This document package includes demolition plans and a related federal contract solicitation. The demolition plans are for relocating a medical ward at the Veterans Affairs Medical Center in Columbia, Missouri to provide improved patient privacy. The plans detail the removal of walls, doors, casework and other fixtures on the third floor in areas A and B. The solicitation is for contract 36C25522R0024 to execute the work outlined in the demolition plans. It is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15. The solicitation does not include pricing terms or response dates. The work involves renovating existing spaces to relocate the medical ward as specified in the demolition drawings numbered AD105 and AD106.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABCDEFGGaHJ
2.82.8
3.73.7
7.37.3
8.28.2
BaH.5
6.2
5.4
6.7
4.64.6
6.36.3
8.08.0
1.9
5.55.5
1.1
F.1 E.a2 Aa
4.4
2.05D2.05D 2.05D2.05D
2.05A2.05A
2.05B 2.05B 2.05B
2.05D
2.05D 2.05B
2.05
2.05
2.05
2.05
2.05B
2.05B
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.032.03
2.03 2.03
2.03
2.03
2.03
2.03
2.03 2.03
2.03
2.03 2.03
2.03
2.03
2.032.03 2.032.03
2.172.03
2.032.03
2.03
2.03
2.03
2.03
2.03
2.03
2.03
2.032.03
2.03
2.03
2.03
2.052.03 2.032.03
2.03
2.032.032.03
2.05
2.03
2.05 2.05
2.17
2.03
2.052.03
2.03
2.03
2.03
2.17
2.032.03
2.03
2.03
2.03 2.03
2.03
2.032.03
2.032.17
2.03
2.032.03
2.03
2.032.03
2.03
2.03
2.05
2.05
2.03
2.05
2.05 2.05 2.05 2.05D 2.05 2.05D
2.05D2.05 2.052.05
2.05
2.052.05
2.052.05
2.052.05
2.032.05
2.05D2.05D
2.05D2.05D
2.05D
2.05D
2.05D2.05
2.05D2.05
2.05D
2.05D
2.05D
2.05D2.05D
2.05D2.05D
2.052.05D
2.052.05
2.05D2.05D2.052.05
2.052.05
2.05D2.05D
2.05D2.05
2.05
2.05D2.05D2.05D2.05D
2.05D
2.052.05
2.05
2.052.05D
2.05D2.05 2.05D2.05
2.052.05D
2.05
2.05
2.052.05D
2.05
2.05D
2.05D2.05
2.05D
2.052.052.05
2.05D
2.05
2.05
2.052.05 2.05D2.05
2.05D
2.05
2.05
2.05
2.05D2.052.05
2.05
2.052.05
2.05
2.052.05
2.05D2.05
2.05
2.052.05
2.05
2.05D2.05D
2.052.05 2.052.05D
2.052.05
2.05
2.05D2.05
2.05D 2.05D
2.05
2.05
2.05B
2.05B 2.05B
2.05B
2.05B 2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B 2.05B
2.05B
2.05B
2.05B
2.05B
2.05B 2.05B
2.05B
2.05B
2.03
2.03
2.05B 2.05B 2.05B
2.05B
2.05B 2.05B
2.20
2.20 2.20 2.20 2.20 2.20
2.202.202.20
2.202.20
2.202.20
2.202.20
2.202.202.202.20
2.20
2.20
2.20
2.20
2.20
2.20
2.202.20
2.202.20
2.202.202.20
2.20
2.202.202.20
2.202.20 2.202.20
2.20
2.20
2.20 2.20 2.20
2.20
2.20
2.20 2.20
2.20
2.02
2.20
2.02
2.02
2.02
2.02
2.022.022.02
2.05A
2.05A
2.05A 2.05A
2.05A
2.05B
2.03
2.05D
2.05A
2.05A 2.05A
2.05A
2.05A
2.05A
2.05A
2.05A
2.05A
2.05A
2.05A
2.05A
2.082.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08 2.08 2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08 2.08
2.08
2.08
2.08
2.08
2.08 2.08 2.08 2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08 2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08 2.08
