About this file

Attachment J.5 Quality Assurance Surveillance Plan

View the file

Other files for this federal contract opportunity

Other files attached to Professional Support Services to Detect and Control Emerging and Zoonotic Infectious Diseases, newest first.
File Type Posted
Questions_and_Answers_-_2014-N-15787_-_amendment_00002.docx DOCX document
AMENDMENT_00002_-_SF_30.pdf PDF
J_9_0_WD_05-2133_(Rev-12)_-_Amendment_00001.pdf PDF
Questions_and_Answers_-_2014-N-15787.docx DOCX document
RFP_2014-N-15787_as_amended_00001.pdf PDF
J2_Labor_Category_Descriptions_-_amendment_00001.docx DOCX document
AMENDMENT_00001_-_SF30.pdf PDF
J4_Sample_Task_Order__2_-_Data_Entry_Center_Services_-_amendment_00001.docx DOCX document
J_10_Customer-Client_Survey_Letter_and_Past_Performance_Survey_Document_-_Amendment_00001.docx DOCX document
J3_Sample_Task_Order__1_-_DGMQ_Professional_Services_-_Amendment_00001.docx DOCX document
J_1_Section_B_Pricing_Table_-_Amendment_00001.xls XLS spreadsheet
J4_Sample_Task_Order__2_-_Data_Entry_Center_Services.docx DOCX document
J_7_0_ACH-Vendor.pdf PDF
J_4_1Sample_Task_Order_2_-_EDN_Rules_Of_Behavior_v7_1.pdf PDF
J_1_Section_B_Pricing_Table.xls XLS spreadsheet
J_4_2_Sample_Task_Order_2_-_EDN_USER_AGREEMENT_v7.doc DOC document
RFP_2014-N-15787.pdf PDF
J2_Labor_Category_Descriptions.docx DOCX document
J_8_0_Controls_for_Government_Property_and_Guidance_on_Removing_Government_Property_from_CDC_Facilities.pdf PDF
J_4_3_WD_05-2133_(Rev-12).pdf PDF
J3_Sample_Task_Order__1_-_DGMQ_Professional_Services.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 2014-N-15787 J.5 Quality Assurance Surveillance Plan

Quality Assurance Surveillance Plan (QASP)

Division of Global Migration and Quarantine Professional Services IDIQ

12/10/2013

Version 1.0

31 Vision

1.1 Mission

3 Purpose 4 Authority 5 Roles and Responsibilities

5.1 Program / Project Manager

Error! Bookmark not defined.

5.2 Contracting Office (CO)

5.3 Contracting Officer's Representative (COR)

5.4 Other Key Government Personnel

5.5 Contractor Representatives

6 Performance Requirements and Method of Surveillance

6.1 Contract Surveillance

6.2 Surveillance Matrix

Appendix 1 - Surveillance Matrix Appendix 2 - Corrective Action Report (CAR) Appendix 3 - Customer Complaint Record Appendix 4 - Performance Assessment Report (PAR)

Quality Assurance Surveillance Plan (QASP) Division of Global Migration and Quarantine Professional Services IDIQ

1 Vision

Aims to prevent the introduction, transmission, or spread of communicable diseases from foreign countries into the United States.

1.1 Mission

To reduce morbidity and mortality among immigrants, refugees, travelers, expatriates, and other globally mobile populations, and to prevent the introduction, transmission, and spread of communicable diseases through regulation, science, research, preparedness, and response.

3 Purpose

This Quality Assurance Surveillance Plan (QASP) is a government-developed document used to determine if the contractor's performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the detailed process for a continuous oversight process:

What will be monitored

How monitoring will take place

Who will be conduct the monitoring

How monitoring efforts and results will be documented

The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QASP provides the structure for the government's surveillance of the contractor's performance to assure that it meets contract standards. It is the government's responsibility to be objective, fair and consistent in evaluating contractor performance.

The QASP is not part of the contract nor is it intended to duplicate the contractor's quality control plan. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.

The government may provide a copy of the QASP to the contractor to facilitate open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor.

Bottom line, the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.

4 Authority

Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition Regulation, Inspection of Services clauses, which provides for inspection, acceptance and documentation of the service called for in the contract or order. This acceptance is to be executed by the contracting officer or a duly authorized representative.

