2 AJP-Replace_Chilled_Water_Loop_100_Const_Drawings_2024_01_19.pdf
PDF 36 MB Posted
- Attached to
- Z2DA--626A4-22-211 - AJP-Replace Chilled Water Loop Federal contract opportunity
- Solicitation number
- 36C24924R0074
About this file
This document appears to be a set of construction drawings for Project #626A4-22-211 "AJP-Replace Chilled Water Loop" at the Tennessee Valley Healthcare System VA Medical Center in Murfreesboro, Tennessee. The related federal contract opportunity is Solicitation Number 36C24924R0074, which seeks a contractor to furnish all labor, material, equipment, and supervision necessary to accomplish the work for this project. The work includes demolition and new construction, such as general construction, civil, structural, architectural, mechanical, plumbing, electrical, low voltage, and industrial hygiene. The NAICS code is 238220 Plumbing, Heating, and Air Conditioning Contractors, with a $19M small business size standard. The PSC Code is Z2DA Repair or Alteration of Hospitals and Infirmaries, and the project magnitude of construction is between $5M and $10M. The contract is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 0002 RFI Responses 626A4-22-211 - Construction AJP Replace Chilled Water Loop.pdf | ||
| 36C24924R0074 0002.pdf | ||
| Amend 0002 - 18235 GEOTECH REPORT.pdf | ||
| Site Visit Scanned Sign In Sheet.pdf | ||
| 36C24924R0074 0001.pdf | ||
| 4 Contractor EMR Certification Form.docx | DOCX document | |
| 8 Price Schedule Project 626A4-22-211 AJP-Replace Chilled Water Loop.xlsx | XLSX spreadsheet | |
| 36C24924R0074.pdf | ||
| 3 AJP-Replace_Chilled_Water_Loop_100_Const_Specs_2024_01_19.pdf | ||
| 6 UEI _ TAX ID.docx | DOCX document | |
| 7 Calculation of Self Performed Work.docx | DOCX document | |
| 1 Wage Determination TN20240187 06212024 626A4-22-211 Replace Chilled Water Loop.pdf | ||
| 5 RFI Form.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.aeworks.com
A u to d e s k D o c s /V
M U
R -0
A J P
-R e p la c e
C h ill e d W a te r L o o p /V
M U
R -0
M
E P
R
.r v t
/1
/2
:4
:5
P
M
G001
COVER SHEET AJP - REPLACE CHILLED
WATER LOOP
3400 LEBANON RD
MURFREESBORO, TN 37129
626A4-22-211
N/A
01.19.2024 MJC AC
100% CONSTRUCTION
DOCUMENTS
ALVIN C. YORK VA MEDICAL CENTER
REPLACE CHILLED WATER LOOP
PROJECT #626A4-22-211
3400 LEBANON ROAD
MURFREESBORO, TN 37129
PROJECT DIRECTORY
OWNER:
ALVIN C. YORK VAMC
3400 LEBANON ROAD
MURFREESBORO, TN 37129
657-867-6000
ARCHITECT / MEP ENGINEER:
AE WORKS, LTD
418 BEAVER STREET
SEWICKLEY, PA 15143
412-287-7333
CONTACT: MICHAEL CARROLLCONTACT: MICHAEL SNELL
MEP ENGINEER:
HGA
333 EAST ERIE STREET
MILWAUKEE, WI 53202
CONTACT: MATTHEW MIKOLAINIS
CIVIL ENGINEER:
PALMER ENGINEERING
1040 MONARCH STREET
SUITE 210
LEXINGTON, KY 40513
CONTACT: CHRIS MISCHEL
GENERAL
G001 COVER SHEET
G002 PHASING PLAN
CIVIL
C-001 EXISTING CONDITIONS
CD-002 OVERVIEW DEMOLITION PLAN
CD-003 DEMOLITION AREA - AREA 1
CD-004 DEMOLITION AREA - AREA 2
CD-005 DEMOLITION AREA - AREA 3
C-100 OVERVIEW EROSION CONTROL PLAN
C-101 EROSION CONTROL PLAN - AREA 1
C-102 EROSION CONTROL PLAN - AREA 2
C-103 EROSION CONTROL PLAN - AREA 3
C-200 OVERVIEW UTILITY PLAN
C-201 UTILITY PLAN - AREA 1
C-202 UTILITY PLAN - AREA 2
C-203 UTILITY PLAN - AREA 3
C-300 PROFILES
C-301 PROFLIES
C-302 PROFILES
C-400 DETAILS
ARCHITECTURAL
01-A101 BLDG 01 & 120 - ARCHITECTURAL PLAN
02-A101 BLDG 02 - ARCHITECTURAL PLAN
04-A101 BLDG 04 - ARCHITECTURAL PLAN
116-A101 BLDG 116 - ARCHITECTURAL PLANS
A102 BLDG 3, 5, 7, 8, 9 & 11 ENLARGED ARCHITECTURAL PLANS
MECHANICAL
M001 MECHANICAL SYMBOLS, ABBREV., AND GENERAL NOTES
MSD201 SITE - PIPING - DEMOLITION PLAN
MS201 SITE - PIPING - NEW WORK PLAN
01-MD201 BLDG 01 & 120 - CHILLED WATER DEMOLITION PLAN
02-MD200 BLDG 02 - TUNNEL CHILLED WATER DEMOLITION PLAN
02-MD201 BLDG 02 - CHILLED WATER DEMOLITION PLAN
03-MD201 BLDG 03 - CHILLED WATER DEMOLITION PLAN
04-MD201 BLDG 04 - CHILLED WATER DEMOLITION PLAN
10-MD201 BLDG 10 - CHILLED WATER DEMOLITION PLAN
11-MD201 BLDG 11 - CHILLED WATER DEMOLITION PLAN
17-MD201 BLDG 17 - CHILLED WATER DEMOLITION PLAN
105-MD201 BLDG 105 & 117 - CHILLED WATER DEMOLITION PLAN
107-MD201 BLDG 107 - CHILLED WATER DEMOLITION PLAN
116-MD201 BLDG 116 - CHILLED WATER DEMOLITION PLAN
01-M201 BLDG 01 & 120 - CHILLED WATER PLAN
02-M200 BLDG 02 - TUNNEL CHILLED WATER & STEAM PLAN
02-M201 BLDG 02 - CHILLED WATER PLAN
03-M201 BLDG 03 - CHILLED WATER PLAN
04-M201 BLDG 04 - CHILLED WATER PLAN
10-M201 BLDG 10 - CHILLED WATER PLAN
11-M201 BLDG 11 - CHILLED WATER PLAN
17-M201 BLDG 17 - CHILLED WATER PLAN
105-M201 BLDG 105 & 117 - CHILLED WATER PLAN
107-M201 BLDG 107 - CHILLED WATER PLAN
