2-26-31 Part 2 Project Manual 2026-01-23.pdf

PDF 4 MB Posted

Attached to
Beyer EC Restroom Renovation and Plumbing Upgrades
Solicitation number
IFB No. 26-31
Issued by
Washington County, Illinois

About this file

This is a Project Manual for the Beyer Early Childhood Center Toilet Room Renovations, issued by Rockford Public School District #205 in Rockford, Illinois under Invitation for Bid (IFB) No. 26-31. The project, with LDG Project No. 2025-180 and RPS Project No. 2607, was issued for bidding and construction on January 22, 2026, and is located at 333 15th Avenue, Rockford, Illinois 61102. The design was prepared by Larson & Darby Group Architecture-Engineering-Interiors (Illinois Design Firm Registration Number: 184-000280). The scope of work encompasses comprehensive toilet room renovations including selective demolition, installation of new plumbing fixtures and piping systems, HVAC modifications, electrical work, finishes including gypsum board, tiling, painting, and various specialties such as plastic toilet compartments, solid surfacing countertops, and door hardware. The Project Manual includes detailed specifications organized into multiple divisions covering general requirements, existing conditions, wood and plastic composites, thermal protection, openings, finishes, specialties, furnishings, plumbing, HVAC, electrical, communications, and electronic safety systems.

The contract requires contractors to submit a Schedule of Values breaking down the contract sum by specification section at least ten days before the initial Application for Payment, with payment applications submitted on AIA Document G702/703 according to the established schedule. Contractors must provide three copies of each application with mechanic's lien waivers from subcontractors and suppliers covering the construction period of the previous application. The project requires a comprehensive Gantt-chart-type Construction Schedule within 30 days of the Notice of Award, with monthly updates reflecting actual progress and including a recovery schedule if work falls 14 or more calendar days behind schedule. Activities should not exceed 20 days in duration unless specifically authorized by the Architect, and procurement activities for long lead items must be identified separately with review and resubmittal times incorporated into the schedule. The contract mandates coordination drawings where installation is not completely indicated on Shop Drawings, particularly for mechanical, plumbing, fire-protection, electrical systems, and structural penetrations, with the Contractor bearing full responsibility for coordination details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

BEYER EARLY CHILDHOOD CENTER TOILET ROOM RENOVATIONS

ROCKFORD PUBLIC SCHOOL DISTRICT #205

ROCKFORD, ILLINOIS

IFB No. 26-31

PROJECT MANUAL

FOR

333 15TH AVE.

ROCKFORD, ILLINOIS 61102

LDG PROJECT NO.: 2025-180

RPS PROJECT NO.: 2607

RPS IFB #: 26-31

DATE: Issued for Bidding and Construction – January 22, 2026

BY:

LARSON & DARBY GROUP ARCHITECTURE-ENGINEERING–INTERIORS

4949 HARRISON AVENUE, SUITE 100 ROCKFORD, ILLINOIS 61108

Illinois Design Firm Registration Number: 184-000280

ANDREW MACKLIN

Licensed Architect

LIC. EXPIRES: 11/30/2026

Date

Registered Professional Engineer

LIC. EXPIRES: 11/30/2025

Date

Fire Suppression: Work of Division 21 – Fire Suppression is the engineering responsibility of the Contractor selected by Owner for this Work.

© 2026, LARSON & DARBY GROUP

BEYER EARLY CHILDHOOD CENTER TOILET ROOM RENOVATION

LDG 2025-180 PROJECT MANUAL TABLE OF CONTENTS TOC - 1

PROJECT MANUAL TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING DOCUMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

• Bidding and Contracting Requirements by RPS 205

CSI 1.5c Substitution Request

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 20 00 Price And Payment Procedures

