does not include state or local sales tax; see Paragraph "Taxes" of Instructions To Bidders. Base Bid does include all Cash Allowances and Quantity Allowances described in Section 01200. Base Bid does NOT include Bid Alternates described in Section 01200.
UNIT PRICES:
Should the undersigned be required to perform work over and above that required by the Contract Documents, or should he be ordered to omit work required by the Contract Documents, he will be paid an extra or shall credit the Owner, as the case may be, on the basis of unit prices stated herein, prices quoted being sum total compensation payable or creditable for such items installed and in place, including overhead and profit, general conditions and duration related expenses and all other expenses associated with the work.
Work Unit Price
Excavation and off-site removal of unsuitable soil and replacement of off-site backfill (57 stone) compacted. Cu. Yd. $
LINE ITEM:
Work Price
Cost of Field Verification during Mandatory Site Visit (included in Base Bid). $_____________
BF-2
Addenda have been received as follows:
Addendum No. Date
The undersigned further agrees to sign a Contract for all work in the above amounts, if offered within thirty
(30) days after receipt of Bids, and to furnish surety as specified, and upon failure to do so, agrees to forfeit to the Owner, attached cashier's check, certified check or Bid Bond in the amount of:
$ of Base Bid).
The undersigned further agrees to begin work promptly after a Notice to Proceed with an adequate force, carry the work forward as rapidly as possible and complete the entire Project no later than ____________ consecutive calendar days after the date to begin as specified in the Notice to Proceed.
The undersigned hereby states that he will use the following major subcontractors if awarded the Contract:
Plumbing:
HVAC:
Electrical:
The undersigned agrees that he has executed and submitted with his bid the Statement of Bidder's Qualification which is attached as the last page of this Bid Form.
It is distinctly understood that the Owner reserves the right to reject any and all Bids and to waive informalities and technicalities if considered to be in the best interest of the Owner.
Bidder hereby verifies that he is properly licensed in accordance with North Carolina state laws governing his respective trade and has entered his NC license number on the first page of this Bid Form.
Name of Bidder
By Signature
Title
Date Proposal Executed: , 202___ .
Note: Execute and include "Statement of Bidder's Qualifications" as the last page of this Bid Form.
BF-3
STATEMENT OF BIDDER'S QUALIFICATIONS
1. When was firm organized?
2. When and where was firm incorporated?
3. How many years has firm been engaged in contracting business under its present firm name?
4. Undersigned ( ) is willing ( ) is not willing to furnish a recent Financial Statement if requested to do so by Owner. (Note failure to provide financial information could result in disqualification.)
5. Three projects completed within last five (5) years approximating this project in size and scope.
Owner Type Building: Approx. Cost: Architect
A.
B.
C.
6. Have you ever refused a contract at your original bid?
7. Have you ever defaulted on a contract?
If answer to either 6 or 7 above is yes, explain circumstances on attached sheet.
(This statement must be subscribed and sworn to before a Notary Public.)
Sworn to and subscribed Firm Name:
before me this ____ day By:
of ______________, 202___ Title:
Notary Public
T H
E L
IN
E
S H
O W
N A
B O
V E
I S
E X
A C
T L
Y O
N E
I N
C H
L O
N G
A T
T H
IS
S
H E
E T
S O
R
IG
IN
A
L
P A
G E
S
IZ
E
ORIG SUBMISSION:
CURRENT:
SHEET NAME:
SHEET:
A
B
C
D
E
1 2 3 4 5 6
DATE DESCRIPTION∆
MECHANICAL GENERAL
NOTES AND LEGENDS
-8
V a ld e s e
P a rk s
R e c re a ti o n
D e p a rt m e n t
M a s s e l A v e S
E V a ld e s e
N
C
T O
W N
O F
V A
L D
E S
E
D R
A U
G H
N A
Q U
A T
IC
C
E N
T E
R
S T
R U
C T
U R
E
STRUCTURAL/MEP ENGINEER:
ARCHITECT:
WALTER ROBBS ARCHITECTS,
A MICHAEL GRAVES COMPANY
530 N. Trade Street, Suite 301 Winston Salem, NC 27101 T 336.725.1371
MICHAELGRAVES.COM
MICHAEL
GRAVES
Project Number:
File Name: 240133-M0101
240133
Plotted: 10/18/2024 12:17 PM
CONSULTING
ENGINEERS
7900 Triad Center Drive, Suite 200 Greensboro, NC 27409-9075 t: 336 855 0993
NC License No. F-0508 www.skaeng.com
SKA Consulting Engineers, Inc.