109-M201 BLDG 109 - CONDENSER WATER PHASING PLAN
116-M201 BLDG 116 - CHILLED WATER PLAN
MD401 ENLARGED CHILLED WATER DEMOLITION PLANS
M401 ENLARGED CHILLED WATER PLANS
M501 MECHANICAL DETAILS
M502 MECHANICAL DETAILS
M503 MECHANICAL DETAILS
M504 MECHANICAL DETAILS
M601 CHW CAMPUS SCHEMATIC
M602 CDW SYSTEM SCHEMATIC
M603 BUILDING SCHEMATICS
M604 BUILDING SCHEMATICS
M605 BUILDING SCHEMATICS
M606 STEAM SCHEMATIC
M701 MECHANICAL SCHEDULES
M801 MECHANICAL CONTROL DIAGRAMS
ELECTRICAL
E001 ELECTRICAL SYMBOLS AND ABBREVIATIONS
02-ED201 BLDG 02 - ELECTRICAL DEMOLITION PLAN
03-ED201 BLDG 03 - ELECTRICAL DEMOLITION PLAN
04-ED201 BLDG 04 - ELECTRICAL DEMOLITION PLAN
09-ED201 BLDG 09 - ELECTRICAL DEMOLITION PLAN
10-ED201 BLDG 10 - ELECTRICAL DEMOLITION PLAN
11-ED201 BLDG 11 - ELECTRICAL DEMOLITION PLAN
105-ED201 BLDG 105 & 117 - ELECTRICAL DEMOLITION PLAN
120-ED201 BLDG 120 - ELECTRICAL DEMOLITION PLAN
02-E201 BLDG 02 - ELECTRICAL PLAN
03-E201 BLDG 03 - ELECTRICAL PLAN
04-E201 BLDG 04 - ELECTRICAL PLAN
09-E201 BLDG 09 - ELECTRICAL PLAN
10-E201 BLDG 10 - ELECTRICAL PLAN
11-E201 BLDG 11 - ELECTRICAL PLAN
105-E201 BLDG 105 & 117 - ELECTRICAL PLAN
120-E201 BLDG 120 - ELECTRICAL PLAN
ED401 ENLARGED ELECTRICAL DEMOLITION PLANS
E401 ENLARGED ELECTRICAL PLANS
E501 ELECTRICAL DETAILS
E701 ELECTRICAL PANEL SCHEDULES
SHEET INDEX
LAND SURVEYING:
HONOR ENGINEERING
1100 NORTH MOUNTAIN ROAD
HARRISBURG, PA 17112
CONTACT: MATT WARNER
ENVIRONMENTAL ENGINEER:
MABBETT
105 CENTRAL STREET
SUITE 400
STONEHAM, MA 02180
CONTACT: MICHAEL DELANEY
VICINITY MAP
LOCATION MAP
# Revisions Date
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.aeworks.com
A u to d e s k D o c s /V
M U
R -0
A J P
-R e p la c e
C h ill e d W a te r L o o p /V
M U
R -0
M
E P
R
.r v t
/1
/2
:4
:2
P
M
G002
PHASING PLAN AJP - REPLACE CHILLED
WATER LOOP
3400 LEBANON RD
MURFREESBORO, TN 37129
626A4-22-211
01.19.2024 MJC AC
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
PHASING PLAN
1. GENERAL REQUIREMENTS
a. CONTRACTOR SHALL SUBMIT A PHASING PLAN PRIOR TO THE START OF PROJECT WORK. THE PLAN WILL BE REVIEWED BY THE ENGINEER AND THE VA.
b. THE CHILLED WATER SYSTEM IS SHUT DOWN WHEN THE AIR TEMP IS BELOW 45°F. SHUTDOWNS MUST BE COORDINATED WITH THE VA AT LEAST 21 DAYS IN
ADVANCE.
c. THE UNDERGROUND CHILLED WATER PIPING IS IN POOR CONDITION AS LEAKS HAVE OCCURRED IN THE SYSTEM.
d. CONTRACTOR MUST VERIFY PIPE CONDITION AT EACH POINT OF CONNECTION. REPORT ALL PIPE OBSERVATIONS AT TIE IN POINTS PAYING ATTENTION TO
PITTING OR OTHER DEGRADATION.
e. BUILDING 1 REQUIRES 24/7 COOLING.
f. THE WORK OF THIS PROJECT WILL CREATE A CHILLED WATER LOOP ALLOWING BI-DIRECTIONAL FLOW IN THE QUAD. THIS DECREASES THE AMOUNT OF
DISTRIBUTION TO THE SYSTEM THAT WILL NEED TO BE ISOLATED WHEN MAINTENANCE IS PERFORMED ON THE SYSTEM.
g. TO ALLOW PARTIAL SHUTDOWNS, A VALVE MANIFOLDS WILL BE INSTALLED AT EVERY TAKE-OFF TO ALLOW ISOLATION OF A PORTION OF THE LOOP, OR THE
BUILDING.
h. CONTRACTOR SHALL PHASE THE SHUTDOWNS IN SUCH A WAY THAT THE EXTENT OF SHUTDOWNS REQUIRED IS PROGRESSIVELY LESS, AS THE PROJECT IS
CONSTRUCTED. THIS CONCEPT IS REFLECTED IN THE SUGGESTED PHASING OUTLINE BELOW.
i. DO NOT ABANDON ANY ABOVE GROUND PIPING IN PLACE. REMOVE PREVIOUSLY ABANDONED PIPING IN GENERAL WORK AREA TO IMPROVE WORK CONDITIONS, AND TO FACILITATE WORK AS PIPES AND ROUTING IS BEING VERIFIED.
j. UNDERGROUND PIPING WILL BE REMOVED AS SHOWN ON DRAWINGS (CIVIL AND MECHANICAL) AND AS REQUIRED TO FACILITATE INSTALLATION OF NEW PIPING.
k. MAKE PROVISIONS SUCH AS ADDITIONAL VENT AND DRAIN VALVES FOR HYDROSTATICALLY TESTING, CHEMICALLY CLEANING AND FLUSHING OF ALL PIPE BY
SECTIONS.
l. AS INSTALLATION WORK IS COMPLETED, HYDROSTATICALLY TEST, CHEMICALLY CLEAN AND FLUSH PIPING. FOLLOW PIPE MANUFACTURER PROCEDURES FOR
HYDROSTATICALLY TESTING OF HDPE PIPE.
m. NEW CHILLED WATER PIPING SHALL ALSO BE HYDROSTATICALLY TESTED, CHEMICALLY CLEANED AND FLUSHED.
2. THE GENERAL SCOPE OF WORK INCLUDES:
a. CHILLED WATER SCOPE OF WORK IS SUMMARIZED AS FOLLOWS. SEE DRAWINGS AND SPECIFICATIONS FOR COMPLETE SCOPE DESCRIPTION.
1. REPLACE ALL UNDERGROUND CHILLED WATER DISTRIBUTION PIPING WITH NEW HDPE PIPING SIZED AND LOCATED AS SHOWN ON THE DRAWINGS.
2. REPLACE ALL ABOVE GROUND CHILLED WATER MAINS AS SHOWN ON DRAWINGS.
3. NEW UNDERGROUND VALVES WILL BE STAINLESS STEEL. TRANSITION FROM HDPE TO STANDARD WEIGHT STAINLESS STEEL PIPING AND VALVES AS SHOWN
ON DRAWINGS AND SPECIFIED.
4. THE UNDERGROUND CHILLED WATER PIPING WILL BE INSTALLED WHILE THE EXISTING PIPING IS STILL IN OPERATION. BUILDING CONNECTIONS SHALL BE
ROUTED NEAR THE EXISTING BUILDING CONNECTIONS TO MINIMIZE TIE-IN TIME.
5. THE NEW PIPING WILL BE TESTED AND CLEANED BEFORE CONNECTIONS ARE MADE.
6. THE NEW CHILLED WATER MAIN WILL HAVE VALVE MANIFOLDS CUT IN AT A LOCATION FOR EACH BUILDING, CONSISTING OF SEGMENTATION VALVES ON BOTH
SIDES OF THE MAIN LINE TEE AND BRANCH TAKE-OFF. USE THESE VALVES TO ISOLATE THE BUILDING AND CONNECT THE NEW PIPING. THIS WORK SHOULD BE
DONE WHEN THE OUTSIDE AIR IS BELOW 45°F TO MINIMIZE DISRUPTION.
7. DO NOT USE HDPE (ELBOWS, TEES) UNLESS SHOWN ON DRAWINGS.
8. PROVIDE VALVE BOXES OR VAULTS FOR UNDERGROUND PIPING. BRING UNDERGROUND VENTS TO SURFACE.
9. REPLACE ALL BUILDING MAIN CHILLED WATER SHUT-OFF VALVES.
10. TEMPORARY COOLING WILL NEED TO BE PROVIDED TO ALL BUILDINGS IF THE WORK CANNOT BE COMPLETED WITHOUT DISRUPTION TO COOLING
REQUIREMENTS.
11. REUSE BUILDING CONNECTION POINTS UNLESS NEW POINTS AID IN THE PHASING OF THE WORK.
12. REPLACE CHILLED WATER MAINS LEAVING CUP FROM NEW ISOLATION VALVES AT RISER TO UNDERGROUND INTERFACE. SEE DRAWINGS.
13. PROVIDE VAULTS AND VALVE BOXES AS SHOWN ON DRAWINGS.
b. CONDENSER WATER SCOPE IS SUMMARIZED AS FOLLOWS. SEE DRAWINGS AND SPECIFICATIONS FOR COMPLETE SCOPE DESCRIPTION.
1. IN THE CDW PUMP ROOM, REMOVE THE CAP OF THE CDWS MAIN AND REPLACE WITH A LINE SIZE ISOLATION VALVE.
2. IN THE CENTRAL PLANT, REPLACE THREE CDW MAINS INTO A SINGLE MAIN AND TIE INTO HEADER.
3. INSTALL THE NEW CDW PIPING BETWEEN THE PLANT AND THE PUMP HOUSE. TIE IN THE NEW CDWS MAIN TO THE NEW LINE SIZE VALVE AND REMOVE THE
EXISTING THREE BURIED LINES.
4. DEMO THE EXISTING LINES.
c. ADDITIONAL PLANT WORK:
1. NEW FLOW METERS ARE TO BE ADDED TO THE CONDENSER AND CHILLED WATER PIPING OF EACH CHILLER. SEE DRAWINGS FOR LOCATION. TIE INTO BAS AND
USE FLOWMETER SIGNALS AS PRIMARY LOW SIGNALS. USE EXISTING DP BASED FLOW SIGNALS AS BACKUP SIGNALS. DISPLAY BOTH SIGNALS ON CONTROL
SCREEN.
3. PHASING PLAN: CONTRACTOR SHALL DEVELOP A PHASING PLAN FOR ALL WORK AND SUBMIT FOR APPROVAL. THE FOLLOWING IS A SUGGESTED ORDER OF WORK.
COMPLETE ALL WORK SPECIFIED IN CONSTRUCTION DOCUMENTS INCLUDING PLANS AND SPECIFICATIONS.
a. CHILLED WATER
1. PROVIDE NEW CHILLED WATER VALVES TO PICK UP OLD MAINS FROM NEW MAINS. THESE VALVES WILL BE CLOSED PERIODICALLY DURING THE PHASING OF
WORK TO ALLOW FOR PARTIAL CHW SHUTDOWNS.
2. INSTALL BUILDING BRANCH ISOLATION VALVES AT THE EXISTING MAINS WHERE THEY DO NOT EXIST IF REQUIRED TO ACCOMPLISH THIS PHASING..
3. TEST THE EXISTING BRANCH ISOLATION VALVES AT THE MAINS TO PROVE THEY WILL HOLD. IF THEY DO NOT, THIS MAY REQUIRE MORE EXTENSIVE
SHUTDOWNS.
4. EXCAVATE AND INSTALL UNDERGROUND CHILLED WATER PIPING AS SHOWN ON THE PLANS. PIPING MAY BE PREINSULATED OR FIELD INSULATED- SEE
SPECIFICATIONS. LEAVE JOINTS OPEN UNTIL HYDROSTATIC TESTING IS COMPLETED.
5. THIS PIPING WILL INCLUDE ALL BRANCH ISOLATION VALVES FROM MAIN TO BUILDING FOR LATER BUILDING BY BUILDING CHANGEOVER.
6. NEW PIPING MUST BE HYDROSTATICALLY TESTED, CLEANED, FLUSHED AND REFILLED.
7. ADD 2” RECIRCULATION VALVES AT EACH BRANCH OF NEW PIPING FOR FLUSHING AND PURPOSES AND TO CIRCULATE WATER DURING TESTING AND STARTUP.
8. MOVE SOURCE OF COOLING FROM OLD MAIN TO NEW MAINS ONE BY ONE, TO TRANSITION TO NEW PIPING. AFTER TRANSITION, OLD PIPING WILL STILL BE
CONNECTED TO PLANT. BRANCHES NO LONGER IN USE MUST BE CAPPED AT EACH VALVE OR DISCONNECTED POINT TO PREVENT LEAKAGE.
9. WHEN ALL LOADS ON THE OLD PIPING ARE COMPLETELY TRANSITIONED TO NEW PIPING, DEMO EXISTING AS SHOWN ON DRAWINGS.
10. MECHANICAL ROOMS, EXCEPT FOR BUILDING 1, SHALL BE RE-PIPED AS SHOWN ON THE FLOOR PLANS.: WHEN CONSIDERING PHASING, NOTE THE FOLLOWING
GUIDELINES.
11. EACH MECHANICAL ROOM MAY REQUIRE A NEW TEE AND VALVES TO MAKE CONNECTIONS TO BOTH THE OLD AND NEW MAINS AND ALLOW TRANSITION
WITHOUT RESPECT TO WEATHER RESTRICTIONS.
12. THE WORK CAN BE COMPLETED WHEN THE CHILLER PLANT IS OFF, WHICH IS WHEN THE OUTSIDE AIR TEMPERATURE IS BELOW 45°F. ALLOW TIME TO DRAIN
AND REFILL WITH TREATED WATER WHERE VALVING DOES NOT ALLOW EASY ISOLATION.
13. COORDINATE WITH THE VA TO CONFIRM THE BUILDING SHUTDOWN.
14. PROVIDE TEMPORARY COOLING, PIPING OR VALVES AS REQUIRED TO ALLOW CONTINUED SERVICE WHILE THE NEW PIPING IS BEING INSTALLED. IF THIS IS
DONE, THE BUILDING SHUTDOWN REQUIRED TO CONNECT THE NEW PIPING NEEDS TO BE WHEN THE CENTRAL PLANT IS SHUTDOWN OR COORDINATED WITH A
PERIOD WHEN THE BUILDING DOES NOT NEED COOLING.
15. BUILDING 1 REQUIRES A CONTINUAL COOLING SOURCE. COORDINATE WITH THE VA FOR THE BUILDING SHUTDOWN.
16. AFTER ALL PIPING HAS BEEN TESTED AND CLEANED, BUILDINGS CAN BE CONNECTED TO THE NEW LOOP.
17. CONNECT ONE BUILDING AT A TIME.
18. ISOLATE THE EXISTING BRANCH PIPING TO THE BUILDING.
19. ROUTE THE NEW PIPING INTO THE BUILDING TO MAKE THE NEW CONNECTION.
20. FILL WITH CHEMICALLY TREATED WATER AND VENT THE BRANCH PIPING.
21. REPEAT THIS AROUND THE CAMPUS UNTIL ALL BUILDINGS HAVE BEEN SWITCHED OVER FROM THE EXISTING SYSTEM TO THE NEW SYSTEM.
22. REMOVE THE EXISTING PIPING WHERE IT IS EXPOSED ONCE IT IS NO LONGER IN USE.
b. CONDENSER WATER
1. ISOLATE THE CDWS HEADER IN THE PUMP HOUSE. DRAIN THE HEADER AND INSTALL A LINE SIZE ISOLATION VALVE AT THE END.
2. INSTALL THE PIPING MAINS BETWEEN THE TOWERS AND THE PLANT.
3. IN THE CENTRAL PLANT, DEMOLISH THE EXISTING CDWS AND CDWR HEADER PER THE FLOOR PLAN AND CONNECT TO THE NEW CDWS AND CDWR LINE.
4. CONNECT THE CDW LINES AT THE TOWERS.
5. DEMO THE EXISTING LINES ONCE THEY ARE NO LONGER IN USE.
BUILDING 7
BUILDING 8
BUILDING 9
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 4
BUILDING 5
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
EASTVIEW DRIVE
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
VETERANS CIRCLE
#1
#2
#3
#4
#5
#6
#7
#8
BUILDING 106
BUILDING 16
BOILER PLANT
CANOPYPAINT
SHOP
BUILDING 15
MAINT.
OPERATIONS
BUILDING 13
MAINT.
OPERATIONS
BUILDING 12
MAINT.
OPERATIONS
BUILDING 11
PAVILION
BUILDING 112
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
EXISTING CONDITIONS
C-001
NOTES :
1. UNDERGROUND UTILITIES AND PIPING SYSTEMS SHOWN
ARE FROM ABOVE GROUND EVIDENCE, AND ARE
APPROXIMATE ONLY PER TOPOGRAPHIC SURVEY BY
HONOR ENGINEERING. NO EXCAVATION PERFORMED
THIS SURVEY. CONTACT ALL UTILITY OWNERS PRIOR TO
ANY EXCAVATION.
LEGEND
CONTROL POINT TABLE
BENCHMARK NORTHING EASTING ELEVATION DESCRIPTION
1 576559.78 1856451.59 568.42 IRON PIN
2 576328.50 1856098.28 579.06 IRON PIN
3 576140.00 1856008.80 582.67 MAGNAIL
4 575797.18 1856300.89 586.32 IRON PIN
5 575688.80 1856083.70 587.83 IRON PIN
6 575318.45 1856542.38 588.84 IRON PIN
7 575582.96 1856676.99 585.39 IRON PIN
8 575675.24 1856822.27 584.39 IRON PIN
BUILDING 9
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 4
BUILDING 5
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
EASTVIEW DRIVE
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
VETERANS CIRCLE
#1
#2
#3
#4
#5
#6
#7
#8
BUILDING 106
BUILDING 16
BOILER PLANT
CANOPYPAINT
SHOP
BUILDING 15
MAINT.
OPERATIONS
BUILDING 13
MAINT.
OPERATIONS
BUILDING 12
MAINT.
OPERATIONS
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
AREA 1
AREA 2
AREA 3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
OVERVIEW DEMOLITION PLAN
CD-002
DEMOLITION NOTES:
1. ALL DEMOLISHED MATERIALS BECOME THE PROPERTY OF THE CONTRACTOR UNLESS OTHERWISE DESIGNATED.
CONTRACTOR TO DISPOSE OF THE MATERIAL OFF THE OWNER'S PROPERTY TO A PROPER AND APPROVED LANDFILL AT NO
ADDITIONAL COST.
2. ALL PAVEMENT, BASE COURSES, SIDEWALKS, CURBS, BUILDING FOUNDATIONS, ETC., IN THE AREA TO BE DEMOLISHED
SHALL BE REMOVED TO SUBGRADE.
3. ALL ITEMS OF CONSTRUCTION REMAINING AND NOT SPECIFICALLY MENTIONED THAT INTERFERE WITH THE NEW
CONSTRUCTION SHALL BE REMOVED AS DIRECTED BY THE COR.
4. CONTRACTOR SHALL PROVIDE PROTECTION TO ALL PAVEMENT, CURB & GUTTER, SIDEWALKS, TREES, UTILITIES, AND STRUCTURES THAT ARE TO REMAIN. CONTRACTOR SHALL REPAIR ALL DAMAGE AT NO ADDITIONAL COST TO THE
DEPARTMENT OF VETERAN AFFAIRS..
5. CAVITIES LEFT BY STRUCTURE REMOVAL SHALL BE BACKFILLED WITH CRUSHED STONE AND COMPACTED. SEE EARTHWORK
SPECIFICATION.
6. THE CONTRACTOR SHALL CONFORM TO ALL LOCAL CODES AND OBTAIN ALL PERMITS PRIOR TO BEGINNING WORK.
7. THE CONTRACTOR SHALL VERIFY THE EXACT LOCATION OF ALL EXISTING UTILITIES, TAKE CARE TO PROTECT UTILITIES
THAT ARE TO REMAIN, AND REPAIR CONTRACTOR CAUSED DAMAGES ACCORDING TO LOCAL STANDARDS AT THE
CONTRACTOR'S EXPENSE.
8. COORDINATE ALL DEMOLITION WITH THE APPROPRIATE UTILITY COMPANY AND THE DEPARTMENT OF VETERAN AFFAIRS PRIOR TO PERFORMING THE WORK AND OBTAIN APPROVAL TO ENSURE MINIMAL INTERRUPTIONS IN SERVICE TO EXISTING
FACILITIES.
9. ANY HAZARDOUS MATERIALS ON-SITE MUST BE DISPOSED OF IN ACCORDANCE WITH ALL LOCAL, STATE, AND FEDERAL
AGENCIES HAVING JURISDICTION. COORDINATE DISPOSAL WITH THE COR.
10. EROSION CONTROL SHALL BE INSTALLED AS NECESSARY DURING DEMOLITION OPERATIONS TO ENSURE THAT ANY SEDIMENT TRANSPORT AND RUNOFF THAT DOES OCCUR WILL REMAIN ON-SITE OR BE MINIMIZED.
11. ALL TRENCHING, PIPE LAYING, AND BACKFILLING SHALL BE IN ACCORDANCE WITH FEDERAL OSHA REGULATIONS.
12. CONTRACTOR SHALL NOTIFY ALL UTILITY COMPANIES HAVING UNDERGROUND UTILITIES ON SITE OR IN THE RIGHT-OF-WAY
PRIOR TO EXCAVATION. CONTACT TENNESSEE 811 AND LOCATE ALL UTILITIES PRIOR TO COMMENCING DEMOLITION OPERATIONS. ANY UTILITIES NOT AFFILIATED WITH TENNESSEE 811 MUST BE CONTACTED DIRECTLY.
13. SITE DEMOLITION DRAWINGS ARE INTENDED TO GENERALLY SHOW THE DEMOLITION NECESSARY TO COMPLETE THE NEW WORK. THE CONTRACTOR SHALL REVIEW ALL DOCUMENTS AND VISIT AND OBSERVE THE SITE PRIOR TO SUBMITTING HIS BID, AND SHALL INCLUDE IN HIS BID ALL WORK NECESSARY TO ACCOMPLISH THE NEW WORK, WHETHER OR NOT SHOWN ON
THESE DEMOLITION DRAWINGS.
14. ALL TREES ARE TO REMAIN UNLESS SPECIFICALLY NOTED OTHERWISE. CONSULT WITH THE DEPARTMENT OF VETERAN
AFFAIRS AND DESIGN TEAM BEFORE REMOVING ANY TREES NOT NOTED ON THIS PLAN.
15. REFER TO UTILITY PLAN FOR RELOCATION OF UTILITIES.
16. FOR CONCRETE REMOVAL, REMOVE TO THE NEAREST CONSTRUCTION JOINT. PROVIDE A CLEAN SAW CUT JOINT TO ALL
EXISTING EDGES OF CONCRETE TO REMAIN.
17. ALL PAVING, FENCING, REGULAR STRIPING, ADA STRIPING, ADA PARKING PAVEMENT SYMBOLS, WHEEL STOPS, AND STORM
INFRASTRUCTURE TO BE RESTORED AFTER CONSTRUCTION PER DETAILS PROVIDED ON SHEET C-400.
18. ALL CONFLICTING UNDERGROUND ELECTRIC AND COMMUNICATION LINES TO BE REROUTED AROUND OR ABOVE/BELOW
PROPOSED CHILLED WATER LINE VALVE VAULTS.
19. PROJECT IS BEING DESIGNED CONCURRENTLY WITH VA STEAM DISTRIBUTION UPGRADES AND AREAS OF COORDINATION
HAVE BEEN ESTABLISHED IN THESE DOCUMENTS. CONTRACTOR SHOULD REFER TO THOSE CONSTRUCTION DOCUMENTS
FOR FIELD-COORDINATION PURPOSES TO ALLOW FOR PIPING RIGHT-OF-WAY ALLOWANCES.
20.
LEGEND
CONCRETE SIDEWALK REMOVAL & REPLACEMENT
BUILDING CONFLICT (ROUTE THRU)
ASPHALT PAVING REMOVAL & REPLACEMENT
BUILDING 120
BUILDING 3
BUILDING 4
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
#2
#3
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
AR
EA
M
AT
C H
LI
N
E
AR
EA
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
DEMOLITION PLAN - AREA 1
CD-003
DEMOLITION PLAN KEY
CONCRETE SIDEWALK REMOVAL & REPLACEMENT
BUILDING CONFLICT (ROUTE THRU)
ASPHALT PAVING REMOVAL & REPLACEMENT
KEY DESCRIPTION
A
B
C
D
E REMOVE AND REPLACE SIGN
REMOVE TREE
F REMOVE CONCRETE CURB AND GUTTER
G PROTECT WATER VALVE
H PLACE TREE PROTECTION FENCE AROUND EXISTING TREES
I TREE TO REMAIN IF ROOT SYSTEM IS NOT COMPROMISED
J RAMP REMOVAL AND REPLACEMENT
K
CONTRACTOR TO FIELD VERIFY EXISTING CHILLED WATER LINES ARE
LOCATED WHERE PROPOSED CHILLED WATER LINES ARE TO BE INSTALLED.
IF SO, NEW CHILLED WATER LINES CAN BE INSTALLED WHEN EXISTING
CHILLED WATER LINES ARE NOT BEING USED DEPENDING ON THE TIME OF
YEAR PER VA UTILITY SERVICES SCHEDULE.
L REMOVE AND REPLACE FENCE
BUILDING 9
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 5
VETERANS CIRCLE
#4
#5
PAVILION
AR
EA
AREA 3
M
AT
C H
LI
N
E
AR
EA
MATCHLINE AREA 2
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
DEMOLITION PLAN - AREA 2
CD-004
DEMOLITION PLAN KEY
CONCRETE SIDEWALK REMOVAL & REPLACEMENT
BUILDING CONFLICT (ROUTE THRU)
ASPHALT PAVING REMOVAL & REPLACEMENT
KEY DESCRIPTION
A
B
C
D
E REMOVE SIGN
REMOVE TREE
F REMOVE CONCRETE CURB AND GUTTER
G PROTECT WATER VALVE
H PLACE TREE PROTECTION FENCE AROUND EXISTING TREES
I TREE TO REMAIN IF ROOT SYSTEM IS NOT COMPROMISED
J RELOCATE SWING
K
CONTRACTOR TO FIELD VERIFY EXISTING CHILLED WATER LINES ARE
LOCATED WHERE PROPOSED CHILLED WATER LINES ARE TO BE INSTALLED.
IF SO, NEW CHILLED WATER LINES CAN BE INSTALLED WHEN EXISTING
CHILLED WATER LINES ARE NOT BEING USED DEPENDING ON THE TIME OF
BUILDING 5
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
#4
#6
#7
#8
MATCHLINE AREA 2
MATCHLINE AREA 3
MATCHLINE AREA 1
MATCHLINE AREA 3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
DEMOLITION PLAN - AREA 3
CD-005
DEMOLITION PLAN KEY
CONCRETE SIDEWALK REMOVAL & REPLACEMENT
BUILDING CONFLICT (ROUTE THRU)
ASPHALT PAVING REMOVAL & REPLACEMENT
KEY DESCRIPTION
A
B
C
D
E REMOVE SIGN
REMOVE TREE
F REMOVE CONCRETE CURB AND GUTTER
G PROTECT WATER VALVE
H PLACE TREE PROTECTION FENCE AROUND EXISTING TREES
I TREE TO REMAIN IF ROOT SYSTEM IS NOT COMPROMISED
J RELOCATE SWING
K
CONTRACTOR TO FIELD VERIFY EXISTING CHILLED WATER LINES ARE
LOCATED WHERE PROPOSED CHILLED WATER LINES ARE TO BE INSTALLED.
IF SO, NEW CHILLED WATER LINES CAN BE INSTALLED WHEN EXISTING
CHILLED WATER LINES ARE NOT BEING USED DEPENDING ON THE TIME OF
BUILDING 9
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 4
BUILDING 5
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
EASTVIEW DRIVE
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
VETERANS CIRCLE
#1
#2
#3
#4
#5
#6
#7
#8
BUILDING 106
BUILDING 16
BOILER PLANT
CANOPYPAINT
SHOP
BUILDING 15
MAINT.
OPERATIONS
BUILDING 13
MAINT.
OPERATIONS
BUILDING 12
MAINT.
OPERATIONS
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
AREA 1
AREA 2
AREA 3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
OVERVIEW EROSION CONTROL
PLAN
C-100
EROSION CONTROL NOTES:
1. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE REGULATIONS OF THE DEPARTMENT OF VETERAN AFFAIRS AND
THE STATE OF TENNESSEE.
2. LAND DISTURBING ACTIVITIES SHALL NOT COMMENCE UNTIL APPROVAL TO DO SO HAS BEEN RECEIVED FROM ALL GOVERNING
AUTHORITIES.
