2-Plans 10521 S Lake Ave Pond Downwell.pdf
PDF 1 MB Posted
- Solicitation number
- 2026-027
- Issued by
- Salt Lake County, Utah
About this file
This is a construction plans and specifications document for the City of South Jordan, Utah, detailing the standard notes and requirements for the installation of a stormwater drywell system at 10521 S Lake Avenue. The project involves the installation of a primary drywell chamber with a 4-foot diameter and an 8-foot-by-8-foot reinforced concrete footing, requiring a minimum overall depth to be determined by a geotechnical engineer. The work includes excavation, dewatering, installation of 50 linear feet of 4-inch PVC drain piping connecting to an existing stormwater chamber, placement of HDPE pipe materials for the complete drywell system, stabilization of materials, compaction and backfill operations, finish grading, site cleanup, and revegetation to existing conditions. The project must be substantially complete within 45 days of the Notice to Proceed, with an anticipated issuance date of October 13, 2026. Bids are to be submitted electronically through the State of Utah's Bonfire procurement website, with all submission times and deadlines controlled by that platform. The contractor is responsible for all mobilization and demobilization, traffic control, construction surveying and staking, material testing and quality control, labor, supplies, equipment, subcontractors, utilities, and overhead and profit.
The specifications document establishes comprehensive requirements for construction activities within South Jordan City right-of-way, including mandatory compliance with South Jordan City Construction Standards and Specifications, the APWA Manual of Standard Specifications, and MUTCD standards. Key requirements include obtaining all necessary permits and inspections, locating and protecting existing utilities at the contractor's expense, performing storm drain piping television inspection after compaction and prior to asphalt placement, installing geotextile fabric and filter materials as specified, achieving minimum compaction levels of 96% modified Proctor density, performing percolation testing after final installation, and submitting as-built drawings in DXF and PDF formats prior to 90 percent bond release. The contractor must comply with South Jordan City working hours of Monday through Friday, 7:00 a.m. to 4:00 p.m., and obtain prior written approval from the City Engineer for any overtime or weekend work. All stormwater construction activities require a Utah Pollutant Discharge Elimination System permit and a Storm Water Pollution Prevention Plan managed through the City's online system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Bid Documents - Lake Ave Storm Water Drywell Installation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOUTH JORDAN CITY
S-01 - 03
SHEET INDEX
10521 S LAKE AVE POND DOWNWELLS
COVER SHEET / INDEX
STANDARD NOTES
VICINITY MAP
PROJECT LOCATION
10521 S LAKE AVE
A HTU
SOUTHJORDAN
S.
J.
C
AN
AL
U .S
.L .C
AN
AL
U .L
.D .C
AN
AL
W .J
. C
AN
AL
W
U-111
11400 S
10600 S
9800 S
10400 S
W
W
W
W
I-1
W . 13
W
OLD BINGHAM HWY 10200 S
BINGHAM CREEK
BA
N
G
ER
TE
R
H W
Y
M O
U N
TA
IN
V
IE
W C
O R
R
ID
O R
R
ED
W O
O D
R O
AD
JO
R
D
AN
R
IV
ER
JO
R
D
AN
G
AT
EW
AY
PR
O
SP
ER
IT
Y
R D
11800 S
10000 S
No. 173076-2202
BRAD
KLAVANOPR
O
FE
SS IONAL ENG INEER
* STAT E OF UTAH
MIDAS CREEK
G R
AN
D
VI
LL
E
AV
E
S JO
RDAN PKWY
LAKE AVE
DAYBREAK PKWY
U -1
BA
C C
H U
S H
W Y
KANE
SAN JUAN
GARFIELD
WAYNE
PIUTEBEAVER
IRON
WASHINGTON
MILLARD
SEVIER
EMERY GRAND
JUAB
UTAH
CARBON
SANPETE
TOOELE
BOX ELDER
SALT
LAKE
WASATCH DUCHESNE
UINTAH
DAGGETTSUMMIT
DAVIS
MORGAN
WEBER
RICHCACHE PROJECT LOCATION
SOUTH JORDAN CITY
SP-01 SITE PLAN
DT-01 DOWNWELL DETAILS AND SPECIFICATIONS
CHAPTER 1
STANDARD NOTES
(Updated 3-19-24)
The South Jordan City Standard Notes are required to be included as part of all construction plans for residential or commercial development. Plans submitted by public or private entities for all other types of projects within City right-of-way, its easements or property shall reference the South Jordan City Standard Notes and Specifications.
1.1 South Jordan City General Notes
1. All work done or improvements installed within South Jordan City including but not limited to excavation, construction, roadwork and utilities shall conform to the South Jordan City Construction Standards and Specifications, City Municipal Code, the latest edition of the APWA Manual of Standard Specifications and Manual of Standard Plans, the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD) and any state or federal regulations and permit requirements of various governing bodies. The contractor is responsible to have a copy of these specifications and to know and conform to the appropriate codes, regulations, drawings, standards and specifications.