P R
O J
E C
T
2024.09.27
T H
E L
IN
E
S H
O W
N A
B O
V E
I S
E X
A C
T L
Y O
N E
I N
C H
L O
N G
A T
T H
IS
S
H E
E T
S O
R
IG
IN
A
L
P A
G E
S
IZ
E
ORIG SUBMISSION:
CURRENT:
SHEET NAME:
SHEET:
A
B
C
D
E
1 2 3 4 5 6
DATE DESCRIPTION∆
MECHANICAL GENERAL
NOTES AND LEGENDS
-8
V a ld e s e
P a rk s
R e c re a ti o n
D e p a rt m e n t
M a s s e l A v e S
E V a ld e s e
N
C
T O
W N
O F
V A
L D
E S
E
D R
A U
G H
N A
Q U
A T
IC
C
E N
T E
R
S T
R U
C T
U R
E
STRUCTURAL/MEP ENGINEER:
ARCHITECT:
WALTER ROBBS ARCHITECTS,
A MICHAEL GRAVES COMPANY
530 N. Trade Street, Suite 301 Winston Salem, NC 27101 T 336.725.1371
MICHAELGRAVES.COM
MICHAEL
GRAVES
Project Number:
File Name: 240133-M0101
240133
Plotted: 10/18/2024 12:17 PM
CONSULTING
ENGINEERS
7900 Triad Center Drive, Suite 200 Greensboro, NC 27409-9075 t: 336 855 0993
NC License No. F-0508 www.skaeng.com
SKA Consulting Engineers, Inc.
P R
O J
E C
T
2024.09.27
File #
MECHANICAL GENERAL NOTES
240133-M1001.DWG
1. CONTRACTOR SHALL LEAD AND ACHIEVE COORDINATION OF ALL TRADES SO THAT ALL WORK WILL FIT
AND CAN BE PROPERLY INSTALLED BY ALL CONTRACTORS. MECHANICAL CONTRACTOR BE RESPONSIBLE
FOR OBTAINING INFORMATION FROM ALL TRADES TO SHOW LOCATION, SIZES AND COORDINATION ON
OVERLAY SHOP DRAWINGS (SEE SPECIFICATION SECTION 15010 FOR ADDITIONAL REQUIREMENTS).
2. ALL DUCT LAYOUTS ARE GENERALLY DIAGRAMMATIC. CONTRACTOR SHALL VERIFY AVAILABLE SPACE
FOR INDICATED DUCTS BASED ON DETAILED SHOP DWGS. AND MEASUREMENTS AND SURVEYS TAKEN OF
THE FIELD CONDITIONS.
3. ALL PIPE LAYOUTS ARE GENERALLY DIAGRAMMATIC. CONTRACTOR SHALL VERIFY AVAILABLE SPACE FOR
INDICATED PIPES BASED ON DETAILED SHOP DWGS. AND MEASUREMENTS AND SURVEYS TAKEN OF THE
FIELD CONDITIONS.
4. CONTRACTOR SHALL COORDINATE LOCATIONS OF ALL DUCT AND PIPING TO INTERFACE WITH PLUMBING, FIRE PROTECTION, ELECTRICAL, CONTROLS , STRUCTURAL, AND ALL OTHER WORK, EXISTING OR NEW.
SEE MECHANICAL GENERAL PROVISIONS IN SPECS FOR FURTHER DETAILS.
