This is a Request for Bid issued by the Maine Department of Conservation's Forest Service on May 8, 2009, for vehicle modification and reconditioning services. The bid seeks qualified bidders to modify approximately 10 law enforcement vehicles to departmental specifications and simultaneously strip out and recondition an equal number of existing vehicles to their original wiring configuration. The vehicle fleet consists of seven 2009 Dodge 3/4 ton 4x4 pick-ups with 8-foot beds, two 2009 GMC half-ton 4x4 club cabs, and one 2009 GMC half-ton 4x4 pick-up with an 8-foot bed. The successful bidder is responsible for pickup and delivery of all vehicles at the Department of Conservation Bolton Hill facility located at 2870 North Belfast Avenue in Augusta, Maine. The successful bidder will be awarded an initial two-year contract with the department reserving the right to renew for up to three additional years in one-year increments based on performance metrics including work quality, delivery, and project management. The department anticipates an average workload of two vehicles per week, with potential increases to three vehicles per week based on operational needs.

Prior experience in modifying emergency response vehicles is mandatory, and the award of the bid will be based on a price per vehicle for both setup and strip-out work. Pricing submissions should include separate line items for the price per vehicle for modifications, price per vehicle for strip-outs, and an hourly rate for work not covered by the contract. The successful bidder must demonstrate flexibility to reprioritize vehicles based on departmental needs, maintain transparent project management and inventory tracking of departmental-owned parts and supplies, and allow inspection by a qualified electronics technician selected by the department representative. All materials and methods, including wiring, connectors, and hardware, require advance departmental approval. A bidders' meeting may be required after bid submission but before award, during which bidders must present prior experience, facility details, material and methods, and proof of insurance.

Text of this file

REQUEST FOR BID

MAINE FOREST SERVICE

MAY 8, 2009

The Department of Conservation (Maine Forest Service) is seeking bids to modify approximately 10 - law enforcement vehicles to the department’s specifications. In addition to modifying these new trucks, the successful bidder will also be expected to strip out and recondition the same number (10) of existing vehicles to their original wiring configuration prior to modification. The equipment removed from these vehicles will be bench tested and cleaned (if necessary). This equipment will be reinstalled in the new vehicles.

The vehicles to be modified will include approximately:

7 - 2009 Dodge 3/4 ton 4x4 pick ups with 8’ beds 2 - 2009 GMC ½ ton 4x4 pick ups club cabs.

1 – 2009 GMC ½ ton 4x4 pick up w/ 8’ bed.

The successful bidder will be expected to pick up and deliver all vehicles included in this bid at the Dept. of Conservation Bolton Hill facility located at 2870 North Belfast Ave. in Augusta, Me. 04330.

Award of this bid will be based on a price per vehicle set up and strip out. Prior experience in modifying emergency response vehicles will be a must.

Modifications to all vehicles will vary from make to make and possibly vehicle to vehicle. The department representative will notify the successful bidder of any changes to be made on a case by case basis. These changes could include but are not limited to installing different radios, sirens, etc. or installing emergency lights in different locations from vehicle to vehicle.

The successful bidder will be awarded a 2 year contract. The department reserves the right to renew the contract to the successful bidder for up to an additional 3 years in 1 year increments based on the performance of the bidder during the 2009 contract. The criteria to renew will be based on work quality and overall performance, such as delivery and project management.

The successful bidder will be expected to manage this project keeping the department representative informed as to the status of the vehicles, and the quantities of parts and supplies owned by the department that the bidder holds and uses for the installation into the vehicles.

The average number of vehicles that the department will require to be completed is 2 per week. That number may increase at any given time up to a maximum of 3 per week, based on the department’s needs.

The successful bidder must be flexible to stop working on one vehicle and complete another vehicle at any given time based on the department’s needs. This should be considered a priority project by the bidder.

The department reserves the right to inspect any and all vehicle modifications and installations. The inspection may take place at the bidders location or at the departments Bolton Hill facility located on Route 3 in Augusta. A qualified electronics technician selected by the department representative will conduct the inspection. All areas of work are to be inspected, and the recommendations of the technician are to be implemented as directed, not only on the inspected vehicle but on all subsequent vehicles as well.

The department will give the successful bidder a reasonable opportunity to make corrections needed to any or all vehicles as recommended by the technician selected by the department.

The department reserves the right to pull the contract from the successful bidder and award the contract to the next bidder in line, if the requirements listed in this document are not met as determined by the department representative.

All materials and methods used by the successful bidder for modifications will be approved in advance by the department representative. These materials include but are not limited to wiring, connectors, nuts and bolts, and all other hardware.

A meeting of the department representatives and bidders may be required after the bids have been sent in but before an award is made. All bidders should be prepared to present and discuss their plans for this project, prior experience, facility where project will take place, material and methods, and proof of insurance. The department representative will be prepared to the best of his ability to give more details for the project. All information discussed will be kept confidential.

maine DEPARTMENT OF CONSERVATION FOREST service

VEHICLE BID

Price per vehicle for modifications $______________________________________________

Price per vehicle for strip-outs $_________________________________________________

Price per hour for any work not covered by contract $______________________________

Signature of authorized representative___________________________________________

Company___________________________________________________________________

Date________________________________________________________________________

Other files

File Type Posted
Forest_Serv_Picture_A_2009.doc.crdownload CRDOWNLOAD file
FOREST_SERVICE_RADIO_CONSOLE_09(2).xls XLS spreadsheet
Solicitation_terms.doc DOC document
FOREST_SERVICE_OUTLINE_OF_WORK_20092.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .