Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
1
Mobilization
1
EA
$
$
2
Material Costs
240
LF
$
$
3
Labor Install Costs
240
LF
$
$
TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID: