2-Part III.pdf

PDF 449 KB Posted

Attached to
HMGP Acquisition/Demolition Project - Renovo Borough, Clinton County, PA
Solicitation number
Not on record
Issued by
Columbia County, Pennsylvania

About this file

Summary

This is a Technical Specifications document (Part III) for the HMGP Acquisition/Demolition Project in Renovo Borough, Clinton County, Pennsylvania. The project involves the demolition of 16 connected residential structures and associated ancillary buildings located at 133-163 14th Street in Renovo Borough. The work includes removal of all structures, basements to 4.5 feet below grade, garages, sheds, private sidewalks, rubbish, and asbestos abatement as needed, with property restoration upon completion. Public sidewalks and curbs are to remain in place unless damaged during demolition, in which case the contractor must replace them at no additional cost. The sealed bid opening is scheduled for April 8, 2026 at 11:00 A.M. local time via the PennBid program. The technical specifications address detailed requirements for mobilization and closeout, traffic control maintenance, dust control, water pollution control, submittals, temporary facilities, erosion and sedimentation control, concrete work, site clearing, excavation, backfill, compaction, and grading and seeding. All structures have been declared unsafe to enter and require continuous adequate wetting during demolition to prevent asbestos particle release, with the Engineer's Certified Asbestos Inspector present on-site during the demolition process.

Mobilization and closeout costs, including mobilization, demobilization, insurance, bonds, permits, inspection fees, traffic control plans, audio-video documentation, schedules, cleaning, and restoration, are included in a lump-sum bid price with fifty percent payable upon five percent contract completion and fifty percent payable upon final completion of all work and restoration. Traffic control expenses are billed at seventy-five percent prorated over contract duration with twenty-five percent held until substantial completion. All submittals, shop drawings, samples, CPM schedules, dust control, water pollution control, site clearing, excavation, backfill, grading, and seeding are included in the mobilization/demobilization lump-sum bid price and shall not be paid separately. The contractor is responsible for all utility coordination through PA One Call System (1-800-242-1776), asbestos abatement notification forms submitted 10 days prior to abatement, and an allowance of $3,600 for unforeseen asbestos issues, with additional costs reimbursable upon receipt submission if costs exceed this amount. The contractor must obtain and pay for all required permits from Renovo Borough and comply with all applicable local, state, and federal codes and regulations.

View the file

Other files

File Type Posted
4-Part II.pdf PDF
6-Addendum 1 - Complete.pdf PDF
3-Part V.pdf PDF
1-Part I.pdf PDF
5-Part IV.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART III – TECHNICAL SPECIFICATIONS

01010 Mobilization and Close-Out 1 - 3

01020 Maintenance and Protection of Traffic During Construction 1 - 2

01040 Dust Control 1

01050 Unforeseen Project Water Pollution Control (Soil Erosion) 1

01060 Submittals 1 - 4

01080 Special Requirements 1

01090 Color Audio - Video - Electrography 1 - 4

01100 Temporary Facilities and Controls 1 - 4

01110 Erosion and Sedimentation Control – Narrative Report 1 - 2

01129 Cement Concrete 1 - 5

01130 Concrete Sidewalk 1 – 2

01134 Concrete Curing 1

01140 Concrete Curb 1 - 2

01191 PA One Call 1

02110 Site Clearing - Demolition 1 - 2

02214 Excavation, Backfill and Compaction 1 – 4

02937 Grading and Seeding 1 - 5

01000-020926

PART III - CONTENTS

SECTION 01010

MOBILIZATION AND CLOSE-OUT

1. GENERAL

This Work shall consist of assembling all materials, workmen, storage yards and any other materials or facilities as required under this Contract or in reference to any Local, State or Federal regulations pertaining to this Project.

This item shall include the cost of required Insurance, Payment and Performance Bonds, Warranty Bonds and/or any related initial and final expenses associated with this Project.

This item includes the cost of PA One Call compliance, Temporary Facilities and Controls, necessary Contractors Licenses and Permits, any Agency Inspection Fees, Traffic Plan, Audio/Video Record, Schedules, Cleaning and Final Restoration, Record Drawings, Survey Stakeout, Water Pollution Control, Erosion and Sedimentation Control, Dust Control, CPM Schedule, Cash Flow Projection Schedule, Plan of Operation and all other incidental items necessary to fully complete the Project, as would be normally expected for a Project of this nature in the location of Work, not covered by unit or lump sum price.

2. MATERIALS

A. Materials under this part of this Specification are limited to those required for Mobilization for each Contractor but not intended for incorporation in the completed Contracts.

3. EXECUTION

A. All equipment required to diligently start the respective Contractors construction Work shall be on the site in satisfactory operating condition. The physical construction facilities, personnel and equipment shall be set up and operating at the required efficiency to diligently pursue the Work. No mobilization- demobilization costs will be paid to relocate material or equipment.

4. CLEANING-UP

A. In addition to the requirements of the General Conditions and to the requirements for special cleaning in the various other sections of the Specifications, the Contractor, except as noted, shall perform final cleaning as follows:

1. Dust, and if necessary wash, all adjacent vehicles and/or structures.

B. Final cleaning shall be performed after the Work is completed and immediately before turning the Work over to the Owner.

C. Cleaning materials shall be free from harmful abrasive and shall be acceptable to the Manufacturers of the materials on which they are used.

