Elk Clark Stewardship IRSC Coconino National Forest Solicitation 12363N22Q4069 Flagstaff Ranger District
APPENDIX A
TECHNICAL SPECIFICATIONS FOR SERVICE WORK ITEMS
SECTION I – DESCRIPTION OF WORK:
The Elk Clark Stewardship IRSC is comprised of nine cutting units, together totaling approximately 1,738 acres of ponderosa pine forest. The goal of this project is to mechanically cut and remove all included timber/product to help restore the forest to more historic conditions. Maintenance of approximately 32 miles of road will also be required. The cutting units are primarily leave tree marked with one cutting unit using the designation by prescription (DXP) method. There are approximately 39 existing landings that contain residue/biomass that require removal from national forest land.
SECTION II – WORK ITEMS
Mandatory Item 1: Mechanically Cut and Remove Included Products (Contract Area):
Cut and remove from Contract Area all included products as identified in Appendix B. Road maintenance will also be required commensurate with use (see Appendix C for Road Maintenance requirements).
1. Cut and remove all merchantable and non-merchantable timber as designated on the ground or as described in the cutting guide for designation by prescription units.
2. Remove all slash (residue/biomass) at designated areas as displayed on the Contract Area Map that are outside of the cutting units as well as from cutting units 1-9 and 12. These products shall be transported off the National Forest. Some slash may be left on the Contract Area as erosion control for landings, skid trials, and temporary road closeout by written agreement.
3. All landings including the designated areas displayed on the Contract Area Map shall be treated in accordance with requirements of provisions in Appendix B (state applicable C provisions).
4. Obliteration of all existing temporary roads as displayed on the Contract Area Map and newly created temporary roads.
SECTION III – CONTROL OF WORK
The Contractor agrees to conduct its operations under this contract and other related business activities in compliance with Federal, State, and local statutes, standards, orders, permits and other regulations.
The Contractor shall meet all State and local environmental quality laws applicable to National Forest system lands.
Work may be done any time during the term of the contract, except under the conditions described in Appendix B C6.313#.
SECTION IV – INSPECTION AND ACCEPTANCE
For All Work Items:
At any point during the project, the Contractor and/or Project Manager may request (documented through email, text, or hand-written request) an in the field consultation with the Forest Service to inspect work progress, review contract specifications, or clarify issues. The Forest Service shall respond to Contractor’s request within 5 working days, excluding weekends and federal holidays.
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Government Inspection Procedures – The COR, or a designated inspector (GTM), will make periodic inspections while work is in progress, usually daily at first, as needed to assure work is proceeding satisfactorily. The Contractor shall notify the COR when units are started, when problems are encountered and when contract work needs government oversight.
1. When unit is completed and ready for government inspection, Contractor’s designated Project manager shall request unit inspection in writing, prior to moving out of the general area.
2. The COR, or designated inspector, will determine compliance with contract specifications through informal visual inspections. In the event visual inspection indicates work to be in non-compliance with specifications, prompt corrective action and/or rework shall be required.
Government Inspection Procedures – Formal (Plots)
1. In the event visual inspection indicates work and / or rework to be in non-compliance with contract specifications, a series of verification plots shall be installed by the Government to determine compliance with specifications and percent of satisfactory work for treatment of each unit not meeting specification as observed with visual inspection.
2. Government verification plots will be consistent with Appendix B C6.36# Acceptance of Work for C2.355# Designation by Prescription treatment units.
3. For all other units and treatment areas, Government verification plots will consist of a series of fixed area plots that will have 4 quadrants of pass or fail.
4. Plots and grid will be distributed so that a representative sample is obtained. Pile locations including landings may be sampled in plots to determine overall quality.
5. The COR or designated inspector will mark the center of each plot on the ground using flagging, stakes, or pin flags. Additional flagging will be hung near the plot center so that it may be seen from a distance.
The inspector will include the plot number, their initials and date on the flagging.
6. Plots will be numbered to correlate with the inspection form and transects on a unit map.
7. The minimum number of verification plots, per treatment unit, shall be as follows:
Unit Acreage Minimum No. of Plots
1 – 9 1 plot per 2 acres 10 – 29 10 plots 30 – 59 1 plot per 4 acres 60 – 99 20 plots 100 1 plot per 5 acres
8. Determination of acceptability of the work performed will be based on Government verification inspections and will be considered conclusive.
9. At each plot, the Government will examine the plot area and record findings.
Table 1 – Minimum Acceptable Quality Levels (AQL) of Work
ITEM DESCRIPTION SCHEDULE UNIT Min AQL
Mechanically Cut and Remove Included Products
MANDATORY ACRE 95%
Unsatisfactory Performance
1. If the work quality falls below the minimum AQL, the COR will immediately notify the Contractor, in writing, and order him to improve the quality of subsequent tree cutting.
2. If after rework has been performed and reinspected, and work quality still falls below minimum AQL percent, payment will either be made at a reduced rate, or not at all, as determined in SECTION V below.
3. Repeated failure to produce work quality at or above the minimum acceptable standard will be considered reason for contract termination for cause.
Reinspection Upon Contractor Request
1. If Government inspection results are unacceptable to the Contractor, a reinspection may be requested, in writing, within 5 business days after receipt of notice of said inspection results. The same inspection procedure will be used; however, the inspection pattern will be shifted so that new inspection plots will not overlap previously inspected plots.
2. If reinspection results – rounded up to the nearest whole percent – indicate a variance of more than 5 percent from the first inspection, the results of the second inspection will be used to calculate work quality, and the Government will bear the cost of reinspection.
3. If reinspection results – rounded up to the nearest whole percent – are within 5 percent of the first inspection, plots from the initial inspection and the reinspection will be combined and used to calculate work quality, and the Contractor shall bear the cost of reinspection.
SECTION V – ACCEPTANCE METHODS
Method of Measurement for Acreages
Acreages were determined by using Global Positioning Systems (GPS). The acreage for each work item will be rounded to the nearest acre and is final unless:
a. The contract is modified or,
b. The Government makes a determination to remeasure.
Acceptance – Item 1 Mechanically Cut and Remove Biomass
1. If informal visual inspection indicates acceptable work quality, treatment unit will be accepted.
2. In the event that formal inspections are used, contractor shall be required to rework areas that are not acceptable and/or not meeting the 95% minimum AQL.
3. Road maintenance inspection will be visual. Rework will be required if work does not meet specifications of Appendix C.
*Stewardship Credits will be earned first, whenever practical. Forest Service Funds will be used if the availability of Stewardship Credits is exhausted or if appropriated dollars are obligated to a specific item.
SECTION VI – DEFINITIONS
ACCEPTABLE QUALITY LEVEL (AQL): Acceptance of work will be based on compliance with all specifications corresponding to the appropriate task(s); refer to the Performance Requirements Summary in Section E.4 of the contract. A minimum AQL is required for all service work – hand or mechanical. The minimum AQL will receive a satisfactory performance rating.
BIOMASS TREES: Any designated species greater than 2-inch DBH or greater than 4ft height.
BOLE SPACING: The horizontal distance in feet from the edge of one leave tree bole to another leave tree bole, measured from the outside bark of each tree.
CIRCULAR PLOT: A sample plot within a thinning unit that is used to determine the number of desirable trees and other contract specifications.
COARSE WOODY DEBRIS: Woody material left on the ground to meet wildlife habitat requirements.
CROWN RATIO: The ratio of live crown length (tip of leader to base of the crown) to total tree length/height.
CROWN SPACING: The horizontal distance in feet between the dripline of a live crown to another live crown.
CLEARCUT: A cutting prescription in which all trees within a boundary are designated to be cut.
CROWN RATIO: The ratio of live crown length (tip of leader to base of the crown) to total tree length/height.
CROWN SPACING: The horizontal distance in feet between the dripline of a live crown to another live crown.
CUT TREES: Trees that do not possess the characteristics of desirable leave trees and are required to be cut.
As described by the contract or otherwise marked to be cut.
CUTTING UNIT: See Treatment Unit definition
DAMAGED TREES: Trees damaged beyond recovery. A tree that is larger than 2 feet in height, and has the top knocked out, is leaning more than 10 degrees, has less than one half of its original limbs, or has approximately 50% of bark removed from the circumference of the bole.
DBH: Diameter at breast height, measured at a point of 4.5 feet above the ground level on the uphill side of the tree.
DECKING: Stockpiling of trees in a designated area.
DEAD/DYING TREES: Trees with the crown foliage changing from green to red, yellow, or needleless. Any tree that has pitch tubes indicating Mountain Pine Beetle infestation.
DESIGNATION BY SPECIES AND DIAMETER (DXSD): A cutting prescription in which species and diameter are used to determine which trees will be left and which will be cut.
DIB: Diameter inside bark.
HANG-UP TREE: Any cut tree suspended above ground level.
HEALTHY REGENERATION: Young, healthy, dwarf mistletoe free conifers, less than 4.9 inches in diameter, free of defect or characteristics listed in Section II, 2.2.2.
LEAVE TREE: Trees that possess desirable characteristics and that serve to create the basis for designated spacing requirements or are otherwise designated to be left.
NON-SAWTIMBER TREE: For all conifer species, minimum diameter of 5 inches DBH to minimum diameter by species identified in Appendix B, Division A.
OVERSTORY REMOVAL: A cutting prescription where all trees greater than a specified size are cut. Trees less than the specified size are protected.
PAYMENT UNIT: See Treatment Unit.
PERFORMANCE REQUIREMENTS SUMMARY (PRS): Identifies the key service outputs of the contract that will be evaluated by the Government to assure contract performance standards are met by the Contractor.
PILING: Material moved to an agreed upon location shall be piled for future treatment by Forest Service.
PROGRESSION OF WORK: Work conducted in a progressive, workmanlike and orderly manner by the Contractor.
RESERVE CLUMPS: Groups of trees within a treatment area that are protected from cutting, may also include Individual Reserve trees.
SAWTIMBER TREE: Included timber meeting sawlog size specifications as defined in Appendix B, Division A.2.
SLASH: Woody material existing or created that has accumulated on the forest floor. Woody material includes logs, pieces of logs, tops, and branches.
UNIT: See Treatment Unit.
TEMPORARY ROADS: Non-permanent roads that are constructed by Contractor for the purpose of treatment unit access.
TREATMENT UNIT: An individual area on the ground in which activities will be performed and which may appear as a separate pay item in the Schedule of Items.
UNSATISFACTORY WORK: If work quality falls below the AQL, the COR will issue a work order or notice of noncompliance to the Contractor in writing. Untreated or unsatisfactory treated areas shall be reworked to obtain satisfactory work quality.
WHOLE TREE YARDING: Whole tree logging includes cutting tree and removing the entire tree, including tops and branches, to the landing.
WILDLIFE TREE: Standing tree marked to be reserved as a wildlife tree. Used by birds and small mammals for shelter, nesting, perching, etc.