This document is a Request for Quotes (RFQ) and combined synopsis/solicitation for commercial items issued by the Federal Emergency Management Agency (FEMA) under FAR Part 12. FEMA's Logistics Management Directorate seeks to procure one new Liquid Petroleum Gas (LPG) floor scrubber meeting specifications outlined in the Statement of Work (Attachment 1), with Freight-on-Board (FOB) destination delivery to FEMA Ponce Annex in Puerto Rico (1,000 Carr. 506 Coto Laurel, PR 00780). This is a total set-aside for small business concerns. The purchase order will be for 120 days from the time of award. Solicitation number is 70FB7026Q00000016, with questions due by 3:00 p.m. Eastern Time on Monday, June 22, 2026, and quotes due by 12:00 p.m. Eastern Time on Thursday, June 25, 2026. The Government anticipates awarding a Firm Fixed Price (FFP) contract demonstrating best value, with quotes remaining firm for 60 calendar days after solicitation close.
Evaluation will be based on three factors: Factor 1 (Technical Approach/Specifications—most important), Factor 2 (Delivery Date), and Factor 3 (Price). Non-price factors combined are more important than price. Offerors must complete a fillable Excel pricing template (Attachment 2) and demonstrate that the proposed LPG floor scrubber meets all technical specifications, provide a delivery plan considering location, weather, and transportation availability with certified technician installation and setup, and ensure past performance aligns with contract requirements. Offerors must be registered in the System for Award Management (SAM) with an active Unique Entity ID at time of award. The contract is subject to standard FAR clauses, DHS security requirements, and includes provisions regarding AI prohibition, covered telecommunications equipment, delinquent tax liability representations, and Iranian sanctions compliance. Late quotes will not be accepted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2.2.1 Attachment 1_ SOW - Ponce Annex Floor Scrubbers.pdf | ||
| FEMA RFQ 70FB7026Q00000016.pdf | ||
| 2.2.1 Attachment 2_Scrubber Price sheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 70FB7026Q00000016
This is a combined synopsis/solicitation for commercial item prepared in accordance with the format in RFO Part 12, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. [1]
Federal Emergency Management Agency (FEMA) is issuing a Request for Quotes (RFQ) under FFO Part 12 Acquisition of Commercial Products and Commercial Services. The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Regulations. The Government anticipates awarding a Firm Fixed Price (FFP) that demonstrates the best value to the Government.
SECTION A: REQUIREMENT[footnoteRef:1] [1: ]
FEMA Logistics Management Directorate is seeking to procure one (1) new Liquid Petroleum Gas (LPG) Floor Scrubber meeting the specifications listed in the Statement of Work Freight-on-board (FOB) destination delivery to FEMA Ponce Annex, PR. This acquisition is a total set-aside for small business concerns.
A.1 Description See Attachment 1 – Statement of Work (SOW) entitled “Attachment 1 – SOW
A.2 Period of Performance The Purchase Order will be for 120 days from time of award.
A.3 Place of Performance FOB Destination to:
FEMA – Ponce Annex 1,000 Carr. 506 Coto Laurel, PR 00780
Hours of Performance: The contractor shall schedule all delivery activities with the Contracting Officer’s Representative (COR), Distribution Center supervisor, and FEMA Transportation after award.
Point of Contact: Government POC shall be provided upon contract award.
In case of inclement weather not permitting arrival of participants, the Government reserves the right to make one adjustment to the period of performance with advance notice.
All referenced FAR and HSAR provisions and clauses may be accessed electronically at http://acquisition.gov .
SECTION B: SECURITY
The Contractor shall comply with the Department of Homeland Security’s (DHS) technical, management, and operational security controls to ensure that the Government’s security requirements are met. DHS 4300A policy guide will be used for Sensitive Systems and DHS 4300B policy guide will be used for National Security Systems.
B.1 Release of Information All information relating to the items to be delivered or services to be performed under this contract may not be disclosed by any means without prior approval of the Contracting Officer.
Dissemination of public disclosures includes but is not limited to: permitting access of such information by foreign national or by any other person, entity, and publication of technical or scientific papers, advertising, or any other proposed public release. The contractor shall provide adequate physical protection to such information so as to preclude access by any person or entity not authorized such access by the Government.