01010-020926

MOBILIZATION AND CLOSE OUT

D. Each Contractor shall remove all his field offices, storage facilities and any other materials or items that were used by him during construction and not incorporated into the Project. Leave these temporary service areas in a clean condition and repair or replace any damaged areas ready to be turned over to the Owner.

5. FINAL RESTORATION

A. In addition to the requirements specified in the various Sections of these Specifications each Contractor shall make final restoration of all areas disturbed by his temporary construction facilities such as, but not limited to, office and storage trailers.

B. In general, the Contractor shall repair all walks, roadways and any other areas damaged during construction, inside or outside the construction limits, to the satisfaction of the Engineer.

6. INITIAL PAYMENT

A. Fifty percent (50%) of the price bid for Mobilization and Close-Out shall be payable to the respective Contractor whenever five percent (5%) of the Work of the Contract is completed. For the purposes of this item five percent (5%) of the Work shall be considered completed when the total of payments earned, exclusive of the amount bid for this item, as shown on the monthly certificates of the approximate quantities of Work done, prepared in conformance with the General Conditions shall exceed five percent (5%) of the total price bid for this Contract.

7. FINAL PAYMENT

A. The final fifty percent (50%) of the price Bid for Mobilization and Close-Out shall be payable to the respective Contractor when the following Work has been performed:

1. Completed all of the Work.

2. Clean-up and all final restoration of all disturbed areas related to the Contract.

3. Delivered all required documents enumerated in the Specifications including,

a. Required warranties and guarantees

b. Special bonds

c. Certificates from Manufacturers and Suppliers

d. Certificates from regulatory agencies and/or authorities

e. Maintenance and equipment instructions

4. Delivered, properly executed, the following:

a. Contractor's Affidavit

b. Statement of Surety Company (with Power of Attorney and

Statement of Surety's Financial Conditions) 01010-020926

MOBILIZATION AND CLOSEOUT

c. Two Year Maintenance Bond (s) (with Power of Attorney and Statement of Surety's Financial Conditions)

d. Contractor's Release

e. All final MBE/WBE paperwork

8. INSPECTOR'S FIELD OFFICE AND INSPECTION FACILITIES

A. No inspector's field office shall be required for this Project.

B. The Work shall, at all times, be made available for inspection by the Engineer, Resident Project Representative, Owner and all agencies having jurisdiction over the Work.

01010-020926

MOBILIZATION AND CLOSE OUT

SECTION 01020

MAINTENANCE AND PROTECTION

OF TRAFFIC DURING CONSTRUCTION

This Work is for the maintenance and protection of traffic adjacent to and within the construction area of all Work areas on this Project and for all costs associated with detours and maintaining detours, including permits from the respective review agencies and for all flag persons. Traffic shall mean vehicular and pedestrian travel within or adjacent to the Project area.

2. MATERIAL

Furnish material and traffic control devices necessary for the maintenance and protection of traffic, and conforming to the Traffic Control Plan; 67 PA Code, Chapter 211 and 67 PA Code, Chapter 203; and, if required as follows:

- Temporary Concrete Barrier - Section 627.2

- Reset Temporary Concrete Barrier - Section 628.2

- Temporary Signing and Detour Signing - Section 1103

Storage of materials and equipment is prohibited on the pavement and shoulder (30 ft. from edge of pavement).

A. General:

Comply with the requirements of 67 PA Code, Chapter 203. Install and maintain the traffic control devices on a Traffic Control Plan or an accepted alternate plan, approved by the Engineer, submitted at the preconstruction conference. The Traffic Control Plan may be revised by the Engineer, in writing. Schedule construction operations to permit movement of traffic, during the various phases of construction, with minimum interference. If traffic interruptions become too frequent, cease operations in the area concerned, as directed. Take satisfactory remedial action to correct the situation before continuing operations.

Traffic control devices shall include painted lines and markings, removal of existing lines and markings and restoration of lines and markings at the end of the construction Work.

01020-020926

B. Accommodation of Traffic:

For indicated detours, furnish, erect, maintain, and remove the detour signs, unless otherwise specified. Also, temporarily cover, revise, or remove existing permanent guide signs, in the vicinity of the construction site and in accordance with the detour signs.

Erect, maintain, and remove the detour signs and the modification of directional signs, as indicated, and as required for construction conditions. Restore original signs to their original state upon removal of the detour. Provide adequate flag persons, watch persons, and other personnel to adequately protect the traveling public, workers, inspectors, equipment, both public and private, from accident, injury, or damage at all times.

Open any substantially completed section of roadway for the use and convenience of traffic, as directed.

Do not start Work until the traffic control plan Schedule and operation methods have been reviewed and accepted.

4. MEASUREMENT AND PAYMENT

Seventy-five percent (75%) of the price bid for traffic control shall be payable to the respective Contractor prorated over the Contract time with twenty-five percent (25%) of the price bid held until substantial completion of the Contract. All traffic control expenses shall be at the lump sum bid price shown on the Bid Form, complete in place in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

01020-020926

SECTION 01040

DUST CONTROL

Maintain Dust Control necessary for the duration of the Project to avoid unstabilized areas.

Submit methods of Dust Control and plan of operation prior to demolition for review and approval by the Engineer.

All structures have been declared unsafe to enter to complete the asbestos and lead testing. The facility and building materials must be kept adequately wet at all times, starting with the demolition process, through site cleanup, transport and final disposal. "Adequately wet" means sufficiently wet to prevent the release of particulates and there are no visible emissions observed from any asbestos-containing material. If visible emissions are observed, the demolition must cease, and additional wetting must be performed until no emissions are occurring. However, the absence of visible emissions is not sufficient evidence of being adequately wet. For a complete discussion of the structurally unsound and in danger of imminent collapse provisions under the Asbestos NESHAP, please refer to 40 C.F.R. §§ 61.141 and 61.145(a)(3), 61.145(c)(4) -(9).

Do not start Work until the Dust Control Plan, Schedule and operation methods have been reviewed and accepted.

The Engineer shall have the authority to order Dust Control Work to be completed by others if the Contractor fails to correct inadequate Dust Control within 24 hours of notice and deductions from the Contractors payment shall be made to pay for dust control.

All Dust Control expense shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

01040-020926

DUST CONTROL

SECTION 01050

UNFORESEEN PROJECT WATER POLLUTION CONTROL

(SOIL EROSION)

This Work is construction of temporary control measures, as ordered during the Contract life, to control water pollution and soil erosion meeting the requirements of PennDOT, Publication 408 Specifications, Section 845, as last revised and Clinton County Conservation regulations.

When and as directed during construction, provide temporary pollution and erosion control measures to prevent or abate unforeseen conditions. All work shall be completed to prevent sedimentation from leaving the project area.

During the preconstruction conference or prior to the start of construction, submit an Erosion Control Plan outlining the Schedules for accomplishing temporary and permanent erosion and water pollution control. Do not start Work until the Erosion Control Plan, Schedules, and operation methods have been reviewed and accepted.

This item shall be included in the Erosion and Sedimentation Control lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job.

01050-020926

UNFORESEEN PROJECT WATER POLLUTION CONTROL

SECTION 01060

SUBMITTALS

The Contractor shall be responsible for preparing a CPM Schedule, Cash Flow Projection Schedule, Plan of Operation and other submittals outlined in the Contract Documents for the entire Project and shall include all Subcontract Schedules for the Work.

Each Contractor shall process the Shop Drawings required by his Contract to the Engineer and he shall be responsible for their timely submission in accordance with the Shop Drawing Schedule which is included in the overall progress or Work Schedule as described in item 3 of this Section.

Any proposed deviations/substitutions from that specified shall be clearly noted on the cover letter transmitting the Shop Drawing. Failure to note deviations/substitutions shall be cause for rejection of equipment, materials, etc., after installation.

All submissions shall be marked with the Specification section containing the item submitted for review.

Revised Shop Drawings submitted for review shall be marked "Resubmission".

"Or Equal" items for all equipment and materials shall be considered for approval.

2. SUBMITTAL PROCEDURES

All submittals shall be delivered to the Engineer for approval within 10 days of Notice to Proceed.

The Engineer shall screen the submittals to insure that they have been properly certified and identified by each Contractor. If they are submitted properly, the items shall be processed for review, acceptance and/or resubmission.

The processed submittals shall be returned to the Contractor within 20 days of receipt by the Engineer.

3. SCHEDULE

The General Contractor shall prepare a CPM Schedule for the entire Project, showing the order in which each Contractor proposes to carry on his Work and salient features, including submission of Shop Drawings and samples and procurement of materials, to meet date of completion. The other Contractors shall be consulted in the preparation of this Schedule and shall signify their approval of the finished Schedule by their signature.

Each activity in the progress or Work Schedule shall be identified and a time for the performance of such activity indicated. Each activity shall be preceded by all Work that must be accomplished prior to that activity. All abbreviation, codes and/or symbols used shall be described in the Schedule.

01060-020926

4. SUBMISSION

Submit four (4) copies of the CPM Schedule to the Engineer for review within fifteen (15) days after award of Contract. Weather related days shall be included in the CPM Schedule. Update and resubmit CPM Schedule monthly thereafter until completion of the Work. Updated CPM Schedule shall have completed activities removed or indicated as such. Whenever modifications are made to the Contract which add or delete activities and/or revise time of completion, CPM Schedule shall be revised and resubmitted to the Engineer within ten (10) days after such modification is authorized.

In the event that the Work is behind the CPM Schedule, the CPM Schedule shall be revised, through the use of overtime Work or by other means, to insure that the Work is completed within the Contract time. Under these circumstances, overtime Work shall be performed at no additional cost to the Owner.

5. SHOP DRAWINGS AND MANUALS

Shop Drawings are defined as drawings, diagrams, illustrations, Schedules, performance chart, brochures and other data prepared by each Contractor which illustrate how specific portions of the Work shall be fabricated and/or installed.

Shop Drawings are not part of the Contract Documents, but are a supplementary means of communications to assist in the understanding of what each Contractor proposes to provide and to establish that whatever he intends to install either does or does not conform to the drawing and Specifications.

In the instance of a request for a substituted item, each Contractor shall verify that it shall fit into the space allocated to the originally required item giving due regard to all other trade requirements.

Where modifications to the Contract Documents are proposed, the Contractor must clearly indicate such deviation in writing in his transmittal letter. If the modification and/or substitutions are agreed to by the Engineer, the Contract Documents shall be appropriately modified. However when additional Work is required, the Contractor is advised that he must pay the Engineer for redesign to accommodate that revised substitution as well as pay other Contractor’s for extra Work required by them for the change. No increase in the Owner's construction cost shall be allowed.

