PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
PROJECT: Plumas NF Lookouts Restrooms
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 001 |
| Mobilization |
| 1 |
| LS |
| $___________ |
| $___________ |
| 002 |
| Argentine LO Restroom Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 003 |
| Dixie Mountain LO Restroom & Stairs Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 004 |
| Mt Hough LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 005 |
| Mills Peak Staff LO LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 006 |
| Mills Peak Parking LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 007 |
| Smith Peak LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| 008 |
| Thompson Peak LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| BASE PLUMAS NF LOOKOUTS RESTROOMS TOTAL: |
| $___________ |
B.2 SCHEDULE OF ITEMS - (OPTION 1)
PROJECT: Red Rock LO Restroom Decommission and Construction – OPTION 1
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 009 |
| Red Rock LO Restroom Decommission and Construction |
| 1 |
| LS |
| $___________ |
| $___________ |
| RED ROCK LOOKOUT OPTION 1 TOTAL: |
| $___________ |
B.3 SCHEDULE OF ITEMS - (OPTION 2)
PROJECT: Pike Co LO Restroom Excavation – OPTION 2
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 010 |
| Pike Co LO Restroom Excavation |
| 1 |
| LS |
| $___________ |
| $___________ |
| PIKE CO LOOKOUT OPTION 2 TOTAL: |
| $___________ |
B.4 SCHEDULE OF ITEMS - (OPTION 3)
PROJECT: Red Rock LO Restroom Decommission and Construction – OPTION 3
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 011 |
| Pike Co LO Restroom Furnish and Installation |
| 1 |
| LS |
| $___________ |
| $___________ |
| PIKE CO LOOKOUT OPTION 3 TOTAL: |
| $___________ |
| BASE + OPTION 1, 2, & 3 TOTAL: |
| $__________________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation, contractors must submit pricing for all items.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |
| POC & Title: |