5. COORDINATE DUCTWORK ROUTING AND SIZES WITH PIPING, CONDUIT, STRUCTURES AND OTHER
INTERFERENCES TO AVOID CONFLICTS. IF SIZE MUST BE CHANGED, USE EQUIVALENT FRICTION METHOD
TO SELECT REVISED SIZE.
6. ALL DIMENSIONS ARE SHOWN FOR FREE FLOW AREA IN NEW HVAC DUCTWORK. ADD INSULATION
THICKNESS WHERE REQUIRED TO OBTAIN REQUIRED SHEET METAL DIMENSIONS.
7. WHERE REQUIRED FOR CLEARANCE, PIPING AND CONDUIT SHALL BE INSTALLED BETWEEN LIGHTS AND
UNDER DUCTWORK.
8. TO PROVIDE ADEQUATE CLEARANCE WHERE DUCT CROSSINGS ARE EXTREMELY TIGHT, LOCATE FLANGED
JOINTS AND DUCT REINFORCING SO THAT FLANGES AND REINFORCING OCCUR WHERE ADEQUATE SPACE
IS AVAILABLE.
9. CONTRACTOR SHALL FURNISH AND INSTALL ALL ACCESS DOORS IN DUCTWORK AS REQUIRED FOR FIRE
DAMPERS, CONTROLS, LOCATIONS RECOMMENDED BY SMACNA, AND WHERE REQUIRED BY THE
CONTRACT DRAWINGS AND/OR THE SPECIFICATIONS. ALL ACCESS DOORS REQUIRED MAY NOT BE
SHOWN ON THE DRAWINGS. REFER TO TYPICAL DETAIL FOR SIZING REQUIREMENTS.
10. ACCESS DOORS IN BUILDING FINISHES SHALL BE FURNISHED AND INSTALLED UNDER THE GENERAL
CONSTRUCTION DIVISIONS OF THE SPECIFICATIONS.
11. LOCATE ALL CONTROL VALVES, DAMPERS, AND THE LIKE, IN ACCESSIBLE POSITIONS WITH ADEQUATE
MAINTENANCE CLEARANCE. COORDINATE AND LOCATE DEVICES SO ACCESS IS NOT BLOCKED BY LIGHTS, GRILLES, DUCTWORK, PIPING, STRUCTURE, CONDUIT AND THE LIKE. THE GENERAL CONTRACTOR SHALL
PROVIDE ACCESS DOORS IN WALLS AND NON LAY-IN TYPE CEILINGS AS NECESSARY. THE MECHANICAL
CONTRACTOR SHALL PROMPTLY NOTIFY THE G.C. OF THE SIZE, LOCATION AND TYPE OF ALL ACCESS
DOORS REQUIRED IN BUILDING SURFACES.
12. MAINTAIN A MINIMUM OF 12" CLEARANCE FOR ACCESS TO CONTROLS ON ALL DAMPERS, CONTROL VALVES
AND THE LIKE.
13. MATERIALS, EQUIPMENT AND INSTALLATION SHALL COMPLY WITH ALL REQUIREMENTS OF THE
SPECIFICATIONS. SEE MECHANICAL GENERAL PROVISIONS AND ALL OTHER MECHANICAL SECTIONS.
14. ELBOWS IN ALL DUCTWORK SHALL BE SMACNA SMOOTH RADIUS TYPE. SEE DUCTWORK SPECIFICATIONS.
SQUARE MITERED ELBOWS ARE SHOWN IN MANY PLACES ON THESE DRAWINGS FOR SIMPLICITY OF
DRAFTING, BUT SQUARE MITERED ELBOWS SHALL NOT BE USED EXCEPT WHERE ABSOLUTELY
NECESSARY TO FIT IN A SPECIFIC SITUATION, AND WHERE SPECIFICALLY APPROVED BY THE OWNER'S
REPRESENTATIVE. WHERE SQUARE MITERED ELBOWS MUST BE USED, TURNING VANES SHALL BE
PROVIDED PER SPECIFICATIONS.
15. ALL BRANCH DUCT CONNECTIONS SHALL BE 45° ENTRY TYPE FOR RECTANGULAR DUCTS, TYPICAL
WHETHER SPECIFICALLY INDICATED OR NOT.
16. REFER TO CONTRACT SPECIFICATIONS FOR DUCT CONSTRUCTION PRESSURE CLASSIFICATIONS AND
JOINT SEALING CLASSIFICATIONS, UNLESS OTHERWISE NOTED ON THE DRAWINGS.
17. CONTRACTOR SHALL ADJUST ALL AIR DISTRIBUTION AND BALANCING DAMPERS TO OBTAIN SCHEDULED
OR NOTED AIR FLOW RATES. SEE TESTING AND BALANCING REQUIREMENTS IN SPECIFICATIONS.
18. AIR DISTRIBUTION DEVICES ARE SHOWN APPROXIMATELY LOCATED. CONTRACTOR SHALL COORDINATE
LOCATION WITH LIGHTING AND REFLECTED CEILING PLANS. CONFLICTS AND/OR DEVIATIONS SHALL BE
BROUGHT TO THE ATTENTION OF THE OWNER'S REPRESENTATIVE.
19. EQUIPMENT CONNECTION SIZES, ELEVATION, AND CONFIGURATIONS ARE SUBJECT TO CHANGE WHEN
CERTIFIED VENDOR SHOP DRAWINGS ARE RECEIVED. CONTRACTOR SHALL CHECK CERTIFIED SHOP
DRAWINGS PRIOR TO INSTALLATION OF DUCTWORK AND PIPING, AND SHALL MAKE REQUIRED
ADJUSTMENTS AT NO ADDITIONAL COST TO THE OWNER.
20. EQUIPMENT SELECTIONS SCHEDULED ON THE DRAWINGS AND IN THE SPECIFICATIONS INDICATE A
MINIMUM LEVEL OF ACCEPTABLE PERFORMANCE. SUBSTITUTION OF EQUIPMENT AND MATERIALS SHALL
BE MADE IN ACCORDANCE WITH THE PRIOR APPROVAL CLAUSE LOCATED IN THE MECHANICAL GENERAL
PROVISIONS.
21. ALL PIPE ELEVATIONS ARE TO BOTTOM OF PIPE (NOT INSULATION), UNLESS NOTED OTHERWISE.
22. PROVIDE OFFSETS IN PIPING AS REQUIRED TO PROVIDE FOR THERMAL EXPANSION, PER SPECIFICATIONS.
23. CONTRACTOR SHALL COORDINATE CLOSELY WITH THE GENERAL CONTRACTOR TO VERIFY THAT
ADEQUATE OPENINGS ARE PROVIDED IN THE BUILDING STRUCTURAL SYSTEMS AND SLABS TO ALLOW FOR
INSTALLATION OF MECHANICAL DUCTWORK AND PIPING SYSTEMS.
24. MECHANICAL CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING IN THE FIELD THAT THE MECHANICAL
EQUIPMENT AND DUCTWORK FOR THIS PROJECT HAS BEEN INSTALLED IN SUCH A MANNER THAT
VIBRATIONS WILL NOT BE TRANSMITTED TO THE BUILDING STRUCTURE. THIS SHALL INCLUDE , BUT NOT BE
LIMITED TO, AVOIDING CONTACT BETWEEN DUCTWORK, DUCTWORK SUPPORTS AND CEILING HANGERS, CONDUIT, WALL STUDS OR BRACES, PIPING AND PIPING HANGERS, AND THE LIKE. CEILING GRID SUPPORT
HANGERS SHALL NOT BE SUSPENDED FROM DUCTWORK OR DUCTWORK SUPPORTS.