2.08
2.08
2.08
2.03
2.05 2.03
2.03
2.03
2.03
2.03
2.032.03 2.032.03
2.03
2.01
2.01
2.04
2.05B 2.05B
2.052.05 2.05
2.05
2.032.032.032.032.03
2.05
2.05
2.03B 2.11
2.10
2.10
2.122.12
2.10
2.05
2.05
2.05
2.052.05
2.05A
2.05A
2.20
2.20
2.03
2.032.03
2.03
FIRST FLOOR ROOF BELOW
M E
C H
A N
IC
A
L R
O O
M
F
IR
S T
F L O
O R
R O
O F
FIRST FLOOR
ROOF BELOW
S E
C O
N D
F L O
O R
C O
R R
R
O O
F B
E L O
W
THIRD FLOOR
BALCONY
FIRST FLOOR ROOF BELOW
AD101
2.16 2.16 2.16 2.16 2.16 2.16
2.16 2.16
2.16
2.16 2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
2.16
-4"
-1"
-4"
-4"
-1"
-1"
-1"
-4"
-4"
-1"
-1"
2.08A
2.08A
2.08A
2.08A
2.08A
2.08A
2.08A
2.08A
2.08A
2.30
2.30
2.30
2.31
2.05
2.05
BID ITEM #2
(REF. GI001)
2.05A
2.05D 2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05
2.05D
2.14
D301A
D353
D353A
D332D
D332A
D332B
D333
D333A
D333B
D334
D335
D336 D337
D338
D339
D340
D341
D339A
D338A
D334A
D335A
D338B
D342
D343
D344
D345
A335
A347
A316
A358
A317
A357
A319
A356
A321
A353
A354
A321A
A325
A352 A351
A350
A332
A348
C3A4A
A328
A331
A337
A338
A339
A340
A341
A342
A343
A344
A345
A346
A339A
A330
A330A
A330B
A329
A327
A326
A323
A322
A318
A318A
A329AA327A
A326A
A323A
A320
B344
B318
A313
A314 A306A
A346A
C3A6
C3A5
C3A4
D308C D301B
D301
C3C7
#3 #2 #1
B347
CORR.
#4
#5
B318A
C3A2
B345
C3A4
A312
A300
C3A3
D346
D348
D347 D329
C3D4
GENERAL DEMOLITION NOTES
A. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS PRIOR TO WORK BEGINNING. THE
CONTRACTOR IS RESPONSIBLE FOR INFORMING THE ARCHITECT OF ANY CONDITIONS THAT
DIFFER FROM THE INFORMATION INDICATED IN THE DRAWINGS.
B. PROTECT ALL EXISTING BUILDING COMPONENTS WHICH ARE TO REMAIN. REPAIR ANY
DAMAGED AREAS AS REQUIRED TO RETURN THEM TO THEIR ORIGINAL CONDITION.
C. VERIFY EXTENT OF DEMOLITION WORK WITH INFORMATION SHOWN IN THE DRAWINGS AND
WORK THAT IS NOT SHOWN AND MAY BE REQUIRED TO COMPLETE THE INTENDED WORK.
D. ALL WORK SHALL COMPLY WITH REQUIRED LOCAL CODES. CONTRACTOR IS RESPONSIBLE
FOR OBTAINING REQUIRED PERMITS AND INSPECTIONS FOR ALL WORK ASSOCIATED WITH
THIS CONTRACT.
E. CONTRACTOR SHALL REPAIR ALL DISTURBED AREAS AS REQUIRED TO MATCH
SURROUNDING EXISTING FINISHES NOT DISTURBED.
F. TYPES OF FLOOR, WALL, AND CEILING FINISHES INDICATED FOR REMOVAL BY DEMOLITION
NOTES ARE FOR GENERAL INFORMATION ONLY FROM INFORMATION OBTAINED FROM
EXISTING PLANS AND OBSERVATIONS. CONTRACTOR SHALL FIELD VERIFY MATERIAL TYPES
ONSITE PRIOR TO BID AND INCLUDE NECESSARY WORK IN HIS BID.
G. ALL APPLIANCES, FURNITURE, AND EQUIPMENT TO REMAIN THE PROPERTY OF THE
OWNER - CONTRACTOR TO COORDINATE REMOVAL, RELOCATION AND STORAGE OF
EQUIPMENT FROM DEMO AREAS WITH OWNER.
H. MISCELLANEOUS FLOOR PENETRATIONS AND DEMO FOR NEW MECHANICAL AND
ELECTRICAL WORK SHALL BE COORDINATED FROM ARCHITECTURAL, MECHANICAL, AND
ELECTRICAL PLANS.