3. THE CONTRACTOR SHALL STRICTLY ADHERE TO THESE EROSION CONTROL PLANS AND THE STORM WATER POLLUTION
PREVENTION PLAN (SWPPP) DURING CONSTRUCTION.
4. NO LAND DISTURBING ACTIVITIES SHALL BEGIN UNTIL ALL PERIMETER EROSION AND SEDIMENT CONTROL MEASURES HAVE
BEEN INSTALLED.
5. ALL EXPOSED AREAS SHALL BE PLANTED WITHIN 14 DAYS OF FINAL GRADING.
6. SHOULD CONSTRUCTION STOP FOR LONGER THAN 14 DAYS, THE SITE SHALL BE SEEDED AS SPECIFIED (TEMPORARY SEEDING, MULCHING, OR TRACKING).
7. SEDIMENT AND EROSION CONTROL MEASURES SHALL BE INSPECTED BY THE CONTRACTOR AT LEAST ONCE EVERY SEVEN (7)
DAYS AND AFTER EVERY 0.5 INCH RAIN.
8. THESE PLANS SHALL NOT BE CONSIDERED ALL INCLUSIVE AS THE SITE CONTRACTOR SHALL TAKE ALL NECESSARY
PRECAUTIONS TO PREVENT SOIL AND SEDIMENT FROM LEAVING THE SITE. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES WILL BE INSTALLED IF DEEMED NECESSARY BY ONSITE INSPECTIONS BY THE SITE CONTRACTOR.
9. THE CONTRACTOR, AND THEIR SUB-CONTRACTORS, SHALL COMPLY WITH ALL STATE AND LOCAL ORDINANCES THAT APPLY.
10. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE ESTABLISHMENT OF PERMANENT SOIL STABILIZATION.
11. ALL WORK SHALL BE DONE IN STRICT ACCORDANCE WITH THE PROJECT DOCUMENTS.
12. WHEN INSTALLING CHILLED WATER LINES IN PAVED AREAS, PAVEMENT SHALL BE CLEANED OFTEN TO PREVENT VEHICLE
SEDIMENT TRACKING THROUGHOUT THE SITE.
13. ALL STOCKPILES SHALL BE LOCATED ON THESE PLANS WHEN PLACED. STOCKPILES SHALL BE SURROUNDED BY SILT FENCE. IF
STOCKPILES ARE NOT USED FOR 14 DAYS OR MORE, TEMPORARY STABILIZATION THROUGH SEED AND/OR MULCH SHALL BE
APPLIED.
14. ALL SANITARY WASTE FACILITIES, FUEL STORAGE INCLUDING SECONDARY CONTAINMENT, AND CONCRETE WASH OUT AREAS
SHALL BE LOCATED ON THESE PLANS WHEN PLACED ON SITE.
15. EXCAVATING CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVAL OF THE CONCRETE WASHOUT ONCE ALL CONCRETE WORK
ON SITE IS COMPLETE.
16. STABILIZE EARTHEN EMBANKMENTS IMMEDIATELY WITH TEMPORARY OR PERMANENT VEGETATION IN ACCORDANCE WITH
REQUIREMENTS OF THE TENNESSEE BMP MANUAL FOR CONSTRUCTION ACTIVITIES.
17. ALL TEMPORARY EROSION CONTROL MEASURES SHALL BE MAINTAINED TO ENSURE CONTINUED PERFORMANCE OF THEIR
INTENDED FUNCTION.
18. ALL EROSION CONTROL MEASURES ARE DESIGNED FOR THE TWO YEAR - 24 HOUR STORM EVENT.
19. EROSION CONTROL/CONSTRUCTION PHASING SHOWN ON THESE PLANS REPRESENTS THE OPINION OF THE ENGINEER AND IS
NOT INTENDED TO BE A SCHEDULE OR COMPREHENSIVE LIST OF EVENTS. ALL MEASURES MAY NOT BE LISTED AND THOSE LISTED MAY NOT ALL BE REQUIRED. THE CONTRACTOR SHOULD USE DISCRETION TO EVALUATE THE CONSTRUCTION SCOPE AND DETERMINE THE BEST SEQUENCE OF CONSTRUCTION UTILIZING APPROPRIATE SEDIMENT AND EROSION CONTROL
METHODS.
20. PROJECT IS BEING DESIGNED CONCURRENTLY WITH VA STEAM DISTRIBUTION UPGRADES AND AREAS OF COORDINATION HAVE BEEN ESTABLISHED IN THESE DOCUMENTS. CONTRACTOR SHOULD REFER TO THOSE CONSTRUCTION DOCUMENTS FOR
FIELD-COORDINATION PURPOSES TO ALLOW FOR PIPING RIGHT-OF-WAY ALLOWANCES.
EROSION CONTROL/CONSTRUCTION PHASING:
A. CONTRACTOR TO OBTAIN ALL PERMITS AND PERMISSIONS REQUIRED BY TENNESSEE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION (TDEC) .
B. CONSTRUCTION SHALL NOT COMMENCE UNTIL APPROVAL BY ALL GOVERNING AUTHORITIES IS OBTAINED.
C. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE SEDIMENT IS NOT TRACKED ONTO ADJACENT PAVED AREAS.
ADJACENT PAVED AREAS TO BE INSPECTED AT THE END OF EACH WORKING DAY AND ANY SEDIMENT SHALL BE
REMOVED BY THE CONTRACTOR IMMEDIATELY.
D. INSTALL PERIMETER EROSION CONTROL MEASURES, INCLUDING SILT FENCE AND INLET PROTECTION.
E. BEGIN CLEARING AND GRUBBING OPERATIONS. CLEARING AND GRUBBING SHALL BE DONE IN AREAS WHERE
EARTHWORK WILL BE PERFORMED AND ONLY IN AREAS WHERE CONSTRUCTION IS PLANNED TO COMMENCE WITHIN 14
DAYS AFTER CLEARING AND GRUBBING.
F. COMMENCE SITE DEMOLTIION.
G. SEED AND PROTECT EMBANKMENTS FOLLOWING INSTALLATION.
H. INSTALL PROPOSED CHILLED WATER LINES. REPLACE PAVING AND CURBS AS SOON AS POSSIBLE AFTER CONSTRUCTION
COMPLETION IN THE AREA.
I. INLET PROTECTION SHALL BE REPLACED AFTER PAVING OPERATIONS AT ALL INLETS AND BE MAINTAINED UNTIL
CONTRIBUTING AREAS ACHIEVE FINAL STABILIZATION AND/OR ALL POLLUTANT SOURCES ARE ELIMINATED.
J. CARRY OUT FINAL GRADING, SEEDING AND PLANTING IN ALL AREAS. ALL DISTURBED AREAS SHALL BE SEEDED UNLESS
OTHERWISE SPECIFIED WITHIN THE CONSTRUCTION DRAWINGS AND SPECIFICATIONS. AREAS 6:1 AND STEEPER SHALL BE MULCH PROTECTED, WHICH IS TO BE MAINTAINED UNTIL VEGETATION IS THOROUGHLY ESTABLISHED. AREAS
STEEPER THAN 3:1 SHALL RECEIVE EROSION CONTROL BLANKET UNLESS OTHERWISE NOTED.
K. FINAL REMOVAL OF EROSION CONTROL MEASURES MAY ONLY OCCUR ONCE ALL PAVING IS COMPLETED AND ALL
EXPOSED SURFACES ARE STABILIZED.