5 Roles and Responsibilities

The following personnel shall oversee and coordinate surveillance activities.

5.1 Contracting Office (CO)

The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine and document the final assessment of the contractor's performance in the governments past performance tracking system.

Assigned CO: <enter name> Organization or Agency: <enter organization or Agency name> Telephone: <enter number> Email: <enter address>

5.2 Contracting Officer's Representative (COR)

The COR is responsible for providing continuous technical oversight of the contractor's performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor's actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the CO. The COR is required to provide an annual performance assessment to the CO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government's behalf.

5.3 Other Key Government Personnel

(enter name or delete these line if not applicable) This may include performance monitors, inspectors, technical experts, or others who provide information that helps the COR monitor contractor performance.

5.4 Contractor Representatives

The following employees of the contractor serve as the contractor's Program Manager and Task Manager for this contract. (Complete this section after the contract award) Program Manager - <upon award, enter name> Telephone: <enter number> Email: <enter address> Task Manager - <upon award, enter name> Telephone: <enter number> Email: <enter address> Other Key Contract Personnel - <upon award, enter name or delete these lines if not applicable> Title: <enter title> Telephone: <enter number> Email: <enter address> 6 Performance Requirements and Method of Surveillance

DEFAULT TEXT:

This section describes the special requirements for this effort. The following sub-sections provide details of various considerations on this effort.

6.1 Contract Surveillance

The goal of the QASP is to ensure that contractor performance is effectively monitored and documented. The COR's contribution is their professional, non-adversarial relationships with the CO, COR and the contractor, which enables positive, open and timely communications. The foundation of this relationship is built upon objective, fair, and consistent COR evaluations of contractor performance against contract requirements. The COR uses the methods contained in this QASP to ensure the contractor is in compliance with contract requirements. The COR function is responsible for a wide range of surveillance requirements that effectively measure and evaluate the contractor's performance. Additionally, this QASP is based on the premise that the contractor, not the government, is responsible for management and QC/QA actions to successfully meet the terms of the contract.

6.2 Surveillance Matrix

The Surveillance Matrix (Attachment 1) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these performance elements. Inspection of each element will be documented in the COR file.

Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performs surveillance, using this QASP, to determine the quality of the contractor's performance as it relates to the performance element standards. The PRS should be used to form the foundation of the COR's inspection checklist.

In evaluating the quality of contractor’s performance, the following performance ratings may be used.

[If your organization requires that you use a different rating mechanism, insert it here.] Performance

Rating Criteria

Excellent / Outstanding
Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Good
Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Appendix 1 - Surveillance Matrix

Statements
Standards/AQLs
Inspections
Ratings

3.1 Provide timely and high-quality responses to requests for Task Orders for services

a) Submit Task Order proposals within two weeks.

What: Date Task Order proposal is submitted.

How: 100% Review

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

Standard(s): Inspection applies to all standards

3.1.1 The Contractor shall provide responses for services as defined in Task Orders for public health program development, management, and operations.

a) Quality of content of Task Order proposals are implementable.

What: Review Task Order Proposals

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

3.1.2 The Contractor shall provide responses for services as defined in Task Orders for communication, training, education, and collaboration.

a) Quality of content of Task Order proposals are implementable.

What: Review Task Order proposals

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

3.1.3 The Contractor shall provide responses for services as defined in Task Orders for data entry and help desk services.

a) Quality of content of Task Order proposals are implementable.

What: Review Task Order proposals

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

3.1.4 The Contractor shall provide responses for services as defined in Task Orders for performance management, strategic planning, and organizational improvement.

a) Quality of content of Task Order proposals are implementable.

What: Review Task Order proposals

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

3.1.5 The Contractor shall provide responses for services as defined in Task Orders for surge capacity and emergency response.

a) Quality of content of Task Order proposals are implementable.

What: Review Task Order proposals

Who: COR

Incentive: Performance will impact the Contractor performance evaluation using the Contractor Performance Assessment Reporting System (CPARS). The evaluation will be considered when future AGENCY contract selections are made.

