This is a Notice of Intent to Award a Contract Without Engaging in a Standard Procurement Process issued by the Utah Department of Transportation (UDOT) Procurement for RC Hunt Electric. The notice addresses the continuation and expansion of technology systems installations at Utah's Ports of Entry, specifically including e-screening system upgrades, tire anomaly classification system (TACS) installations, commercial vehicle sorting systems, and associated infrastructure. The scope encompasses installation of weigh-in-motion sensors, USDOT readers, license plate readers, cameras, masts, poles, signs, technical wiring, and conduit at ten additional Port of Entry locations throughout the state. The contract term extends through June 30, 2028, with no renewal options. The requesting unit has identified this procurement as a sole source award based on the existence of an ongoing contract with RC Hunt Electric and cited project delays resulting in funding challenges as justification for the single-source approach.
The estimated total term cost for this procurement is $2,000,000.00 in additional funding, with freight costs designated as not applicable (F.O.B. Destination, Freight Prepaid). RC Hunt Electric is identified as the incumbent vendor with an existing contract. The justification for sole source procurement centers on compatibility considerations, as the proposed work involves continuing and expanding existing e-screening systems already installed at multiple Ports of Entry throughout Utah. The requesting unit indicated that no market research identified alternative sources and that the existing contract provides the foundation for this continuation. UDOT Procurement opened a public notice period to determine whether other qualified providers could meet the stated specifications; however, no valid challenges were anticipated following the solicitation period, after which UDOT Procurement may award the contract without competition if no competing offers were received.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-01. General Information- Notice of Sole Source (1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF UTAH - DEPARTMENT OF TRANSPORTATION
UDOT Procurement NOTICE OF INTENT TO AWARD A CONTRACT WITHOUT ENGAGING IN A STANDARD PROCUREMENT PROCESS UDOT Procurement is publishing this notice pursuant to the Utah Procurement Code. The Requesting Unit submitted this form to UDOT Procurement claiming that it intends to award a contract without competition if it is determined by UDOT Procurement, in writing, that:
· there is only one source for the procurement item.
· transitional costs are a significant consideration in selecting a procurement item; or
· the award of a contract is under circumstances, described in rules adopted by the applicable rulemaking authority, that make awarding the contract through a standard procurement process impractical and not in the best interest of the procurement unit.
In the subsequent pages the Requesting Unit has identified its justification for pursuing this process.
Determination of Other Interested Providers The intent of this notice is to determine if there are any other interested and qualified providers that meet the specifications of this notice. Any such providers must submit the following information:
· The name of the provider; and
· A detailed explanation of the challenge, including documentation showing that there are other competing sources for the procurement item.
In addition, a provider should include:
· Documentation that the provider can provide a comparable or better procurement item that meets or exceeds the specifications.
· Documentation that the provider can also provide the same proprietary procurement item or an equivalent procurement item; and
· If transitional costs are identified as the justification for this notice, submit a cost comparison of the identified transitional costs with the provider’s anticipated transitional costs.
Regardless of any prior communications with UDOT Procurement or the State, all providers interested in responding to this notice must submit a response to this posting containing complete responses to all of the information requested above.
DO NOT CONTACT THE REQUESTING UNIT. Any questions regarding this notice, including obtaining additional information, must be obtained through UDOT Procurement during the publication period. No action is required if you agree with this Notice.
If, after the public notice period has passed, UDOT Procurement determines that there are other interested and qualified providers that meet the specifications of this notice; UDOT Procurement will not award a contract pursuant to this notice.
If, after the public notice period has passed, no valid challenges have been received, then the UDOT Division of Procurement may award a contract to the identified vendor without competition.
Please read the entire form very carefully before responding to this notice.
It is anticipated that this procurement will result in a:
| RESULT |
| ACTION |
X
Contract
MOU
1. The term of this contract will be: expires 06/30/2028 and renewal options: none.
| Purchase Order |
| 1. Insert the Accounting Coding: Example: 8301 XDA B87E12 |
Coding for this Purchase Order: Unit FORMTEXT
Appr FORMTEXT
Obj FORMTEXT
Activity FORMTEXT
Function FORMTEXT
Other
___ GAX
___ P Card
1. NOTICE: The GAX option is for EXTENUATING circumstances only. Requesting Unit may not make the procurement until after the solicitation process is completed and the method of payment has been approved by UDOT Procurement.
NOTICE: The Requesting Unit may not make the procurement until after the solicitation process is completed and the purchase order or contract is fully signed by and delivered to all required parties.
| Description of procurement item to be purchased: |
| Technology systems at our POE’s |
| Estimated Total Term Cost/Cost per quote: |
| Additional Funding $2,000,000.00 |
| Freight Cost (F.O.B. Destination, Freight Prepaid): |
| NA |
| Vendor Name: |
| RC Hunt Electric |
Explain in detail the service or product to be procured (additional information is found on any attached Scope of Work):
Continuing the install and upgrade e-screening systems out of Port of Entry’s, including identifying Out of Service Carriers through integration with our VMS signs. Finishing ongoing project on installing Tire anomaly classification systems(TACS). Installing Commercial Vehicle sorting systems.
Installation of weigh-in-motion sensors, USDOT readers, license plate readers, cameras, masts, poles, signs, technical wiring, and other equipment typical to the other e-screening systems already in place at Ports of Entry in the State of Utah.
The Port Operations Enhancement project includes installation of sensors, technical wiring, conduit, and other equipment necessary for implementation of tire anomaly system technology at ten additional locations throughout the State of Utah.
The Operations and Maintenance project includes maintenance and possible replacement (as determined by the Division) and/or repairs of currently installed equipment, systems, sensors, and other equipment vital to our e-screening operations.
CHECK THE THAT BOX IDENTIFIES WHY A CONTRACT SHOULD BE AWARDED WITHOUT ENGAGING IN A STANDARD PROCUREMENT PROCESS:
| X |
| There is only one source for the procurement item, or Compatibility of equipment, technology, software, accessories, replacement parts, or service, including professional services, is the paramount consideration. |
| Complete section A |
| Transitional costs are a significant consideration in selecting a procurement item and the results of a cost-benefit analysis demonstrate that transitional costs are unreasonable or cost-prohibitive. |
| Complete section B |
| The award of a contract is under circumstances, described in rules adopted by the applicable rulemaking authority, that make awarding the contract through a standard procurement process impractical and not in the best interest of the procurement unit. |
| Complete section C |
| Procurement item is needed for Trial use or testing to determine whether the item will benefit the agency. |
| Complete section D |
SECTION A: ONLY ONE SOURCE
| 1. |
| What is unique about this procurement item to justify an award of contract without engaging in a standard procurement process? (Explain in detail why the service or product is only available from a single supplier.) |
Project Delays resulting in funding challenges
| 2. |
| Could the procurement item be reasonably modified to allow for competition? |
No there is an existing contract
| 3. |
| Explain the market research performed. |
Existing contract
| 4. |
| What research have you conducted to ensure the requested item is not available on an existing state cooperative contract? |
Existing contracts
| 5. |
| List the names of other similar vendors contacted, contact person, and a summary of their response, |
NA
| 6. |
| Disclose in space below if the requestor has any personal, financial, or fiduciary relationship with the recommended vendor. |
No
SECTION B: TRANSITIONAL COSTS
| 1. |
| Describe the existing equipment, technology, software, accessories, replacement parts, or service, hereafter referred to as equipment; include the original purchase price and date of purchase for the existing equipment. |
| 2. |
| Supply the following: |
| a. |
| Procurement method that was used to purchase the existing equipment (IFB, RFP, Sole Source): |
| b. |
| Solicitation number, RQS number, or sole source number for the existing equipment: |
| c. |
| Contract number for the existing equipment: |
| 3. |
| Attach the cost-benefit analysis, as required by Utah Code Section 63G-6a-802 that demonstrates that transitional costs are unreasonable or cost-prohibitive. |
SECTION C: STANDARD PROCUREMENT PROCESS IMPRACTICABLE
| 1. |
| Review R33-8-101c |
and provide the supporting justification that awarding through a standard procurement process is impractical and not in the best interest of the procurement unit under the circumstances; including any supporting documentation.
| 2. |
| Supply the following, if applicable: |
| a. |
| Procurement method that was used to purchase the existing equipment. (IFB, RFP, Sole Source): |
| b. |
| Solicitation number, RQS number, or sole source number for the existing equipment: |
| c. |
| Contract number for the existing equipment |
SECTION D: PROCUREMENT ITEM IS NEEDED FOR TRIAL USE OR TESTING
| 1. |
| Describe why is the trial use or testing necessary? (Explain the purpose of the trial use or testing of the procurement item.) |
| 2. |
| What is the anticipated end result of the trial or test? |
| 3. |
| Do any other similar vendors provide this product or service? |
| a. |
| If yes, list the company names, and whether their products will be tested: |
| 4. |
| What criteria were used to choose this vendor? |
| 5. |
| What is the scope, size, and location of test or trial? |
| 6. |
| Contracts for trial and testing must follow the criteria listed in UCA 63G-6a-802.3, and the period for a trial use or testing of a procurement item under a trial use contract may not exceed 24 months, unless the procurement officer provides a written exception documenting the reason for a longer period. Exception attached yes: no: |
LEASING PERSONAL PROPERTY (Not Real Property)
Lease requests must include an approved FI 9 State of Utah Lease Obligation Record form from the Division of Finance. The FI 9 State of Utah Lease Obligation Record form can be found on the Division of Finance website finance.utah.gov under Forms. The Finance policy FIACCT 09-21.00 Fixed Assets – Leases can be found on the Division of Finance website under Accounting Policies and Procedures. Approved FI 9 attached.
�(1) In accordance with Subsection 63G-6a-802(1)(c), the procurement official may consider, as applicable, the following circumstances when making a determination as to whether awarding a contract through a standard procurement process is impractical and not in the best interest of the procurement unit:
(a) a contract award to a specific supplier, service provider, or contractor is a condition of a donation or grant that will fund the full cost of the supply, service, or construction item;
(b) public utility services, when only one public utility service is available in an area;
(c) an item where compatibility is the overriding consideration; or
(d) a used procurement item that presents a unique, specialized, or time-limited buying opportunity.