SECTION C: CONTRACT ADMINSTRATION DATA
C.1 Identification of Government Officials
The Government Officials assigned to this contract are as follows:
Administrative Contracting Officer:
Name: Ed Ruud Email: Ed.Ruud@fema.dhs.gov
Contracting Officer’s Representative:
Name: To be provided at time of award Email:
C.2 Invoice Approval (JUN 2014) The following FEMA individual (in addition to the Contracting Officer) is hereby delegated authority to accept goods and services and to review and approve invoices for this contract:
Authorized Invoice Approver:
Name: TBD Title: Contracting Officer Representative Email:
C.3 Contract Provisions and Clauses Notice Listing Contract Clauses Incorporated by Reference The following contract clauses pertinent to this section are hereby incorporated by reference (by Citation Number, Title, and Date) in accordance with the clause at “RFO 52.252-2 CLAUSES INCORPORATED BY REFERENCE”.
| NUMBER |
| TITLE |
| DATE |
| 52.202-1 |
| Definitions |
| Jun-20 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| May-14 |
| 52.203-7 |
| Anti-Kickback Procedures |
| Jun-20 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or |
Improper Activity May-14
| 52.203-17 |
| Contractor Employee Whistleblower Rights and Requirement to |
Inform Employees of Whistleblower Rights Nov-23
| 52.203-18 |
| Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. |
| Jan-17 |
| 52.204-7 |
| System for Award Management |
| Nov-24 |
| 52.204-16 |
| Commercial and Government Entity Code Reporting |
| Aug-20 |
| 52.204-17 |
| Ownership or Control of Offeror |
| Aug-20 |
| 52.204-18 |
| Commercial and Government Entity Code Maintenance |
| Aug-20 |
| 52.204-19 |
| Incorporation by Reference of Representations and Certifications |
| Dec-14 |
| 52.211-5 |
| Material Requirements |
| Aug-00 |
| 52-232-1 |
| Payments |
| Apr-84 |
| 52.232-33 |
| Payment of Electronic Funds Transfer-System for Award |
Management Oct-18
| 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| Jun-13 |
| 52.233-1 |
| Disputes |
| May-14 |
| 52.243-1 |
| Changes Fixed-Price |
| Aug-87 |
| 52.244-6 |
| Subcontractors for Commercial Items |
| Oct-25 |
| HSAR Number |
| Title |
| Date |
| 3052.212-70 |
| Contract Terms and Conditions Applicable to DHS Acquisition of Commercial Items |
| JUL 2023 |
| 3052.222-70 |
| Strikes or picketing affecting timely completion of the contract work |
| DEC 2003 |
| 3052.222-71 |
| Strikes or picketing affecting access to a DHS facility |
| DEC 2003 |
| 3052.242-72 |
| Contracting officer's representative |
| DEC 2003 |
C.4 LOCAL CLAUSE
The Contractor will not use or deploy the use of Artificial Intelligence, as defined by 15 U.S.C. 9401(3), unless expressly authorized by the Contracting Officer.
The term ‘‘artificial intelligence’’ means a machine-based system that can, for a given set of human- defined objectives, make predictions, recommendations or decisions influencing real or virtual environments. Artificial intelligence systems use machine and human-based inputs to –
· perceive real and virtual environments;
· abstract such perceptions into models through analysis in an automated manner; and
· use model inference to formulate options for information or action.
(End of Local clause)
C.5 RFO 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (AUG 2025) (DEVIATION 25-21) (EFFECTIVE NOVEMBER 28, 2025)
(a) Submission of offers. Submit signed and dated offers to the office specified in this solicitation at or before the exact time specified in this solicitation. As a minimum, offers shall include—
(1) The solicitation number;
(2) The name, address, telephone number of the Offeror;
(3) The Offeror’s Unique Entity Identifier (UEI) and, if applicable, Electronic Funds Transfer (EFT) indicator;
(4) Information necessary to evaluate the factors contained in the provision at 52.212-2 or as described in the solicitation;
(5) Responses to provisions that require Offeror completion of information, representations, and certifications (other than those collected via the System for Award Management (SAM)); and
(6) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and any solicitation amendments.
(b) Period for acceptance of offers. The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.
(c) Late submissions, modifications, revisions, and withdrawals of offers.
(1) Offerors are responsible for submitting offers and any modifications or revisions to the Government office designated in the solicitation by the time specified in the solicitation.
(2) Any offer, modification, or revision received after the time specified for receipt of offers is “late” and will not be considered unless it is received before award is made and the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition. However, a late modification of an otherwise successful offer that makes its terms more favorable to the Government will be considered at any time it is received Page 51 of 465 and may be accepted.
(3) If an emergency or unanticipated event interrupts normal Government processes so that offers cannot be received at the Government office designated for receipt of offers by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of offers will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(4) Offerors may withdraw their offers by written notice to the Government received at any time before award.
(d) Contract award (not applicable to Invitation for Bids). The Government intends to evaluate offers and award a contract without discussions with Offerors. Therefore, the Offeror’s initial offer should contain the Offeror’s best terms. However, the Government reserves the right to conduct discussions, if necessary. The Government may reject any or all offers if such action is in the public interest, accept other than the lowest offer, and waive informalities and minor irregularities in offers received.
(e) Debriefings. If a post award debriefing is given to requesting Offerors, the Government will disclose the following information, if applicable:
(1) The agency’s evaluation of the significant weak or deficient factors in the debriefed Offeror’s offer.
(2) The overall evaluated cost or price and technical rating of the successful Offeror and the debriefed Offeror and past performance information on the debriefed Offeror.
(3) The overall ranking of all Offerors when any ranking was developed by the agency during source selection.
(4) A summary of the rationale for award.
(5) For acquisitions of commercial products, the make and model of the product to be delivered by the successful Offeror.
(6) Reasonable responses to relevant questions posed by the debriefed Offeror as to whether the agency followed source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities.
(End of provision) C.6 RFO 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (AUG 2025) (DEVIATION 25-21) (EFFECTIVE NOVEMBER 28, 2025)
(a) Evaluation factors. The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors will be used to evaluate offers:
A.1 Evaluation Factors and Criteria:
1. Factor Identification – The Government will evaluate the offerors using the following factors.
Factor 1 – Technical Approach Factor 2 – Delivery Date Factor 3 – Price
2. Order of Importance - Factor 1, Technical Specification is the most important factor, and more important than Factor 2, Delivery Date. The non-price factors 1 and 2 combined are more important than factor 3, Price.
3. Basis for Award – Award will be made upon the offeror’s proposal that provides the best value to the Government using the evaluation factors and tradeoff process. All evaluation factors other than price, when combined, are more important than price.
A.2 Proposal Instructions:
1. Technical Proposal
A. Factor 1 – Technical Approach The offerors shall demonstrate meeting the technical specifications of providing one (1) LGP Floor Sweeper Scrubber as outlined in the Statement of Work, section 3.
B. Factor 2 – Delivery Plan The offerors shall describe the no-later-than date of delivery to FEMA Distribution Center Ponce Annex. The offeror shall consider the delivery location, as well as weather and transportation availability to factor into the plan. The offeror shall provide technical installation and setup from a certified technician into the plan.
2. Non-Technical Proposal A. Factor 3 – Price The offeror shall complete ATTACHMENT 2_SCRUBBER (Fillable) and submit it in an unaltered electronic Excel format. The Government will evaluate pricing for accuracy and completeness based on information submitted by the Offeror’s Factor 3. This process will involve verification that pricing is presented in the requested format.
SECTION D: EVALUATION METHODOLOGY
D.1 Technical Proposal Evaluation Technical Evaluation Ratings and Definitions Each offeror’s technical proposal will be evaluated for completeness and to determine whether the proposed scrubber meets the requirements and criteria as specified in the SOW. The table below provides definitions of the adjectival ratings to be used in evaluating each offeror’s technical proposal for Factors 1 and 2.
| TERM |
| Definition |
| High Confidence |
| The Government has High Confidence that the Offeror understands the requirement, proposes a sound approach, and will be successful in performing the contract with little or no Government intervention. |
| Some Confidence |
| The Government has Some Confidence that the Offeror understands the requirement, proposes a sound approach, and will be successful in performing the contract with some Government intervention. |
| Low Confidence |
| The Government has Low Confidence that the Offeror understands the requirement, proposes a sound approach, or will be successful in performing the contract even with Government intervention. |
A. Factor 1 – Technical Approach The technical specifications will be evaluated to determine whether the offeror’s proposed items meet the minimum technical specificities outlined in the SOW Section 3.
B. Factor 2 – Delivery Plan The Delivery Plan will be evaluated for the earliest and most reasonable dates, considering weather and transportation available considerations.
1. Price Proposal Evaluation
A. Factor 3 – Past Performance Each offeror past performance shall assess the offerors capability to perform the requirements of this purchase order by evaluating their past performance on previous contracts similar in size, scope, complexity and relevant to the requirement. The offeror’s past performance will be evaluated for relevance to the requirements in the SOW.
D.2 Price Proposal Evaluation
A. Price proposal evaluation will not receive an adjectival rating B. The Government will perform price evaluation to determine whether proposed prices are fair and reasonable; and for completeness based on information. For the price to be reasonable in its nature and amount, it should not exceed that which would be incurred by a prudent person in the conduct of a competitive business. Offerors are cautioned that unreasonably high prices may cause your proposal to be deemed not fair and unreasonable. Unit price is no more than two decimal places.
C. The Government reserves the right to also perform price evaluation to determine whether the proposed prices are realistic. For the price to be realistic, it should not be overly optimistic and impractically low. Offerors are cautioned that unrealistically low prices, as to pose a risk to the completion of the work, may cause your proposal to be deemed unrealistic and do not pose clear understanding of the scope.
D. In evaluating price, the Government will utilize one or more proposal analysis techniques from F RFO 15.404-1. Examples of such techniques include, but are not limited to the following:
· Comparison of proposed prices received in response to the solicitation.
· Comparison of proposed prices to historical prices paid, whether by the Government or other than the Government, for the same or similar items.
· Comparison with competitive published price lists, published market prices of commodities, similar indexes, and discount or rebate arrangements.
· Comparison of proposed prices with independent Government cost estimates.
· Comparison of proposed prices with prices obtained through market research for the same or similar services.
D.3 Quote Submission Instructions Questions are due by 3:00 pm Eastern Time on Monday, June 22, 2026. Quotes must be submitted via email by 12:00 pm on Eastern Time Thursday, June 25, 2026. Offerors shall reference the Solicitation Number 70FB7026Q00000015 from on all documentation submitted in response to this solicitation. Late Quotes will not be accepted.
Quotes MUST be good for 60 calendar days after close of the solicitation.
This solicitation requires registration with System for Award Management (SAM) in order to be considered for award, pursuant to applicable regulations and guidelines. Registration information can be found at www.sam.gov. Registration must be “ACTIVE” at time of award. The Unique Entity ID must be included in the quote as well.
Upon receipt of quote, the Government shall verify the Offeror followed the formatting directions and is not listed in the Excluded Parties List System (EPLS). Offerors found on the EPLS shall not be considered for award, in accordance with FAR 9.405(3).
D.4 Government-Furnished Equipment and Information The Contractor shall provide the appropriate equipment to perform all requirements under this contract.
(b) Options (if applicable). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. The evaluation of options does not obligate the Government to exercise the option(s).
(c) Notice of award. A written notice of award or acceptance of an offer furnished to the successful Offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
D.5 RFO 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (AUG 2025) (DEVIATION 25-21) (EFFECTIVE NOVEMBER 28, 2025)
(a) Definitions. The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference.
(b) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall—
(1) Notify the Contracting Officer in writing as soon as possible;
(2) Remedy the delay as quickly as possible; and
(3) Notify the Contracting Officer when the occurrence is over.
(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(4) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(5) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures for interest credits prescribed in FAR part 32 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon—
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Government-financed air transportation; and 41 U.S.C. chapter 21 relating to procurement integrity.
(r) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services;
(2) The Disputes, Payments, Invoice, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) Other contract clauses incorporated in the solicitation or contract;
(4) Addenda to this solicitation or contract;
(5) Solicitation provisions incorporated in the solicitation;
(6) Other paragraphs of this clause;
(7) Other documents, exhibits, and attachments; and
(8) The specification.
(s) Unauthorized obligations.
(1) Except as stated in paragraph (s)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government-authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (s)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(t) Comptroller General examination of record. This paragraph applies if this contract was awarded using other than sealed bid procedures and is in excess of the simplified acquisition threshold on the date of award of this contract.
(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.
