2-Exhibit B - Mt. Ogden Admin Building Price Schedule.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
25-04031VW Mt Ogden Administration Building Construction
Solicitation number
25-04031VW
Issued by
Weber County, Utah

About this file

This is a Price Schedule exhibit (Exhibit B) for the City of Ogden's 25-04031VW Mt. Ogden Administration Building Construction project located at Wall Avenue and 18th Street in Ogden, Utah. The document provides a standardized cost estimate form structure for bidders to complete pricing for three distinct project components: the Administration Building, the Canopy and Bus Parking structure, and construction Alternates. The Administration Building pricing encompasses 16 line items including foundations, vertical structure, floor and roof structures, exterior cladding, roofing and waterproofing, interior partitions and glazing, finishes, specialties, stairs and vertical transportation, all mechanical, electrical, fire protection systems, site preparation, paving and landscaping, and on-site utilities. The Canopy and Bus Parking section includes 8 corresponding line items with similar structural and site work categories. Four alternates are specified: Alternate 1 for Level 2 Exterior Patio (add), Alternate 2 for Fence Type B (deduct), Alternate 3 for AESS Detailing (deduct), and Alternate 4 for metal panel options including a deduct for Citadel 2000 RS panels and an add for concealed panel exterior metal wall systems.

Bidders must provide total costs and percentages for General Conditions, General Requirements, Bonds and Insurance, and Overhead & Profit, with these percentages applying to all future change orders during construction. Pricing must include installation of infrastructure for audio/visual systems, access control, security cameras, wireless access points, and network systems with electrical conduits and junction boxes, but excludes equipment and equipment installation costs. The document requires bidders to provide additional details or clarifications as necessary to complete the comprehensive cost estimate for this multi-component municipal construction project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING

25-04031VW Mt. Ogden Administation Building Project Cost Estimate Form - Exhibit B Administration Building

DESCRIPTIONAMOUNT
BUILDING AND SITE COST SUMMARY
01FOUNDATIONS
02VERTICAL STRUCTURE
03FLOOR AND ROOF STRUCTURES
04EXTERIOR CLADDING
05ROOFING, WATERPROOFING, AND SKYLIGHTS
06INTERIOR PARTITIONS, DOOR, AND GLAZING
07FLOOR, WALL, AND CEILING FINISHES
08FUNCTION AND EQUIPMENT SPECIALTIES
09STAIRS AND VERTICAL TRANSPORTATION
10PLUMBING SYSTEMS
11HEATING, VENTILTATION, AND AIR CONDITIONING
12ELECTRIC LIGHTING, POWER, AND COMMUNICATIONS
13FIRE PROTECTION SYSTEMS
14SITE PREPARATION AND DEMOLITION
15SITE PAVING, STRUCTURES, AND LANDSCAPING
16UTILITIES ON SITE
SUBTOTAL
GENERAL CONDITIONS%
GENERAL REQUIREMENTS%
BONDS%
INSURANCE%
OVERHEAD & PROFIT%
TOTAL CONSTRUCTION COST
Provide additional details or clarifications as necessary
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for A/V, but should not include equipment or equipment installation.
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for access control, security cameras, wireless access points, and network, but should not include equipment or equipment installation.
Provide total cost and percentage values for General Conditions, General Requirements, Bonds and Insurance, and Overhead and Profit.

These percentages will apply to all change orders during construction.

CANOPY

25-04031VW Mt. Ogden Administation Building and Site Project Cost Estimate Form - Exhibit B Administration Building

DESCRIPTIONAMOUNT
CANOPY AND BUS PARKING COST SUMMARY
01FOUNDATIONS
02VERTICAL STRUCTURE
03FLOOR AND ROOF STRUCTURES
04ROOFING, WATERPROOFING, AND SKYLIGHTS
05ELECTRIC LIGHTING, POWER, AND COMMUNICATIONS
06SITE PREPARATION AND DEMOLITION
07SITE PAVING, STRUCTURES, AND LANDSCAPING
08UTILITIES ON SITE
SUBTOTAL
GENERAL CONDITIONS%
GENERAL REQUIREMENTS%
BONDS%
INSURANCE%
OVERHEAD & PROFIT%
TOTAL CONSTRUCTION COST
Provide additional details or clarifications as necessary
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for A/V, but should not include equipment or equipment installation.
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for access control, security cameras, wireless access points, and network, but should not include equipment or equipment installation.
Provide total cost and percentage values for General Conditions, General Requirements, Bonds and Insurance, and Overhead and Profit.

ALTERNATES

25-04031VW Mt. Ogden Administation Building and Site Project Cost Estimate Form - Exhibit B Administration Building

DESCRIPTIONAMOUNT
ALTERNATES COST SUMMARY
01ALTERNATE 1 - LEVEL 2 EXTERIOR PATIO (ADD)
ALTERNATE 1 - INDIRECT COST (ADD)
02ALTERNATE 2 - FENCE TYPE B (DEDUCT)
ALTERNATE 2 - INDIRECT COST (DEDUCT)
03ALTERNATE 3 - AESS DETAILING (DEDUCT)
ALTERNATE 3 - INDIRECT COST (DEDUCT)
04ALTERNATE 4 - METAL PANEL DEDUCT MP1, METAL FACED COMPOSITE WALL PANELS, CITADEL 2000 RS METAL PANEL (DEDUCT)
ALTERNATE 4 - INDIRECT COST (DEDUCT)
ALTERNATE 4 - MP2, CONCEALED PANEL EXTERIOR METAL WALL (ADD)
ALTERNATE 4 - INDIRECT COST (ADD)
Provide additional details or clarifications as necessary
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for A/V, but should not include equipment or equipment installation.
Pricing should include installation of infrastructure including electrical, conduits, and junction boxes for access control, security cameras, wireless access points, and network, but should not include equipment or equipment installation.
Provide total cost and percentage values for General Conditions, General Requirements, Bonds and Insurance, and Overhead and Profit.