2. The existence and location of any overhead or underground utility lines, pipes, or structures shown on these plans are obtained by a research of the available records. Existing utilities are located on plans only for the convenience of the Contractor. The contractor shall bear full responsibility for the protection of utilities and the engineer bears no responsibility for utilities not shown on the plans or not in the location shown on the plans. This includes all service laterals of any kind.
The Contractor shall, at his own expense, locate all underground and overhead interferences, which may affect his operation during construction and shall take all necessary precautions to avoid damage to same. The Contractor shall use extreme caution when working near overhead utilities so as to safely protect all personnel and equipment, and shall be responsible for all cost and liability in connection therewith.
3. The Contractor shall take all precautionary measures necessary to protect existing utility lines, structures, survey monuments and street improvements which are to remain in place, from damage, and all such improvements or structures damaged by the Contractor's operations shall be repaired or replaced satisfactory to the City Engineer and owning utility company at the expense of the Contractor.
4. All construction shall be as shown on these plans, any revisions shall have the prior written approval of the City Engineer.
5. Permits are required for any work in the public way. The Contractor shall secure all permits and inspections required for this construction.
6. Curb, gutter, and sidewalk, found to be unacceptable per City Standards and APWA shall be removed and replaced.
7. Contractor shall provide all necessary horizontal and vertical transitions between new construction and existing surfaces to provide for proper drainage and for ingress and egress to new construction. The extent of transitions to be as shown on plans.
8. Any survey monuments disturbed shall be replaced and adjusted per Salt Lake County Surveyors requirements.
9. All privacy walls, new or existing, are only shown on civil plans for the purpose of reviewing grading relationships; flood control and sight distance at intersections. All walls shall have a minimum 2 ft x 2 ft x 30 inch deep spot footings. Bottom of all footings on all walls shall be a minimum of 30 inches below finished grade. Walls greater than 6 feet require a separate permit and inspection by the Building Department.
10. All construction materials per APWA must be submitted and approved by the City Engineer prior to the placement of asphalt within City Right of Way.
11. Request for inspection by the City of South Jordan engineering dept. shall be made by the contractor at least 48 hours before the inspection services will be required, except in an emergency as defined by the South Jordan City Municipal Code § 12.08.010.
12. Work in public way, once begun, shall be prosecuted to completion without delay as to provide minimum inconvenience to adjacent property owners and to the traveling public.
13. The contractor shall take all necessary and proper precautions to protect adjacent properties from any and all damage that may occur from storm water runoff and/or deposition of debris resulting from any and all work in connection with construction.
14. Power poles and/or other existing facilities not in proper location based on proposed improvements shown hereon will be relocated at no expense to the City of South Jordan. Power lines and all other aerial utilities are to be buried and poles removed as determined by the City Engineer.
15. Curb and gutter with a grade of less than four-tenths of one percent shall be constructed by forming. Each joint shall be checked for a grade prior to construction and water tested as soon as possible after construction.
16. Contractor to follow Salt Lake County Noise Ordinance Standards.
17. Contractors are responsible for all OSHA requirements on the project site.
18. A UPDES (Utah Pollutant Discharge Elimination System) permit is required for all construction activities as per state law as well as providing a Storm Water Pollution Prevention Plan to the City.
19. Developer is responsible for locating and repairing all underground streetlight wires, water lines, storm drain lines and irrigation lines until 90% of the bond has been released.
20. All City maintained utilities including; waterline, fire hydrants, streetlight wiring, and storm drain must be in public right of way or in recorded easements.
21. Contractor shall work South Jordan City regular working hours of Monday through Friday 7:00 am to 4:00 pm. If Contractor permits overtime work or work on a Saturday, Sunday or any legal holiday, Contractor shall receive prior approval by City Engineer. Contractor shall obtain all permits and pay Overtime Inspection Fee’s to The City of South Jordan on the Thursday prior to the Saturday, Sunday or legal holiday requested. This applies to all work within the public right of way including traffic control and access..
22. Prior to 90% bond release, a legible as-built drawing must be submitted to the City of South Jordan stamped and signed by a professional engineer. As-builts must show all changes and actual field locations of storm drainage, waterlines, irrigation, street lighting, and power. As-builts will be held to the same standard as approved design drawings, no “redlined plans” allowed. In the absence of changes, copies of the approved drawings will be required stating “installed as per drawings”. As-built drawings for new developments shall be submitted to the City in the following formats and quantities prior to the 90% bond release: 1 .dxf copy, 1 .pdf copy.
23. Filter fabric wrapped around an inlet grate is not an acceptable inlet sediment barrier. See Chapter 9 of South Jordan City Construction Standards and Specifications for details of approved storm water BMPs.
24. Asphalt paving between October 15 and April 15 is not allowed without a written exception from the Engineering Department.
