This is Addendum 1 to a solicitation document issued by the Palm Beach County Board of County Commissioners, Facilities Development and Operations Department, Capital Improvements Division, for the Convention Center Cooling Tower Water Line Replacement re-bid project (2022-040567.1-R2). The addendum, issued on June 2, 2026, modifies the original bid documents and requires prospective bidders to acknowledge receipt and attach the addendum to their bid proposals under penalty of disqualification. The project involves phased construction of specialized piping systems in accordance with the engineer's drawings and specifications, with the scope divided into two separate items: Item 1 specifies CPVC Schedule 80 piping, and Item 2 specifies Aquatherm Blue Pipe or an approved equal product. Bidders may submit proposals for one or both items, and the County reserves the right to award to the lowest responsive and responsible bidder for the item deemed most advantageous to the County within budget availability.
The addendum requires bidders to use a revised bid/quote form provided as Attachment 1 and mandates that any product substitutions or "or equal" alternatives must be submitted by the prime contractor at least ten business days prior to the bid due date with complete equipment and material cut sheets and manufacturer performance criteria data for County review and Engineer of Record approval. The County has established a formal substitution review process requiring submission to the Project Manager, with the Engineer of Record responsible for making the final equality recommendation to the County before acceptance. Failure to acknowledge receipt of this addendum by signing and attaching it to the bid form may result in bidder disqualification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOARD OF COUNTY COMMISSIONERS
PALM BEACH COUNTY, FLORIDA
FACILITIES DEVELOPMENT AND OPERATIONS DEPARTMENT
CAPITAL IMPROVEMENTS DIVISION
PROJECT NAME: Convention Center - Cooling Tower Water Line Replacement (RE-BID)
PROJECT NUMBER: 2022-040567.1-R2
ADDENDUM NUMBER: ONE
DATE OF ISSUANCE: 6/2/2026
TO: Prospective Bidders
This addendum forms a part of the contract documents, modifies the original bid documents and shall be as binding as if contained therein. Acknowledge receipt of this addendum in the space provided on the "Bid Proposal Form". Failure to do so may subject the Bidder to disqualification.
This Addendum consists of two (2) pages and one (1) attachment.
Attachments:
• Attachment #1 – REVISED QUOTE/BID FORM
CHANGE TO IFQ/B
1. Delete Quote/Bid Form and replace with Revised Bid/Quote Form attached hereto as with Attachment
1. The Bidder must use the Revised Bid/Quote Form in responding to this solicitation.
CHANGE TO IFQ/B ATTACHMENT C
1. 2. SCOPE OF WORK, delete and replace subsection “a.” with the following:
a. Contractor to phase construction in accordance with Engineer’s drawings and specifications. See previously submitted Exhibit “1”, sheet M-100, notes #13 & #14, where the piping requirement has been split into two separate and distinct items. Each item includes salient characteristics for the specialized piping requirements as set forth in the
Engineer’s drawings and specifications.
i. Item 1 – CPVC Sch. 80 piping as set forth in Exhibit “1”, sheet M-100, note #13 or
ii. Item 2 – Aquatherm Blue Pipe, or equal, as set forth in Exhibit “1”, sheet M-100, note
#14
• Any “or equal” product substitutions must be submitted by the Prime
Contractor at least (10) business days prior to bid due date and will require
Owner’s written approval. Substitution requests are to be submitted for
County review to the Project Manager and shall include all equipment and material cut sheets and manufacturer’s performance criteria data for all equipment and components for review and acceptance by the County.
Naming acceptable manufacturers does not relieve the contractor from compliance with all design requirements shown on the drawings and technical specifications or listed herein. Engineer of Record is responsible to review the substitution(s) in order to make final equality recommendation to the Owner.
iii. Bidder may bid on one or both items. The County reserves the right to select the contractor offering the lowest responsible/responsive bid for the item deemed most advantageous to the County, in its sole discretion, and meets overall operational needs and is within budget availability.
PLEASE ACKNOWLEDGE RECEIPT OF THIS ADDENDUM NO. ONE BY SIGNING
BELOW AND ATTACHING THIS ADDENDUM TO YOUR BID FORM. THIS ADDENDUM
MUST BE SIGNED BY AN AUTHORIZED AGENT AND ATTACHED TO YOUR BID FORM,
AND RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED ON THE “BID
PROPOSAL FORM”. FAILURE TO DO THIS MAY RESULT IN BIDDER’S
DISQUALIFICATION.
ACKNOWLEDGMENT OF RECEIPT:
END OF ADDENDUM 1