2022-26 Addendum No. 1
158 KB Posted
- Attached to
- Thompson Road Sewer Replacement
- Solicitation number
- 2022-26
- Issued by
- Henry County, Georgia
About this file
This is Addendum No. 1 to the bid solicitation for the Thompson Road Sewer Replacement project issued by the City of Perry, Georgia. The project involves the installation of 1,800 linear feet of 12-inch gravity sewer main along with associated manholes, bores, services, and accessories. The addendum revises the bid submission deadline from the originally scheduled date of Tuesday, May 24, 2022 at 10:15 a.m. to Tuesday, June 7, 2022 at 10:15 a.m., with bids to be received at Perry City Hall, 1211 Washington Street, Perry, GA 31069. A non-mandatory pre-bid meeting was scheduled for Tuesday, May 10, 2022 at 10:00 a.m. at the same location. The project will be awarded as a single contract with substantial completion required within 90 consecutive calendar days from the Notice to Proceed and final completion within 120 consecutive calendar days. The project is managed by GWES, LLC., located at 733 Carroll Street, Perry, GA 31069, telephone (478) 235-0307.
Bidders must obtain contract documents, including plans, specifications, and bid forms, for a non-refundable fee of $200 from GWES, LLC. Each bid must be accompanied by a Bid Bond or certified cashier's check equal to 10 percent of the base bid, with the surety company licensed to do business in Georgia and carrying a minimum "A" rating with financial strength at least five times the contract price. Bidders must affix their Georgia Utility Contractor License Number to the outside of the bid envelope; bids without this license number will not be opened. Bidders are required to submit E-Verify documentation with their bid to be deemed responsive. The contractor must acquire all necessary Federal, State, and local permits prior to the Notice to Proceed, while the City of Perry will acquire all necessary easements and rights-of-way. Bids may not be withdrawn for sixty days following the closing time for bid receipt. The City reserves the right to reject any or all bids and to waive informalities.
Text of this file
ADDENDUM NO. 1
For The
THOMPSON ROAD SEWER REPLACEMENT
CITY OF PERRY
Item No. 1
Specifications, Section 00100 – Invitation to Bid, Revised
The bid date for this project is changed to Tuesday, June 7, 2022 at 10:15 a.m. The revised Invitation to Bid is included as part of this addendum.
May 16, 2022
Engineer of Record Date
CITY OF PERRY
THOMPSON ROAD SEWER REPLACEMENT
APRIL 2022 (REV. MAY 2022) 033.58.1.21 00 01 00 - 1
SECTION 00 01 00
INVITATION TO BID
PART 1: GENERAL
1.1 Competitive Cost Sealed Bids
Separate sealed Bids for construction of Thompson Road Sewer Replacement for the City of
Perry (Bid Number 2022-26) will be received until Tuesday, June 7, 2022 at 10:15 a.m. in
Perry City Hall, 1211 Washington Street, Perry, GA 31069. Bids will then be publicly opened and read aloud at said office. Any bid received after Tuesday, June 7, 2022 at 10:15 a.m. will not be considered by the Owner. Following the closing time for the receipt of bids no bid may be withdrawn for a period of sixty (60) days.
1.2 Scope of Work
The work to be performed and provided under this Contract shall consist of furnishing all labor, materials, tools, equipment, safety equipment, permitting, erosion and sedimentation control measures, taxes, profit, overhead, and other costs and effort required to complete the following:
Installation of 1,800 L.F. of 12” gravity sewer main along with associated manholes, bores, services, and accessories. The time allotted for substantial completion of the work is 90 consecutive calendar days from the Notice to Proceed, and the time allotted for final completion of work is 120 consecutive calendar days from the Notice to Proceed.
Contractor will be required to coordinate all work with the City of Perry and other utility owners who have facilities within the project corridor. The project will be managed by GWES, LLC. located at
733 Carroll Street, Perry, GA 31069, telephone number (478) 235-0307.
All Work shall be completed in accordance with the plans and specifications. The Work will be awarded in one (1) Contract.
1.3 Plans, Specifications and Contract Documents
The Instructions to Bidders, Bid Forms, Contract Agreement, Drawings, Specifications and forms of Bid Bond, Performance Bond, Payment Bond and other Contract Documents may be obtained upon payment (non-refundable) of $200 from:
GWES, LLC.
733 Carroll Street
Perry, GA 31069
(478) 235-0307
1.4 Contractor License
The Bidder shall affix to the outside of its Bid envelope, its Georgia Utility Contractor License
Number, not the license number of a Utility manager or a subcontractor’s Georgia Utility
Contractor License Number. No bid will be opened unless the Contractor’s Utility License
Number is affixed to the envelope.
CITY OF PERRY
THOMPSON ROAD SEWER REPLACEMENT
APRIL 2022 (REV. MAY 2022) 033.58.1.21 00 01 00 - 2
1.5 Bonds
Each Bid must be accompanied by a Bid Bond or certified cashier’s check, in the amount of 10% of the base bid, prepared on the form of Bid Bond, section 00410, attached to the Contract
Documents or a Surety Company’s Standard Bid Bond, duly executed by the Bidder as principal and having as surety thereon a surety company licensed to do business in the State of Georgia and listed in the latest issue of U.S. Treasury Circular 570 with an “A” minimum rating of performance and a financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. Each Bond shall be accompanied by a “Power of Attorney” empowering the attorney-in-fact to bind the surety and certified to include the date of the bond.
1.6 Pre-Bid Meeting
A non-mandatory pre-bid meeting will be held Tuesday, May 10, 2022 at 10:00 a.m. in Perry
City Hall, 1211 Washington Street, Perry, Georgia 31069.
1.7 Permits
Contractor will acquire all necessary Federal, State and local permits preceding the issuance of the Notice to Proceed.
1.8 Easements & Rights-of-Way
Owner has or will acquire all necessary easements and rights-of-way for permanent installations preceding the issuance of the Notice to Proceed.
1.9 Reservation of Rights
The Owner reserves the right to reject any or all Bids, to waive informalities and to re-advertise.
2.0 Contractor E-Verify
Contractor shall supply E-Verify documentation with the bid to be deemed responsive.
END OF SECTION 00 01 00
Other files
| File | Type | Posted |
|---|---|---|
| Thompson Road Sewer Replace | — | |
| Award Information | — | |
| 2022-26 Addendum No. 2 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .