2. Statement of Work.pdf
PDF 1019 KB Posted
- Attached to
- LUCERNE CAMPGROUND CONSTRUCTION PHASE 5 Federal contract opportunity
- Solicitation number
- 1240LT26Q0026
- Issued by
- Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for Lucerne Campground Construction Phase 5, a reconstruction project located in the Flaming Gorge National Recreation Area near Manila, Utah. The scope includes demolition of two existing restroom buildings and adjacent concrete sidewalks, with new construction of precast concrete restroom buildings with showers in Loops E and F, family unit shelters, irrigation water main lines, electrical control wiring for irrigation zones, and asphalt trench repairs. The contract base work requires 180 calendar days from May 11, 2026 to November 30, 2026. Optional work includes windscreen fencing, roadside strips planting and irrigation, Loops E & F planting and irrigation systems, additional irrigation mainline segments, and tree line bubbler irrigation systems, each adding 30 calendar days if awarded.
The SOW establishes comprehensive technical specifications across 29 specification sections covering construction staking, measurement and payment procedures, mobilization, submittal requirements, quality control, erosion control, waste disposal, structural demolition, concrete work, painting, signage, precast vault restroom buildings, pre-manufactured shelters, water distribution systems, curb valves, irrigation pumps, electrical systems, and earthwork. Key requirements include contractor-furnished quality control testing, sediment and erosion control plans, stream protection measures, dust abatement, pressure-washed construction equipment, traffic control per MUTCD standards, and compliance with Federal accessibility standards. All work must meet 2012 International Building Code standards for structural design with 200 psf snow load and 90 mph wind load requirements. The project involves coordination with existing utilities, seasonal reservoir conditions, and public campground access maintenance throughout construction, with the Contracting Officer responsible for final inspection and approval of all completed work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Attendance - Amendment 001.pdf | ||
| 1.1 Solicitation Terms and Conditions Amendment 001.pdf | ||
| 3.1 SOI - Lucerne Amendment 001.pdf | ||
| FAR 52.222-90 Amendment 001.pdf | ||
| Questions-Answers Amendment 001.pdf | ||
| 2.1 Statement of Work Addition Amendment 001.pdf | ||
| 6. Supplemental Drawings Existing Irrigation.pdf | ||
| 5. Drawings.pdf | ||
| 0. Quote -Checklist.docx | DOCX document | |
| 1. Solicitation Terms and Conditions.pdf | ||
| 3. SOI - Lucerne.pdf | ||
| 4. Experience Questionnaire.docx | DOCX document | |
| 7. Davis-Bacon Act WD - UT20260079.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
LUCERNE CAMPGROUND CONSTRUCTION PHASE 5
1.1 SCOPE OF CONTRACT
A. This project consists of reconstructing portions of the Lucerne Campground.
B. Base:
1. Demolition work includes the following:
a. Removing and disposing of two existing restroom buildings and adjacent concrete sidewalks. The existing potable water, sewer and electrical utilities are to remain, as designated.
2. New construction work includes the following:
a. Furnishing and installing new precast concrete restroom buildings (one with showers) in Loops E and F, including sidewalks, signs, finish grading, new electrical service and connection to existing water and sewer systems.
b. Constructing new family unit shelters in Loops E and F.
c. Constructing a portion of the irrigation water main line.
d. Installing electrical control wiring for Zones 26 to 29 and the Treeline
Bubbler Zones.
e. Asphalt trench repair.
C. Options: Optional new construction work includes the following:
1. Option: Windscreens
a. Constructing wind screen fencing for family units in Loops E and F.
2. Option: Roadside Strips Planting and Irrigation System (Zones 26 to 29)
a. Installing landscaping and hydro seed and constructing an irrigation system for the Roadside Strip Areas, including Zones 26 to 29
3. Option: Loops E & F Planting and Irrigation Systems (Zones 18 to 25)
a. Installing landscaping, trees and hydroseed.
b. Constructing an irrigation system for Loops E and F Zones 18 to 25.
4. Option: Irrigation Mainline Segments 2 & 3
a. Constructing the “Segment 2 and 3” irrigation mainline, including asphalt trench repairs.