25. DUCTWORK AND HVAC EQUIPMENT THAT WILL BE SUBJECTED TO RECIRCULATED AIRFLOW SHALL BE
PROTECTED FROM DIRT, DUST AND DEBRIS THAT IS PREVALENT AT THE CONSTRUCTION JOB SITE.
PROVIDE APPROVED PROTECTION WHILE DUCTWORK AND HVAC EQUIPMENT ARE STORED, FABRICATED
AND INSTALLED ON THE JOB SITE.
26. ALL ASPECTS OF THE WORK REQUIRED FOR THIS PROJECT SHALL COMPLY, AS A MINIMUM, WITH THE
PROVISIONS OF ASHRAE 90.1 AND THE NC STATE BLDG. CODE.
27. REFER TO MECHANICAL DRAWINGS FOR LOCATION OF CONTROL POWER SUPPLY. COORDINATE EXACT
LOCATION WITH ELECTRICAL CONTRACTOR.
28. CONTRACTOR SHALL PREPARE, SUBMIT, AND OBTAIN APPROVAL ON SHOP DRAWINGS SHOWING ALL
DUCTWORK, UTILITIES, STRUCTURAL, PIPING, AND OTHER INTERFERENCES BEFORE BEGINNING
INSTALLATION. SEE SPECIFICATIONS FOR DETAILED SHOP DRAWING REQUIREMENTS.
GRILLE OR REGISTER
M
DUCTWORK
20x12
30x12
30x12
DAMPERS
VD
DUCT SECTION, SUPPLY (DIMENSIONS
FOR NET FREE FLOW AREA)
DUCT SECTION, RETURN OR EXHAUST
(DIMENSIONS FOR NET FREE FLOW AREA)
DUCT SIZE (FIRST FIGURE SIDE
SHOWN)(DIMENSIONS FOR NET FREE
FLOW AREA)
THERMOSTAT
POINT OF CONNECTION (NEW TO
EXISTING OR END OF DEMOLITION)
POINT OF DISCONNECTION (START OF
DEMOLITION)
VOLUME
ELECTRIC OPERATED
OPPOSED BLADE
PARALLEL BLADE
SUPPLY
EXHAUST OR RETURN
Dwg.#
SYMBOLS - AIR MOVING DEVICES AND COMPONENTS:
NO SCALE
240133-M1002.DWG
FLEXIBLE CONNECTION
MISCELLANEOUS
HYGROMETER
XXX
TOP
XXX
BOTTOM
INDICATES MOUNTING HEIGHT FROM
FINISHED FLOOR TO THE TOP OF
EQUIPMENT, LOUVER, DUCT, PIPE, ETC.
INDICATES MOUNTING HEIGHT FROM
FINISHED FLOOR TO THE BOTTOM OF
EQUIPMENT, LOUVER, DUCT, PIPE, ETC.
EXISTING PIPING TO BE
REMOVED
EXISTING PIPING TO
REMAIN
GAS
MANUAL THROTTLING
VALVE
SOLENOID OPERATED
VALVE
GATE VALVE
CHECK VALVE
BALL VALVE
BUTTERFLY VALVE
POINT OF CONNECTION
NEW TO OLD
INDICATES EXISTING
INSTRUMENTATION OR
EQUIPMENT TO BE
REUSED.
SYMBOLS - VALVES AND PIPING SPECIALTIES
240133-M1003.DWG
G
S
TOP TAKE OFF
BOTTOM TAKE OFF
ELBOW TURNED UP
ELBOW TURNED DOWN
PIPE CONTINUES
CONCENTRIC REDUCER
ECCENTRIC REDUCER
GENERAL:
THE WORK COVERED IN THE SPECIFICATIONS AND SHOWN ON THE DRAWINGS
CONSISTS IN PROVIDING A COMPLETE SYSTEM INCLUDING LABOR, MATERIALS, ETC.