25. To ensure proper planting, protection and irrigation of trees, mitigating risk of tree failure or future damage to infrastructure, contractors are required to follow the standards and specifications of the ISA - International Society of
Arboriculture.
26. All small cell construction must follow the South Jordan Small Cell Infrastructure Design Guidelines.
27. All construction of Low Impact Development (LID) must follow the South Jordan City Low Impact Development Handbook 2020. With the development of any residential subdivision that proposes LID in public park strips, the developer must construct/install such to completeness, including but not limited to vegetation and landscape irrigation. The developer is responsible to maintain the LID (including landscape) until such time the developer connects any LID landscape irrigation to owner’s irrigation of the respective building lot.
Developer’s LID maintenance responsibilities include but not limited to cleaning, repairing, protecting and clear of any debris. The building lot owner shall maintain in perpetuity any LID constructed anywhere on the building lot, including the park strip area within public right of way.
28. When a proposed development borders a collector, minor collector or arterial street and is required to construct collector street fencing along the back of sidewalk, the development shall also be required put in a concrete mow strip from the back of sidewalk to underneath the fence panels. Concrete mow strips shall also be required between the sidewalk and fencing along the rear of double frontage lots
29. One-way valves are required on residential land drain lines that go from a foundation drain on a home to a public storm drain system.
1.2 City of South Jordan Traffic Notes
1. When a designated “Safe Route To School” is encroached upon by a construction work zone the safe route shall be maintained in a manner acceptable to South Jordan City and the Jordan School District.
2. If the improvements necessitate the obliteration, temporary obstruction, temporary removal or relocation of any existing traffic pavement marking, such pavement marking shall be restored or replaced with like materials to the satisfaction of the City Engineer, Public Works Director or designee.
3. The street Sign Contractor shall obtain street names and block numbering from the Planning Department prior to construction.
4. The Contractor shall be responsible for providing and installing all permanent signs shown on the plans. Street name signs shall conform in their entirety to current City Standards. All other signs shall be standard size unless otherwise specified on the plans. All sign posts shall be installed in accordance with the current City Standards.
5. All permanent traffic control devices called for hereon shall be in place and in final position prior to allowing any public traffic onto the portions of the road(s) being improved hereunder, regardless of the status of completion of paving or other off-site improvements called for per approved construction drawings unless approved by the City Engineer.
6. The Contractor shall be responsible for notifying Utah Transit Authority (UTA) if the construction interrupts or relocates a bus stop or has an adverse effect on bus service on that street to arrange for temporary relocation of stop.
7. Before any work is started in the right-of-way, the contractor shall install all advance warning signs for the construction zone. The contractor shall install temporary stop signs at all new street encroachments into existing public streets.
All construction signing, barricading, and traffic delineation shall conform to the Manual of Uniform Traffic Control Devices (MUTCD) per the current edition adopted by UDOT and be approved by the City of South Jordan before construction begins.
8. All signs larger than 36” X 36” or 1296 square inches per sign pole shall be mounted on a Slip Base system per UDOT standard drawing SN 10B (detail drawing attached to standard drawings) with a “Z” bar backing. Signs of this size are not allowed to be mounted on a yielding pole.
9. Sign components such as sheeting, EC film, inks, letters and borders are all required to be from the same manufacturer. Only EC film may be used to achieve color. Vinyl EC film is not accepted.
10. All new roundabouts, crosswalks, stop bars and legends shall be installed with 90 mil preformed thermo plastic.
11. Stop Lines are required anytime a stop sign is installed.
12. Paving asphalt binder grade shall be PG 58-28 unless otherwise approved by the City Engineer. Asphalt aggregate size shall be ½ inch for residential and collector roads. No more than 15% RAP (reclaimed asphalt pavement) by weight will be allowed in the asphalt mix design for the paving of public and private streets. Up to the 15 percent will be allowed with no change in the specific binder grade. The asphalt mix design shall have no more than 3½ % air voids.
13. Potholing: All potholes must be saw cut square and have a minimum size of 1 square foot. When repairing a pothole, sand or pea gravel meeting South Jordan City standards shall be placed over the exposed utility to a depth of 6 inches. Following the pea gravel will be flowable fill up to 1 inch below the bottom edge of the existing asphalt. The remaining portion of the hole shall be filled with asphalt, which will have an overall thickness of the existing asphalt plus 1 inch.
14. All fill within the public right of way shall be A-1-A to A-3, with the exception of top soil in the park strip for landscaping and trench backfill. Trench backfill material under pavements or surface improvements shall be clean, nonclumping, granular and flowable, 2” minus, A-1-a to A-2-7 soils according to AASHTO 145 soil Classification System. Lime treated flowable fills, if approved, shall have a 28-day strength of 65 PSI.
15. All traffic road closures involving 1 or more lanes of traffic must receive prior approval from the City Engineer or his/her representative. VMS PCMS boards must be placed a minimum of 7 days in advance of any lane closure on collector,minor collector or arterial street. VMS PCMS boards must also be placed in advance of any lane closures on a subdivision street per the City Engineer’s direction.