5. Option: Tree Line Bubblers Irrigation System
a. Constructing an irrigation system for the existing trees along the “Tree Line” parallel to the Entrance Road that provides access to Loops A to E
D. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located in the Flaming Gorge National Recreation Area of the Ashley National Forest, Daggett County, Utah, in Section 20, T 3 N, R 21 E. It is located approximately 8 miles East of Manila, Utah. The project may be accessed from Wyoming State Road 530 and Lucerne Valley Recreation Road.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction areas will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access. The Contractor shall construct a temporary fence with appropriate signing at locations necessary to keep the public out of the work area.
2. Access to Loops A, B, C, D & G and the main entrance road must remain open to the public at all times during construction, except for when work is being performed in those areas. The contractor is responsible for providing traffic control when needed according to Section 1.4 below.
3. Contractor will provide all materials and labor necessary to protect streams and lakes, wet or dry, during construction activities. The Contractor will be required to submit a stream and lake protection plan and receive approval from the Contracting Officer, in writing, prior to the beginning of construction.
4. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
5. Dust Abatement: The contractor shall take precautions to prevent unnecessary windblown dust. It is especially important to prevent dust from blowing into occupied camping areas or other areas that are in use by the public. Cover or water stockpiles. To the extent possible, construct road subgrades during off-peak recreation periods. Keep all exposed subgrades watered or use other approved method to prevent dust from becoming airborne.
6. Water is available at the site for construction purposes. The Contractor will be allowed to pump water directly from the reservoir for construction purposes. The Contractor must submit a plan for pumping water to the Contracting Officer for approval. Potable water shall not be used for construction.
7. Toilet facilities are available at the site.
8. Power is available at the site for construction purposes; however, the Contractor must coordinate payment of electrical costs with the Concessionaire at the expense of the Contractor.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic and public has been submitted by the contractor and approved by the Contracting Officer and Utah Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around.
Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site. Camping will be permitted within the construction area. If the Contractor wishes to camp outside the construction area, the standard fee for camping at the campground will be required.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. Period of Performance 5/11/2026 – 11/30/2026.
1.8 CONTRACT TIME
A. Base: 180 Calendar Days.
B. Option - Windscreens: 30 calendar days if awarded.
C. Option – Roadside Strips Planting and irrigation system (Zones 26-29): 30 calendar days if awarded.
D. Option - Loops E&F planting and irrigation systems (ZONES 18 TO 25): 30 calendar days if awarded.
E. Option – Irrigation mainline segments 2&3: 30 calendar days if awarded.
F. Option – Tree line bubblers irrigation system: 30 calendar days if awarded.
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 010250 - CONSTRUCTION STAKING
SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 024102 - REMOVAL AND DISPOSAL OF STRUCTURES AND
OBSTRUCTIONS
SECTION 033000 - CAST-IN-PLACE CONCRETE
SECTION 033020 - CONCRETE FROM PACKAGED DRY MIX FOR MINOR
STRUCTURES
SECTION 033540 - CONCRETE SIDEWALK
SECTION 099100 - PAINTING
SECTION 101400 - SIGNS
SECTION 133402 - PRECAST CONCRETE VAULT RESTROOM BUILDING
SECTION 136000 - PRE-MANUFACTURED SHELTER
SECTION 221100 - WATER DISTRIBUTION SYSTEMS
SECTION 221102 - CURB VALVES AND BOXES
SECTION 221120 – IRRIGATION BARGE PUMP
SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
SECTION 311000 - CLEARING AND GRUBBING
SECTION 312000 - EARTHWORK
SECTION 312010 - SELECT BORROW
SECTION 312100 - PROJECT SITE PREPARATION AND GRADING
SECTION 312225 - EXCAVATION & EMBANKMENT
SECTION 321200 - HOT-MIX ASPHALT PAVING
SECTION 321203 - CRACK SEAL
SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE
SECTION 322640 - PAVEMENT MARKING
SECTION 322706 - ASPHALT PAVEMENT PULVERIZING
SECTION 323125 - COMPOSITE WOOD FENCES (WINDSCREENS)
SECTION 328000 - IRRIGATION SYSTEM
SECTION 329206 - SEEDING
SECTION 329310 - EXTERIOR PLANTS
END OF SECTION C
March 2026
CONSTRUCTION STAKING 010250-1
USDA FOREST SERVICE, R4
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION 010250 - CONSTRUCTION STAKING
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of the construction staking of roads, parking lots, parking spurs, family units, tent pads, paths, stairways, culverts, retaining walls, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.
1.2 QUALITY CONTROL
A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.
