2-Binder 2 - Specifications - CWU-0089-L Lock Haven Bentley Hall.pdf

PDF 4 MB Posted

Attached to
CWU-89-L: Bentley Street Level Renovation Lock Haven Campus
Solicitation number
Not on record
Issued by
Clearfield County, Pennsylvania

About this file

This is a specifications document for the CWU-0089-L Bentley Street Level Renovation project at Lock Haven University in Pennsylvania. The project involves the renovation of 3,810 square feet of interior space at Bentley Hall on the Lock Haven campus, to be accomplished through separate prime contracts for General Construction, HVAC, and Electrical work. General Construction work includes selective demolition, new interior glazing walls, decorative walls and ceilings, new flooring, new exterior signage, and painting. HVAC work encompasses removal and replacement of ceiling diffusers, installation of a new mini-split heat pump, and resetting of sprinkler heads. Electrical work includes new interior lighting, additional outlets, and new Information Technology infrastructure. A mandatory pre-bid conference with site visit is scheduled for November 12, 2026, at 11:00 AM EST at Bentley Dining Hall. Electronic bids are due no later than 1:00 PM EST on December 8, 2026, through PennBid. The Notice to Proceed is anticipated for early February 2027, with construction commencing on or about March 1, 2027. Substantial Completion, including L&I Inspection and Occupancy Permit, is required by July 2, 2027, with all on-site punch list work completed by July 30, 2027. The main entrance and elevator will be closed at street level after May 10, 2027.

Prime Contractors must meet minimum qualifications of ten years in business and successful completion of at least five similar projects. Each prime contractor must submit an AIA Document A305 Contractor's Qualification Statement, along with resumes of the Project Manager and Superintendent, a Performance Plan, Quality Control Plan, and Safety Plan as part of the bid submission. The Lead Prime Contractor shall be the General Contractor and is responsible for coordinating all work with other separate prime contractors. Minimum staffing levels must include two persons for General Construction, one person for Mechanical work, one person for Plumbing work, and one person for Electrical work, all employed directly by the prime contractor. The document specifies detailed change order procedures with maximum markups of 15% on labor, 10% on materials, 10% on equipment, and 10% on subcontractor costs for contracts up to $6,000,000. Payment procedures include submission of a detailed Schedule of Values coordinated with the construction schedule, with mobilization costs not to exceed 0.75% of contract price and general conditions costs up to 4% of contract price at award. The building will remain occupied throughout construction, with access to elevators and stairs maintained to the greatest extent possible. The Contractor is responsible for all damage to University property or existing finishes caused by construction operations, and the University retains first right of refusal on all removed equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CWU-0089-L Bentley Street Level Renovation Specification Index x

SPECIFICATION INDEX

BENTLEY STREET LEVEL RENOVATION

COMMONWEALTH UNIVERSITY, LOCK HAVEN

NO. SECTION TITLE PAGES

Specification Index 3

DIVISION 1 – GENERAL REQUIREMENTS

01 10 00 Summary 01 10 00 8 01 11 01 Special Provisions 01 11 01 3 01 26 00 Contract Modification Procedures 01 26 00 6 01 29 00 Payment Procedures 01 29 00 8 01 31 00 Project Management and Coordination 01 31 00 4 01 31 19 Project Meetings 01 31 19 4 01 32 00A Construction Progress Documentation 01 32 00 9 01 33 00 Submittal Procedures 01 33 00 6 01 35 00C Safety and Health Requirements 01 35 00C 4 01 45 00 Quality Control 01 45 00 4 01 50 00B Temporary Facilities and Controls 01 50 00B 5 01 60 00 Product Requirements 01 60 00 4 01 62 00 Product Options 01 62 00 3 01 71 23 Field Engineering 01 71 23 2 01 73 29 Cutting and Patching 01 73 29 5 01 74 19 Construction Waste Management and Disposal 01 74 19 4 01 77 00 Closeout Procedures 01 77 00 4 01 78 23 Operation and Maintenance Data 01 78 23 5 01 78 36 Warranties 01 78 36 3 01 78 39 Project Record Documents 01 78 39 2

DIVISON 2 – EXISTING CONDITIONS

02 41 00 Selective Structure Demolition 02 41 00 5

DIVISION 3 – CONCRETE

03 54 16 Hydraulic Cement Underlayment 03 54 16 4

DIVISION 6 – WOOD, PLASTICS & COMPOSITES

06 10 53 Rough Carpentry 06 10 53 4

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

07 21 00 Thermal Insulation 07 21 00 6 07 62 00 Sheet Metal Flashing and Trim 07 62 00 10 07 92 00 Joint Sealants 07 92 00 9

DIVISION 8 – OPENINGS

08 11 13 Hollow Metal Doors and Frames 08 11 13 6 08 80 00 Glazing 08 80 00 9

DIVISION 9 – FINISHES

09 22 16 Non-Structural Metal Framing 09 22 16 7 09 29 00 Gypsum Wall Board 09 29 00 10 09 51 13 Acoustical Tile Ceilings 09 51 13 9 09 54 23 Linear Metal Suspension Systems 09 54 23 7 09 65 13 Resilient Base and Accessories 09 65 13 5 09 65 19 Resilient Tile Flooring 09 65 19 5 09 68 13 Tile Carpeting 09 68 13 5 09 91 13 Exterior Painting 09 91 13 5 09 91 23 Interior Painting 09 91 23 9

CWU-0089-L Bentley Street Level Renovation Specification Index

DIVISION 10 – SPECIALTIES

10 14 19 Dimensional Letter Signage 10 14 19 5 10 14 23 Panel Signage 10 14 23 4

DIVISION 12 – FURNISHINGS

12 48 13 Entrance Floor Mats and Frames 12 48 13 5

DIVISION 21 – FIRE SUPPRESSION

21 05 00 Common Work Results for Fire Suppression 21 05 00 6 21 05 29 Hangers and Supports for Fire Suppression Piping and Equipment 21 05 29 6 21 10 00 Water-Based Fire Suppression Systems 21 10 00 10

DIVISION 23 – HEATING VENTILATING & AIR CONDITIONING

23 00 00 General Provisions for HVAC Systems 23 00 00 12 23 00 01 Basic Mechanical Requirements 23 00 01 4 23 05 93 Testing, Adjusting and Balancing for HVAC 23 05 93 9 23 07 00 HVAC Insulation 23 07 00 10 23 31 13 Metal Ducts 23 31 13 10 23 33 00 Air Duct Accessories 23 33 00 8 23 33 46 Flexible Ducts 23 33 46 4 23 37 13 Air Diffusers, Registers and Grilles 23 37 13 4 23 81 26 Split System Air Conditioners 23 81 26 7

DIVISION 26 – ELECTRICAL

26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 19 4 26 05 26 Grounding and Bonding for Electrical Systems 26 05 26 4 26 05 29 Hangers and Supports for Electrical Systems 26 05 29 3 26 05 33.13 Raceway and Boxes for Electrical Systems 26 05 33.13 7 26 05 33.16 Boxes and Covers for Electrical Systems 26 05 33.16 13 26 05 33.23 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 33.23 2 26 05 53 Identification for Electrical Systems 26 05 53 3 26 09 23 Lighting Control 26 09 23 2 26 27 26 Wiring Devices 26 27 26 6 26 50 00 Lighting 26 50 00 3

DIVISION 27 – COMMUNICATIONS

27 15 13 Communications Copper Horizontal Cabling 27 15 13 7

END OF INDEX

CWU-0089-L Bentley Street Level Renovation Section 011000 - Summary

SECTION 011000

SUMMARY

PART 1 – GENERAL

1.01 WORK COVERED BY CONTRACT DOCUMENTS

Work included under this Project consists of CWU-0089-L Bentley Street Level Renovation.

General, HVAC and Electrical Contracts to renovate 3,810 square feet of interior space.

1.02 MULTIPLE CONTRACT SUMMARY

Work for the Project shall be accomplished by Separate Prime Contractors according to

Pennsylvania statute. The Lead Prime Contractor shall be the General Specific instructions for coordination and responsibilities of the Lead Prime Contractor are contained in Section 0131000, Project Management and Coordination, and elsewhere throughout the Contract Documents. Work included in each Separate Prime Contract shall include, but not be limited to, the following:

A. General Construction CWU-0089-L.1

Selective demolition, new interior glazing walls, new interior decorative walls and ceilings, new flooring, new exterior signage and painting. Coordination with other Prime Contractors.

B. HVAC Construction CWU-0089-L.2

Removal and replacement of ceiling diffusers, new mini-split heat pump, and re-setting of sprinkler heads. Coordination with other Prime Contractors.

D. Electrical Construction CWU-0089-L.4

New interior lighting, additional outlets, new Information Technology infrastructure.

Coordination with other Prime Contractors.

1.03 DESCRIPTION OF BASE BIDS

A. Base Bid #1:

Base Bid #1 shall consist of all General, HVAC, and Electrical Work [---also specify Fire Protection, Elevators, or other Separate Prime Contracts, as necessary---] as shown in the Contract Documents, including, but not limited to, the items described in 1.02 above.

1.05 SUPERINTENDENCE AND PROJECT MANAGEMENT

A. Superintendence.

1. The competent superintendent required by Article 4.2.2 of the General Conditions may be fulfilled by, at a minimum, a working foreman. All other requirements of Article 4.2.2 shall remain in force.

2. If the Contractor holds more than one Separate Prime Contract for this Project, the

Contractor may provide a single person to provide superintendence for all Separate Prime Contracts held.

B. Project Management

1. The project management requirements in Article 4.2.3 of the General Conditions shall be the requirements for this Contract.

2. The person fulfilling this Project Management requirement may be the same person who is fulfilling the Superintendence requirement.

3. If the Contractor holds more than one Separate Prime Contract for this Project, the

Contractor may provide a single person to provide project management for all Separate Prime Contracts held.

1.06 WORK BY OWNER

A. The University will perform certain operations and/or award independent contract(s) for performance of construction-related operations at the Project site. These operations will be conducted simultaneously with the Work under this Contract. All Separate Prime Contractors are expected to cooperate fully with other independent contractors so that work on those contracts may be carried out smoothly, without interfering with, or delaying, the Work under this Contract. The following operations will either be performed by the University or under independent contracts(s): Information Technology, devices and final connections, sprinkler head replacement in areas not affected by the project, and installation of furniture.

B. The University may undertake or award other contracts for work unrelated to this Project, but which may be at or near the site(s) of the Work under this Contract. The Contractor, other contractors, and University employees, shall cooperate with each other and shall adapt scheduling and performance of their work to reasonably accommodate each other, heeding any direction that may be provided by the University. The Contractor shall report to the University any interferences or conflicts immediately, whether committed or experienced.

C. The University will provide the following items:

Wall of Fame plaques for installation by General Contractor.

1. The Contractor shall designate the required delivery dates of University-furnished items in the Project Schedule. The University will schedule deliveries in accordance with the Project Schedule.

2. The University will arrange and pay for delivery of University-furnished items. The

Contractor shall receive, unload, and handle University-furnished items at the site. The University and the Contractor shall jointly inspect deliveries for damage.

3. If, as a result of delivery, University-furnished items are damaged, defective, or missing, the University will arrange for replacement.

4. Once the University-furnished items are on site, the Contractor shall be responsible for protecting the items from damage, including damage from exposure to the elements and from the Contractor's operations. The Contractor shall be responsible to repair or replace items damaged once under his control.

5. The University will arrange for manufacturers' field services, and the delivery of manufacturers' warranties, operating manuals, spare parts, and special tools, as applicable, to the Contractor.

1.07 WORK RESTRICTIONS

A. Existing Facilities, Infrastructure, and Occupancy.

1. The building will remain occupied throughout the work. Access to the elevator and stair shall be maintained throughout the Work to the greatest extent possible. Closure of access to the elevator and stair must be scheduled in advance, be of the shortest duration possible and may be required to be completed ‘off-hours’. Main entrance and elevator will be closed on the street after May 10, 2027.

B. Hazardous Materials.

1. There is a possibility that hazardous materials not identified in the Contract Documents may be discovered on this Project site. Should hazardous or suspicious materials be encountered, the Contractor shall immediately stop work in that area and notify the University. The University will be responsible for investigating the suspicious material, and if it is found to be hazardous, for having it removed. The University will consider an extension of time for delays related to such testing and removal if the work was impacted.

2. Asbestos: There is no known asbestos on this Project. All known asbestos-containing material has been removed from the building as part of an asbestos abatement project.

3. Mercury: All fluorescent and high-intensity discharge lamps containing mercury and which are intended for disposal shall be removed from campus and properly recycled or disposed of by the Contractor, in accordance with statutory and/or regulatory requirements.

4. PCBs: Ballasts found to contain PCBs and which are intended for disposal shall be removed from campus and properly recycled or disposed of by the Contractor, in accordance with statutory and/or regulatory requirements.

5. Lead: No information is available for lead-containing material.

C. The general and special conditions contained herein are not all inclusive. Special conditions identified in the Technical Specifications and on the Drawings take precedence.

D. The Contractor shall provide a reasonable individual to accept deliveries of materials and equipment, and provide labor and equipment to unload delivery trucks. The University will not accept or sign for deliveries of materials or equipment to the Contractor, and the University will not handle or store materials or equipment for the Contractor.

E. The Contractor shall make suitable prior arrangements with the University for the delivery of large equipment or materials in large vehicles to the Project site. The intent is to avoid such deliveries at time of peak commuter traffic to the University. The University will determine if other University entities, such as University Police, need to be involved.

F. Staging and storage areas are identified on the Drawings. The Contractor may not use any other campus locations for use as staging or storage areas without prior approval of the University. Any additional storage or work areas needed for operations shall be off campus and shall be obtained and paid for by the Contractor. The Contractor is responsible for protection and safekeeping of products stored in staging and storage areas on campus. Stored products that interfere with operations of the University or other contractors shall be moved. Roofing materials and bulk materials, of any type and for any contractor, shall not be stored or stockpiled overnight on new or existing roofs.

G. Loading the structure with weight that will endanger the structure is not permitted. Ductwork, conduit, ceiling systems, lighting fixtures, or any other miscellaneous equipment shall not be suspended from new or existing metal roof decks. These components shall be suspended from the structural members, or from a suspension system supported by the structural members. All concentrated loads must be approved by the University. If concentrated loads are not approved, the Separate Prime Contractor furnishing the equipment must provide acceptable means of distributing the load.

H. The Contractor shall make a reasonable attempt to arrange its on-site work to minimize interference with normal University business activities, particularly those activities not directly related to the actual Work or the operation thereof.

I. Contractors are authorized to work whatever hours are required to complete the Work by the specified Contract completion date. The University will normally be providing quality assurance coverage from 7:00 AM to 5:00 PM, Monday through Friday, holidays excepted. Contractors are required to notify the University in writing at least five (5) working days in advance of any work that is planned for outside of the normal coverage hours for the University. Contractors shall not perform any testing or cover-up work outside the normal coverage hours for the University without the prior written approval of the University. The University's failure to approve an expanded work-hour schedule or work on holidays shall not be grounds for a claim against the University.

J. The Contractor shall comply with all University personnel identification and vehicle registration requirements while on the campus.

K. Contractor employees shall park privately-owned vehicles in an area designated by the

University. Contractor employee parking shall not interfere with existing and established parking requirements of the University. If employee parking is on a grassed area, the Contractor shall be responsible for restoration and re-grassing of the area at the end of the Project.

L. The Contractor shall keep fire hydrants adjacent to the Project accessible at all times. No materials or obstructions shall be placed within twenty (20) feet of any such hydrant, or within any other distance as required by law or ordinance.

M. The Contractor shall keep driveways and entrances servicing the campus and adjacent buildings clear and available to the University and to emergency vehicles at all times. Such areas shall not be used for parking or storage of materials. Deliveries shall be scheduled to minimize space and time requirements for storage of materials and equipment.

N. The Contractor shall maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. The Contractor shall not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the University.

O. The Contractor shall provide protection for all existing roads, walkways, pavement, buildings, appurtenances, ground structures, signs, trees, landscaping, grass, etc., scheduled to remain.

The Contractor shall provide means to protect such items from damage and shall repair any damage caused by its operations, at no cost to the University. The Contractor shall return the premises to like-original condition and/or to match adjacent areas that were not affected by the work, subject to approval by the University. Any restoration of the site shall include replacement of landscaping with "like" plants of the same species, size, and shape. Grass remediation shall be by "sod" method rather than seeding. All work shall be approved by the University.

P. At the end of each day, the Contractor shall clean the Project site of scraps, packaging containers, and other trash, and have it removed from the campus. This shall include waste and packaging that has blown outside of the Project site.

Q. Smoking and other use of tobacco products are prohibited in University buildings, including buildings under construction. Contractors and their employees working on University property are prohibited from smoking in University buildings.

R. Alcoholic beverages and controlled substances shall not be carried, consumed, or stored on

University property.

S. Open fires or burning are not permitted on University property.

T. Burying of waste materials on site, to include materials from clearing and grubbing operations, is prohibited without written permission of the University. The Contractor shall remove any such material from the Project site and recycle or dispose of it in a legal manner.

U. The Contractor shall not plan for any blasting operations without prior written approval of the

University.

V. The Contractor is responsible for the behavior of its employees and shall immediately remove from the site any employee engaging in racial or sexual harassment, whether by work or deed.

This includes "catcalls" and inappropriate language. The University will require any Contractor's, subcontractor's, or supplier's personnel to be removed from the job site in the event of misconduct or improper interaction with University students or staff.

W. Regardless of the proximate cause, in the event of any damage occurring to University or private property by any Contractor activity during the life of the contract, the Contractor shall promptly advise the University and participate in a joint assessment of the damage with University personnel. It is essential that the Contractor take all actions necessary to avoid claims by third parties.

X. The University shall have first right of refusal on all removed equipment. Existing pieces of equipment and materials that are to remain the property of the University will be tagged by the University prior to the start of work. Such items shall be moved and/or stored by the Contractor where directed by the University. Equipment shall be stored as complete units with all associated accessories and auxiliary equipment. Equipment shall be disconnected and carefully removed and shall be transported to the storage areas as directed. Equipment shall be stored in a neat and workmanlike manner, tagged, and identified for future use.

1.08 WORK RESTRICTIONS, EXISTING BUILDINGS

A. The University will maintain activities, operations, and normal office hours in the building during the course of the Work. Access to the upper floors via the Street Level entry, elevator and stairs must be maintained to the greatest extent possible. Main entrance and elevator will be closed on the street level after May 10, 2027.

B. If the Contractor is provided keys to the building or portion of the building, the Contractor shall be subject to the University's regulations and policies on key control and access.

C. Upon completion of any portion of Work related to this Contract, the Contractor shall ensure that the building, other than any improvements and changes inherent in the Work, are reasonably maintained and/or are returned to their prior condition.

D. The Contractor shall protect the building and its occupants during the Work, taking all necessary precautions. The Contractor shall make all necessary provisions to keep the operational part of the building safe, weather tight, and dust free at all times, and shall cooperate to keep noise, dirt, and other interferences to a minimum. The Contractor shall repair damage caused by construction operations.

E. The Lead Prime Contractor shall take all necessary precautions to maintain a weather tight envelope during sequence of operations on alteration work of the existing building.

F. Existing Elevators shall be to used and access must be maintained to the greatest extent possible.

G. All existing finishes to remain, including, but not limited to, floor coverings, wall finishes, ceilings, fixtures, etc., shall be adequately protected by the Contractor. Any damage to such finishes shall be repaired by the Contractor causing the damage, at no cost to the University.

H. The Contractor shall not use any University property, such as desks, beds, chairs, etc., as ladders, work benches, etc., in performing the Work. The Contractor shall be responsible for protection from damage or loss of any furniture, furnishings, or equipment remaining in the building.

I. The Contractor shall keep public areas, such as hallways, stairs, elevator, lobbies, and toilet rooms, free from accumulation of waste, rubbish, or construction debris.

J. Use of Restrooms, Sanitary Facilities, and/or Cleanup Facilities: Section 015000, Temporary

Facilities and Controls, outlines requirements for Temporary Sanitary Facilities.

K. The Contractor shall cooperate with the University, and with those in authority for the existing building, to prevent the entrance and exit of all workers and/or others whose presence is forbidden or undesirable.

1.09 PROJECT UTILITY SOURCES

A. The location of existing utilities and equipment is shown on the Drawings in an approximate way only and has not been independently verified by the University. The Contractor shall determine the location of all utilities and equipment, including those overhead and underground, before commencing Work, and shall take all necessary precautions to prevent injury or damage during the performance of the Work. The Contractor agrees to be fully responsible for any and all items at no cost to the System.

B. The Contractor, when performing excavation or demolition work, shall fully comply with the requirements of P.L. 852, Act 287, December 10, 1974, as amended, relative to protection of underground utilities, which shall include, but not be limited to, the following actions:

1. Ascertain the approximate location and type of utility lines at the site by inspecting drawings or by obtaining a list of utility companies' lines on the site from the county Recorder of Deeds and then contacting the utility companies.

2. A minimum of five (5) working days before excavation or demolition, request from the utility companies the steps contractors should take to avoid any damage.

3. Inform the responsible supervisor or foreman and each equipment operator of the information obtained in 1. and 2. above.

4. Report to the utility company and the University any damage to a utility line made or discovered in the course of the work.

5. Alert the University and occupants of premises as to any emergency created or discovered in the course of the work.

6. Provisions of 1., 2., and 3. above do not apply in an emergency. An emergency is any condition constituting a clear and present danger to life or property by escaping gas, exposed wires, or other utility line breaks or defects.

C. The Contractor shall locate, identify, shut-off, and disconnect utility services that are indicated for removal or replacement. The Contractor shall also locate and identify utility services that are not indicated for removal or replacement. If the utility services that are not indicated for removal or replacement must be shut down during construction, the Contractor shall provide bypass connections, as necessary, to maintain continuity of service to occupied areas of buildings and the campus. All switching, securing, and disconnection of University utility services shall be performed in the presence of a knowledgeable University technician or utility representative.

D. During excavation around underground utilities, when the Contractor reaches a point approximately three feet from the estimated location of any underground utility, machine excavation shall be stopped and hand excavation shall be used to uncover the utility line. In the case of utilities as shallow as 12 inches below the surface, hand digging shall begin at the surface or immediately below any pavement. The Contractor is liable for the repair of any utility lines cut, broken, or otherwise damaged, at no additional cost to the University.

E. If a utility line is broken or damaged, or if service is interrupted in any way, the Contractor must immediately notify the University (or the Campus Police outside of normal working hours) and the appropriate utility company. The Contractor shall take immediate action to restore the utility to full service.

F. For any planned utility service interruptions, the Contractor shall furnish a request to the

University for approval at least five (5) working days in advance, or as specified by the University. The request shall identify the affected buildings and the duration of the planned outage. The University will coordinate with affected tenants and customers, as applicable. If the discontinued service is due to any emergency breakdown, the Contractor shall notify the University as soon as possible, and the University will notify those affected tenants and customers, as applicable. Power outages that involve portions of buildings may have to be scheduled for off-hours or weekends.

1.10 PROJECT PHOTOGRAPHS

A. Each Separate Prime Contractor, at its own cost and expense, and prior to beginning any Work, shall furnish photographs or video showing the pre-existing conditions upon which its Work will be constructed. The photographs or video shall include the actual work site and the surrounding areas, and the specific locations or subject matter of the photographs or video shall be coordinated with the University.

B. The Lead Prime Contractor, at its own cost and expense, shall furnish photographs showing the progress of the Work. Photographs shall be taken: (1) between the 1st and 5th day of each month, to show periodic progress of the Work; and (2) at critical junctures of the Work, to show specific features and conditions. The photographs shall be furnished monthly and at the final completion of the Project.

C. Monthly progress photographs shall be taken from not less than ten (10) positions each month.

Progress photographs shall be from the same positions each month, unless the progress of the Work is better shown with alternate views.

D. Photographs shall be in electronic/digital form, or in another form or format as agreed upon by the Contractor and the University. The photographs shall be of sufficient resolution for suitable color printing in 9-inch by 12-inch format. Video shall be in electronic/digital format, unless otherwise directed by the University.

E. The date/time and a description of each photograph and video shall be provided.

1.11 INDUSTRY STANDARDS

A. Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract. Such standards are made a part of the Contract by reference.

B. Where the date of issue of a referenced standard is not specified, standards in effect as of date of Contract shall be in force.

C. The quantity or quality levels shown or specified shall be the minimum and/or maximum provided or performed. The actual installation may comply exactly with the minimum or exceed the minimum, within reasonable limits, if not detrimental to the Work. Uncertainties should be referred to the University for a decision before proceeding.

D. If two or more specified standards provide differing or conflicting minimum and/or maximum levels of quantity or quality, the University shall be consulted for a decision as to the differing or conflicting levels before proceeding.

E. Where copies of standards are needed for performance of the Work, the Contractor shall obtain copies directly from the publication source. Although copies of standards needed for enforcement of requirements may be included as part of required submittals, the University reserves the right to require the Contractor to submit additional copies, as necessary, for enforcement of requirements.

F. Trade association names and titles of general standards are frequently abbreviated. Where such acronyms or abbreviations are used in the Technical Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-generating organization, authority having jurisdiction, or entity applicable to the context of the provision.

1.12 DISSEMINATION OF PLANS AND SPECS

Unless otherwise specified in the Contract Documents, the successful bidder Contractor, upon Contract award, will be furnished, free of charge, the complete sets of drawings and specifications in electronic PDF form.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

END OF SECTION 011000

CWU-0089-L Bentley Street Level Renovation Section 011101 – Special Provisions

SECTION 011101

SPECIAL PROVISIONS

PART 1 - CONTRACTOR QUALIFICATIONS

1.1 Experience and Certifications

A. Prime Contractors shall have the following minimum experience requirements

1. 10 years in business

2. Shall have successfully completed at least 5 projects that involve this type of work.

1.2 Contractor Qualification Statement (REQUIRED AS PART OF BID SUBMISSION)

A. Contractor shall furnish with their Proposal the American Institute of Architects Document A305 "Contractor’s Qualification Statement", which Document is hereby made part of the Contract Documents with the same force and effect as though bound therewith.

B. Document A305 is available for review in the office of the Architect

C. Also, as an attachment to the Statement, provide the Staffing and Organization Chart, including a list of the contractor's principal staff assignments, including the superintendent and other personnel in attendance at the site. Identify individuals, subcontractors, and their duties and responsibilities.