Statements
Standards/AQLs
Inspections
Ratings

3.2 Timely and accurate responses to questions/concerns from COR and Contracting Officer

a) Response time is within a range of an hour up to one day depending on the urgency and complexity.

What: Contract management and responsiveness How: 100% Review

Customer Complaints

Who: COR and Contract Officer

Incentive: Contractor will have to respond to the question/concern. Both positive and negative customer service will be reported into CPARS.

Statements
Standards/AQLs
Inspections
Ratings

3.3 Submit high quality and accurate monthly progress reports

a) Reports of high quality, fully edited, and accurate submitted by the 15th of the month.

AQL: 95% of the time

What: Deliverable; verify submission, accuracy and quality.

How: 100% Review of reports

On-site periodic inspections

Continuous oversight

Who: COR

Incentive: Contractor shall re-perform at own expense.

Statements
Standards/AQLs
Inspections
Ratings

3.4 Management of Task Orders

a) COR receives no more than 4 valid complaints per 12 months.

What: Documentation of valid customer complaints.

How: 100% Review

Customer Complaints

Who: COR

Incentive: Contractor will have to respond to complaints and address appropriately. Both positive and negative customer service will be reported into CPARS.

Statements
Standards/AQLs
Inspections
Ratings

3.5 Submit accurate monthly invoices for each Task Order

a) No invoices per 12 months requiring suspension or disallowance due to mistakes, incompleteness or unallowable costs.

What: Invoice submissions

How: 100% Review

Who: COR and Contract Officer

Incentive: Contractor shall re-perform at own expense.

Appendix 2 - Corrective Action Report (CAR)

CORRECTIVE ACTION REPORT (CAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACTOR

2. CONTRACT NUMBER

3. TYPE OF SERVICES

4. FUNCTIONAL AREA

5. SUSPENSE DATE

6. CONTROL NUMBER

7. DEFICIENCY FORMCHECKBOX

MAJOR FORMCHECKBOX

MINOR

FINDING:

FINDING IMPACT:

Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.

8. QUALITY ASSURANCE PERSONNEL (COR)

TYPED NAME AND GRADE

SIGNATURE AND DATE

9. ISSUING AUTHORITY

TYPED NAME AND GRADE

SIGNATURE AND DATE

10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE

11. COR DETERMINATION

FORMCHECKBOX

ACCEPTED FORMCHECKBOX

REJECTED

12. CLOSE DATE

Appendix 3 - Customer Complaint Record

CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT

SOURCE OF COMPLAINT

ORGANIZATION

BUILDING NUMBER

INDIVIDUAL

PHONE NUMBER

NATURE OF COMPLAINT

CONTRACT REFERENCE

VALIDATION

DATE/TIME CONTRACTOR INFORMED OF COMPLAINT

ACTION TAKEN BY CONTRACTOR

RECEIVED/VALIDATED BY

Appendix 4 - Performance Assessment Report (PAR)

PERFORMANCE ASSESSMENT REPORT (PAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACT/TASK ORDER NUMBER
2. CONTRACTOR
3. TYPE OF SERVICES

4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE

5. COR PHONE
6. SUSPENSE DATE

I. PERFORMANCE

7. FORMCHECKBOX

DEFICIENCY (CHECK ALL BOXES THAT APPLY)

FORMCHECKBOX

NEW

FORMCHECKBOX

REPEAT

FORMCHECKBOX

NO DEFICIENCY NOTED

8. SERVICES SUMMARY or PWS PARAGRAPH ITEM REVIEWED

9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY BOX WAS CHECKED)
10. DETAILED PERFORMANCE ASSESSMENT

II. CONTRACTOR VALIDATION

11. CONTRACTOR REPRESENTATIVE FORMCHECKBOX

CONCUR FORMCHECKBOX

NON-CONCUR

12. CORRECTIVE ACTION ESTIMATED COMPLETION DATE

13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY

III. ACTION CORRECTED

14. FORMCHECKBOX

CONCUR FORMCHECKBOX

NON-CONCUR COR SIGNATURE AND DATE

15. COR REMARKS (REQUIRED)

6. CONTRACTOR REPRESENTATIVE REMARKS

File details come from the government source that posted it. Updated .