16. Roundabouts, including their ingress and egress, shall be constructed with concrete pavement. Engineer shall design cross section and submit to the City for review and approval.
17. Alleyways and Lanes are to have 6 feet maximum spacing for control joints in straight sections and are to have an expansion joint every 60 feet and at all pc's and pt's.
18. Construction of any public street requires a sign off checklist prior to the road being opened to traffic for use by the general public. The checklist must be requested by the Developer. The City's assigned project engineer will prepare the checklist and provide it to the Developer/Contractor.
19. Trees are not allowed to be planted with 30' of a stop sign.
20. Traffic signal poles, mast arms and luminaire extensions must be black powder coated.
1.4 City of South Jordan Grading Notes
1. In the event that any unforeseen conditions not covered by these notes are encountered during grading operations, the Owner and City Engineer shall be immediately notified for direction.
2. It shall be the responsibility of the Contractor to perform all necessary cuts and fills within the limits of this project and the related off-site work, so as to generate the desired subgrade, finish grades and slopes shown.
3. Contractor shall take full responsibility for all excavation. Adequate shoring shall be designed and provided by the Contractor to prevent undermining of any adjacent features or facilities and/or caving of the excavation.
4. The Contractor is warned that an earthwork balance was not necessarily the intent of this project. Any additional material required or leftover material following earthwork operations becomes the responsibility of the Contractor.
5. Contractor shall grade to the lines and elevations shown on the plans within the following horizontal and vertical tolerances and degrees of compaction, in the areas indicated:
Horizontal Vertical Compaction
a. Pavement Area Subgrade 0.1'+ +0.0' to -0.1' See soils Report
b. Engineered Fill 0.5'+ +0.1' to -0.1' See Soils Report
Compaction Testing will be performed by the developer or his representative.
6. All cut and fill slopes shall be protected until effective erosion control has been established.
7. The use of potable water without a special permit for building or construction purposes including consolidation of backfill or dust control is prohibited. The Contractor shall obtain all necessary permits for construction water from the Public Works Department.
8. The Contractor shall maintain the streets, sidewalks and all other public right-of-way in a clean, safe and usable condition. All spills of soil, rock or construction debris shall be promptly removed from the publicly owned property during construction and upon completion of the project. All adjacent property, private or public shall be maintained in a clean, safe and usable condition.
9. In the event that any temporary construction item is required that is not shown on these drawings, the Developer agrees to provide and install such item at his own expense and at the direction of the City Engineer. Temporary construction includes ditches, berms, road signs and barricades, etc.
10. All grading work shall conform to the soils report as prepared by the Soils Engineer and approved by the City Engineer, and as shown on these plans.
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\S ta nd ar d
N ot es
-1 9-
.d w g
8/ 5/
S-01
JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
S
LA
KE
A
VE
P
O N
D D
O W
N W
EL
LS
ST
AN
D
AR
D N
O
TE
S
No. 173076-2202
BRAD
KLAVANOPR
O
FE
SS IONAL ENGINEER
* STAT E OF UTAH
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\S ta nd ar d
N ot es
-1 9-
.d w g
8/ 5/
25JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
CHAPTER 6
STORM DRAIN
(Updated 3-19-24)
SECTION 6.1
GENERAL
6.1.1 GENERAL
A. Storm Water Pollution Prevention Plan:
1. Shall be required for all construction activities as required under the Utah Pollutant Discharge and Elimination System (UPDES) permits and the following:
a) Construction sites with a land disturbance of greater than or equal to one acre, including projects less than one acre that are part of a larger common plan of development or sale.
b) Construction sites related to residential building that disturb a total of one acre or less of land.
c) Any construction activity the City Engineer or Designee deems to pose a unique threat to water quality, air quality, or public health or safety.
2. SWPPP shall be managed through the South Jordan City online storm water management system.
a) All BMP’s covering a storm drain inlet must contain an overflow feature for high volume rain/runoff events. Reference chapter 9 for acceptable inlet protection.
B. Storm Drain pipe in public right of way shall be minimum 18” RCP Class III or
HDPE.
1. Storm Drain lines shall be TV’ed by the contractors hired firm after placement and compaction of road base and prior to placing asphalt. This TV’ed disk shall be reviewed by the City designated Inspector. All areas found defective shall be repair to the satisfaction of the City Inspector before placing asphalt.
2. Storm drain caution tape shall be place and centered 1’ above the pipe.
3. Storm Drain lines will be TV’ed again, by City personnel prior to final bond release. All lines shall be cleaned by Developer prior to City performing the work. Any damaged pipe sections shall be repaired or replaced prior to final bond release.
C. Mirafi filter fabric may be required depending on the presence of groundwater, as determined by the City Engineer.
D. Manholes: Keep the manhole collar and cover down ¼” minimum and ½” maximum below finish asphalt grade. This will allow snowplows to pass over the top without hitting or damaging them, in the winter months.