1.3 MEASUREMENT AND PAYMENT
A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.
PART 2 - PRODUCTS
2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS
A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:
1. Control Points - Northing, Easting, Existing Elevations.
2. Roads, Spurs, Parking Areas - Northing, Easting, and Finish Elevations for centerline and/or edge of roads, spurs, parking areas.
3. Pathways and Trailways - Northing, Easting, and Finish Elevations for centerline.
4. Buildings and Other Structures - Northing, Easting, and Finish Elevations for corners of buildings.
2.2 STAKES
A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top
CONSTRUCTION STAKING 010250-2
2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:
1. Roads, parking lots, and parking spurs -Orange
2. Waterlines, utilities, and culverts -Blue
3. Family Units, group units, stairs, and paths -Red
4. Buildings, excavation and grading -Yellow
5. Tent pads -Blue/White Striped
2.3 SURVEY NOTE PAPER AND BOOKS
A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.
The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.
B. Accuracy requirements:
1. Minimum position close; 1/1000
2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)
3. Cross section and slope stake precision:
a. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.
b. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.
c. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.
3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS
A. Access Roads, Parking Spurs, and Parking lots:
1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope
CONSTRUCTION STAKING 010250-3
stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, typical road section templates, as shown on the drawings and the information provided with staking points.
2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.
B. Group Units, Family Units and Tent Pads
1. Slope stakes shall be established at the corners of family units. Slope stakes shall be written to reference the finish grade of the unit or pad being staked.
C. Paths and Trails
1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, and typical path and trail section templates as shown on the drawings.
2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.
D. Culverts
1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, which ever is greater. The following shall be recorded on these stakes:
a. The actual field measured length
b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.
E. Waterline, Sewerline, & other Utilities
1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.
F. Buildings
1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.
3.3 DISCREPANCIES
CONSTRUCTION STAKING 010250-4
A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.
3.4 VERTICAL CONTROL
A. Vertical control for construction shall be as referenced on the Drawings.
3.5 MARKING STAKES
A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;
PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width
3.6 SURVEY NOTES
A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.
B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The
CONSTRUCTION STAKING 010250-5
party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.
END OF SECTION 010250
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-1
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
7. For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts. Emulsified asphalt will be measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-2
Gallons at 60°F = Gallons at A°F 1+0.00025 (A°F - 60°F)
* A°F is the temperature of the material at the time the gallonage is measured.
a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.
Each vehicle shall bear a plainly legible identification mark.
b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-3
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)
A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-4
B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.
The contractor may remove and replace the defective material or accept the adjustment.
C. The price reduction shall apply to all pay items affected.
D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.
E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)
F. The schedule of price adjustments shall not apply to the following tests:
Test AASHTO Test Method Spot Test T102 Particle Charge T59 Ductility T51
G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.
H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-5
Table 011250-1
Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.
Application
Deviation from Specification Limit Measured in Reproducibility Units*.
Less than 1 1 but less than 2
2 but less than 3
3 or more
Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.
0% 5% 25% Remove & Replace
Price reduction applicable to bituminous material paid for as a separate item.
0% 10% 25% Remove & Replace
* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.
The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bituminous spread rates in increments no greater than 1 foot over the width of the spray bar and variation between increments is no greater than 5 percent.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title Subse ction Required Submittal
C General Specifications 1.3A Stream Protection Plan C General Specifications 1.4A Traffic Control Plan
010250 Construction Staking 3.6 A Survey Notes 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 023701 Sediment & Erosion Control
Measures 1.2A Sediment & Erosion Control Plan
033000 Cast-in-Place Concrete 1.3A Product Data 033000 Cast-in-Place Concrete 1.3B Design Mix 033000 Cast-in-Place Concrete 1.3C Shop Drawings 033000 Cast-in-Place Concrete 1.3D Material Test Reports 099100 Painting 1.4A Color Selection Samples 101400 Signs 1.2A Sign List Submittal 133401 Precast Concrete Restroom Building 1.2A Manufacturer’s Literature 133401 Precast Concrete Restroom Building 1.2B Shop Drawings 133401 Precast Concrete Restroom Building 1.2C Design Calculations 133401 Precast Concrete Restroom Building 1.2D Concrete Delivery Certificates 133402 Precast Concrete Vault Restroom
Building 1.2A Manufacturer’s Literature
133402 Precast Concrete Vault Restroom Building
1.2B Shop Drawings
133402 Precast Concrete Vault Restroom Building
1.2C Design Calculations
133402 Precast Concrete Vault Restroom Building
1.2D Concrete Delivery Certificates
136000 Shelter 1.2A Shop Drawings 221100 Water Distribution Systems 1.3A Product Data 221100 Water Distribution Systems 1.3B Water Disposal Plan 221120 Irrigation Barge Pump 1.2 Product Data 260500 Common Work Results for Electrical 1.2A Product Data 312000 Earthwork 1.3A Bedding and Backfill Certification 312000 Earthwork 1.3A Sieve Analysis
312225 Excavation and Embankment 1.3A Density Test Results
321200 Hot Mix Asphalt Paving 1.2A Product Data 321200 Hot Mix Asphalt Paving 1.2B Job Mix Design
SUBMITTAL PROCEDURES 013300-6
Spec.