01 31 00 Project Management and Coordination

01 32 00 Construction Progress Documentation

AIA C106 Digital Data Licensing Agreement

01 35 16 Alteration Project Procedures

01 50 00 Temporary Facilities And Controls

01 60 00 Product Requirements

CSI 13.1a Substitution Request

01 70 00 Execution And Closeout Requirements

DIVISION 02 - EXISTING CONDITIONS

02 41 19 Selective Demolition

DIVISION 06 – WOOD, PLASTICS, COMPOSITES

06 10 53 Miscellaneous Rough Carpentry

06 41 16 Plastic Laminate Clad Architectural Cabinets

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

07 92 19 Acoustical Joint Sealants

DIVISION 08 - OPENINGS

08 12 13 Hollow Metal Frames

08 14 16 Flush Wood Doors

08 31 13 Access Doors and Frames

08 71 00 Door Hardware

DIVISION 09 - FINISHES

09 22 16 Non-structural Metal Framing

09 29 00 Gypsum Board

09 30 00 Tiling

09 51 13 Acoustical Panel Ceilings

09 65 13 Resilient Base And Accessories

09 91 24 Interior Painting

LDG 2025-180 PROJECT MANUAL TABLE OF CONTENTS TOC - 2

09 96 00 High-performance Coatings

DIVISION 10 – SPECIALTIES

10 21 13.19 Plastic Toilet Compartments

10 28 00 Toilet Accessories

DIVISION 12 – FURNISHINGS

12 36 61.16 Solid Surfacing Countertops

DIVISION 22 - PLUMBING

22 05 00 Common Work Results for Plumbing

22 05 23 General Duty Valves for Plumbing Piping

22 05 29 Hangers and Supports for Plumbing Piping and Equipment

22 05 53 Identification for Plumbing Piping and Equipment

22 07 19 Plumbing Piping Insulation

22 11 16 Domestic Water Piping

22 11 19 Domestic Water Piping Specialties

22 13 16 Sanitary Waste and Vent Piping

22 13 19 Domestic Water Piping Specialties

22 13 19.13 Sanitary Drains

22 34 00 Fuel-Fired Domestic-Water Heaters

22 42 00 Commercial Plumbing Fixtures

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 53 Identification for HVAC Piping and Equipment

23 05 93 Testing, Adjusting, and Balancing for HVAC

23 07 13 Duct Insulation

23 09 23 Direct Digital Control (DDC) System for HVAC

23 09 93 Sequence of Operations for HVAC Controls

23 11 23 Facility Natural Gas Piping

23 31 13 Metal Ducts

23 33 00 Air Duct Accessories

23 36 00 Air Terminal Units

23 37 13 Diffusers, Registers, and Grilles

DIVISION 26 - ELECTRICAL

26 05 00 Common Work Results For Electrical

26 05 19 Low-Voltage Electrical Power Conductors and Cables

26 05 23 Control-Voltage Electrical Power Cables

26 05 26 Grounding and Bonding for Electrical Systems

26 05 29 Hangars and Supports for Electrical Systems

26 05 33 Raceway and Boxes for Electrical Systems

26 05 53 Identification for Electrical Systems

26 09 23 Lighting Control Devices

26 27 26 Wiring Devices

LDG 2025-180 PROJECT MANUAL TABLE OF CONTENTS TOC - 3

26 28 16 Enclosed Switches and Circuit Breakers

26 51 19 LED Interior Lighting

26 52 19 Emergency and Exit Lighting

DIVISION 27 - COMMUNICATIONS

27 15 00 Communications Horizontal Cabling

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 13 Conductors and Cables for Electronic Safety and Security

END OF TABLE OF CONTENTS

© Copyright 2017, CSI, 110 South Union St., Suite 100, Alexandria, VA 22314

Page ___ of ___ Form Version: October 2017 CSI Form 1.5C

SUBSTITUTION

REQUEST

(During the Bidding/Negotiating Stage)

Project:

To:

Re:

Substitution Request Number:

From:

Date:

A/E Project Number:

Contract For:

Specification Title:

Section: Page:

Description:

Article/Paragraph:

Proposed Substitution:

Manufacturer: Address: Phone:

Trade Name: Model No.:

Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.

Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.

The Undersigned certifies:

Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

Same warranty will be furnished for proposed substitution as for specified product.

Same maintenance service and source of replacement parts, as applicable, is available.

Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

Proposed substitution does not affect dimensions and functional clearances.

Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.

Submitted by:

Signed by:

Firm:

Address:

Telephone:

A/E’s REVIEW AND ACTION

☐ Substitution approved - Make submittals in accordance with Specification Section 01 33 00 Submittal Procedures.

☐ Substitution approved as noted - Make submittals in accordance with Specification Section 01 33 00 Submittal Procedures.

☐ Substitution rejected - Use specified materials.

☐ Substitution Request received too late - Use specified materials.

Signed by: Date:

Supporting Data Attached: ☐ Drawings ☐ Product Data ☐ Samples ☐ Tests ☐ Reports ☐

LDG 2025-180 PRICE AND PAYMENT PROCEDURES 01 20 00 - 1

SECTION 01 20 00 - PRICE AND PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 CONTRACT MODIFICATION PROCEDURES

A. On Owner's approval of a proposal from Contractor on AIA Document G709, Architect will issue a Change Order on AIA Document G701, for all changes to the Contract Sum or the Contract Time.

B. When Owner and Contractor disagree on the terms of a proposal, Architect may issue a Construction Change Directive on AIA Document G714, instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order. Construction Change Directive will contain a description of the change and designate the method to be followed to determine changes to the Contract Sum or the Contract Time.

