2024-107 - Morgan CC Wray Campus T.I. Addendum #2.pdf
PDF 98 KB Posted
- Attached to
- 2024-107 Wray Facility Renovation
- Solicitation number
- 2024-107
- Issued by
- Ouray County, Weston CDP, Colorado
About this file
This document is an Addendum #2 for the Morgan Community College Wray Campus Tenant Improvement (T.I.) project, numbered 2024-107, issued by Architectural Workshop on March 25, 2025. The addendum updates Specification Section 01 03 00 to reflect current add alternates for the renovation project. The add alternates include two specific modifications: Add Alternate #1 involves removing existing faux CMU and metal paneling on the west, north, and south building sides, installing a new metal panel system, replacing soffit can lights with linear recessed fixtures, and adding a new window over door 011. Add Alternate #2 focuses on similar paneling removal and metal panel system installation on the east side of the building.
The specification details the process for evaluating and selecting alternates, emphasizing that alternates will be considered in determining the lowest responsible bidder. The document outlines that additive alternates will be added to the base bid in numerical order, subject to available funding. If the total bid exceeds available funds, the project retains the right to reject all bids or adjust the contract by adding or removing alternates. The alternates are designed to provide flexibility in project scope and budget, allowing the college to potentially expand or contract the renovation work based on available resources and bidder proposals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
architectural
WORKSHOP
2024-107 Morgan CC Wray Campus T.I. – Addendum #2
March 25, 2025
Part 1: Additional Revisions to Drawings and Specifications:
R1 - Specification section 01 03 00 has been updated to reflect current add alternates.
See attached.
END OF ADDENDUM 2
Morgan Community College Wray Campus T.I.
Project #: 2024-107
ALTERNATES 01 03 00 - 1
SECTION 01 03 00
ALTERNATES
PART 1 - GENERAL:
1.1 DESCRIPTION OF REQUIREMENTS:
A. Deductible Alternates: Deductible alternates, if used in determining the lowest responsible bidder, shall be deducted from the base bid of each bidder in the numerical order listed to the extent that the deduction of alternates results in a total within available funds to finance the project.
B. Additive Alternates: The lowest responsible bid, taking into account the Colorado resident bidder preference provision of Colorado Law which is hereinafter set forth in Article 48 of the General Conditions, will be determined by and the Contract will be awarded on the base bid plus all additive alternates, to the extent that the addition of alternates results in a sum total within available funds to finance the Contract. If this bid exceeds such amount, the right is reserved to reject all bids. Additive alternates will be used in determining the lowest responsible bidder within the amount available to finance the contract, added in the numerical order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the Contract for purposes of determining the lowest responsible bidder.
C. Deductible and Additive Alternates: The lowest responsible bid, taking into account the
Colorado resident bidder preference provision of Colorado law which is hereinafter set forth in Article 48 of the General Conditions, will be determined by and the Contract will be awarded on the base bid plus all additive alternates, to the extent that the addition of alternates results in a sum total within available funds to finance the Contract, added in the numerical order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the Contract for purposes of determining the lowest responsible bidder.
D. If this bid exceeds the funds available to finance the Contract, the right is reserved to reject all bids or award the Contract on the base bid combined with deductible alternates, deducted in numerical order in which they are listed in both the Architect/Engineer's Specification and the Proposal, to produce a net amount which is within the available funds. Additive alternates will not be used if deductible alternates are used an deductible alternates will not be used if additive alternates are used.
1.2 GENERAL ALTERNATE REQUIREMENTS:
A. General: The description for each alternate is recognized to be incomplete and abbreviated but implies that each change must be complete for the scope of work affected. Refer to applicable sections and to applicable drawings for the specific requirements of the Owner, whether or not references are so noted in the description of each alternate. Modify surrounding work as required to integrate with the work of each alternate.
PART 2 - PRODUCTS
Not Used.
PART 3 - EXECUTION
Morgan Community College Wray Campus T.I.
Project #: 2024-107
ALTERNATES 01 03 00 - 2
3.1 SCHEDULE OF ALTERNATES:
A. Add Alternates:
Add Alternate #1: Remove the existing faux CMU paneling and existing metal paneling.
Then install new metal panel system on the west, north, and south sides of the building.
Replace the existing can lights in the soffits with new linear recessed fixtures. Install a new window over door 011.
Add Alternate #2: Remove the existing faux CMU paneling and existing metal paneling.
Then install new metal panel system on the east side of the building.
END OF SECTION 01 03 00