PART 2 - STAFFING REQUIREMENTS

2.1 Superintendence

A. Superintendence at all times during the performance of the work at the project site, and until the work is completed and accepted, the contractor shall have on site a duly authorized and competent superintendent who shall directly supervise the work. Direct supervision shall be required any time the contractor or any subcontractors are carrying out work on the site.

Communications given by the University at the project site to the superintendent shall be as binding as if is given to the contractor.

B. On project requiring multiple work crews and/or if the contractor has more than one separate prime contract, the contractor shall provide a separate superintendent for each separate prime contract and work crew.

C. The contractor shall not change the assigned superintendent without the approval of the System.

2.2 Management

A. Management for the duration of the contract and until all contract requirements are completed and final payment is made, the contractor shall have a duly authorized and qualified project manager for the contract. The project manager shall be the primary point of contact between the contractor and the system, and between the contractor and the design professional. The project manager shall have the full authority to make decisions and approve contract changes for the contractor.

B. If the contractor has more than one separate prime contract, the contractor shall provide a separate project manager for each separate prime contract.

C. The contractor shall not change the assigned project manager without the approval of the system.

2.3 Resumes (REQUIRED AS PART OF BID SUBMISSION)

A. The System will require the submission of a resumes or statement of qualifications for the proposed Project Manager(s) and the Superintendent(s).

B. All are subject to the review and approval of the University.

2.4 Minimum Self-Performed Work

A. Each Prime Contractor shall adhere to minimum staffing levels specified herein for the Contractor’s Work Force Staff for each crew, which shall be employees of the Contractor. These persons shall be part of the working crew that will be responsible for self-performing General Conditions work, such daily cleaning, emergency and damage response, normal and unforeseen requirement and other general condition requirements. Also each Prime Contractor shall have accident and safety personnel on site.

B. Minimum work force staffing levels employed by the Prime and which shall not be subcontracted are as follows:

1. General Contractor: 2 persons

2. Mechanical Contractor: 1 person

3. Plumbing Contractor: 1 person

4. Electrical Contractor: 1 person

C. Additional employees and subcontracts shall be provided as necessary to complete all require work.

PART 3 - PERFORMANCE REQUIREMENTS

3.1 Performance Plan (REQUIRED AS PART OF BID SUBMISSION)

A. Each Bidder must submit at time of Bid, a performance plan indicating how their firm will address all scheduling requirements, work logistics and processes, manpower levels and special University event dates for accomplishing all work as detailed in Division 1 Section 01100 Summary of Work, Rider B General Conditions, and within this section.

B. The plan may be submitted in any appropriate format, providing it clearly meets the requirements listed above. Failure to submit a complete and feasible plan will result in a rejection of your Bid. It also should be noted and addressed as part of the plan, that this project requires each contractor to self-perform all Division 1 (General Requirements) and Rider B responsibilities that may require a labor response not associated with the administration and supervision requirements of your project manager and site superintendent. These items include, but are not necessarily inclusive of all contract requirements such as, damage prevention, damage response, security, cleanliness, waste management, emergency efforts, deliveries, protection of property, etc.

C. The Performance Plan shall include a documented bar chart schedule, with manpower requirements, equipment lead time, equipment down time, phases, project milestones, and any other soft and hard dates incorporating project requirements as indicated in the contract documents (specifications and drawings).

3.2 Quality Control Plan (REQUIRED AS PART OF BID SUBMISSION)

A. Each Bidder must submit at time of Bid, a Contractor's Quality-Control Plan establishing the quality assurance and quality-control activities and responsibilities as indicated in the Bid

Documents. Along with the Quality-Control Plan, provide resumes of your project manager, site superintendent, quality-control manager and installers /applicators indicating the responsibilities for this project with qualifications and experience of the individual. Failure to submit a complete and feasible Quality-Control Plan and resumes will result in a disqualification of your bid.

3.3 Safety Plan (REQUIRED AS PART OF BID SUBMISSION)

A. Each Bidder must submit at time of Bid, a Contractor's Safety Plan describing the procedures and methodology to assure the safety conditions that must be maintained during construction in accordance with the requirements in Section 013529 Health & Safety Procedures. Along with the Safety Plan, provide resumes of your safety & accident prevention officer indicating the responsibilities for this project with qualifications and experience of the individual. If safety & accident prevention are part of the site superintendent responsibilities, they must be pointed out as part of this submission. Failure to submit a complete and feasible Safety Plan and resumes will result in a disqualification of your Bid.

PART 4 - WORK SEQUENCE & SCHEDULE

4.1 Submittals During Contract Award Period

A. Long lead items provisions

B. Based on the Owner’s Schedule Requirements, the Lead Contractor shall provide a comprehensive Construction Schedule for the Work no later than ten (10) days after the Notice of Award. The schedule shall identify the tasks to be accomplished, how staffing needs will be met, start and completion of each phase, L&I Inspections and occupancy requirements as defined in this contract. Include National Holiday dates and any other dates that have the potential to impact the project schedule.

C. If the dates listed in the Schedule Requirements below as required are not met or the time lines are not met, the contractor shall revise the schedule by providing a recovery schedule with the times listed in the contract. This may require the contractor to work additional days and times at no additional cost to the University.

4.2 Work on the Site shall commence upon issuance of the Notice to Proceed with adequate forces to complete all contracted work no later than the dates established indicated in the Owners Schedule Requirements indicated below. The Contractor shall include all overtime and other premiums with the Bid.

4.3 Schedule Requirements:

A. Notice of Award: to be provided by the University after Bid opening and review

B. Notice to Proceed to be provided by the University: anticipated around early February 2027.

C. Commence Construction Work at the Site: on or about March 1, 2027

D. Substantial Completion including L & I Inspection and Occupancy Permit: July 2, 2027

E. Complete work in this area: July 30, 2027 (including all on-site Punch List work)

END OF SECTION 011101

CWU-0089-L Bentley Street Level Renovation Section 012600 – Contract Modification Procedures

SECTION 012600

CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.01 CONTRACT CHANGE ORDERS

Changes to the Work, consisting of additions, deletions, or other revisions within the general scope of the Contract, involving an adjustment to the contract price or contract time, will be issued on the System’s Construction Change Order Form, or on another form acceptable to, or prescribed by, the University.

1.02 CHANGE ORDER PROCEDURES

A. Changes may be proposed or directed by the University. In doing so, the University will provide to the Contractor a detailed description of the proposed change and supplemental or revised drawings and specifications, as necessary. The University also will request from the Contractor a proposal for any change in Contract price and time. Unless otherwise indicated, the Contractor shall have fourteen (14) days from receipt of the University’s request to submit his proposal for price and time.

B. Changes may be proposed or requested by the Contractor. If the Contractor encounters a condition or situation which he believes requires adjustment to the Contract price or time, he may notify the University and submit a recommended detailed description of the proposed change.

The Contractor shall also submit a proposal for change in the Contract price and time. The Contractor's notification and proposal shall be submitted within fourteen (14) days of encountering the condition or situation. Unless otherwise requested, the University will have seven (7) days from receipt of the Contractor’s request to respond, by either accepting the request and initiating a Change Order, rejecting the request and stating the reasons for such rejection, or revising the proposed change and requesting from the Contractor a proposal for that revised change.

C. All Change Orders shall address Contract price, Contract time, and impacts.

D. All Change Orders shall contain a release statement, with both parties waiving any and all future claims relative to price, time, and impacts relating to the Change Order and work under it, unless otherwise agreed upon by the parties, in which case the Change Order shall contain a statement defining any waivers and/or stipulations.

E. Change Orders will be signed by the Contractor first, and then will be signed by the Contracting Officer, or by the Contracting Officer's authorized representative.

F. When a Change Order is sent to the Contractor to sign, the Contractor shall sign and return it to the University within seven (7) days.

G. A Change Order shall not be effective until signed by the Contracting Officer or their authorized representative. The Contractor should not stop work in progress, or initiate work on a change, until a Change Order is signed by the Contracting Officer or their authorized representative.

H. The signature of the Contracting Officer or their authorized representative on the Change Order constitutes a notice to proceed, unless the Change Order designates otherwise.

1.03 CONTRACTOR PROPOSALS

A. Any proposal submitted by the Contractor in relation to a Change Order shall address change in the contract price, change in the contract time, and any impacts.

B. Unless the price is properly covered in the Unit Price Schedule or as an Item in the Schedule of Values, the Contractor’s proposal shall adequately document and address in detail the costs of labor, materials, equipment, overhead, profit, bond, and any other costs associated with the change. The proposal shall be broken down to contain separate sections detailing labor, materials, equipment, and subcontractors.

1. Labor.

a. For each labor classification listed, the breakdown shall include the classification description, the number of workers in that classification, the total labor hours (H) for all workers in that classification, the hourly base wage rate (BR) for each classification, the hourly total wage rate (WR) for each classification, the base wage rate cost (H x BR) for each classification, and the total wage rate cost (H x WR) for each classification.

b. The hourly base wage rate (BR) is defined as the rate of wages paid by the employer directly to the employee. The hourly total wage rate (WR) is defined as the total rate of wages paid by the employer including wages paid on behalf of the employee. It is acknowledged that in certain situations, the base wage rate (BR) and the total wage rate (WR) may be equivalent.

c. The breakdown shall also include the total of all base wage rate costs for all classifications (TBR), and the total of all total wage rate costs for all classifications (TWR).

d. The Contractor may include a labor burden markup. Labor burden may include Social Security, Medicare, Federal unemployment insurance, state unemployment insurance, workmen’s compensation insurance, and public liability insurance, as appropriate.

Labor burden shall be calculated on the total of all of the base wage rate costs (TBR), and not on the total of all of the total wage rate costs (TWR).

e. The total of all of the total wage rate costs (TWR), plus the labor burden amount, is the pre-markup cost total for labor.

2. Materials.

a. For each material item used, the breakdown shall include the material description, the unit used to detail the quantity, the quantity showing the total number of units, the unit cost, and the total cost for that individual material item.

b. State sales taxes, in accordance with the provisions of PA Act 45 of 1998, may be included with applicable materials items.

c. Any freight charges for specific materials listed shall be included in the unit cost for that material. The University will not acknowledge or honor any separate line items for freight charges.

d. The breakdown shall also include the total of all total costs for all individual material items.

This total is the pre-markup cost total for materials.

3. Equipment.

a. For each type of equipment used, the breakdown shall include the description of that type of equipment, the quantity of that type of equipment, the duration (hours, days, etc.)

of work for that type of equipment, the rental rate for that type of equipment for a unit of the duration, and the total cost for that type of equipment.

b. State sales taxes paid on rental equipment may be included, if documented.

c. The breakdown shall also include the total of all total costs for all individual types of equipment. This total is the pre-markup cost total for equipment.

d. The University expects the Contractor to procure/provide the most economical rental rate available over the duration of the work performed.

e. The University will not pay equipment costs for any piece of equipment not specifically identified, or for any tools, such as hand tools, used in the everyday performance of work.

4. Subcontractors’ proposals supporting the Contractor’s proposal shall contain similar detail.

In some cases, a subcontractor's lump sum cost quotation may be acceptable, if it appears on the subcontractor's letterhead and contains a detailed description of the scope of work it represents.

5. Markups.

a. Standard Markups. For Contracts up to $6,000,000, the Contractor will be allowed maximum markups (combined overhead and profit) for Change Orders per the following:

i. 15% on labor costs (see 1.03 B. 1.)

ii. 10% on materials costs (see 1.03 B. 2.)

iii. 10% on equipment costs (see 1.03 B. 3.)

iv. 10% on subcontractor costs (see 1.03 B. 4.)

b. Negotiated Markup. For Contracts exceeding $6,000,000, the following shall apply.

i. The Contractor shall submit information supporting a general and administrative overhead rate, which, when accepted by the University, shall be used for all Change Orders.

ii. Profit shall be negotiated for each Change Order, with a maximum of 6% for

Change Orders involving significant in-house costs, difficult work, and/or higher risk, and a minimum of 3% for Change Orders involving primarily subcontracted work, easy work, and/or low-risk work. The final determination of profit shall be at the sole discretion of the University.

iii. Separate overhead and profit percent markup calculations shall be sequential, in that order.

iv. In any event, the total/cumulative markup shall not exceed the markups identified in 1.03 B.5.a.

v. The Contractor must use the negotiated markup method for all cost components (labor, materials, equipment, and subcontractors). The Contractor may not use a mix of the standard markup and the negotiated markup on different cost components.

c. Overhead markups shall represent general and administrative overhead costs, and shall not include general conditions costs.

d. Project management shall be part of general and administrative overhead costs.

Project management hours shall not be itemized on Change Orders. However, on significant Change Orders, a limited number of project management hours may be negotiated.

e. The method of application of markups shall be consistent for all Change Orders throughout the duration of the Contract.

f. The Contractor may add a markup for an additional marginal bond cost for Change Orders. The Contractor may be asked to submit information supporting their bond costs, and, in particular, their marginal bond cost.

C. The Contractor’s proposal shall address contract time. If the proposal includes a request for a change in the contract time, the proposal shall adequately address in detail the Project Schedule, and how the change to the Project Schedule impacts the Contract time.

D. The Contractor’s proposal shall address other impacts and impact costs. If the proposal includes a request for other impacts and impact costs, the proposal shall adequately address, in detail, those impacts and impact costs.

1.04 CONSTRUCTION CHANGE DIRECTIVES

A. When the University and the Contractor are not in total agreement on the terms of a Change

Order, or when the amount or extent of the work related to the Change Order is not known, the Contracting Officer may issue a Construction Change Directive, directing the Contractor to proceed with a change in the work, for subsequent inclusion in a Change Order.

B. The Construction Change Directive will be issued on the System’s Construction Change Order

Form, or on another form acceptable to, or prescribed by, the University. The Construction Change Directive will be signed by the Contracting Officer, and will not require acceptance, or a signature, by the Contractor. A Construction Change Directive shall not be effective until signed by the Contracting Officer. The Contracting Officer’s signature on the Construction Change Directive constitutes a notice to proceed, unless the Construction Change Directive designates otherwise.

C. The Construction Change Directive will contain a complete description of the change in the work, or of the known work, and will designate the method to be followed to determine the final change in the contract price, contract time, and/or impacts. The Construction Change Directive will also set a schedule and/or a time frame for the required actions to work toward, and achieve, that determination of final change in price, time, and/or impacts.

D. The Construction Change Directive will designate a not-to-exceed cost for work related to the

Construction Change Directive. The Contractor shall monitor his costs of doing the work, and, before he exceeds the not-to-exceed cost, inform the University of the anticipated date that he will exceed this cost if he continues work. The Contractor shall also inform the University of how much more he anticipates it will cost to complete the work. If the University concurs that the Contractor may properly incur costs related to the work that exceeds the designated not-to-exceed cost, the Contracting Officer will either initiate a Change Order to incorporate the final price of the work, issue a subsequent Construction Change Directive to increase the not-to-exceed cost, or issue a directive to stop the work.

E. The Contractor shall be required to maintain and submit to the University detailed documentation supporting the labor, material, and equipment used related to the Construction Change Directive.

The Contractor may be required to document labor, material, and equipment used on a form or in a format prescribed by the University. When performing work under a Construction Change Directive, the Contractor is expected to prosecute the work in an expeditious and efficient manner, and the University may disallow any costs that the University determines are not reasonable and necessary.

F. When the work related to the Construction Change Directive is complete, or when the amount or extent of the work related to the Construction Change Directive is known, the University and the Contractor shall agree to the actual cost of the work, and a Change Order shall be issued that addresses any final change in the contract price, the contract time, and any impacts.

1.05 ADDITIONAL CONSIDERATIONS

A. For Change Orders involving Work that is identified in the Unit Price Schedule or as an Item in the Schedule of Values, the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .