This document outlines specifications for maintenance dredging of Bradford Bay Channel and Finney Creek in Virginia. Key requirements include dredging the channels to a depth of -7 feet MLLW with 1 foot of allowable overdepth using a hydraulic cutterhead dredge with pump-out to an existing placement site. The contractor must develop a quality control plan and activity hazard analyses, and designate a site safety and health officer. The contractor will be responsible for safety training and permitting requirements. Dredging must be completed by the contract completion date while meeting regulatory and technical specifications for dredging depths, side slopes, and disposal locations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WCV Bradford Bay and Finney Creek Maintenance Dredging FY24WCV
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15 SUMMARY OF WORK
01 22 00 05/08 MEASUREMENT AND PAYMENT
01 30 00 08/08 ADMINISTRATIVE REQUIREMENTS
01 32 01 08/08 PROJECT SCHEDULE
01 33 00 05/11 SUBMITTAL PROCEDURES
01 35 26 02/10 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 08/10 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 02/10 QUALITY CONTROL
01 45 10 02/10 QUALITY CONTROL SYSTEM (QCS)
01 57 20 04/06 ENVIRONMENTAL PROTECTION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 05/08 DREDGING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
DRAFT - N
OT FOR SOLIC
ITATIO
N
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
DRAFT - N
OT FOR SOLIC
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The maintenance dredging work for Waterways on the Coast of Virginia consists of removal of shoaling within the Bradford Bay and Finney Creek by use of a hydraulic cutterhead dredge with pump-out to the existing placement site located in Bradford Bay as indicated in the plans. Dredging will be completed to a depth of -7 feet NOS MLLW 83-01 NTDE, with one (1) foot of allowable overdepth.
1.1.2 Location
The work is located within Bradford Bay and Finney Creek on the Eastern Shore of Virginia.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
DRAFT - N
OT FOR SOLIC
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
05/08
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Payment Item No. 0001 Mobilization and Demobilization
1.2.1.1 Mobilization
1.2.1.2 Demobilization
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Payment Item No. 0002 Dredging Bradford Bay Channel and Finney
Creek (-7 feet MLLW)
1.4 DREDGING MEASUREMENT
1.5 MISPLACED MATERIAL
1.6 EXCESSIVE DREDGING
1.7 MONTHLY PARTIAL PAYMENTS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00 Page 1
DRAFT - N
OT FOR SOLIC
SECTION 01 22 00
MEASUREMENT AND PAYMENT
05/08
PART 1 GENERAL
1.1 SUBMITTALS
Not Used.
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BID SCHEDULE and described below.
All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Payment Item No. 0001 Mobilization and Demobilization
All costs connected with the mobilization and demobilization of all of the Contractor's dredging plant and equipment as defined below will be paid for at the contract lump sum price for this item. Sixty percent of the lump sum price will be paid to the Contractor upon completion of his mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.
1.2.1.1 Mobilization
Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging operations. This shall include as a minimum the following:
a. Transfer of dredge and attendant plant, barges and scows, and other like equipment and machinery.
b. All mobilization, setup, connecting, positioning, and storage of any discharge pipeline and appurtenances.
c. All costs for any other associated work that is necessary in
SECTION 01 22 00 Page 2
DRAFT - N
OT FOR SOLIC
advance of the actual dredging operations.
1.2.1.2 Demobilization
Demobilization shall include general preparation for transfer of plant to its home base.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Payment Item No. 0002 Dredging Bradford Bay Channel and Finney Creek (-7 feet
MLLW)
This work shall include maintenance dredging of Bradford Bay Channel and Finney Creek, as shown in the plans, to a depth of -7 feet MLLW with 1 foot of allowable overdepth. Placement of material shall be at the overboard placement site located within Bradford Bay.
1.4 DREDGING MEASUREMENT
For the dredging line item, payment to be made for all costs associated with dredging shall include the cost of removal, transportation and disposal of dredged material in the placement area, exclusive of the mobilization and demobilization as defined above. The total amount of material removed and to be paid for under this payment item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed. The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of SECTION 35 20 23, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below. The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken immediately before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work. Computations for payment purposes will be made by the Government for the scheduled dredging using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations. Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except
SECTION 01 22 00 Page 3
DRAFT - N
OT FOR SOLIC
on evidence of collusion, fraud, or obvious error.
1.5 MISPLACED MATERIAL
Any material that is deposited elsewhere than in places designated or approved by the Contracting Officer will not be paid for, and the Contractor may be required to remove such misplaced material and deposit it where directed by the Contracting Officer at the Contractor's expense.
1.6 EXCESSIVE DREDGING
Material taken from outside the specific areas to be dredged or beyond the limits as extended in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" will be considered as excessive overdepth dredging, or excessive side slope dredging, for which payment will not be made.
Nothing in these specifications shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of Paragraphs SHOALING and FINAL EXAMINATION AND ACCEPTANCE of Section 35 20 23.
1.7 MONTHLY PARTIAL PAYMENTS
Monthly partial payments will be based on estimated quantities determined by the Contracting Officer.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 22 00 Page 4
DRAFT - N
OT FOR SOLIC
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/08
PART 1 GENERAL
1.1 PRECONSTRUCTION CONFERENCE
1.1.1 Scheduling
1.1.2 Purpose
1.1.3 Discussion Items
1.2 1.3 OTHER MEETINGS DURING THE CONTRACT
1.3 MINUTES OF MEETINGS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 30 00 Page 1
DRAFT - N
OT FOR SOLIC
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/08
PART 1 GENERAL
1.1 PRECONSTRUCTION CONFERENCE
1.1.1 Scheduling
After award of the construction contract and prior to the start of any construction work, the Contracting Officer's Representative (COR) will schedule and conduct an initial preconstruction conference. Subsequent preconstruction conferences will be required and scheduled by the COR prior to the start of any construction work. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend these meetings. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors and major construction work divisions at the conferences. The conferences will be held at a location and time as specified by the COR.
1.1.2 Purpose
The purpose of this preconstruction conferences is to enable the COR to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, and other similar matters. The COR may invite other Government personnel involved in the work to attend this conference.
1.1.3 Discussion Items
The following is a sample list of items for discussion during the preconstruction conference; however, the Contracting Officer's Representative may modify this list or include additional items for discussion as conditions and the work require.
a. Authority of the Contracting Officer/Contracting Officer's Representative.
b. Contractor's Progress Schedule.
c. Correspondence Procedures.
d. Contractor Labor Standards Provisions.
e. Contract Modifications and Administrative Procedures.
f. Contractor's Administrative, Laydown and Storage Areas.
g. Procedures for Processing Submittals.
SECTION 01 30 00 Page 2
DRAFT - N
OT FOR SOLIC
h. Payment Estimate Data and Procedures.
i. Contractor Utilities.
j. Security Requirements and Other Regulations, if applicable.
k. Government Furnished Equipment, if applicable.
l. Disposition of Salvage Property, if applicable.
m. Contractor Insurance Requirements.
n. Environmental Protection Plan.
o. Contractor Performance Evaluation.
p. Emergency and Safety Procedures.
q. Plant and Suitability to Perform the Work.
r. Turnover of Placement Areas After Dredging.
s. Contractor Required Notification Procedures.
t. Contractor's Submittal Register.
u. Contractor's Survey and Information Reporting Procedures.
v. Bench mark descriptions for the project
w. Contractor's Quality Control Plan and Activity Hazard Analysis.
1.2 1.3 OTHER MEETINGS DURING THE CONTRACT
Other meetings may be held after the Preconstruction Conference, for the purpose to discuss concerns and deficiencies that may include the following:
a. Contractor's Site Safety and Health Plan.
b. Quality Control Plan.
c. Environmental Protection Plan.
d. Progress Schedule updates.
1.3 MINUTES OF MEETINGS
The Government will prepare minutes of all meetings.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 30 00 Page 3
DRAFT - N
OT FOR SOLIC
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
08/08
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY ASSURANCE
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Approved Project Schedule
3.1.2 Schedule Status Reports
3.1.3 Default Terms
3.2 BASIS FOR PAYMENT AND COST LOADING
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 PROGRESS SCHEDULE FORMAT
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Procurement Activities
3.3.2.3 Critical Activities
3.3.2.4 Government Activities
3.3.2.5 Definable Features of Work Coding (FOW1, FOW2, FOW3)
3.3.3 Scheduled Project Completion and Activity Calendars
3.3.3.1 Project Start Date
3.3.3.2 Schedule Constraints and Open Ended Logic
3.3.3.3 Early Project Completion
3.3.4 Milestones
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Project Schedule Submission
3.4.2 Periodic Schedule Updates
3.4.3 Standard Activity Coding Dictionary
3.5 OWNERSHIP OF FLOAT
-- End of Section Table of Contents --
SECTION 01 32 01 Page 1
DRAFT - N
OT FOR SOLIC
SECTION 01 32 01
PROJECT SCHEDULE
08/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
The Contractor CQC representative shall be responsible for the preparation and certification as complete all required project Progress Schedule submittals and reports.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design (if any) and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
SECTION 01 32 01 Page 2
DRAFT - N
OT FOR SOLIC
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment.
Lack of an approved schedule update, or qualified scheduling personnel, may result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The Contractor shall submit his Progress Schedule to the Contracting Officer for approval at the Pre-Construction Conference specified in SECTION ADMINISTRATIVE REQUIREMENTS. The Progress Schedule shall be submitted and certified as complete by the Contractor's Quality Control Representative in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed, arrival date of Contractor's plant to the job site, all activities
SECTION 01 32 01 Page 3
DRAFT - N
OT FOR SOLIC
scheduled prior to dredging, dredging start and completion dates, calendar days to completion of all work, and contract completion date.
The Contractor shall indicate on the chart the important work activities that are critical to the timely overall completion of the project. Key dates for important features or portions of work features are milestone dates and shall be so indicated on the chart.
3.3.1 PROGRESS SCHEDULE FORMAT
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule and prepare the Project Schedule using the Precedence Diagram Method (PDM) OR prepare the Progress Schedule in the form of a Gantt Chart.
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval.
The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies as applicable. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Critical Activities
The following activities shall be listed as separate line activities on the Contractor's Project Schedule and may be submitted on a separate sheet. This list represents a partial lists and is not considered complete:
a. Submission and approval of Accident Prevention Plan.
b. Submission and approval of pipeline Routing.
c. Submission and approval of Quality Control Plan.
d. Coast Guard Notification , VMRC, and VADEQ notification.
e. Submittal of current marine plant certification and recent plant inspection.
f. Submission and approval of List of Floating Plant
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to:
a. Government surveys for payment
SECTION 01 32 01 Page 4
DRAFT - N
OT FOR SOLIC
b. Required Contractor submittals for Government approval
c. Inspections required by the contract.
3.3.2.5 Definable Features of Work Coding (FOW1, FOW2, FOW3)
Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00 QUALITY CONTROL. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.
3.3.3 Scheduled Project Completion and Activity Calendars
The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor.
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities: Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event the project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
SECTION 01 32 01 Page 5
DRAFT - N
OT FOR SOLIC
3.3.4 Milestones
The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for mobilization complete (including initial installation of pipeline);
dredging complete.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below.
3.4.1 Project Schedule Submission
Submit the initial Project Schedule, defining the Contractor's planned operations for approval within 15 calendar days after the NTP is acknowledged. The approved Project Schedule will be used for payment purposes . Cost load the Project Schedule to balance the contract award Contract line item numbers (CLINS) shown on the Price Schedule. The initial Project Schedule must include all of the required Plan and Program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan)
3.4.2 Periodic Schedule Updates
Submit periodic schedule updates monthly with requests for progress payment. These submissions will assist the Contracting Officer in assessing the Contractor's progress. Update the percent complete for each activity started, based on the realistic assessment of work completed. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgment of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.
3.4.3 Standard Activity Coding Dictionary
If a CPM/PDM system is used for the Project Schedule, the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 , Appendix A is acceptable; however, since the Resident Engineer Management System (RMS) will not be used for this contract, this structure is not mandatory. A template SDEF compatible schedule backup file (sdef.prx) is available on the QCS website: http://rms.usace.army.mil/ .
3.5 OWNERSHIP OF FLOAT
Float available in the schedule, at any time, shall not be considered for the exclusive use of either the Government or the Contractor.
-- End of Section --
SECTION 01 32 01 Page 6
DRAFT - N
OT FOR SOLIC
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved G
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
1.6.2 Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
1.6.3 Number of Samples SD-04 Samples
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's
Field Reports
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED/ACCEPTED SUBMITTALS
1.14 WITHHOLDING OF PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
DRAFT - N
OT FOR SOLIC
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
DRAFT - N
OT FOR SOLIC
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer's Representative (COR) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications; warranties;
and other such required submittals.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Certificates of insurance
Surety bonds
List of proposed Subcontractors
Construction Progress Schedule
Submittal register
Health and safety plan
Quality Control(QC) plan
Environmental protection plan
SD-06 Test Reports
SECTION 01 33 00 Page 3
DRAFT - N
OT FOR SOLIC
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Daily logs and checklists.
SD-07 Certificates
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements.
Special requirements necessary to properly close out the dredging contract. For example, Record Drawings, as-built drawings or surveys, if applicable. on a
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals , except those SD-01 Pre-Construction Submittals noted above , construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved G
Within the terms of the Contract Clause entitled, "Specifications and
SECTION 01 33 00 Page 4
DRAFT - N
OT FOR SOLIC
Drawings for Construction," they are considered to be "shop drawings."
1.4.2 Information Only
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION
1.5.1 Transmittal Form
Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. . Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
If required,submit three copies of submittals of shop drawings requiring review and approval only by QC organization and five copies of shop drawings requiring review and approval by Contracting Officer.
1.6.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
NOT REQUIRED
1.6.3 Number of Samples SD-04 Samples
NOT REQUIRED
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
NOT REQUIRED
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
NOT REQUIRED
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
Unless otherwise specified, submit two sets of administrative submittals.
1.7 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval
SECTION 01 33 00 Page 5
DRAFT - N
OT FOR SOLIC
of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.8.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.8.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
SECTION 01 33 00 Page 6
DRAFT - N
OT FOR SOLIC
1.9 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00 QUALITY CONTROL SYSTEM
(QCS).
1.9.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
1.9.2 Contractor Use of Submittal Register
Update the following fields in the submittal register with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.9.3 Approving Authority Use of Submittal Register
Update the following fields in the submittal register utilized by Contractor].
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.9.4 Copies Delivered to the Government
If revisions have been made to the submittal register since the previous invoice submission, deliver one copy of submittal register updated by
SECTION 01 33 00 Page 7
DRAFT - N
OT FOR SOLIC
Contractor to Government with each invoice request; otherwise, resubmission of the submittal register is not required with each invoice.
1.10 SCHEDULING
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates when changes are made to the register.
When all items on the register have been fully approved, no further re-submittal is required.
1.11 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. One copy of the approved submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.
1.11.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until
SECTION 01 33 00 Page 8
DRAFT - N
OT FOR SOLIC
resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.12 DISAPPROVED SUBMITTALS
Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.13 APPROVED/ACCEPTED SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 WITHHOLDING OF PAYMENT
Payment for any part of the scheduled work accomplished by the Contractor, including transportation of the Contractor's plant to or from the site of the work, will not be made if required approvals for all parts of the scheduled work have not been obtained.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 9
DRAFT - N
OT FOR SOLIC
-- End of Section --
SECTION 01 33 00 Page 10
DRAFT - N
OT FOR SOLIC
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
02/10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 REGULATORY REQUIREMENTS
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer (SSHO)
1.5.1.1.1 1.6.1.1.6 SSHO Staffing for USACE Dredging Contracts
1.5.1.1.2 SSHO Requirements for Dredging
1.5.1.1.3 Designated Representative (DR) Requirements for
Dredging
1.5.1.1.4 Safety Personnel Training Requirements for Dredging
1.5.1.2 Crane Operators
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer (SSHO)
1.5.3 Meetings
1.5.3.1 Preconstruction Conference
1.6 ACCIDENT PREVENTION PLAN (APP)
1.6.1 EM 385-1-1 Contents
1.7 ACTIVITY HAZARD ANALYSIS (AHA)
1.8 DISPLAY OF SAFETY INFORMATION
1.9 SITE SAFETY REFERENCE MATERIALS
1.10 EMERGENCY MEDICAL TREATMENT
1.11 REPORTS
1.11.1 Accident Reports
1.11.2 Accident Notification
1.11.3 Crane Reports
1.12 HOT WORK
1.13 SEVERE STORMS
1.14 CONFINED SPACE ENTRY REQUIREMENTS.
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
3.1.1 Hazardous Material Exclusions
3.1.2 Unforeseen Hazardous or Otherwise Environmentally Harmful
Material
3.2 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
3.3 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
3.3.1 Training
3.3.2 Fall Protection Equipment and Systems
SECTION 01 35 26 Page 1
DRAFT - N
OT FOR SOLIC
3.3.2.1 Personal Fall Arrest Equipment
3.3.3 Existing Anchorage
3.3.4 Horizontal Lifelines
3.3.5 Guardrails and Safety Nets
3.3.6 Rescue and Evacuation Procedures
3.4 EQUIPMENT
3.4.1 Material Handling Equipment
3.4.2 Weight Handling Equipment
3.5 EXCAVATIONS
3.5.1 Utility Locations
3.5.2 Utility Location Verification
3.5.3 Shoring Systems
3.5.4 Trenching Machinery
3.6 ELECTRICAL
3.6.1 Conduct of Electrical Work
3.6.2 Portable Extension Cords
3.7 WORK IN CONFINED SPACES
3.8 DIVING OPERATIONS
3.8.1 General
3.8.2 Phase Meetings
-- End of Section Table of Contents --
SECTION 01 35 26 Page 2
DRAFT - N
OT FOR SOLIC
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
02/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.32 (2013) Fall Protection
ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE Z359.1 (2016) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components
ASME INTERNATIONAL (ASME)
ASME B30.22 (2016) Articulating Boom Cranes
ASME B30.5 (2014) Mobile and Locomotive Cranes
ASME B30.8 (2015) Floating Cranes and Floating Derricks
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018) Standard for Portable Fire Extinguishers
NFPA 70 (2017; TIA 11-1; Errata 2011) National Electrical Code
NFPA 70E (2018) Standard for Electrical Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014)Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1926 Safety and Health Regulations for
SECTION 01 35 26 Page 3
DRAFT - N
OT FOR SOLIC
Construction
29 CFR 1926.500 Fall Protection
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Government acceptance is required for submittals with a "G, A" designation.
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G, A
Activity Hazard Analysis (AHA); G, A
Crane Critical Lift Plan; G, A
Proof of qualification for Crane Operators; G, A
SD-06 Test Reports
Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."
Accident Reports
Crane Reports
SD-07 Certificates
Confined Space Entry Permit
Hot work permit
1.3 DEFINITIONS
a. High Visibility Accident. Any mishap which may generate publicity and/or high visibility.
b. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
c. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
SECTION 01 35 26 Page 4
DRAFT - N
OT FOR SOLIC
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work (any time lost after day of injury/illness onset);
(3) Restricted work;
(4) Transfer to another job;
(5) Medical treatment beyond first aid;
(6) Loss of consciousness; or
(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.
d. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.
1.4 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1 , and all federal, state, and local, laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer (SSHO)
The contractor shall provide a Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Safety and Health Officer (SSHO). The SSHO shall be at the work site at all times, unless specified differently in the contract, to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, and their training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17 and all associated sub-paragraphs. A Competent Personal shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. The credentials of the Competent Persons(s) shall be approved by the Contracting Officer in consultation with the Safety Office.
1.5.1.1.1 1.6.1.1.6 SSHO Staffing for USACE Dredging Contracts
a. Dredging contracts may include several project sites; this contract will require a minimum of one full-time SSHO assigned per project site.
SECTION 01 35 26 Page 5
DRAFT - N
OT FOR SOLIC
SSHO may be collateral duty in specific conditions listed below.
b. Example of one dredging project site is reflected in the…