This document is Addendum No. 1 for the Genesee Intermediate School District (GISD) MCIC Door & Hardware Replacement project located at 3330 Luce Road in Flushing, Michigan. Issued on April 8, 2019, by MAYOTTEgroup Architects, the addendum modifies the original contract documents for a door and hardware replacement project. The addendum provides clarifications including approving Vale Door as an alternate supplier for FRP doors and aluminum frames, and specifying changes to hardware specifications, such as deleting two surface closers and adding surface auto operators for certain door openings.
The addendum references Drawing A100's Interior Door Schedule, indicating that door openings specified in the schedule will receive new hardware while existing doors will be reused. An add alternate note for replacing interior doors is also revised to apply to opening 617. The document is part of a public procurement process for school district infrastructure improvements, with the pre-bid meeting sign-in sheet from March 28, 2019, attached for reference. The scope of work includes hardware installation and potential door replacements at the MCIC facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2019-03-26 MCIC Door Replacement Request for Bid.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 1 2018-081 – GISD- MCIC Door & Hardware Replacement mjm
ADDENDUM TO THE CONTRACT DOCUMENTS FOR:
CLIENT:
Genesee Intermediate School District 2413 W. Maple Ave.
Flint, MI. 48507
PROJECT:
MCIC Door & Hardware Replacement 3330 Luce Road Flushing, MI 48433
ARCHITECT:
MAYOTTEgroup Architects 6240 W. Mt. Hope Lansing, MI 48917
PURPOSE: This addendum is issued to amplify, clarify, and modify the original contract documents and shall take precedence over them.
DATE ISSUED: April 8, 2019
ATTACHMENTS: Pre-bid Meeting sign-in sheet, dated March 28, 2019
To All Bidders
GENERAL
Item 1 The pre-bid meeting sign-in sheet is attached for reference.
Item 2 Vale Door is an approved alternate supplier for the FRP doors and aluminum frames.
SPECIFICATIONS
Item 3 Reference Section 087100 “Door Hardware” – Hardware Group 13; Delete (2) surface closers 4040XP EDA. Provide surface auto operator as indicated.
Installation of auto operators to be included in scope of work.
DRAWINGS
Item 4 Reference Drawing A100 – Interior Door Schedule; Door openings indicated in the Interior Door Schedule shall receive new hardware only. Existing doors to be reused.
Item 5 Reference Drawing A100 – Interior Door Schedule; Note indicating Add
Alternate to replace existing interior doors to be revised to opening 617.
END OF ADDENDUM NO. 1