6. CATALOG SHEETS

For standard manufactured items considered by the Engineer as not requiring special Shop Drawings, each Contractor shall submit six (6) copies of Manufacturer's catalog sheets showing illustrated cuts of the items to be furnished, all details, sizes, dimensions, performance characteristics capacities, wiring and control diagrams and all other pertinent information.

The Engineer shall retain four (4) copies and return two (2) copies to the Contractor submitting the catalog sheets.

7. SHOP DRAWINGS

Each Contractor shall submit for review six (6) white prints of shop and working drawings of materials fabricated and/or supplied especially for his Contract, and of equipment and materials for which such drawings are specifically requested.

Prior to submitting drawings to the Engineer, the respective Contractor shall check thoroughly all such drawing to satisfy himself that the subject matter conforms to the plans and Specifications in all respects. Drawings which are correct shall be marked with the date, checker's name and certification of the Contractor's approval, and then shall be submitted to the Resident Project Representative. Any Shop Drawings submitted without the respective Contractor's certification shall be returned without review.

The Engineer shall retain four (4) copies and return two (2) copies to the respective Contractor.

Shop Drawings shall show the principal dimensions, weight, structural and operating features, performance characteristics and wiring diagrams, space required, clearances, type and/or brand of finish or drawing. When it is customary to do so, when the dimensions are of particular importance or when so specified, the drawings shall be certified by the Manufacturer or fabricator as correct for this Contract.

When so specified or if considered by the Engineer to be acceptable, Manufacturer's Specifications, catalog data, descriptive matter, illustrations, etc., may be submitted for review in place of shop and working drawings. In such case the requirements shall be specified for shop and working drawings, insofar as applicable.

Each Contractor shall be responsible for the prompt submission of all shop and working drawings in accordance with the Shop Drawing Schedule so that there shall be no delay to the Work due to the absence of such drawings.

No material shall be purchased or fabricated especially for this Contract until the required shop and working drawings have been submitted and reviewed as conforming to the Contract requirements.

All materials and Work involved in the construction shall then be as represented by said drawings.

The Engineer's review of shop and working drawings shall follow a general check made to ascertain conformance with the design concept and functional result of the Project and compliance with the information given in the Contract Documents. Each Contractor is responsible for details and accuracy, for conforming and correlating all quantities and dimensions at the job site; for information that pertains solely to the fabrication processes or to techniques of construction; and for coordination of the Work of all trades.

No Work shall be started or materials and equipment ordered until submittals are approved.

8. MANUALS

Each Contractor shall be responsible for initially submitting to the Engineer two (2) copies of all requested maintenance manuals with the Shop Drawing submittals.

Six (6) complete sets of instructions, technical bulletins and other printed matter shall be furnished and delivered to the Engineer prior to installation of equipment.

9. FIELD DISTRIBUTION

Each Contractor shall be responsible for the required number of processed drawings or catalog cuts for field distribution to all necessary Contractors.

Each Contractor shall have the overall responsibility for coordinating the necessary information to properly coordinate the Work.

10. SUBMISSION OF SAMPLES

Unless otherwise specified, each Contractor shall provide samples in duplicate and identify each sample by an appropriate tag or label listing the name of the Project, the Owner, the Engineer and the Contractor and/or Subcontractor as well as the exact identification of the sample. Tag or label shall be large enough to provide a blank space for review stamps.

Samples of items submitted for destructive tests or for use in testing mixtures with other materials shall not be returned. Review of these items shall be given by letter.

When reviewed, one sample of each item, not submitted for destruction, shall be returned to the respective Contractor and shall be kept and maintained in good condition in the submitting Contractor's office at the Project site for later use in comparison with material actually delivered for the Work. When samples of large fabricated items or of costly items are required, reviewed samples may be installed in the Work if the exact location of such samples is recorded on the Engineer's Record Drawings.

11. CERTIFICATIONS AND TESTS

Two (2) copies of certifications and reports of tests when required under the various sections of the Specifications shall be submitted to the Engineer.

12. MEASUREMENT AND PAYMENT

Shop Drawings, submittals, samples, certifications and tests, CPM Schedule, Cash Flow Projection Schedule and Plan of Operation shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

SECTION 01080

SPECIAL REQUIREMENTS

1. ADDITIONAL CONDITIONS OF THE CONTRACT

These Special Requirements are in addition to, or expansion of the responsibilities of each Contractor noted in the General Conditions.

2. SURVEY OPERATIONS

The Owner shall provide "Reference Marks" for controlling horizontal and vertical alignment and elevation and "Bench Marks" for controlling the vertical alignment for the entire length of the Project.

The Contractor shall provide "Offset Stakeout" as required for the construction of the Work. This "Offset Stakeout" shall be provided as follows:

A. When the Contractor uses a Laser Beam for his construction, the above data shall be provided at 50 foot intervals.

B. When the Contractor uses any other method for his construction or when grades are

1.0 percent or less, the above data shall be provided at 25 foot intervals.

3. JOB CONFERENCES

Scheduled meetings shall be held at the site at a time mutually acceptable to the Owner, Engineer and Contractor. Unscheduled meetings may be arranged at the request of any party when deemed necessary for the proper execution of the Work.

Meetings shall be conducted by the Owner or his Representative and shall be attended by Principals or their designated Representatives, of the Contractors and their major Subcontractors.

