2. Schedule Of Items.docx

DOCX document 36 KB Posted

Attached to
Forest Service -Tropical Storm Hilary Damage Repair
Solicitation number
127EAW25R0056
Issued by

About this file

This document is a Schedule of Items for a Forest Service road repair project in the San Bernardino National Forest, addressing damage from Tropical Storm Hilary. The solicitation (Number 127EAW25R0056) covers repair work on six road segments (1N02, 1N05, and 1N17) with a total project length of 0.46 miles, with an estimated contract value between $1,000,000 and $5,000,000. The project is a Total Small Business Set Aside and includes multiple construction activities such as mobilization, soil erosion control, clearing, roadway excavation, aggregate base installation, asphalt concrete placement, and spillway assembly.

Key project dates include a mandatory site visit scheduled for September 2nd, 2025 at 0900 AM PDT, and a deadline for Requests for Information by September 4th, 2025 at 1000 AM PDT. The solicitation requires contractors to submit pricing for all items, with quantities to be field-verified. A bid bond/guarantee is required for proposals exceeding $150,000. The project is being executed by the Department of Agriculture Forest Service and involves comprehensive road reconstruction and restoration work across multiple road segments in the San Bernardino National Forest.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS

(1) Road - 1N02 M.P. 0.1 || Length (miles) 0.07

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1
20407
Select borrow, compaction method B, finish method A
CQ
C.Y.
1350
25102-5
Placed riprap, class 5
CQ
Ton
402
25209
Geotextile, type IV, D
CQ
S.Y.
330
30102
Aggregate Base Class 2
CQ
Ton
527
30318
Road reconditioning, roadbed, compaction method 3
CQ
Mile
0.07
40607
Asphalt Concrete, CA State DOT, Type A
CQ
Ton
133
60101
Concrete Grout
CQ
C.Y.
45

Road 1N02 M.P. 0.1 Total $

(2) Road - 1N05 M.P. 0.07 || Length (miles) 0.28

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1
20209
Selective clearing
LSQ
L.S.
1
20406
Roadway Excavation
CQ
Mile
0.28
20407
Select borrow, compaction method B, finish method A
CQ
C.Y.
9200
21201
Linear grading
CQ
Mile
0.28
20426
Grade dips, Rolling
CQ
Each
3

Road 1N05 M.P. 0.07 Total $

(3) Road - 1N05 M.P. 0.65 || Length (miles) 0.01

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1
20407
Select borrow, compaction method B, finish method A
CQ
C.Y.
139
20426
Grade dips, Rolling
CQ
Each
1
60601
Spillway assembly – 24” Overside Drain and 20’ Flume
CQ
Each
1

Road 1N05 M.P. 0.65 Total $

(4) Road - 1N05 M.P. 0.79 || Length (miles) 0.01

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1

20407 Select borrow, compaction method B, finish method A

CQ

C.Y.

20426
Grade dips, Rolling
CQ
Each
1
60601
Spillway assembly – 24” Overside Drain and 20’ Flume
CQ
Each
1

Road 1N05 M.P. 0.79 Total $

(5) Road - 1N17 M.P. 0.2 || Length (miles) 0.06

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1
20401
Roadway excavation, compaction method B, finishing method A
CQ
L.S.
1

Road 1N17 M.P. 0.2 Total $

(6) Road - 1N17 M.P. 0.4 || Length (miles) 0.03

Item Number
Description
Method Measure.
Units of Measure.
Quantity
Unit Price
Cost
15101
Mobilization
LSQ
L.S.
1
15713
Soil Erosion & Pollution Control
LSQ
L.S.
1
20158
Clearing and Debris Removal
LSQ
L.S.
1
20401
Roadway excavation, compaction method B, finishing method A
CQ
L.S.
1
20407
Select borrow, compaction method B, finish method A
CQ
C.Y.
20
21102
Roadway obliteration
LSQ
L.S.
1
30101
Crushed Aggregate base, compaction method A
CQ
Ton
75
40607
Asphalt Concrete, CA State DOT, Type A
CQ
Ton
43
62528
Seeding, Fertilizing, and Mulching, hydraulic or dry Method
LSQ
L.S.
1

Road 1N02 M.P. 0.1 Total $

ROADS
LENGTH MILES
TOTAL COST
1
1N02 M.P. 0.1
0.07
$
2
1N05 M.P. 0.07
0.28
$
3
1N05 M.P. 0.65
0.01
$
4
1N05 M.P. 0.79
0.01
$
5
1N17 M.P. 0.2
0.06
$
6
1N17 M.P. 0.4
0.03
$
Project Total Cost
$

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

* One award will be made from this solicitation, contractors must submit pricing for all items.

* Bid Bond/Guarantee. REQUIRED for proposals exceeding $150,000 IAW FAR 52.228-1 Bid Guarantee.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

The contractor shall complete the table below and include the information with their proposal.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID: