2. Schedule.docx
DOCX document 17 KB Posted
- Attached to
- 127EAW25R0012 - O'Neil Creek Bridge Repairs
- Solicitation number
- 127EAW25R0012
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Schedule of Items for the O'Neil Creek Bridge Repairs project issued by the Department of Agriculture Forest Service. The solicitation (Number 127EAW25R0012) is a total small business set-aside construction contract with a project value between $250,000 and $500,000. The project involves bridge repair and replacement work, including specific line items such as mobilization, structure removal, precast prestressed concrete structural members, bridge railing installation, approach rail, temporary traffic control, and object markers.
Key procedural details include a requirement for contractors to submit pricing for all listed items, field verify quantities, and submit proposals with complete documentation. All requests for information must be submitted to Contracting Officer Greg Cunningham by 1:00 PM PST on June 6th, 2025. No pre-proposal site visit will be conducted, but prospective offerors are allowed to independently view the project locations. The solicitation emphasizes that failure to inspect the site will not constitute grounds for claims after contract award.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
PROJECT: O'Neil Creek Bridge Repairs
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 15101 |
| Mobilization (Road) |
| 1 |
| L.S. |
| $___________ |
| $___________ |
| 20305 |
| Removal of Structures and Obstructions |
| 1 |
| L.S. |
| $___________ |
| $___________ |
| 55301 |
| Precast Prestressed Concrete Structural Members 1'-3"x4'-0"x40'-0" Voided Slabs |
| 3 |
| Each |
| $___________ |
| $___________ |
| 55601 |
| Steel Bridge Railing |
| 58 |
| L.F. |
| $___________ |
| $___________ |
| 61701 |
| Bridge Approach Rail, Type II, Class B |
| 50 |
| L.F. |
| $___________ |
| $___________ |
| 61702 |
| Terminal Section Type G4-CRT with Concrete Anchor |
| 2 |
| Each |
| $___________ |
| $___________ |
| 61706 |
| Connection to Bridge Rail Structure |
| 2 |
| Each |
| $___________ |
| $___________ |
| 63306 |
| Object Markers, Type 3 |
| 4 |
| Each |
| $___________ |
| $___________ |
| 63501 |
| Temporary Traffic Control |
| 1 |
| L.S. |
| $___________ |
| $___________ |
| BASE TOTAL: |
| $___________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation, contractors must submit pricing for all items.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |
| POC & Title: |
| Email: |
| Phone Number: |
| UEI Number: |
| Tax ID: |
File details come from the government source that posted it. Updated .