I. REFER TO MECHANICAL, PLUMBING AND ELECTRICAL DEMO PLANS FOR DEMOLITION,
SALVAGE AND RE-USE OF EXISTING ITEMS.
J. PATCH FLOOR AT REMOVED WALLS AND CASEWORK, PREPARE FLOOR TO RECEIVE NEW
FLOORING AS REQUIRED.
K. ALL HOLES IN EXISTING SLAB LEFT FROM REMOVAL OF FIXTURES TO RECEIVE INFILL PER
STRUCTURAL DETAIL.
L. REMOVE ALL STAINLESS STEEL CORNER GUARDS CAREFULLY AND GIVE TO OWNER.
M. ELEMENTS INDICATED WITH A DASHED LINE ARE TO BE DEMOLISHED AND DISPOSED OF AS
A PART OF THIS PROJECT, UNLESS NOTED OTHERWISE.
N. IN EXISTING AREAS, RENOVATION AND DEMOLITION WORK SHALL BE ACCOMPLISHED WITH
MINIMAL DISRUPTION TO OPERATIONS. IF REQUIRED, THE OWNER RESERVES THE RIGHT TO
TEMPORARILY STOP WORK OF SPECIFIC CONSTRUCTION OPERATIONS SHOULD THE
OWNER IDENTIFY AN EMERGENCY OR DANGER EXISTS TO THE WELFARE OF THE
OCCUPANTS ON ACCOUNT OF SUCH WORK OR OPERATIONS.
O. CONTRACTOR SHALL REMOVE AND DISPOSE OF IN A LEGAL MANNER ALL MATERIAL NOT
SCHEDULED FOR REUSE UNDER THIS PROJECT .
P. IN ALL WALLS AND CEILINGS THAT ARE TO BE REMOVED THE CONTRACTOR SHALL BE
RESPONSIBLE FOR DISCONNECTING AT SOURCE AND REMOVING OR CAPPING ELECTRICAL,
PLUMBING, GAS LINES AND MECHANICAL DUCTWORK THAT ARE NOT SCHEDULED FOR
REUSE. CONTRACTOR SHALL REROUTE AND CONTINUE ANY SYSTEM THAT MUST BE
RETAINED FOR NEW CONSTRUCTION. CONTRACTOR SHALL REROUTE AND KEEP
OPERATIONAL ALL SYSTEMS SERVING SPACES IN THE SURROUNDING AREAS TO THE
PROJECT.
Q. ALL ELECTRICAL CIRCUITS FOR EQUIPMENT THAT ARE TO BE REMOVED SHALL BE
DISCONNECTED AT SOURCE AND REMOVED BACK TO PANEL.
R. ALL PIPING GAS, WATER SUPPLY, VENT, DRAIN LINES, ETC. SUPPLYING EQUIPMENT THAT
ARE TO BE REMOVED SHALL BE DISCONNECTED, REMOVED AND CAPPED ABOVE CEILING
OR BELOW FLOOR. CONTRACTOR SHALL REROUTE AS NECESSARY, TO BE BEHIND NEW
CONSTRUCTION. (PATCH FLOOR BACK PRIOR TO TOPPING.)
S. ALL MED GASES AND PLUMBING TO BE REMOVED AT WALLS SCHEDULED FOR DEMOLITION.
T. REMOVE ALL PLUMBING FIXTURES AND EQUIPMENT WITHIN ROOMS SCHEDULED TO BE
DEMOLISHED. SEE MEP PIPING DRAWINGS.
U. RETURN ALL SIGNAGE AFFECTED BY CONSTRUCTION TO OWNER.
WALL DOOR
CEILING
AND GRID
DEMO LEGEND
FLOOR
PENETRATION
GYP BOARD
CEILING/SOFFIT
CONCRETE
PATCH AREA
(-X" = DEPTH OF
PATCH AREA)
-X"
THIRD FLOOR KEY PLAN - AREA A
A
N
OMAHA | LINCOLN | COLORADO SPRINGS | SIDNEY
FARRIS ENGINEERING
farris-usa.com
FE#:202054
117 PIERCE ST, SUITE 110
SIOUX CITY, IOWA 51101
712.252.4014
142 N. MOSLEY ST.
WICHITA, KANSAS 67202
316.262.2500
303 S. TOPEKA
WICHITA, KANSAS 67202
316.262.2691
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F o n e ig h th in c o fo t o q u a rt e r i n t th re h s t o a lf t th a rt rs t o t o d h t th h t
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
CONSULTANTS: ARCHITECT/ENGINEERS:
Drawing Title
Approved: Project Director
Project Title
Location
Date Checked Drawn
Dwg.
Drawing Number
Building Number
Project Number
Office of Construction and Facilities Management
Department of Veterans Affairs
AD105
DEMOLITION PLAN - 3RD FLOOR -
AREA A
RELOCATE MEDICAL WARD
FOR PATIENT PRIVACY
800 HOSPITAL DRIVE COLUMBIA, MO 65201
07-26-2021
589A4-21-100
FINAL CONSTRUCTION DOCUMENTS
AuthorChecker
1/8" = 1'-0"
DEMOLITION PLAN - 3RD FLOOR - AREA A
KEYNOTES
KEY VALUE KEYNOTE TEXT
2.01 REMOVE SEMI-RECESSED FIRE EXTINGUISHER CABINET, CONFIRM REUSE W/COR.
2.02 REMOVE CASEWORK & SALVAGE FOR REUSE, COORDINATE LOCATION WITH OWNER."
2.03 REMOVE DOOR, FRAME AND HARDWARE.
2.03B REMOVE DOOR & FRAME, CREATE RO FOR NEW WINDOW, REF WINDOW ELEVATION,
INFILL TO MATCH EXISTING WALL.
2.04 REMOVE WINDOW & FRAME, INFILL TO MATCH EXISTING WALL."
2.05 REMOVE WALL AND ALL OF ITS BUILDING COMPONENTS (FULL HEIGHT)
2.05A REMOVE FURRING WALL AND ALL OF ITS BUILDING COMPONENTS DOWN TO EXISTING
STRUCTURE
2.05B REMOVE COLUMN FURRING WALLS
2.05D REMOVE FURRING WALLS, COMMUNICATE EXISTANCE OF ANY DUCT WORK OR PIPING
WITH ARCHITECT FOR COORDINATION OF REPLACEMENT WALL
2.08 REMOVE FLOORING AND BASE. PREPARE AREA FOR NEW FLOOR FINISHES AND BASE,
REF. FINISH SCHEDULE.
2.08A REMOVE CONCRETE PATCH AND REPAIR WITH CONCRETE PER STRUCTURAL, SEE
PLAN FOR APPROX DEPTH OF PATCH. PREPARE AREA FOR NEW FLOOR FINISHES AND
BASE, REF. FINISH SCHEDULE.
2.10 REMOVE BALCONY ROOF SYSTEM & ROOF SUPPORTS INCLUDING ANGLE IRONS
ATTACHED TO BRICK, REF. STRUCT. DEMO PLANS FOR MORE INFORMATION
2.11 REMOVE METAL RAILING AND BALCONY FLOOR, REF. STRUCT. DEMO PLANS FOR
MORE INFORMATION
2.12 REROUTE ROOF TOP MECHANICAL UNIT PIPING/POWER FROM UNDERSIDE OF
BALCONY TO ROOF MOUNTED SUPPORTS & RECONNECT ALL POWER AND PIPING
LINES. COORDINATE ANY MECHANICAL UNIT SHUT DOWN WITH COR
2.14 REMOVE ROOF MEMBRANE AS REQUIRED TO REMOVE BALCONY STEEL COLUMNS
AND CONCRETE CURBS TO DECK ON THE 2ND FLOOR. REPAIR ROOF STRUCTURE
WITH LIKE CONSTRUCTION AND PATCH ROOF MEMBRANE.
2.16 REMOVE PATIENT LIFT TRACKS, RAILS AND VETICAL SUPPORTS. REMOVE ALL
THREADED RODS AND SUPPORTS ABOVE CEILING TO STRUCTURE
2.17 TEMPORARILY REMOVE EXISTING CEILING GRID AND TILES AS NECESSARY FOR
DEMO/INSTALL OF MECHANICAL(SEE MECH PLANS); REINSTALL GRID AND TILE AND
REPARE ANY DAMAGES THAT OCCURED DURING CONSTRUCTION.
2.20 REMOVE PLUMBING FIXTURE AND CAP LINES AS REQUIRED, REF. MEP DEMO PLANS
FOR MORE INFORMATION
2.30 REMOVE LIGHT FIXTURE, REF. ELEC. DEMO PLANS FOR MORE INFORMATION
2.31 REMOVE DOOR RELEASE BUTTON, REF. ELEC. DEMO PLANS FOR MORE INFORMATION
N
# Revision Date
1 BID QUESTION RESPONSE 02/23/22
ABCDEFGGaH
8.28.2
9.19.1
10.410.4
BaH.5
8.08.0
F.1 E.a2 Aa
13.6
2.03
2.03 2.032.03
2.03
2.03
2.03
2.17
2.03
2.03
2.17
2.03
2.03
2.03
2.03
2.032.03
2.03
2.03
2.03
2.03
2.03
2.032.03
2.032.03
2.03
2.032.03
2.03
2.03
2.03
2.03
2.03
2.03
2.202.202.202.202.20
2.20 2.20
2.20
2.20
2.20
2.03
2.03
2.202.20
2.202.20
2.05
2.05
2.052.05
2.05
2.052.05
2.05D2.05
2.05
2.052.05
2.03
2.05
2.052.05
2.05
2.05D2.05
2.05
2.05
2.05
2.05
2.05 2.052.05D2.05
2.052.052.05
2.052.05
2.03
2.05A
2.05A
2.05A 2.05
2.05A
2.05
2.05A
2.05B
2.05B
2.05B 2.05B
2.05B
2.05B
2.05B 2.05B
2.05A
2.05A
2.05A
2.05B
2.05B 2.05B 2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.05B
2.03
2.03
2.022.02
2.05A
2.05A
2.05A
2.05A
2.05A
2.05
2.17
2.08 2.08
2.03
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.03
2.03
2.08
2.08
2.08
2.08
2.08
2.08
2.08
2.07
2.07
2.122.12
FIRST FLOOR ROOF BELOW
THIRD FLOOR
BALCONY
AD101
AD101
-1" 2.08A
2.03
2.05
2.05D
BID ITEM #2
(REF. GI001)
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05D
2.05
2.052.05
2.05
2.05
2.052.05
2.05
2.05
2.14
2.14
D320
D321
D322
D323
D318
D319
D324
D325
D326
D327
D328
D329
D316
D353
D353A
D332DD332B
D344
D345
D346
D347 D348
D349
D350
D351
D351A
D330
D331
C3D4
D316C
C3D4
D331A
D331B
D331C C3D5
D352
D330A
D301B
C3D1
C3D3
C357A
C356A
C359
C360A
C360
C339
C358
C340
D316A
C358C
#6
C358A
WALL DOOR
CEILING
AND GRID
DEMO LEGEND
FLOOR
PENETRATION
GYP BOARD
CEILING/SOFFIT
CONCRETE
PATCH AREA
(-X" = DEPTH OF
PATCH AREA)
-X"
GENERAL DEMOLITION NOTES
A. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS PRIOR TO WORK BEGINNING. THE
CONTRACTOR IS RESPONSIBLE FOR INFORMING THE ARCHITECT OF ANY CONDITIONS THAT
DIFFER FROM THE INFORMATION INDICATED IN THE DRAWINGS.
B. PROTECT ALL EXISTING BUILDING COMPONENTS WHICH ARE TO REMAIN. REPAIR ANY
DAMAGED AREAS AS REQUIRED TO RETURN THEM TO THEIR ORIGINAL CONDITION.
C. VERIFY EXTENT OF DEMOLITION WORK WITH INFORMATION SHOWN IN THE DRAWINGS AND
WORK THAT IS NOT SHOWN AND MAY BE REQUIRED TO COMPLETE THE INTENDED WORK.
D. ALL WORK SHALL COMPLY WITH REQUIRED LOCAL CODES. CONTRACTOR IS RESPONSIBLE
FOR OBTAINING REQUIRED PERMITS AND INSPECTIONS FOR ALL WORK ASSOCIATED WITH
THIS CONTRACT.
E. CONTRACTOR SHALL REPAIR ALL DISTURBED AREAS AS REQUIRED TO MATCH
SURROUNDING EXISTING FINISHES NOT DISTURBED.
F. TYPES OF FLOOR, WALL, AND CEILING FINISHES INDICATED FOR REMOVAL BY DEMOLITION
NOTES ARE FOR GENERAL INFORMATION ONLY FROM INFORMATION OBTAINED FROM
EXISTING PLANS AND OBSERVATIONS. CONTRACTOR SHALL FIELD VERIFY MATERIAL TYPES
ONSITE PRIOR TO BID AND INCLUDE NECESSARY WORK IN HIS BID.
G. ALL APPLIANCES, FURNITURE, AND EQUIPMENT TO REMAIN THE PROPERTY OF THE
OWNER - CONTRACTOR TO COORDINATE REMOVAL, RELOCATION AND STORAGE OF
EQUIPMENT FROM DEMO AREAS WITH OWNER.
H. MISCELLANEOUS FLOOR PENETRATIONS AND DEMO FOR NEW MECHANICAL AND
ELECTRICAL WORK SHALL BE COORDINATED FROM ARCHITECTURAL, MECHANICAL, AND
ELECTRICAL PLANS.
I. REFER TO MECHANICAL, PLUMBING AND ELECTRICAL DEMO PLANS FOR DEMOLITION,
SALVAGE AND RE-USE OF EXISTING ITEMS.
J. PATCH FLOOR AT REMOVED WALLS AND CASEWORK, PREPARE FLOOR TO RECEIVE NEW
FLOORING AS REQUIRED.
K. ALL HOLES IN EXISTING SLAB LEFT FROM REMOVAL OF FIXTURES TO RECEIVE INFILL PER
STRUCTURAL DETAIL.
L. REMOVE ALL STAINLESS STEEL CORNER GUARDS CAREFULLY AND GIVE TO OWNER.
M. ELEMENTS INDICATED WITH A DASHED LINE ARE TO BE DEMOLISHED AND DISPOSED OF AS
A PART OF THIS PROJECT, UNLESS NOTED OTHERWISE.
N. IN EXISTING AREAS, RENOVATION AND DEMOLITION WORK SHALL BE ACCOMPLISHED WITH
MINIMAL DISRUPTION TO OPERATIONS. IF REQUIRED, THE OWNER RESERVES THE RIGHT TO
TEMPORARILY STOP WORK OF SPECIFIC CONSTRUCTION OPERATIONS SHOULD THE
OWNER IDENTIFY AN EMERGENCY OR DANGER EXISTS TO THE WELFARE OF THE
OCCUPANTS ON ACCOUNT OF SUCH WORK OR OPERATIONS.
O. CONTRACTOR SHALL REMOVE AND DISPOSE OF IN A LEGAL MANNER ALL MATERIAL NOT
SCHEDULED FOR REUSE UNDER THIS PROJECT .
P. IN ALL WALLS AND CEILINGS THAT ARE TO BE REMOVED THE CONTRACTOR SHALL BE
RESPONSIBLE FOR DISCONNECTING AT SOURCE AND REMOVING OR CAPPING ELECTRICAL,
PLUMBING, GAS LINES AND MECHANICAL DUCTWORK THAT ARE NOT SCHEDULED FOR
REUSE. CONTRACTOR SHALL REROUTE AND CONTINUE ANY SYSTEM THAT MUST BE
RETAINED FOR NEW CONSTRUCTION. CONTRACTOR SHALL REROUTE AND KEEP
OPERATIONAL ALL SYSTEMS SERVING SPACES IN THE SURROUNDING AREAS TO THE
PROJECT.
Q. ALL ELECTRICAL CIRCUITS FOR EQUIPMENT THAT ARE TO BE REMOVED SHALL BE
DISCONNECTED AT SOURCE AND REMOVED BACK TO PANEL.
R. ALL PIPING GAS, WATER SUPPLY, VENT, DRAIN LINES, ETC. SUPPLYING EQUIPMENT THAT
ARE TO BE REMOVED SHALL BE DISCONNECTED, REMOVED AND CAPPED ABOVE CEILING
OR BELOW FLOOR. CONTRACTOR SHALL REROUTE AS NECESSARY, TO BE BEHIND NEW
CONSTRUCTION. (PATCH FLOOR BACK PRIOR TO TOPPING.)
