This is a Scope of Work document issued by the State of Utah Division of Purchasing in conjunction with the Wildlife Resources division for the delivery of cobble rock to support dike enhancement at Farmington Bay Waterfowl Management Area. The project requires delivery of 3,750 tons of cobble rock sized between 3 to 10 inches to the Turpin Parking Lot, located approximately 3.5 miles from the main entrance off Glover's Lane in Farmington, Utah. The cobble rock will be used by DRW staff to reinforce and strengthen the Turpin Dike line; the contractor's responsibility is limited to delivery and temporary placement only. Delivery must commence after May 20th, 2026, and be completed by June 19th, 2026. The contractor is responsible for providing an estimated delivery schedule, coordinating with WMA managers regarding road access, and ensuring safe transport without damage to existing infrastructure or the parking lot. The contract term extends from the time of award until June 19th, 2026.
The solicitation is structured as an Invitation for Bid (IFB) that will result in a single contract award to the lowest cost responsive and responsible vendor. The contractor must guarantee its pricing for the entire duration of the delivery process. The delivery site is accessible via Glover's Lane near 1325 West in Farmington, Utah, with specific coordinates provided for both the main entrance and the Turpin Parking Lot destination. The scope of work includes coordination requirements with WMA management and completion criteria that mandate no damage to infrastructure and efficient transport of materials to the designated site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Vendor Prerequisites - IFB Agency.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATT B: Scope of Work BD26-75 Dike Enhancement Cobble Rock Enhancement at Turpin Dike Line, Farmington Bay WMA
Project Overview: The purpose of this project is to enhance the Turpin Dike line at the Farmington Bay Waterfowl Management Area (WMA) by hiring a vendor to deliver cobble rock per the specs listed below. The cobble rock will range in size from 3 inches to 10 inches and will be used to strengthen and improve the dike's structure. The DRW staff will be reinforcing the Dike with the Cobble-stone, the contractor is not expected to and delivery of the rock is the only thing required for this Purchase Order.
Scope of Work Details:
1. Cobble Rock Specifications:
• The cobble rock required for this project should be in the size range of 3 inches to 10 inches.
2. Delivery of Cobble Rock:
• A total of up to 3750 tons of cobble rock will need to be delivered to the project site.
• Delivery will be made directly to the Turpin parking lot, which is located approximately 3.5 miles from the entrance off Glover's Lane.
• The delivery vehicles will be able to side dump the cobble rock directly into the parking lot.
3. Transportation and Access:
• The contractor is responsible for ensuring that the Cobble Rock is transported in a safe and efficient manner.
• The delivery trucks must be capable of safely accessing the Turpin parking lot without causing damage to existing infrastructure.
• If any issues with road access or conditions arise, the contractor will need to address them accordingly.
4. Schedule and Timeline:
• The delivery of Cobble Rock can start after May 20th and must be completed by June 19th.
• The contractor will be responsible for providing an estimated delivery schedule, including dates and times of delivery to avoid congestion or disruption to other activities at the WMA.
5. Site Map:
• A site map detailing the Turpin parking lot and access routes to the delivery location is attached for reference.
6. Deliverables:
• Delivery of 3750 tons of cobble rock to the designated site by June 19th, 2026.
• Safe unloading and temporary placement of the cobble rock in the Turpin parking lot area.
• Coordination with WMA Managers for road access.
7. Completion Criteria:
• Delivery of cobble rock to the site as per the project specifications by June 19th, 2026.
• No damage to the Turpin parking lot or surrounding infrastructure.
• Safe and efficient transport of materials to the project site.
Location Marker on Map
Approximate Coordinates Description
Main Entrance Top-Right Yellow Pushpin 40.9577° N, -111.9166° W This is the main gate located off Glovers Lane (near 1325 West in
Farmington, UT).
Turpin Parking Lot
Bottom-Left Yellow Pushpin 40.9192° N, -111.9687° W This is the parking area at the four-way intersection at the end of the drivable main dike road.
| ATT B: Scope of Work BD26-75 Dike Enhancement |
| 1. Cobble Rock Specifications: |
| 2. Delivery of Cobble Rock: |
| 3. Transportation and Access: |
| 4. Schedule and Timeline: |
| 5. Site Map: |
| 6. Deliverables: |
| 7. Completion Criteria: |