Instructions delivered or commitments made at these meetings shall be binding on all parties concerned.

4. EXISTING UTILITY SERVICE

The Contractor is specifically required to maintain "in-use" at all times, sanitary sewer lines, sewer laterals, water lines, gas lines, storm water connections, manholes and storm sewer inlets so that no public or private property is damaged, has service interrupted or is inconvenienced due to the construction. Contractor is solely responsible for damage to all utility lines, properly marked, as required by PA One Call.

5. MEASUREMENT AND PAYMENT

Cost for the above Work shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

01080-020926

SPECIAL REQUIREMENTS

SECTION 01090

COLOR AUDIO-VIDEO ELECTROGRAPHY

A. Scope:

1. Description of Work

Provide all labor, materials and equipment to furnish color audio-video electrography including still pictures for the entire Project prior to the start of any construction Work.

Provide the Owner with two (2) copies of acceptable audio-video tapes of the total survey.

Work shall consist of, but not be limited to, the following:

a. At no time shall the Contractor be allowed to use any electrical circuits within a building structure in order to protect the electrical circuits from overloading.

b. All videotaping shall be done during regular business hours, unless otherwise specified by the Engineer.

c. The Contractor must enter and leave the Owner’s property in a professional and orderly workmanship-like manner.

2. Field Checks

The Contractor and the Engineer shall review the days taping and, if tapes are judged unsatisfactory, the subject Project area shall be retaped.

3. Qualifications

a. Owner's Requirements:

The Owner may make such investigation as deemed necessary to determine the ability of the Contractor to perform the Work, and the Contractor shall furnish to the Owner all such information and data for this purpose as the Owner may request, or modify such justification as submitted by the Contractor of his ability to perform this Work as specified.

The Contractor shall notify the Engineer seven (7) calendar days prior to beginning of taping.

01090-020926

A "sample" route of this Project must be taped by the Contractor for the Owner's and Engineer's review. The sample route will be established by the Engineer. It shall be the taping of the sample route that the job quality standards shall be based and judged. This "sample" tape shall be submitted to the Owner before any additional taping is started to allow the tape to be reviewed by the Owner and Engineer.

4. Submittals

The Contractor shall submit to the Engineer, prior to starting Work at his own expense, a sample 3/4 inch color video tape meeting the exact contract requirements.

2. PRODUCTS

A. Equipment:

All equipment, accessories and materials to perform this service shall be furnished by the Contractor.

At the bottom of the video, periodic transparent alpha numeric information shall appear. This information shall consist of the name of the Project, name of the area covered, direction of travel, viewing side, etc.

B. Digital:

To preclude the possibility of tampering or editing in any manner, all video recordings must, by electronic means, display continuously and simultaneously generated transparent digital information to include the date and time of recording as well as the corresponding Engineering stationing numbers. The date information shall contain the month, day, and year, i.e., 06/15/2019, and shall be placed directly below the time information. The time information shall consist of hours, minutes and seconds separated by colons, i.e., 10:35:10. This transparent information shall appear on the extreme lower left-hand third of the screen.

3. REQUIREMENTS

A. Multi-Camera Requirements:

The audio-video tape shall consist of one (1) video and two (2) audio tracks, all of which must be recorded simultaneously. All tracks shall consist of original live recordings and thus shall not be copies of other audio or video recordings. Audio track 1 shall contain the narrative commentary of the electrographer recorded simultaneously with his fixed elevation video record of the zone of influence of construction. Audio track 2 shall contain the narrative commentary and evaluations of the ground level remote technician whose function shall be to provide a complete circumspection of any features not adequately visible to the electrographer and to describe in detail the extent of any unusual features encountered. In order to maintain viewer orientation, transition from fixed camera overview to remote camera picture shall be by means of an electronic dissolve.

B. Lighting Requirements:

The color audio-video tape recording of surface features of the Project area located within the area of coverage of construction specified by the Engineer shall have the following minimum lighting:

1. In order to produce the proper detail and perspective, a minimum of 25,000 watts or 3400 Kelvin temperature lighting shall be required to fill the shadow area caused by all objects.

AREA TYPICALLY CHARACTERIZED BY AVE RATE MAX

50 ft/min.

High Density Demolition at the Borough of Renovo 133 14th Street; 135 14th Street;

137 14th Street; 139 14th Street;

141 14th Street; 143 14th Street;

145 14th Street;147 14th Street;

149 14th Street;151 14th Street;

153 14th Street; 155 14th Street;

157 14th Street; 159 14th Street;

161 14th Street and 163 14th Street.

The Owner shall have the authority to designate what areas may be omitted or added for audio-video coverage.

The color audio-video tape recording of exterior surfaces of existing buildings and miscellaneous structures and adjacent properties and buildings in the area of the Project as requested by the Engineer shall have the following tape coverage:

A. Taped coverage shall include all surface features located within the area of coverage of construction supported by appropriate audio description. Audio description shall be made simultaneously with video coverage. Building exterior coverage shall include, but not be limited to, all masonry features of the building such as walls, foundations or chimneys.

B. An electronic insert showing the exterior view of the Project being recorded shall be displayed in the upper right-hand corner of the television picture. This view shall be no larger than 20% of the picture area and must begin showing the address before the 360 degree pan. The electrographer shall pan and zoom in and out as to control sufficiently the clarity of objects being viewed and shall not exceed a rate of more than 2 inches per second on telephoto zoom.