S. ALL MED GASES AND PLUMBING TO BE REMOVED AT WALLS SCHEDULED FOR DEMOLITION.
T. REMOVE ALL PLUMBING FIXTURES AND EQUIPMENT WITHIN ROOMS SCHEDULED TO BE
DEMOLISHED. SEE MEP PIPING DRAWINGS.
U. RETURN ALL SIGNAGE AFFECTED BY CONSTRUCTION TO OWNER.
THIRD FLOOR KEY PLAN - AREA B
BN
OMAHA | LINCOLN | COLORADO SPRINGS | SIDNEY
FARRIS ENGINEERING
farris-usa.com
FE#:202054
117 PIERCE ST, SUITE 110
SIOUX CITY, IOWA 51101
712.252.4014
142 N. MOSLEY ST.
WICHITA, KANSAS 67202
316.262.2500
303 S. TOPEKA
WICHITA, KANSAS 67202
316.262.2691
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F o t o a rt e r i n t th h t o t th a rt rs t o t o d h t th h t
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
CONSULTANTS: ARCHITECT/ENGINEERS:
Drawing Title
Approved: Project Director
Project Title
Location
Date Checked Drawn
Dwg.
Drawing Number
Building Number
Project Number
Office of Construction and Facilities Management
Department of Veterans Affairs
AD106
DEMOLITION PLAN - 3RD FLOOR -
AREA B
RELOCATE MEDICAL WARD
FOR PATIENT PRIVACY
800 HOSPITAL DRIVE COLUMBIA, MO 65201
07-26-2021
589A4-21-100
FINAL CONSTRUCTION DOCUMENTS
AuthorChecker
1/8" = 1'-0"
DEMOLITION PLAN - 3RD FLOOR - AREA B
KEYNOTES
KEY VALUE KEYNOTE TEXT
2.02 REMOVE CASEWORK & SALVAGE FOR REUSE, COORDINATE LOCATION WITH OWNER."
2.03 REMOVE DOOR, FRAME AND HARDWARE.
2.05 REMOVE WALL AND ALL OF ITS BUILDING COMPONENTS (FULL HEIGHT)
2.05A REMOVE FURRING WALL AND ALL OF ITS BUILDING COMPONENTS DOWN TO EXISTING
STRUCTURE
2.05B REMOVE COLUMN FURRING WALLS
2.05D REMOVE FURRING WALLS, COMMUNICATE EXISTANCE OF ANY DUCT WORK OR PIPING
WITH ARCHITECT FOR COORDINATION OF REPLACEMENT WALL
2.07 REMOVE RAILING
2.08 REMOVE FLOORING AND BASE. PREPARE AREA FOR NEW FLOOR FINISHES AND BASE,
REF. FINISH SCHEDULE.
2.08A REMOVE CONCRETE PATCH AND REPAIR WITH CONCRETE PER STRUCTURAL, SEE
PLAN FOR APPROX DEPTH OF PATCH. PREPARE AREA FOR NEW FLOOR FINISHES AND
BASE, REF. FINISH SCHEDULE.
2.12 REROUTE ROOF TOP MECHANICAL UNIT PIPING/POWER FROM UNDERSIDE OF
BALCONY TO ROOF MOUNTED SUPPORTS & RECONNECT ALL POWER AND PIPING
LINES. COORDINATE ANY MECHANICAL UNIT SHUT DOWN WITH COR
2.14 REMOVE ROOF MEMBRANE AS REQUIRED TO REMOVE BALCONY STEEL COLUMNS
AND CONCRETE CURBS TO DECK ON THE 2ND FLOOR. REPAIR ROOF STRUCTURE
WITH LIKE CONSTRUCTION AND PATCH ROOF MEMBRANE.
2.17 TEMPORARILY REMOVE EXISTING CEILING GRID AND TILES AS NECESSARY FOR
DEMO/INSTALL OF MECHANICAL(SEE MECH PLANS); REINSTALL GRID AND TILE AND
REPARE ANY DAMAGES THAT OCCURED DURING CONSTRUCTION.
2.20 REMOVE PLUMBING FIXTURE AND CAP LINES AS REQUIRED, REF. MEP DEMO PLANS
FOR MORE INFORMATION
N
# Revision Date
1 BID QUESTION RESPONSE 02/23/22
| Sheets |
| AD105 - DEMOLITION PLAN - 3RD FLOOR - AREA A |
| AD106 - DEMOLITION PLAN - 3RD FLOOR - AREA B |