(2) The Contractor shall make available at its offices, at all reasonable times, the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR part 4, longer period required by statute, or periods specified in other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.
(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This clause does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(u) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of clause) Alternate I (Aug 2025) (DEVIATION 25-21) (effective November 28, 2025). When contemplating a time-and-materials or labor-hour contract, substitute the following paragraphs (a), (b), (i), (l), and (m) for those in the basic clause.
(a) The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference. As used in this clause— Direct materials means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.
Hourly rate means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are—
(1) Performed by the contractor;
(2) Performed by the subcontractors; or
(3) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.
Materials means—
(1) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;
(2) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;
(3) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);
(4) The following subcontracts for services which are specifically excluded from the hourly rate: [Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and
(5) Indirect costs specifically provided for in this clause.
Subcontract means any contract, as defined in FAR 2.101, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.
(b) Inspection/Acceptance.
(1) The Government has the right to inspect and test all materials furnished and services performed under this contract at all places and times before acceptance. The Government will perform inspections and tests in a manner that will not unduly delay the work.
(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.
(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.
(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (b)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. [Insert portion of labor rate attributable to profit.] (5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may –
(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or
(B) Terminate this contract for cause.
(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.
(6) Notwithstanding paragraphs (b)(4) and (5) of this clause, the Government may, at any time, require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to —
(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor’s managerial personnel; or
(ii) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.
(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.
(9) Unless otherwise specified in the contract, the Contractor’s obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.
(i) Payments.
(1) Work performed. The Government will pay the Contractor as follows upon the submission of commercial invoices approved by the Contracting Officer:
(i) Hourly rate.
(A) The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the contract by the number of direct labor hours performed. Fractional parts of an hour shall be payable on a prorated basis.
(B) The rates shall be paid for all labor performed on the contract that meets the labor qualifications specified in the contract. Labor hours incurred to perform tasks for which labor qualifications were specified in the contract will not be paid to the extent the work is performed by individuals that do not meet the qualifications specified in the contract, unless specifically authorized by the Contracting Officer.
(C) Invoices may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer) to the Contracting Officer or the authorized representative.
(D) When requested by the Contracting Officer or the authorized representative, the Contractor shall substantiate invoices (including any subcontractor hours reimbursed at the hourly rate in the schedule) by evidence of actual payment, individual daily job timecards, records that verify the employees meet the qualifications for the labor categories specified in the contract, or other substantiation specified in the contract.
(E) Unless the Schedule prescribes otherwise, the hourly rates in the Schedule shall not be varied by virtue of the Contractor having performed work on an overtime basis.
(1) If no overtime rates are provided in the Schedule and the Contracting Officer approves overtime work in advance, overtime rates shall be negotiated.
(2) Failure to agree upon these overtime rates shall be treated as a dispute under the Disputes clause of this contract.
(3) If the Schedule provides rates for overtime, the premium portion of those rates will be reimbursable only to the extent the overtime is approved by the Contracting Officer.
(ii) Materials.
(A) If the Contractor furnishes materials that meet the definition of a commercial product at FAR 2.101, the price to be paid for such materials shall not exceed the Contractor’s established catalog or market price, adjusted to reflect the—
(1) Quantities being acquired; and
(2) Any modifications necessary because of contract requirements.
(B) Except as provided for in paragraph (i)(1)(ii)(A) and (D)(2) of this clause, the Government will reimburse the Contractor the actual cost of materials (less any rebates, refunds, or discounts received by the contractor that are identifiable to the contract) provided the Contractor—
(1) Has made payments for materials in accordance with the terms and conditions of the agreement or invoice; or
(2) Makes these payments within 30 days of the submission of the Contractor’s payment request to the Government and such payment is in accordance with the terms and conditions of the agreement or invoice.
(C) To the extent able, the Contractor shall—
(1) Obtain materials at the most advantageous prices available with due regard to securing prompt delivery of satisfactory materials; and
(2) Give credit to the Government for cash and trade discounts, rebates, scrap, commissions, and other amounts that are identifiable to the contract.
(D) Unless listed below, other direct and indirect costs will not be reimbursed.