C. All videotaping shall be done during regular business hours unless otherwise specified by the Owner.

01090-020926

Color Audio-Video Electrography shall be included in the Mobilization/Demobilization lump sum bid price on the Bid Schedule, complete in place, in accordance with the Contract Documents and good construction practices for a complete job, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

SECTION 01100

TEMPORARY FACILITIES AND CONTROLS

A. Scope:

The Contractor is referred to conditions and requirements given in various Sections of the Specifications insofar as such documents affect the Work of this Section.

2. OCCUPYING PRIVATE LAND

Written consent from the Private Owner(s) shall be obtained by the Contractor prior to entering of/or occupying with men, tools, materials or equipment any land other than the property or that of the Owner for any purpose related to his performance of the Work on this Contract.

3. PROTECTION OF EXISTING UTILITIES

The Contractor shall conduct his operations and take all special precautions necessary to protect equipment, utility lines, roadways and subsurface, submerged and overhead facilities which are to remain in place and undisturbed by his operations under this Contract. The Contractor shall immediately notify the Owner of the facilities or areas which are disturbed, damaged or injured as a result of the Contractor's operations, and determine the proper method of replacing or repairing the affected facilities at least to the conditions which existed prior to the Contractor's operations.

The Contractor shall, at his own expense, replace, repair or restore the affected facilities or areas to their original condition or shall reimburse the Owner of said facilities or areas for such expenses as the said Owner may accrue in performing the Work, and the Contractor shall not be entitled to receive additional compensation under this Contract for such Work.

4. INTERFERENCE WITH/AND PROTECTION OF STREETS

The Contractor shall not close or obstruct any portion of a street, road or private way without obtaining permits therefore from the Owner. If any street or private way shall be rendered unsafe by the Contractor's operations, he shall make such repairs or provide such temporary ways or guards as shall be acceptable to the appropriate authority.

The Contractor shall assume full responsibility for the maintenance and restoration of those areas within the construction area and also those adjacent roadways on which equipment must operate to reach the construction area.

Street, roads, private ways and walks not closed shall be maintained passable by the Contractor at his expense, and the Contractor shall assume full responsibility for the adequacy and safety of provisions made.

The Contractor shall, 48 hours in advance of closing any street, notify the Owner, the police and fire departments in writing, and notify County Emergency Response Agency, with a copy to the Engineer.

01100-020926

He shall cooperate with the police department in the establishment of alternate routes and, at his own expense, shall provide adequate, plainly marked detour signs. The signs shall be as required by the Owner that has jurisdiction over the project.

For the proper control of traffic, the Contractor shall provide an adequate number of persons employed at his own expense.

Absolutely no equipment or material may be left within highway right-of-ways at the end of the working day.

5. ACCESS

Provide suitable access for residents to their homes and for emergency vehicles and fire protection vehicles, such as temporary ramps between existing surfaces and excavated surfaces. Provide necessary temporary walks of timber or bituminous materials to ensure safe ingress and egress to homes. Provide adequate temporary street lighting for pedestrian safety during the construction stage. Suitably cover and mark all clean outs extending above the excavation in order to provide for pedestrian safety. Provide adequate signing for pedestrian and vehicular safety.

6. PROTECTION OF FACILITIES AND EQUIPMENT

Until final acceptance of the Work under this Contract, the Contractor shall continuously maintain adequate protection, of his Work and Work in progress from damage and shall protect from loss or damage Contractor-furnished machinery, equipment, materials and supplies being handled, including property considered for progress payments wherever located as well as other property of the Owner from loss or damage arising out of or in connection with the prosecution of his Work.

The Contractor shall make good any such loss or damage. The Contractor shall adequately protect adjacent private and public property as provided by law and the Contract Documents.

Since the Contractor shall not load or permit any part of any structure to be loaded with a weight that would endanger its safety, it shall be the Contractor's responsibility to verify the acceptable load carrying capacity of any structure his equipment or Work will affect.

The Contractor shall immediately report in writing, giving full details, to the Owner all accidents which arise out of or in connection with the performance of the Work, whether on or adjacent to the site, which cause death, serious personal injury or substantial property damage. In addition, the accident shall be reported immediately by telephone or messenger to the Engineer. If a claim is made or suit is filed by anyone against the Contractor on account of any accident, the Engineer shall be notified in writing with a copy to the Owner, giving full details of the claim.

The Contractor shall assume all risks of loss or damage of any kind to any vehicles, machinery, equipment, materials or supplies which he shall provide in doing the Work.

The Contractor shall conduct his Work in such a manner as to adequately protect property owned by others on or about the Owner's premises from damage by the construction operations.

No trimming or cutting of trees is allowed unless written authorization is granted by the applicable private property owner, Owner, and the Engineer. Any anticipated tree trimming or cutting shall be submitted to the Engineer in advance of reaching the subject area.

7. DUST CONTROL

During the progress of the Work, the Contractor shall conduct his operations and maintain the area of his activities so as to minimize the creation and dispersion of dust.

8. SANITARY

The Contractor shall provide, maintain and remove when no longer required, an adequate number of temporary, prefabricated, chemical-type toilets with proper enclosures for the use of workmen and women of all trades during construction. Locate toilets where directed.

The Contractor shall keep toilets clean and supplied with toilet paper, hand cleanser, and towels at all times and comply with all local and state health requirements and sanitary regulations.

9. WATER

The Contractor shall make necessary arrangements and supply all water required during entire construction period and provide suitable drinking water for all workers on the Project.

10. TEMPORARY WATER SUPPLY

In the event the water supply to a building or user will be disrupted for more than one hour, the Contractor shall provide temporary water service to all such buildings or users.

11. ELECTRICITY

The Contractor shall make necessary arrangements and supply and pay for all temporary electric service and lighting required during the entire construction period. Temporary electric service shall be of sufficient capacity and characteristics to supply proper current for various types of construction tools, motors, welding machines, lights, heating plant, pumps and other items required.

Remove temporary service and lighting when no longer required.

12. FUEL, POWER, ETC. FOR TESTING

Unless otherwise specified, the Contractor shall pay for all potable water and electricity required for testing of installed Work. Fuel shall be provided by the Contractor. Labor and supervision required for making tests shall be provided by the Contractor for all the installed Work involved.

13. SECURITY

The Contractor shall provide and pay for an adequate level of security protection to protect the property and material of all Contractors from pilferage, removal or damage at all times.

14. OFFICES AND STORAGE

The Contractor shall, for his own use, provide and maintain such temporary office facilities as he may require and such watertight storage sheds with floors as may be required for storage of his materials which might be damaged by weather. The Contractor shall allocate suitable space for office and storage for each Subcontractor, subject to the acceptance of the Engineer.

Materials stored in the open at the Project site shall be stored on planks or other dunnage as necessary to keep materials from contact with the ground and shall be covered with tarpaulins for protection from weather.

All temporary offices and storage facilities shall be removed by their installer when no longer required.

15. UNDERGROUND FACILITIES

The Contractor shall meet all requirements of Pennsylvania Act 38, as last revised and related to underground utilities. Toll Free access number for PA One Call System is 1-800-242-1776.

16. MEASUREMENT AND PAYMENT

Cost for all work listed in this section shall be at the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

301100-020926

SECTION 01110

EROSION AND SEDIMENTATION CONTROL

NARRATIVE REPORT

The purpose of the Narrative Report is to fully describe the proposed Project and outline the erosion and sedimentation control measures and facilities to be utilized.

The rules and regulations as set forth in the Pennsylvania Department of Environmental Protection and the Clinton County Soil and Water Conservation District, Soil Conservation Service (S.C.S.)

shall apply to this Project.

The Contractor shall comply with the rules and regulations as set forth in Document No. 363-2134- 008, Erosion and Sediment Pollution Control Program Manual, Volume 34, TAB 6, March 2000 or as last revised. The Contractor shall also familiarize himself with the construction guidelines as described in the Soil Erosion and Sedimentation Control Manual, by PA D.E.P., April 15, 2000 or as last revised.

2. PROJECT DESCRIPTION

The Work comprises the demolition of all structures, sheds, other ancillary property structures, private sidewalks (public sidewalks to remain), cap water and sewer laterals at curb line (work with public works), one water and sewer lateral in the middle shall be brought up to 3’ grade and capped, rubbish, asbestos abatement as needed, property restoration and all appurtenances for a complete job in accordance with the Contract Documents. All Structures have been declared unsafe to enter to complete the asbestos testing. The Engineer’s Certified Asbestos Inspector will be onsite during the demolition process. The building materials must be kept adequately wet at all times, starting with the demolition process, through site cleanup, transport and final disposal. "Adequately wet" means sufficiently wet to prevent the release of particulates and there are no visible emissions observed from any asbestos-containing material. If visible emissions are observed, the demolition must cease, and additional wetting must be performed until no emissions are occurring. However, the absence of visible emissions is not sufficient evidence of being adequately wet. For a complete discussion of the structurally unsound and in danger of imminent collapse provisions under the Asbestos NESHAP, please refer to 40 C.F.R. §§ 61.141 and 61.145(a)(3), 61.145(c)(4) -(9).

3. STAGING OF EARTHMOVING ACTIVITIES

The staging of earthmoving activities with the installation of temporary and permanent control facilities shall be employed to minimize soil erosion and sedimentation.

Remove foundation to 4.5 feet below grade, punch 6” diameter holes in concrete basement floors in 6 foot intervals. All excavation, backfill and compaction with clean, non-organic material, 3” maximum size aggregate, compacted to 100% optimum dry density, grading, lawn restoration to level of adjacent undisturbed elevation, materials, workmanship and all appurtenances for a complete job.

01110-020926

EROSION AND SEDIMENTATION

CONTROL NARRATIVE REPORT

Excavation materials from the foundation area shall be placed on the upgrade side of the excavation to allow sediment to be captured by the excavated area.

All excavated materials that remain uncovered for more than 20 days shall be stabilized with the cover specifications listed below. Any stockpiled materials shall be stored with side slopes at a maximum of 3:1.

After backfilling, pavement and gravel areas shall be stabilized with like materials. Any ground cover areas disturbed shall be stabilized in accordance with the following: topsoil, lime, fertilizer, seeding and mulch at the rates outlined in Item 4 below.

All seeding shall be done in accordance with PennDOT, Form 408 Specifications, Section 804, as last revised. Lime shall be pulverized agricultural limestone, fertilizer shall be 10-20-20 analysis commercial fertilizer, seed shall be Formula B and mulch shall be straw as per PennDOT, Form 408 Specifications, Section 805, as last revised.

Mulched areas must be checked periodically and immediately after severe storms for damage, until the mulching is no longer necessary for erosion protection. Damaged areas shall be repaired as soon as possible.

Prior to construction, silt sock shall be placed at all areas of potential silt drainage to surface waters and/or stormwater inlets to filter any sediment laden runoff and prevent it from leaving the construction area.

4. PERMANENT CONTROL FACILITIES AND MEASURES

Topsoil, lime, fertilizer, seeding and mulches at the following rates:

1. Topsoil Minimum 4 inch depth after compaction

2. Lime 800 pounds per 1,000 square yards

3. Fertilizer 192 pounds per 1,000 square yards

4. Seed 21 pounds per 1,000 square yards

5. Mulch 1,200 pounds per 1,000 square yards

Concrete Sidewalks shall be installed as specified in other sections of these Contract Documents if damaged during cleanup.

5. MEASUREMENT AND PAYMENT

Payment for this item shall be at the Mobilization/Demobilization lump sum price on the Bid Form, complete in place in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.

01110-020926

EROSION AND SEDIMENTATION

CONTROL NARRATIVE REPORT

SECTION 01129

CEMENT CONCRETE

1. GENERAL

Cement concrete used for various structures and construction items shall be Class AA as specified herein, or as shown on the Contract Drawings, meeting the requirements of the PennDOT, Form 408 Specification, as last revised, except no fly ash shall be allowed as part of the proposed mix design.

Before placing the concrete, the Contractor shall make all necessary arrangements and have all materials on hand and in place, if necessary, for curing and protecting the concrete.

When the air temperature is seventy-five (75) degrees F or above or when specified by the Engineer, a Pennsylvania Department of Transportation approved retarder admixture for concrete shall be used. No concrete shall be poured or placed when air temperature is below forty (40) degrees F without the approval of the Engineer. When the air temperature is forty (40) degrees F or below or when specified by the Engineer, an approved accelerator admixture of either Type I or Type II calcium chloride representing two (2) percent by weight of cement shall be used.

2. STRENGTH

Cement concrete shall have a minimum compressive strength as specified by the PennDOT, Form 408 Specifications, as last revised, for the classes mentioned above.

3. CEMENT

Cement shall be of best quality, normal strength, air entraining cement, fresh and free from lumps, conforming to the current standard chemical and physical requirements of PennDOT, Form 408 Specifications, as last revised. Cement for field mixing shall be delivered in bags, each containing one (1) cubic foot, having a net weight of ninety-four (94) pounds.

4. AGGREGATES

The fine aggregate shall be composed of hard durable grains, thoroughly cleaned by washing, free from lumps, of clay and all vegetable and deleterious substances. The fine aggregate shall meet the grading and quality requirements for PennDOT, Form 408 Specifications, as last revised, Type A, CC Sand or Type B, BC Sand #2.

The coarse aggregate shall consist of crushed stone, or washed and crushed gravel, having clean, hard, strong, durable, uncoated particles. The coarse aggregates shall meet the PennDOT, Form 408 Specifications, as last revised; Type A quality requirements and gradation necessary to obtain the desired strength.

5. WATER

Water shall be free from oil, acid, alkali, organic matter and other deleterious substances injurious to the finished product.

01129-020926

6. PROPORTIONING

Proportioning of the cement, coarse aggregate, fine aggregate, and water shall be in accordance with the American Concrete Institute's method by a competent and certified ready-mixed plant operator. The exact proportioning shall be done using the above mentioned mixture characteristics as a basis.

7. MORTAR

Mortar shall be composed of one (1) part cement and two (2) parts fine aggregate and mixed with sufficient water to form a plastic composition. Mortar shall be prepared in quantities for immediate use, and mortar which has partially set shall be disposed of and not re-tempered for use in the Work.

8. FIELD MIXED CONCRETE

Proportioning for field mixed Class AA concrete shall be one (1) part cement to five (5) parts aggregate. The quantity of coarse aggregate used shall not exceed one and one half (1-1/2) times the quantity of fine aggregate.

Field mixing shall be done in a batch mixer capable of combining the aggregates, cement, and water within a specified time into a homogeneous mixture, and discharging the mixture without segregation. The mixing time for a one (1) cubic yard or small mixer shall be one (1) minute, and larger mixers shall require an additional fifteen (15) seconds for each additional one-half (1/2) cubic yard.

The entire contents of the drum shall be discharged completely before any materials for the succeeding batch are placed therein. Concrete shall be in place within thirty (30) minutes after the water has been added. Partially hardened concrete shall not be used. Concrete shall not be mixed or placed when the air temperature is below forty (40) degrees F without the approval of the Engineer.

9. READY-MIXED CONCRETE

Ready-mixed concrete shall conform to the requirements of PennDOT, Form 408 Specifications, as last revised, except fly ash shall not be allowed. The batching and mixing plant shall provide a system of precise meters for material volumes and admixture control. The Engineer shall have free access at all times to the batching and mixing plant for sampling of all materials and observation of concrete preparation for the Project.

Delivery of concrete to the Site of the Work and its discharge from the truck mixer or agitator shall be completed within one-half (1/2) hour after the introduction of the mixing water to the cement and aggregates, or cement to the aggregates.

No concrete shall be placed when the air temperature is below forty (40) degrees F without the approval of the Engineer.