Storm Drain manhole lid specifications: ASTM A 48-93, Class 35B Cast iron construction, machined flat bearing surface, removable lid with cleated surface and pick holes, H-20 highway load rating; lid molded with South Jordan City name and logo imprinted on lid; Provide Model A-1180 manufactured by D & L Supply., or acceptable equal. (See drawings section for detail.)
E. Developments must provide theft-resistant permanent installation of a City-approved storm drain marker at each storm water inlet. The marker item number is SD-SP, a stainless steel, painted blue, matte finish, embossed, fish symbol, optional serialization, 30 year warranty, with ¼” square hole made by Almetek Industries, Inc. Installation requires drive rivet and approved adhesive.
Lettering on the marker as appropriately follows:
“Only Rain in the Drain” markers installed anywhere storm water discharges to a retention or detention pond. (See drawings section for detail.)
F. A cleanout box with 24” silt trap is required before a private storm water system enters the City’s storm drain system. All private storm drainage conveyance systems shall also have a snout in place or an oil water separator system, approved by the City Engineer, before it discharges into the city system.
Facility’s that use large amounts of hydrocarbons such as gas stations, vehicle lube facilities, vehicle repair, and or paving facilities, shall be required to have a hydrodynamic separator in place prior to discharging into the city system, unless otherwise approved by the City Engineer or Public Works Director.
G. The first storm drain inlet box down gradient from a dumpster enclosure shall be required to have a snout and a 24” minimum silt trap, or larger as required by manufacturer recommendations for snout installation.
H. Silt traps are required for all catch basins, inlets, manholes etc. Silt traps shall be 12” deep, measured from invert of lowest pipe to bottom of box.
I. Boxes: During installation, grout boxes inside and out, and strip the forms from inside and outside of the boxes. Clean all dirt, rocks and debris from inside of the boxes. If using a pre-cast box, make sure to form a 6” collar around the outside of box with soil below pipe dug down and formed, and poured with concrete to engineering inspectors discretion. Before pouring concrete collar, contractor shall give engineering inspector 24-hour prior notice.
Inlet and combo boxes shall be precast or knockout boxes (unless otherwise approved by the City Engineer) and must accommodate an 18” x 48” frame and grate. Hooded grates are not allowed due to debris accumulating in the storm drain.
J. All onsite retention and detention basins shall be designed for a 100 year 24 hour storm event. The calculations and storm intensities used in the design must be submitted to the city for review and approval. Percolation rates are not allowed to be used in the capacity calculations for the storm water basins unless otherwise approved by the City Engineer. Retention basins shall be required to drain within 3 days of the storm event. Engineer shall provide a design that meets that criteria.
All calculations must be stamped and signed by a registered professional engineer.
K. For residential developments with underground storm water storage systems, storm drain calculations will not be allowed to include the void space in the gravel towards the total storage volume capacity. For commercial developments with underground storm water storage systems, storm drain calculations will not be allowed to include the void space in the gravel towards the total storage volume capacity unless approved by the City Engineer on a case by case basis. Projects allowed to count the gravel void space will need to show an acceptable overflow path for the storm water, in case the underground storage were ever to over top.
In addition, the storm water drainage system will require an approved separator unit to filter out sediment, oils and debris from the storm water prior to it entering the underground storm water storage chambers.
SECTION 6.2
REINFORCED CONCRETE PIPE
6.2.1 DESCRIPTION
This item shall govern for the furnishing and installing of reinforced concrete pipe and materials for construction.
6.2.2 MATERIALS
A. Pipe Type:
Shall be minimum 18”, RCP Class III.
B. Bedding and Backfill (RCP):
A City specified material (A-1-a to A-2-7 under AASHTO Soil Classification system) will be used for trench backfill. Place 1”minus gravel 6 inches under pipe and up to spring line (no squeegee or chips). Tamp underneath the haunches to prevent settlement. Compaction of 96% modified proctor is required.
SECTION 6.3
POLYPROPYLENE PIPE
6.3.1 DESCRIPTION
This item shall govern for the furnishing and installing of all Polypropylene Pipe, materials for construction and all related connections and fittings.
6.3.2 MATERIALS
Unless otherwise specified on the plans, pipe and joint fittings shall conform to the following:
A. Eighteen through 60-inch (460 through 1500 mm) pipe shall be smooth interior and annular exterior corrugated polypropylene (PP) pipe meeting the requirements of ASTM F2881 or AASHTO M330, Type S, for respective diameters. The pipe supplied shall be watertight as defined in the joint performance requirements of this specification.
B. Virgin material for 18 through 60-inch pipe and fitting production shall be an impact modified copolymer meeting the material requirements of ASTM F2881 and AASHTO M330, for respective pipe diameters.