(1) Other direct costs. The Government will reimburse the Contractor on the basis of actual cost for the following, provided such costs comply with the requirements in paragraph (i)(1)(ii)(B) of this clause: [Insert each element of other direct costs (e.g., travel, computer usage charges, etc. Insert “None” if no reimbursement for other direct costs will be provided. If this is an indefinite delivery contract, the Contracting Officer may insert “Each order must list separately the elements of other direct charge(s) for that order or, if no reimbursement for other direct costs will be provided, insert ‘None’”.]
(2) Indirect costs (material handling, subcontract administration, etc.). The Government will reimburse the Contractor for indirect costs on a pro-rata basis over the period of contract performance at the following fixed price: [Insert a fixed amount for the indirect costs and payment schedule. Insert “$0” if no fixed price reimbursement for indirect costs will be provided. (If this is an indefinite delivery contract, the Contracting Officer may insert “Each order must list separately the fixed amount for the indirect costs and payment schedule or, if no reimbursement for indirect costs, insert ‘None’).”]
(2) Total cost. The total cost to the Government for the performance of this contract shall not exceed the ceiling price set forth in the Schedule. The Contractor agrees to use its best efforts to perform the work specified in the Schedule and all obligations under this contract within such ceiling price. If at any time the Contractor has reason to believe that the hourly rate payments and material costs that will accrue in performing this contract in the next succeeding 30 days, if added to all other payments and costs previously accrued, will exceed 85 percent of the ceiling price in the Schedule, the Contractor shall notify the Contracting Officer giving a revised estimate of the total price to the Government for performing this contract with supporting reasons and documentation. If at any time during the performance of this contract, the Contractor has reason to believe that the total price to the Government for performing this contract will be substantially greater or less than the stated ceiling price, the Contractor shall so notify the Contracting Officer, giving a revised estimate of the total price for performing this contract, with supporting reasons and documentation. If at any time during performance of this contract, the Government has reason to believe that the work to be required in performing this contract will be substantially greater or less than the stated ceiling price, the Contracting Officer will so advise the Contractor, giving the revised estimate of the total amount of effort to be required under the contract.
(3) Ceiling price. The Government will not be obligated to pay the Contractor any amount in excess of the ceiling price in the Schedule, and the Contractor shall not be obligated to continue performance if to do so would exceed the ceiling price set forth in the Schedule, unless and until the Contracting Officer notifies the Contractor in writing that the ceiling price has been increased and specifies in the notice a revised ceiling that shall constitute the ceiling price for performance under this contract. When and to the extent that the ceiling price set forth in the Schedule has been increased, any hours expended and material costs incurred by the Contractor in excess of the ceiling price before the increase shall be allowable to the same extent as if the hours expended and material costs had been incurred after the increase in the ceiling price.
(4) Access to records. At any time before final payment under this contract, the Contracting Officer (or authorized representative) will have access to the following (access shall be limited to the listing below unless otherwise agreed to by the Contractor and the Contracting Officer):
(i) Records that verify that the employees whose time has been included in any invoice meet the qualifications for the labor categories specified in the contract;
(ii) For labor hours (including any subcontractor hours reimbursed at the hourly rate in the schedule), when timecards are required as substantiation for payment—
(A) The original timecards (paper-based or electronic);
(B) The Contractor’s timekeeping procedures;
(C) Contractor records that show the distribution of labor between jobs or contracts; and
(D) Employees whose time has been included in any invoice for the purpose of verifying that these employees have worked the hours shown on the invoices.
(iii) For material and subcontract costs that are reimbursed on the basis of actual cost—
(A) Any invoices or subcontract agreements substantiating material costs; and
(B) Any documents supporting payment of those invoices.
(5) Overpayments/Underpayments. Each payment previously made shall be subject to reduction to the extent of amounts, on preceding invoices, that are found by the Contracting Officer not to have been properly payable and shall also be subject to reduction for overpayments or to increase for underpayments. The Contractor shall promptly pay any such reduction within 30 days unless the parties agree otherwise. The Government will pay any such increases within 30 days, unless the parties agree otherwise. The Contractor’s payment will be made by check. If the Contractor becomes aware of a duplicate invoice payment or that the Government has otherwise overpaid on an invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury, as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, and then at the rate applicable for each six-month period as established by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) The Contracting Officer will issue a final decision if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt in a timely manner;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer.
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR part 32 in effect on the date of this contract.
(viii) Upon receipt and approval of the invoice designated by the Contractor as the “completion invoice” and supporting…