Section Section Title Subse ction Required Submittal
321200 Hot Mix Asphalt Paving 1.2C Material Certificate 321203 Crack Seal 1.2A Product Data 321204 Crushed Aggregate Base or Surface
Course 1.2A Aggregate Base – Source, Gradation, Material Properties 321204 Crushed Aggregate Base or Surface
Course 1.2B Compaction Test Results and
Proctor 322640 Pavement Markings 1.3A Product Data 323125 Composite Wood Fences 1.5A Product Data/Samples 323125 Composite Wood Fences 1.5B Recycled Content/Materials 323125 Composite Wood Fences 1.5C Product Data/Maintenance 328000 Irrigation System 1.2A Product Data 329206 Seeding 1.3A Seed Certification 329310 Exterior Plants 1.3A Product Data 329310 Exterior Plants 1.3B Mineral Mulch 329310 Exterior Plants 1.3C Product Certificates 329310 Exterior Plants 1.3D Planting Schedule 329310 Exterior Plants 1.3E Maintenance Instructions
END OF SECTION 013300
QUALITY CONTROL 014100-1
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
QUALITY CONTROL 014100-3
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
B.
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
033000 2.13 Mixing and Delivery Each Truck 033000 3.13 Concrete – Slump, Air, Temperature 1 composite per truck load delivered 033000 3.13 Concrete - Compression Test
Specimens at 7 days and 28 days (see spec)
221100 3.2O HDPE Pipe - Bent Strap Test Once Daily 221100 3.5A Hydrostatic Testing of Water
System See Spec.
221100 3.5B Pressure and Leakage Test – Water Line
See Spec.
221120 2.1 Pump Performance Test See Spec.
260500 1.3 Electrical Testing See Spec.
QUALITY CONTROL 014100-4
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency 312000 3.14C Compaction Test – at Pipe Zone One per 600 Feet of
Trench 312000 3.14C Compaction Test – at Pipe Zone One test – at each road crossing 312000 3.14D Compaction Test – above Pipe
Zone One per 600 Feet of
Trench 312000 3.14D Compaction Test – above Pipe
Zone One test every other lift – at each road crossing
312000 3.14I Tracer Wire Conductivity Test Until Passing 312000 3.17A Compaction Test – Backfill/Fills One per Building 312000 3.20D Compaction Test – Paved Asphalt and Comfort Stations See Spec.
312000 3.20D Compaction Test – Exterior Concrete Slabs
See Spec
312225 3.11B Moisture-Density Relationship One Test for Each Soil Type
Encountered 312225 3.11B Compaction – Road Embankment
(Method 4) One test every 300
sq. yd. of embankment per lift
312225 3.11B Compaction – Subgrade One test every 1000
sq. yd. of subgrade
321200 3.9B Gradation and Asphalt Content One per 700 tons or Min. of 1 per Project
321200 3.9C Field Density Tests – Asphalt One test for every 300 sq. yd. of pavement 321204 3.4A Compaction Tests – Road Base and
Surface Course One test for every
300 sq. yd. of aggregate
321204 3.4A Compaction Tests – Aggregate Base for Concrete Slabs
One test for each family unit or group area 321204 3.4A Compaction Tests – Aggregate
Base for Concrete Slabs One test for each prefabricated building pad
END OF SECTION 014100
SEDIMENT AND EROSION CONTROL MEASURES 023701-1
LUCERNE CAMPGROUND CONSTRUCTION PHASE 4
SECTION…