C. Joints shall be installed in accordance with manufacturer’s installation instructions. All Bell-and-Spigot pipe joints shall be thoroughly cleaned. Joint lubricant, supplied by the manufacturer, shall be liberally applied to entire interior of bell and gasket on spigot prior to assembly. Watertight joints shall be bell-and-spigot meeting the watertight requirements of ASTM F2881. Gaskets shall be made of polyisoprene meeting the requirements of ASTM F477. Gaskets shall be installed by the pipe manufacturer and covered with a removable wrap to ensure the gasket is free from debris. A joint lubricant supplied by the manufacturer shall be used on the gasket and bell during assembly.
D. Fittings shall conform to ASTM F2881, with the exception of meeting the watertight joint performance requirements of ASTM D3212. Bell & spigot connections shall utilize a spun-on, welded or integral bell and spigot with gaskets meeting ASTM F477.
6.3.3 INSTALLATION
Installation shall be in accordance with the product manufacturer’s published installation guides and these instructions.
A. All pipe and fittings shall be delivered to the site and unloaded with handling that conforms to the manufacturer’s instructions for reasonable care. Pipe shall not be rolled or dragged over gravel or rock during handling. The Contractor shall take necessary precautions to ensure the method used in lifting or placing the pipe does not induce undue stress fatigue in the pipe.
B. Bedding and Backfill:
Bedding shall be gravel or compacted road base as per South Jordan City standards. A stable and uniform bedding shall be provided for the pipe and any protruding features of its joint and/or fittings. The middle of the bedding, equal to one-third of the pipe outside diameter, shall be loosely placed while the remainder shall be compacted to a minimum of 96% of maximum density per AASHTO T99, or as shown in the plans. Pipe bedding shall be a minimum of 4” – 6” in thickness. The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe. Backfill shall be placed in layers of 8” loose lift thickness and brought up evenly and simultaneously on both sides of the pipe to an elevation not less than one foot (1’) above the top of the pipe. Each layer shall be thoroughly compacted; backfill shall be compacted to a minimum compaction level of 96% Density (Modified Proctor).
C. Trench Widths - Where trench walls are stable or supported, provide a width sufficient, but no greater than necessary, to ensure working room to properly and safely place and compact haunching and other embedment materials. The space between the pipe and trench wall must be wider than the compaction equipment used in the pipe zone. Minimum width shall be not less than the greater of either the pipe outside diameter plus 16 in. or the pipe outside diameter times 1.25, plus 12 in. In addition to safety considerations, trench width in unsupported, unstable soils will depend on the size and stiffness of the pipe, stiffness of the embedment and in-situ soil, and depth of cover.
D. Dewatering - Do not lay or embed pipe fittings or drainage structures in standing or running water. At all times prevent runoff and surface water from entering the trench. When water is present in the work area, dewater to maintain stability of in-situ and imported materials. Maintain water level below pipe bedding and foundation to provide a stable trench bottom. Use, as appropriate, sump pumps, well points, deep wells, geofabrics, perforated underdrains, or stone blankets of sufficient thickness to remove and control water in the trench. When excavating while depressing ground water, ensure the ground water is below the bottom of cut at all times to prevent washout from behind sheeting or sloughing of exposed trench walls. Maintain control of water in the trench before, during, and after pipe system installation and until embedment is installed and sufficient backfill has been placed to prevent flotation of the pipe, fitting, or drainage structures. To preclude loss of soil support, employ dewatering methods that minimize removal of fines and the creation of voids in in-situ materials.
No. 173076-2202
BRAD
KLAVANOPR
O
FE
SS IONAL ENGINEER
* STAT E OF UTAH
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\S ta nd ar d
N ot es
-1 9-
.d w g
8/ 5/
S-02
JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
S
LA
KE
A
VE
P
O N
D D
O W
N W
EL
LS
ST
O
R M
D R
AI
N
N O
TE
S
ABBREVIATION LIST
SIGN
CONIFEROUS TREE
BUSH
DECIDUOUS TREE
CABLE TV RISER
GUY WIRE ANCHOR
POWER OR UTILITY POLE
STREET LIGHT POLE
WATER METER
FIRE HYDRANT
GAS METER
WATER VALVE
GAS VALVE
MAILBOX
WATER MANHOLE
TELEPHONE MANHOLE
STORM DRAIN MANHOLE
SANITARY SEWER MANHOLE
SET PROPERTY CORNER
FOUND PROPERTY CORNER
POST / BOLLARD
GAS MANHOLE
ELECTRICAL MANHOLE
HEDGE / TREE LINE
CATCH BASIN
ELECTRICAL BOX
GAS
G
CONTROL POINT
SECTION CORNER
BENCHMARK OR STREET MONUMENT
SYMBOLS
DY
H
IRRIGATION VALVE
IRR
CABLE TV
GAS
IRRIGATION
POWER OVERHEAD
SANITARY SEWER
STORM DRAIN
WATER
TELEPHONE
IRRIGATION BOX
E
T
SD
SS
W
UTILITY LINETYPES EXISTING
UTILITY LINETYPES PROPOSED
SD COMBO BOX
GM
E
BURIED FIBER OPTIC
ELECTRIC TRANSFORMER
W
15 15
W
TELEPHONE OVERHEAD
POWER
FIBER OPTIC DUCT
CABLE TV OVERHEAD
IRRIGATION
STORM DRAIN
WATER
IRR
SD
W
No. 173076-2202
BRAD
KLAVANOPR
O
FE
SS IONAL ENGINEER
* STAT E OF UTAH
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\S ta nd ar d
N ot es
-1 9-
.d w g
8/ 5/
S-03
JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
S
LA
KE
A
VE
P
O N
D D
O W
N W
EL
LS
AB
BR
EV
IA
TI
O
N L
IS
T
AN
D
L
EG
EN
D
PROPERTY LINETYPES
RIGHT OF WAY
CONSTRUCTION EASEMENT
PROPERTY LINE
ROW
C/E
AC ASPHALT CONCRETE
APWA AMERICAN PUBLIC WORKS ASSOCIATION
BOW BACK OF WALK
CB CATCH BASIN
C/E CONSTRUCTION EASEMENT
C&G CURB AND GUTTER
℄ CENTERLINE
CMP CORRUGATED METAL PIPE
CO CLEAN OUT
COM COMMUNICATION
CONC CONCRETE
CY CUBIC YARD
DIA DIAMETER
DIP DUCTILE IRON PIPE
DWG DRAWING
DWY DRIVEWAY
Eg EXISTING GROUND
ELEV ELEVATION
ELEC ELECTRICAL
EOC EDGE OF CONCRETE
EOP EDGE OF PAVEMENT
EX EXISTING
FG FINISH GROUND
FL FLOW LINE
FLG FLANGE
FNC FENCING
FT FOOT
GB GRADE BREAK
GND GROUND
HP HIGH POINT
HYD FIRE HYDRANT
ID INSIDE DIAMETER
IN INCH
INV INVERT
IRR IRRIGATION
L LENGTH
LF LINEAR FEET
LT LEFT TURN
MAX MAXIMUM
MH MANHOLE
MID MID POINT OF CURVE
MIN MINIMUM
MJ MECHANICAL JOINT
NTS NOT TO SCALE
OH OVERHEAD
PC POINT OF CURVATURE
POB POINT OF BEGINNING
PSI POUND PER SQUARE INCH
PP POWER POLE
⅊ PROPERTY LINE
PRC POINT OF REVERSE CURVE
PT POINT OF TANGENCY
PUE PUBLIC UTILITY EASEMENT
PVC POLYVINYL CHLORIDE
PVI POINT OF VERTICAL INTERSECTION
R RADIUS
REQ'D REQUIRED
ROW RIGHT OF WAY
RT RIGHT TURN
S SLOPE
SD STORM DRAIN
SS SANITARY SEWER
STA: STATION
STD STANDARD
S/W SIDEWALK
T TANGENT
TBC TOP BACK OF CURB
TEMP TEMPORARY
TG TOP OF GRATE
TYP TYPICAL
UTBC UNTREATED BASE COURSE
C
TELEPHONE / COMM RISERT
AutoCAD SHX Text catv
AutoCAD SHX Text g
AutoCAD SHX Text irr
AutoCAD SHX Text pwr[oh]
AutoCAD SHX Text ss
AutoCAD SHX Text sd
AutoCAD SHX Text w
AutoCAD SHX Text tel
AutoCAD SHX Text bfo
AutoCAD SHX Text tel[oh]
AutoCAD SHX Text pwr
AutoCAD SHX Text fo[duct]
AutoCAD SHX Text catv[oh] sd sd sd sd sd
SD
SD
SD
SD
SD
SECONDARY DOWN WELL LOCATION
RIM ELEV= MATCH EXISING GROUND
N: 7373129.02 E: 1500276.99
SEE SHEET DT-01 FOR DETAILS
(FIELD TO VERIFY FINAL LOCATION)
Existing Storm Drain Bubble Up
SDCONNECT
4" PVC TO EXISTING DOWN
WELL
INSTALL 50 L.F. OF 4" PVC DRAIN LINE
PRIMARY DOWN WELL LOCATION
RIM ELEV= MATCH EXISTING GROUND
N: 7373121.76 E: 1500290.12
SEE SHEET DT-01 FOR DETAILS
(FIELD TO VERIFY FINAL LOCATION)
-1.00%
Existing Storm Drain Injection Well
(RIM ELEV= 4795.93)
N: 7373082.19 E: 1500259.55
N
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\1
S L ak e
Av e
Po nd
D ow nw el l S ite
P la n.
dw g
8/ 5/
SP-01
JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
S
LA
KE
A
VE
P
O N
D D
O W
N W
EL
LS
SI
TE
P
LA
N
BRAD
KLAVANOPR
O
FE
SS IONAL ENGINEER
* STA T E OF UTAH
No. 173076-2202
LAKE AVE
10521 S LAKE AVE
4.00'Ø
4.00' DIA.
