The document is a Schedule of Material Submittals for an HVAC Unit Replacement project (Solicitation/Contract No. 25-0003) for the Department of the Air Force Space Command. The project involves replacing HVAC units at Hatzor Air Base in Israel, requiring comprehensive documentation and submission of various materials throughout the project lifecycle.
Key submission requirements include a progressive schedule, digital permit, construction work schedule, vehicle/personnel roster, worksite site plan, design drawings at 65% and 95% completion, calculations, field testing plan, balancing/testing results, warranty documents, O&M manuals, and as-built drawings. Specific submission timelines are tied to key project milestones, such as Award Date (AWD) or Notice to Proceed (DNTP), with most initial submittals required within 7 days of award. The project requires multiple copies of technical documentation and allows for review and potential resubmittal of critical project materials. The site visit is scheduled for 16 July 2025, with questions to be answered by 22 July 2025.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER : | PROJECT TITLE: | SOLICITATION/CONTRACT NO.: | ||||||||||||||||||
| 25-0003 | HVAC Unit Replacements | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | ||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NO. OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||||||
| CERTIFICATIONS | DRAWINGS | SAMPLES | PRODUCT DATA | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | REPORTS / TEST RESULTS | OTHER | ||||||||||||
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| GENERAL | |||||||||||||||||||||
| 1 | AF 3064 - Prog Schedule | X | AWD+7 | ||||||||||||||||||
| 2 | AF 66 | X | AWD+7 | ||||||||||||||||||
| 3 | Dig Permit | X | AWD+7 | ||||||||||||||||||
| 4 | Construction Work Schedule | X | AWD+7 | ||||||||||||||||||
| 5 | Vehicle/Personnel Roster | X | AWD+7 | ||||||||||||||||||
| 6 | Worksite Laydown Yard - Site Plan | X | AWD+7 | ||||||||||||||||||
| 7 | 65% Design (DA, Drawings, & Specs) | ||||||||||||||||||||
| 8 | 95% Design (DA, Drawings, & Specs) | ||||||||||||||||||||
| 9 | Calculations (Structural & Electrical) | ||||||||||||||||||||
| 10 | Field Testing Plan | X | X | DNTP+14 | |||||||||||||||||
| 11 | Balancing/Testing Results | X | Final+10 | ||||||||||||||||||
| 12 | Warranty Documents | X | X | Final+10 | |||||||||||||||||
| 13 | O&M Manuals | X | X | X | Final+10 | ||||||||||||||||
| 14 | 1354 Checklist | X | X | Final+10 | |||||||||||||||||
| 15 | As-Builts (AutoCAD & PDF) | X | X | Final+10 |