L. WHEN FINAL STABILIZATION IS COMPLETE, CONTRACTOR TO COORDINATE WITH ENGINEER AND TENNESSEE DEPARTMENT OF ENVIRONMENTAL CONSERVATION (TDEC) TO FILE A NOTICE OF TERMINATION AND ANY OTHER ITEMS
NECESSARY FOR FINAL STABILIZATION.
LEGEND
CHILLED WATER RETURN
PROP. SILT FENCE
CHILLED WATER SERVICE
PROP. INLET PROTECTION
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
EXISTING STORM LINE
PROP. PIPE INLET PROTECTION
BUILDING 4
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
#2
#3
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
M
AT
C H
LI
N
E
AR
EA
M
AT
C H
LI
N
E
AR
EA
113 L.F.
SILT FENCE
52 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
67 L.F.
SILT FENCE
8 L.F.
SILT FENCE
10 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
134 L.F.
SILT FENCE
34 L.F.
SILT FENCE
32 L.F.
SILT FENCE
193 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
60 L.F.
SILT FENCE
223 L.F.
SILT FENCE
31 L.F.
SILT FENCE
134 L.F.
SILT FENCE
PIPE INLET PROTECTION (TYP.)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
EROSION CONTROL PLAN -
AREA 1
C-101
LEGEND
CHILLED WATER RETURN
PROP. SILT FENCE
CHILLED WATER SERVICE
PROP. INLET PROTECTION
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 5
VETERANS CIRCLE
#4
#5
PAVILION
M
AT
C H
LI
N
E
AR
EA
MATCHLINE AREA 3
M
AT
C H
LI
N
E
AR
EA
MATCHLINE AREA 2
MATCHLINE AREA 3
MATCHLINE AREA 1
193 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
60 L.F.
SILT FENCE
223 L.F.
SILT FENCE
303 L.F.
SILT FENCE
28 L.F.
SILT FENCE
29 L.F.
SILT FENCE
78 L.F.
SILT FENCE INLET PROTECTION (TYP.)
14 L.F.
SILT FENCE
42 L.F.
SILT FENCE
39 L.F.
SILT FENCE
396 L.F.
SILT FENCE
26 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
22 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
249 L.F.
SILT FENCE
74 L.F.
SILT FENCE149 L.F.
SILT FENCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
EROSION CONTROL PLAN -
AREA 2
C-102
LEGEND
CHILLED WATER RETURN
PROP. SILT FENCE
CHILLED WATER SERVICE
PROP. INLET PROTECTION
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
#4
#6
#7
#8
MATCHLINE AREA 2
MATCHLINE AREA 3
MATCHLINE AREA 1
MATCHLINE AREA 3
223 L.F.
SILT FENCE
303 L.F.
SILT FENCE
28 L.F.
SILT FENCE
29 L.F.
SILT FENCE
78 L.F.
SILT FENCE INLET PROTECTION (TYP.)
14 L.F.
SILT FENCE
42 L.F.
SILT FENCE
39 L.F.
SILT FENCE
396 L.F.
SILT FENCE
26 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
22 L.F.
SILT FENCE
142 L.F.
SILT FENCE
54 L.F.
SILT FENCE
55 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
156 L.F.
SILT FENCE
41 L.F.
SILT FENCE
57 L.F.
SILT FENCE
5 L.F.
SILT FENCE
75 L.F.
SILT FENCE
INLET PROTECTION (TYP.)
INLET PROTECTION (TYP.)
97 L.F.
SILT FENCE
35 L.F.
SILT FENCE
18 L.F.
SILT FENCE
27 L.F.
SILT FENCE
24 L.F.
SILT FENCE
138 L.F.
SILT FENCE
158 L.F.
SILT FENCE
133 L.F.
SILT FENCE
81 L.F.
SILT FENCE
108 L.F.
SILT FENCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
EROSION CONTROL PLAN -
AREA 3
C-103
LEGEND
CHILLED WATER RETURN
PROP. SILT FENCE
CHILLED WATER SERVICE
PROP. INLET PROTECTION
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
BUILDING 9
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 4
BUILDING 5
BUILDING 6
BUILDING 118
BUILDING 107
BUILDING 116
EASTVIEW DRIVE
EA
ST
M
AI
N
ST
RE
ET
EASTVIEW DRIVE
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
VETERANS CIRCLE
#1
#2
#3
#4
#5
#6
#7
#8
BUILDING 106
BUILDING 16
BOILER PLANT
CANOPYPAINT
SHOP
BUILDING 15
MAINT.
OPERATIONS
BUILDING 13
MAINT.
OPERATIONS
BUILDING 12
MAINT.
OPERATIONS
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
6" CHWR
6" CHWS
6" CHWR
6" CHWS
3" CHWS
3" CHWR
6" CHWS
12" CHWS
16" CHWS
16" CHWR
8" CHWR
8" CHWS
12" CHWR
" C
HW
S
12" CHWR
6" CHWS
6" CHWR
6" CHWS
6" CHWR
12" CHWR
12" CHWS
" C
HW
S
24" CWR
4" CHWS
6" CHWR
6" CHWS
4" CHWR
6" CHWS
6" CHWR
24" CWS
24" CWS
24" CWR
6" CHWR
6" CHWS
8" CHWS
8" CHWR 8" CHWR
8" CHWS
6" CHWS
6" CHWR
3" CHWS
3" CHWR
3" CHWR
3" CHWS
4" CHWS
3" CHWS
3" CHWR
6" CHWS
6" CHWR
6" CHWS
6" CHWR
3" CHWR
3" CHWS
12" CHWS
12" CHWR
LINE-A
LINE-B
LINE-C
LINE-D
LIN
E-B
LINE-B
LINE-D
LIN
E-
D
LINE-D
LIN
E-
E
LIN
E-E
LIN
E-
F
LINE-G
LIN
E-
H
LIN
E-
I
LIN
E-
J
LIN
E-K
LIN
E-
L
12" CHWS
LINE-M
LIN
E-
N
LIN
E-O
LINE-P
LINE-P
LINE-Q
LINE-R
LINE-S
6" CHWR
10" CHWS
10" CHWR LIN
E- T
LINE-U
2" CHWR
2" CHWS
4" CHWR
LIN
E-
P
AREA 1
AREA 2
AREA 3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
OVERVIEW UTILITY PLAN
C-200
SITE UTILITY NOTES:
1. ALL CONSTRUCTION MUST CONFORM TO DEPARTMENT OF VETERANS AFFAIRS, AND STATE OF TENNESSEE STANDARDS.
2. ALL WORK SHALL BE COMPLETED IN ACCORDANCE WITH THE PROJECT SPECIFICATIONS.
3. CONTRACTOR SHALL HAVE APPROVAL OF ALL GOVERNING AGENCIES AND PROVIDERS HAVING JURISDICTION OVER THE
SYSTEM PRIOR TO INSTALLATION.
4. CONTRACTOR SHALL COORDINATE WITH UTILITY PROVIDERS AND THE ENGINEER FOR REVIEW AND APPROVAL PRIOR TO
MAKING CONNECTIONS TO THEIR SYSTEMS.
5. THE CONTRACTOR IS RESPONSIBLE FOR ALL UTILITY TAP AND TIE ON FEES REQUIRED.
6. LOCATION OF EXISTING SITE UTILITIES SHALL BE VERIFIED BY THE CONTRACTOR (TENNESSEE 811) AND AS NECESSARY BY
CONTACTING UTILITIES DIRECTLY.
7. THE CONTRACTOR IS RESPONSIBLE FOR ANY DAMAGE TO EXISTING STRUCTURES AND/OR UTILITIES DURING
CONSTRUCTION.
8. THE CONTRACTOR SHALL PROVIDE A 2-FT x 2-FT x 6-IN THICK CONCRETE APRON AROUND ALL CLEANOUTS, VALVES, AND
METERS OUTSIDE OF BUILDING.
9. ALL TRENCHING, PIPE LAYING, AND BACKFILLING SHALL BE IN ACCORDANCE WITH FEDERAL OSHA REGULATIONS.
10. ALL PROPOSED UTILITY CROSSINGS SHALL BE VERIFIED BY THE CONTRACTOR. CONTRACTOR SHALL MAINTAIN A MINIMUM
OF 18-IN VERTICAL SEPARATION BETWEEN UTILITY CROSSINGS AT NO COST TO THE GOVERNMENT.
11. CONTRACTOR SHALL FURNISH ALL NECESSARY APPURTENANCES FOR UTILITY CONNECTIONS.
USE EXTREME CAUTION WHEN EXCAVATING UTILITIES UNDERGROUND UTILITIES. UNDERGROUND UTILITIES ILLUSTRATED ARE
APPROXIMATE AND ARE SHOWN TO ALERT CONTRACTORS TO THEIR PRESENCE. CONTRACTOR SHALL LOCATE/VERIFY UTILITIES BY HAND TOOL EXCAVATION. CONTRACTOR SHALL MARK AND MAINTAIN ALL EXISTING UTILITIES, INCLUDING OWNER'S FIBER OPTIC CABLE, FOR THE DURATION OF THE PROJECT TO MINIMIZE POTENTIAL FOR DAMAGE AND DISRUPTION
OF EXISTING SERVICES.
12. PROJECT IS BEING DESIGNED CONCURRENTLY WITH VA STEAM DISTRIBUTION UPGRADES AND AREAS OF COORDINATION HAVE BEEN ESTABLISHED IN THESE DOCUMENTS. CONTRACTOR SHOULD REFER TO THOSE CONSTRUCTION DOCUMENTS
FOR FIELD-COORDINATION PURPOSES TO ALLOW FOR PIPING RIGHT-OF-WAY ALLOWANCES.
LEGEND
CHILLED WATER RETURN
GATE VALVE
CHILLED WATER SERVICE
REDUCER
PIPE BENDS
X" CHWS
X" CHWR
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
BUILDING 4
BO
IL
ER
P
LA
NT
R
OA
D
VE
TE
RA
NS
C
IR
CL
E
NORTHVIEW DRIVE
#2
#3
BUILDING 11
BUILDING 17
PAVILION
BUILDING 10
6" CHWR
6" CHWS
" C
HW
S
12" CHWR
4" CHWS
4" CHWR
8" CHWR
8" CHWS
3" CHWS
3" CHWR
3" CHWR
3" CHWS
4" CHWS
3" CHWS
3" CHWR
12" CHWS
12" CHWR
LINE-A
LINE-B
LINE-C
LINE-D
LIN
E-B
LINE-B
LIN
E-
E
LINE-G
LIN
E-
H
LIN
E-
I
10" CHWS
10" CHWR
LINE-U
2" CHWR
2" CHWS
4" CHWR
M
AT
C H
LI
N
E
AR
EA
AR
EA
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
UTILITY PLAN - AREA 1
C-201
LEGEND
CHILLED WATER RETURN
GATE VALVE
CHILLED WATER SERVICE
REDUCER
PIPE BENDS
X" CHWS
X" CHWR
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
EXISTING STORM LINE
UTILITY PLAN KEY
VALVES TO BE PLACED IN VAULT WITH LINE TEE. VALVES AND TEES ON
NEW ISOLATION VALVES AT EACH BUILDING TEE - SEE MECHANICAL PLANS
KEY DESCRIPTION
A
B
C
D
PLAN ARE OVERSIZED FOR CLARITY ON PLANS. CONTRACTOR TO
BEGIN DIRECTIONAL BORE OF WALKWAY BUILDING (COORDINATE WITH
STRUCTURAL ENGINEER FOR ANY REQUIREMENT FOR BORING
UNDERNEATH STRUCTURE).
END DIRECTIONAL BORE OF WALKWAY BUILDING (COORDINATE WITH
STRUCTURAL ENGINEER FOR ANY REQUIREMENT FOR BORING
UNDERNEATH STRUCTURE).
COORDINATE WITH DESIGN TEAM ON PLACEMENT OF VAULT WITH RESPECT
TO EXISTING UTILITIES IN THE AREA. SEE MECHANICAL PLANS FOR VAULT DETAILS.
E
PROPOSED CHILLED WATERLINES THAT REQUIRE DEMOLITION OF EXISTING
CHILLED WATERLINES MUST BE INSTALLED WHEN EXISTING CHILLED WATER
LINES ARE NOT BEING USED DEPENDING ON THE TIME OF YEAR PER VA
UTILITY SERVICE SCHEDULE.
BUILDING 2
BUILDING 1
BUILDING 120
BUILDING 117
BUILDING 105BUILDING 3
BUILDING 5
VETERANS CIRCLE
#4
#5
PAVILION
6" CHWR
6" CHWS
12" CHWS
12" CHWR
" C
HW
S
12" CHWR
12" CHWR
12" CHWS
" C
HW
S
6" CHWR
6" CHWS
8" CHWS
8" CHWR 8" CHWR
8" CHWS
6" CHWS
6" CHWR
3" CHWS
3" CHWR
6" CHWS
6" CHWR
6" CHWS
6" CHWR
12" CHWS
12" CHWR
LINE-D LINE-D
LIN
E-
D
LINE-D
LIN
E-
E
LIN
E-E
LIN
E-
F
LINE-G
LIN
E-
H
LIN
E-
I
LIN
E-
J
LIN
E-K
LIN
E-
L
12" CHWS
LINE-M
LIN
E-
N
10" CHWS
10" CHWR LIN
E- T
AR
EA
AREA 3
M
AT
C H
LI
N
E
AR
EA
MATCHLINE AREA 2
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
NOT APPLICABLE
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
AJP - REPLACED CHILLED
WATER LOOP
MURFREEBORO CAMPUS, 3400 LEBANNON
ROAD, MURFREESBORO, TN 37129
VA #:626A4-22-211
N/A
Project Director
01.19.2024 CMM RMT
100% CONSTRUCTION
DOCUMENTS
# Revisions Date
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.com
01/19/2024
UTILITY PLAN - AREA 2
C-202
LEGEND
CHILLED WATER RETURN
GATE VALVE
CHILLED WATER SERVICE
REDUCER
PIPE BENDS
X" CHWS
X" CHWR
EXISTING U.G. TELEPHONE
EXISTING U.G. ELECTRIC
EXISTING WATERLINE
EXISTING STEAM LINE
EXISTING SANITARY
EXISTING CHILLED WATER
EXISTING STORM LINE
UTILITY PLAN KEY
VALVES TO BE PLACED IN VAULT WITH LINE TEE. VALVES AND TEES ON
NEW ISOLATION…