THE TERM "PROVIDE" USED THROUGHOUT SPECIFICATIONS AND ON DRAWINGS SHALL
MEAN TO "FURNISH, INSTALL AND CONNECT WITH ALL RELATED ACCESSORIES AS
REQUIRED FOR COMPLETE INSTALLATION READY FOR USE."
COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES, LAWS AND REGULATIONS
APPLICABLE TO MECHANICAL, HEATING, VENTILATING AND AIR CONDITIONING
INSTALLATION.
THE ENTIRE INSTALLATION SHALL COMPLY WITH THE REQUIREMENTS OF THE NORTH
CAROLINA STATE BUILDING CODE.
THE CONTRACTOR SHALL PAY ALL INSPECTION FEES AND SHALL INCLUDE THE COST OF
SUCH FEES IN HIS PROPOSAL.
CHECK AND VERIFY WITH THE OWNER, EQUIPMENT SUPPLIERS, AND ALL OTHER
DOCUMENTS FOR THE PROJECT THE EXACT REQUIREMENTS FOR PROVIDING
REQUIRED AND COMPLETE SERVICES FOR EQUIPMENT, SYSTEMS, ETC. AS SHOWN OR
INDICATED. MINOR CHANGES IN PIPE, DUCTS, DIFFUSER, GRILLE OR EQUIPMENT
LOCATIONS MAY BE MADE AT ANY TIME PRIOR TO ROUGHING-IN OF THE MECHANICAL
WORK WITHOUT ANY ADDITIONAL COSTS.
ALL EQUIPMENT SHALL HAVE UL LABEL AS APPLICABLE.
SUBMIT ELECTRONICALLY SUBMITTAL DATA FOR APPROVAL FOR ALL MATERIALS AND
EQUIPMENT. PRIOR TO SUBMITTAL, THE CONTRACTOR SHALL STAMP ALL SHOP
DRAWINGS AND SUBMITTAL DATA AS "APPROVED", INDICATING FULL COMPLIANCE WITH
THE DRAWINGS AND SPECIFICATIONS. SHOP DRAWINGS AND SUBMITTAL DATA WILL
NOT BE REVIEWED WITHOUT THE "APPROVED" STAMP.
SHOP DRAWINGS AND SUBMITTAL DATA SHALL BE CLEARLY MARKED WITH EQUIPMENT
SIZES, CAPACITIES, ETC. INDICATED FOR THE PROJECT. INDICATE CLEARLY THE EXACT
REQUIREMENTS FOR ACCESS FOR SERVICE AND MAINTENANCE AND MINIMUM
CLEARANCES FOR COMPLIANCE WITH ALL APPLICABLE CODES. ALL SHOP DRAWINGS
SHALL BE SUBMITTED AS SOON AS POSSIBLE AFTER AWARD OF THE CONTRACT.
FURNISH TO THE OWNER TWO (2) SETS OF MARKED UP MECHANICAL, HEATING AND AIR
CONDITIONING PRINTS WITH ALL DEVIATIONS AND CORRECTIONS SHOWING THE
AS-BUILT AND DIMENSIONED, IF NECESSARY, LOCATIONS, ELEVATIONS, ETC. OF ALL
PIPING, EQUIPMENT, DUCTS, VALVES, ETC., UNDERGROUND, IN WALLS, ABOVE CEILINGS
AND OTHERWISE CONCEALED, WHICH WILL REQUIRE SERVICE AND MAINTENANCE.
FURNISH, PLACE AND GROUT NEATLY IN PLACE SCHEDULE 40 BLACK STEEL PIPE
SLEEVES FOR PIPING, CONDUITS, ETC., RUN DIRECTLY BELOW WALL FOOTINGS,
THROUGH ALL SLABS, ETC. EXTEND VERTICAL SLEEVES IN SLABS MINIMUM 1" ABOVE
FINISHED FLOOR AND CAULK WATERTIGHT BETWEEN SLEEVE AND SLAB, AND BETWEEN
EACH PIPE AND SLEEVE.
EXECUTION:
INSTALL THE PACKAGED ROOFTOP AIR CONDITIONING UNITS IN ACCORDANCE WITH THE
MANUFACTURER'S RECOMMENDATIONS.
MAINTAIN REQUIRED VERTICAL AND LATERAL CLEARANCES FOR PROPER PERFORMANCE,
SERVICE ACCESS, MAINTENANCE AND SAFETY.
ALL PENETRATIONS SHALL BE SEALED VERMIN PROOF AND MOISTURE TIGHT.
TEST AND OBTAIN SPECIFIED PERFORMANCE AS REQUIRED IN ACCORDANCE WITH THE
MANUFACTURER'S RECOMMENDATIONS.
ADJUST AS NECESSARY TO OBTAIN REQUIRED PERFORMANCE.
GAS PIPING:
GAS PIPE AND PIPE NIPPLES SHALL BE ANSI/ASTM A-312, SEAMLESS, STANDARD WEIGHT,
STAINLESS STEEL, THREADED AND COUPLED.
THREADED FITTINGS SHALL COMPLY WITH ANSI B1.20.1.
BELOW GRADE GAS PIPING SHALL BE SDR-11 MDPE GAS PIPE. PROVIDE WARNING TAPE
AND TRACER WIRE. GAS PIPING SHALL BE 24" BELOW GRADE.
VALVES SHALL BE BALL TYPE STAINLESS STEEL BODY MATCHING PIPING GRADE.
ALL GAS PIPING SHALL BE LABELED AS "NATURAL GAS".
CONNECTIONS TO EQUIPMENT SHALL INCLUDE DIRT LEG.
ELECTRICAL WORK:
POWER WIRING UP TO AND INCLUDING JUNCTION BOXES, DISCONNECT SWITCHES, ETC.
AS INDICATED, WILL BE PROVIDED BY THE ELECTRICAL CONTRACTOR AT LOCATIONS AS
SHOWN. WIRING, CONDUITS AND CONNECTIONS FROM LOAD SIDE OF DISCONNECT
SWITCHES, JUNCTION BOXES, ETC. TO EQUIPMENT TERMINALS, AND TEMPERATURE
CONTROL AND INTERLOCK WIRING, SHALL BE INCLUDED IN THE MECHANICAL CONTRACT.
CLEANING, PAINTING:
CLEAN ALL PIPING, HANGERS, DUCTWORK, GRILLES, DIFFUSERS, EQUIPMENT, ETC. AND
LEAVE READY FOR USE. PAINT NEW GAS PIPING OUTSIDE THE BUILDING RUN AT WALL
AND ABOVE ROOF. COLOR TO BE SAFETY YELLOW.
GUARANTEE:
REFER TO GENERAL CONDITIONS OF THE CONTRACT FOR CONTRACT COMPLETION AND
WARRANTY REQUIREMENTS. GUARANTEE ALL MATERIALS, EQUIPMENT AND
WORKMANSHIP FOR ONE YEAR FROM THE DATE OF FINAL ACCEPTANCE BY OWNER AS
STATED IN WRITING, EXCEPT REFRIGERATION COMPRESSORS WHICH SHALL HAVE
ADDITIONAL 4 YEAR EXTENDED GUARANTEE. REPAIR AND/OR REPLACE, WITHOUT ANY
COST TO THE OWNER, ANY DEFECTIVE PART OR PARTS OF THE WORK WITHIN THE
GUARANTEE PERIOD FROM THE TIME THE SYSTEM IS PUT INTO OPERATION AS
DETERMINED BY THE DATE OF FINAL CERTIFICATE OF PAYMENT WITH EXCEPTIONS AS
NOTED.
PROVIDE PERIODICAL INSPECTION AND ADJUSTMENT SERVICE THROUGHOUT THE
GUARANTEE PERIOD.
Dwg.#
MECHANICAL SPECIFICATIONS
240133-M1004.DWG
4COORDINATE WITH FABRIC ENCLOSURE PROVIDER FOR VENT PENETRATION
REQUIREMENTS.
BURNER BOX. SEE MANUFACTURER SPECIFICATIONS AND INSTRUCTIONS.
INFRARED HEATER CHAIN SUPPORT ATTACHED TO BLDG. STRUCTURAL
SYSTEM. SEE MANUFACTURER INSTALLATION DETAILS.
INFRARED HEATER .
Dwg.#
TYPICAL INFRARED HEATER
INSTALLATION DETAIL
NO SCALE
240133-M7001.DWG
M1.1
4"Ø
ELEVATION "A"
Dwg.#
KEY NOTES:
240133-M7001.DWG
30.0°
4"Ø
4"Ø
Dwg.#
EXHAUST
SYSTEM CONTROL DIAGRAM
NO SCALE
240133-M7002.DWG
M1.1
EC
EC
120 VAC
EC
EC
M
DS
EXHAUST
DAMPER
FAN SHALL BE MANUALLY SWITCHED.
Dwg.#
KEY NOTES:
240133-M7002.DWG
T
INFRARED HEATER CONTROLS
240133-M7003.DWG
M1.1
EXHAUST INTAKE
G HEATER
CONTROLS
DS FWE
EC
120 VACDwg.#
NOTES:
240133-M7003.DWG
1. SEE PLANS FOR TEMPERATURE SENSOR LOCATIONS.
2. MULTIPLE HEATERS TO BE CONTROLLED BY SINGLE THERMOSTAT.
TOTAL GAS LOAD
1350 CFH @ 2 PSI
400' TOTAL DEVELOPED LENGTH - SCHEDULE 40 METALLIC
Dwg.#
GAS SYSTEM DIAGRAM
NO SCALE
240133-M7004.DWG
M1.1
HP U.G. GAS SUPPLY.
EXISTING
GAS METER
M
3/4"
IRH
150 CFH
IRH
150 CFH
3/4"
IRH
150 CFH1-1/4"
3/4"
3/4"
3/4"
IRH
150 CFH
3/4"
IRH
150 CFH
3/4"
IRH
150 CFH
3/4"
IRH
150 CFH
3/4"
IRH
150 CFH
3/4"
IRH
150 CFH
1-1/4"
1. PIPING RUNOUTS TO EQUIPMENT SHALL TEE INTO THE TOP OF GAS MAINS AS SHOWN.
2. GAS COCKS SHALL BE INSTALLED UPSTREAM OF DIRT LEGS.
3. COORDINATE W/EQUIPMENT MANUFACTURER FOR REGULATOR REQUIREMENTS.
4. VENT LINE TERMINATION SHALL BE TURNED DOWN AND PROVIDED WITH INSECT SCREEN PER N.C.
CODE REQUIREMENTS.
5. GAS PIPING SHALL BE PRIMED AND PAINTED SAFETY YELLOW.
6. PROVIDE INDIVIDUAL VENT LINES FROM EACH INDOOR REGULATOR. DO NOT COMBINE VENTS FROM
REGULATORS.
7. GAS PRESSURE REGULATOR BY MECHANICAL CONTRACTOR EXCEPT WHERE REGULATOR IS
RELOCATED W/ EQUIPMENT.
GAS MAIN (2 PSIG)
6" MIN. DIRT LEG
GAS REGULATOR
GROUND JOINT UNION
GAS DUTY ISOLATION
VALVE (INST. WITHIN 6' OF
UNIT CONNECTION)
Dwg.#
TYPICAL CONNECTION TO
GAS-FIRED EQUIPMENT
NO SCALE
240133-M8001.DWG
M1.1
Dwg.#
NOTES:
240133-M8001.DWG
1 10/18/24 ADDENDUM 1
| 000020 TOC 24-858-(ADDENDUM #1) |
| 000030 Advertisement for Bids (ADDENDUM #1)24-858- |
| 000060 Bid Form (ADDENDUM #1)24-858 |
| 15M_001_M0101_24-858_20241018 |