1.00'
10.00'
15.00'
4.00'Ø
SETTLING
CHAMBER
DEPTH
10.00' MIN.
10.00'
OVERALL DEPTH
TO BE DETERMINED
BY
GEOTECHNICAL
ENGINEER
22 6
11 11
12.50' 12.50'
1.00'1.00'
CONE HEIGHT
VARIES
6" -1.0% SLOPE
6"
8.00'
4.00'Ø
#4 BARS @ 6" O.C.
BOTH WAYS, TOP AND BOTTOM
MAINTAIN 3" CLEAR.
#4 BARS - INSTALL 3" CLEAR.
TOP AND BOTTOM, EDGE OF
HOLE.
8.00'
C he ck ed
B y:
D at e:
D es ig ne d By
D ra w n
By
N O
D
AT
E
R
EV
IS
IO
N C
O M
M
EN
TS
W es t T ow ne C en te r D r.
/ S ou th J or da n, U
T
Te le ph on e:
(8
) 2
-3
/ W eb
: W W
W .S
JC
.U
TA
H
.G O
V
A H
T U
SO
U T H
JO
R D A N
F:
\E
N G
IN
EE
R
IN
G \C
IP
P ro je ct s\ La ke A ve S to rm
W at er D ry w el l I ns ta lla tio n\ C
AD
\S
JC
D ry w el l D et ai l L ak e Av e Po nd .d w g
8/ 5/
DT-01
JW
H JW
H
SO
U
TH
J
O R
D
AN
C
IT
Y
S
LA
KE
A
VE
P
O N
D D
O W
N W
EL
LS
D R
YW
EL
L
SY
ST
EM
D
ET
AI
LS
A N
D S
PE
C
IF
IC
AT
IO
N S
BRAD
KLAVANOPR
O
FE
SS IONAL ENGINEER
* STA T E OF UTAH
No. 173076-2202
MODIFIED FLAT-BOTTOM MANHOLE CONE
(NOT USED)
MIN. 30" DIA BOLTED CAST IRON RING AND SOLID SOUTH JORDAN CITY STORM DRAIN COVER
GRADED BASIN, CITY VAC TRUCK ACCESS TO BE PROVIDED AT A MIN HORIZONTAL DISTANCE OF 15' AND NO MORE THAN 8% INCLINE
FROM EACH MANHOLE LID
COMPACTED BASE MATERIAL
CONCRETE LINER, 4000 PSI 48" I.D. AND 54" O.D., CENTER IN HOLE WITH 2-FT X 2-FT OPENING IN BOTTOM FOR DRAINAGE
8-FT X 8-FT X 1-FT REINFORCED CONCRETE FOOTING (SEE DETAIL)
6" DIA CONE SHAPED SCREEN10
6" DIA SCH 40 PVC OVERFLOW PIPE
6" DIA DR-14 FUSED HDPE PIPE
1" TO 1-1/2" WASHED ROCK
6" DIA SLOTTED DR-14 FUSED HDPE PIPE
MIN. 4' DRILLED SHAFT
FABRIC SEAL, UV RESISTANT GEOTEXTILE. COVER GRATE UNTIL PAVING AND OR LANDSCAPING IS COMPLETE.17
4" DIA SCH 40 PVC CONNECTOR PIPE W/ VENTED ANTI-SIPHON INTAKE & FLOW REGULATOR, PIPE TO BE FULLY CAPPED UNTIL BASIN
FULLY VEGETATED OR AS APPROVED BY CITY ENGINEER.
A1A TO A2.7 COMPACTED BACKFILL TO 96%20
(2) LAYER OF FILTER FABRIC
KEYED NOTES
NON-WOVEN GEOTEXTILE FABRIC MIRFI 140 NL. OR APPROVED EQUALL. FABRIC TO BE DIAMETER OF HOLE, HELD APPROX 15' OFF
THE BOTTOM OF EXCAVATION.
DRY WELL SYSTEM
1. PRIMARY CHAMBER REQUIRED ON ALL DRY WELL SYSTEMS.
2. NO OUTSIDE PIPE CONNECTIONS TO PRIMARY OR SECONDARY CHAMBERS. ONLY SURFACE DRAINAGE IS
ALLOWED
3. PERCOLATION TEST TO BE PERFORMED AFTER FINAL INSTALLATION OF DRY WELLS AND LANDSCAPING.
NOTES
(2) LAYERS OF NON-WOVEN GEOTEXTILE FABRIC MIRAFI 140 NL. OR APPROVED EQUALL. PLACED AFTER OVERFLOW PIPE HAS BEEN
INSTALLED
LADDER RUNGS
SUPPORT BRACKET (TYP), FORMED 12 GA STEEL, FUSION BONDED EPOXY COATED
4" DIA 1" LONG SLOTTED SCH 40 PVC INTAKE SCREEN
CONCRETE FOOTING