1.2 PAYMENT PROCEDURES

A. Submit a Schedule of Values at least 10 days before the initial Application for Payment. Break down the Contract Sum into at least one line item for each Specification Section in the Project Manual table of contents. Coordinate the Schedule of Values with Contractor's Construction Schedule.

1. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

2. Provide separate line items in the Schedule of Values for initial cost of materials and for total installed value of that part of the Work.

3. Owner may require additional breakdown of cost to align with different funding sources.

Contractor shall coordinate the schedule of values with the Owner prior to first Application for Payment.

B. Submit 3 copies of each application for payment on AIA Document G702/703, according to the schedule established in Owner/Contractor Agreement.

1. With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

2. Submit final Application for Payment after completion of Project closeout procedures with release of liens and supporting documentation.

a. Include consent of surety to final payment on AIA Document G707 and insurance certificates.

b. Submit final meter readings for utilities, a record of stored fuel, and similar data as of the date of Substantial Completion.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 01 20 00

LDG 2025-180 PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Project meetings.

B. Related Requirements:

1. Section 01 73 00 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.

Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.3 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

LDG 2025-180 PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2

1.4 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within plenums to accommodate layout of light fixtures and other components indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Review: Architect will review coordination drawings to confirm that, in general, the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make suitable modifications and resubmit.

1.5 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Owner name.

2. Owner's Project number.

3. Name of Architect.

4. Architect's Project number.

5. Date.

6. Name of Contractor.

7. RFI number, numbered sequentially.

LDG 2025-180 PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3

8. RFI subject.

9. Specification Section number and title and related paragraphs, as appropriate.

10. Drawing number and detail references, as appropriate.

11. Field dimensions and conditions, as appropriate.

12. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract

Time or the Contract Sum, Contractor shall state impact in the RFI.

13. Contractor's signature.

14. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: AIA Document G716.

D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 01 26 00 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the

Contract Sum, notify Architect in writing within five days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1.6 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Use of Architect's Digital Data Files: Digital data files of Architect's CAD drawings may be provided by Architect for Contractor's use during construction.

1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.

LDG 2025-180 PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4

2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.

3. Contractor shall execute a data licensing agreement in the form of AIA Document C106 Digital Data Licensing Agreement.

a. Subcontractors, and other parties granted access by Contractor to Architect's digital data files shall execute a data licensing agreement in the form of AIA Document C106.

B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.7 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

B. Progress Meetings: Conduct progress meetings at regular intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site use.

8) Temporary facilities and controls.

9) Progress cleaning.

10) Quality and work standards.

11) Status of correction of deficient items.

12) Field observations.

13) Status of RFIs.

14) Status of Proposal Requests.

15) Pending changes.

16) Status of Change Orders.

LDG 2025-180 PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5

17) Pending claims and disputes.

18) Documentation of information for payment requests.

4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

LDG 2025-180 CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1

SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

2. Construction schedule updating reports.

3. Site condition reports.

1.2 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. PDF file.

B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

C. Construction Schedule Updating Reports: Submit with Applications for Payment.

D. Site Condition Reports: Submit at time of discovery of differing conditions.

1.3 COORDINATION

A. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.4 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Computer Scheduling Software: Prepare schedules using current version of a program that is capable of managing construction schedules.

B. Time Frame: Extend schedule from date established for the Notice of Award to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

C. Activities: Treat each floor or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect.

2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

3. Submittal Review Time: Include review and resubmittal times indicated in Section 01 33 00 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with submittal schedule.

LDG 2025-180 CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2

4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion.

5. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.

D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase.

2. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated in Section 01 10 00 "Summary." Delivery dates indicated stipulate the earliest possible delivery date.

3. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Limitations of continued occupancies.

c. Uninterruptible services.

d. Partial occupancy before Substantial Completion.

e. Use-of-premises restrictions.

f. Provisions for future construction.

E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.

F. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:

1. Unresolved issues.

2. Unanswered Requests for Information.

3. Rejected or unreturned submittals.

4. Notations on returned submittals.

5. Pending modifications affecting the Work and the Contract Time.

G. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate final completion percentage for each activity.

H. Recovery Schedule: When periodic update indicates the Work is 14 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule. Indicate changes to working hours, working days, crew sizes, equipment required to achieve compliance, and date by which recovery will be accomplished.

I. Distribution: Distribute copies of approved schedule to Architect, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

LDG 2025-180 CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 3

1.5 GANTT-CHART SCHEDULE REQUIREMENTS

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice of Award.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1.6 REPORTS

A. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information.

Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 32 00

)")'*+,-./#%'01234'5'6217&'89:;<=>?@ABACDDEAFGHACDIJAK;AL?MANOM<=PFGAQGR@=@S@MA9TAN<P?=@MP@R&')UU'V$WX%Y'V/Y/VZ/[&'\)]̂ "̂_̀'aX$Y')")b''*+,-./#%'$Y' cV+%/,%/['de'f&g&'0+ceV$WX%'hij'i#['"#%/V#i%$+#iU'aV/i%$/Y&'f#i-%X+V$k/['V/cV+[-,%$+#'+V'[$Y%V$d-%$+#'+l'%X$Y')")b''*+,-./#%m'+V'i#e'c+V%$+#'+l'$%m' .ie'V/Y-U%'$#'Y/Z/V/',$Z$U'i#[',V$.$#iU'c/#iU%$/Ym'i#['j$UU'd/'cV+Y/,-%/['%+'%X/'.in$.-.'/n%/#%'c+YY$dU/'-#[/V'%X/'Uij&AL?=RAH9PSOMG@AoFRA:<9HSPMHAK;A NQNAR9T@oF<MAF@AIDpJqpIEA9GADrsICsCDIEASGHM<At<HM<Au9vwxIICEyqEyzIAo?=P?AM{:=<MRA9GADIsDIsCDIx|AFGHA=RAG9@AT9<A<MRF}MvA fY/V'̂+%/ỲAAA ~IIqwJyxIqr�A

1'

)**"a"�̂ g')̂ *'*�h�a"�̂ g̀''

L?MAFS@?9<A9TA@?=RAH9PSOMG@A?FRA

FHHMHA=GT9<OF@=9GAGMMHMHAT9<A=@RA

P9O:}M@=9GvAL?MAFS@?9<AOF;AF}R9A

?F�MA<M�=RMHA@?MA@M{@A9TA@?MA9<=>=GF}A

NQNAR@FGHF<HAT9<OvANGA��������������

�����������������@?F@AG9@MRAFHHMHA

=GT9<OF@=9GAFRAoM}}AFRA<M�=R=9GRA@9A

@?MAR@FGHF<HAT9<OA@M{@A=RAF�F=}FK}MA

T<9OA@?MAFS@?9<AFGHAR?9S}HAKMA

<M�=MoMHvANA�M<@=PF}A}=GMA=GA@?MA}MT@A

OF<>=GA9TA@?=RAH9PSOMG@A=GH=PF@MRA

o?M<MA@?MAFS@?9<A?FRAFHHMHA

GMPMRRF<;A=GT9<OF@=9GAFGHAo?M<MA

@?MAFS@?9<A?FRAFHHMHA@9A9<AHM}M@MHA

T<9OA@?MA9<=>=GF}ANQNA@M{@vA

L?=RAH9PSOMG@A?FRA=O:9<@FG@A}M>F}A

P9GRM�SMGPMRvA89GRS}@F@=9GAo=@?AFGA

F@@9<GM;A=RAMGP9S<F>MHAo=@?A<MR:MP@A

@9A=@RAP9O:}M@=9GA9<AO9H=T=PF@=9GvA

A

¦§̈©ª«¬®̄©°̈°±²³́©²µ̄©¶«̈³·©²̈©µ́²¬̧¹© º�

»���� ¡��¼�¥ ¢� ¥�¤��£ £¤½�¾£½£ �¿�¾� ��ÀÁÂ¥�¤��£ £¤½�¼�¥ ¢ÁÃÄ��

¦Å²¶́ ©̄²¬́®®©²̈©±«̈³²±³©°̈Æ«¬¶²³°«̈ ©̄°̈±ÇȰ̈É©́Ḉ±³¬«̈°±©²¬́®®́®¹©

Ê�¥��¤��¤��¾�¥Ë¢�Ì¥�ÍÎ�

ÏÐÏÐ�Ñ�¥¥£��¤�ÒÓ�¤Í�Ô�ÕÍ£ ��Ö××�

Ø�ÙÚ��¥�Ô�Û¿¿£¤�£��ÜÖÖ×Ý�

�¤�� ¡��¼�¥ ¢�¥�Ù�£Ó£¤½� ¡��¾£½£ �¿�¾� ��ÀÁØ�Ù�£Ó£¤½�¼�¥ ¢ÁÃÄ��

¦Å²¶́ ©̄²¬́®®©²̈©±«̈³²±³©°̈Æ«¬¶²³°«̈ ©̄°̈±ÇȰ̈É©́Ḉ±³¬«̈°±©²¬́®®́®¹©

��¥� ¡����¿¿�Þ£¤½�¼¥�ß�Ù Ä� ¦Å²¶́©²̈©Ç«±²³°«̈©«¬©²¬́®®¹© ¡��Â¥�¤��£ £¤½�¼�¥ ¢��¤��Ø�Ù�£Ó£¤½�¼�¥ ¢��½¥��������¿¿�Þ�à�

�ºá��âã��� ä á�å�

� ������á�æ�âçäåäâ�å� ���å�äååäâ��âã��ä�ä �á��� �� áä ��å�� â��ä äâ�å�

è� áä��åä���ã���â��â
é���â�æ��å�

äâ�� ê� �ä�ä �á��� ä á�� ���������á�æ�âçäåäâ�å� ë� ì �¡��ÎÍ¥Î������� ¡£��Ò½¥����¤ �£�� ��½¥�¤ ���¿£Ù�¤����¥��� ¡��Â¥�¤��£ £¤½�¼�¥ ¢� �� ¡��Ø�Ù�£Ó£¤½�¼�¥ ¢���¥� ¡��Ø�Ù�£Ó£¤½�¼�¥ ¢í��Í������¾£½£ �¿�¾� ���¤� ¡��¼¥�ß�Ù Ô��¤�� �� �� ���¥ ¡� ¡��¿£Ù�¤��� �¥��à�� ë� ì��¡£��Ò½¥����¤ �£�� ¡���¤ £¥���¤��£¤ �½¥� ����½¥����¤ �Ë� Þ��¤� ¡��Î�¥ £��à�îïÙ�Î � ����Î�Ù£�£Ù�¿¿¢��� ���¥ ¡�¡�¥�£¤Ô� ¡£��Ò½¥����¤ ������¤� �Ù¥�� ���¤¢�� ¡�¥�Ù�¤ ¥�Ù Í�¿� ¥�¿� £�¤�¡£Î�Ë� Þ��¤� ¡��Î�¥ £��à� ë� ì��ð�¥�ÎÍ¥Î�������� ¡£��Ò½¥����¤ Ô� ¡�� �¥��¾£½£ �¿�¾� ��£�����£¤��� ��£¤Ù¿Í����¤¿¢� ¡����£ ����£��¤ £�£���£¤�Ò¥ £Ù¿��ñ�Ë�¿�Þà�

��������������������������� ! "##$ %&' "#() *� +�, -.,��/%& 0&1���2�, �3 -�/���,/�1���44�5�67�8�5�8�59�:��;�<=�=>?�@7�8����A�� �����8� B5

�����:�CD�E�F���

BD5�67��GHI�H�:�����5�H��

�H4�@5�H���8��E�H��7 5�J�:�5�B5 5�:�8�5�C��� K��7�8����A�� ���L� 5�H�D�B 5�� K���L�

HD�5�8�4�����8�9�5����9�4�H�:��5�

��H4�B��H4���8L�H�:�I�44�C��B5 8�����:�� ��7��

HM�

��M�����B

88�C4����:�5��7��4HI� +��1 '�/2.,&� N%1 ���'2/,' *�

-0- 1�3�N%�, %� (#O)PO($ �& #QR("R"#($ 2&',� S�',� T�UVW(("$XP$XY( N��/� ,Z���,1 �& #(R#(R"#(W[ %&' �1 &�� 3�� �,1%\,U E8�5�=

��8? ]((PV)XW(PQ̂

_̀abcbàdefghijfkhlm�nhohklm�nlkl�hp�ijghfji�lp�nhohklm�nlkl�qefklhfhfo�qefghijfkhlm�er�stphfjpp�ureurhjklrv� hfgerwlkhef�kxlk�kxj�yrlfpwhkkhfo�zlrkv�ijphoflkjp�lfi�qmjlrmv�wlr{p�lp�|qefghijfkhlm}|� _̀�ba�yxj�yrlfpwhkkhfo�zlrkv�orlfkp�ke�kxj��jqjh�hfo�zlrkv�l�fefj�qmtph�j�mhwhkji�mhqjfpj�ke�tpj�kxj�nhohklm�nlkl� hijfkhghji�hf��rkhqmj���pemjmv�lfi�j�qmtph�jmv�ke�ujrgerw�pjr�hqjp�ger��er�qefpkrtqkhef�eg��kxj�zre�jqk�hf�lqqerilfqj� �hkx�kxj�kjrwp�lfi�qefihkhefp�pjk�gerkx�hf�kxhp��orjjwjfk}�� _̀�b��yxj�krlfpwhpphef�eg�nhohklm�nlkl�qefpkhktkjp�l��lrrlfkv�sv�kxj�yrlfpwhkkhfo�zlrkv�ke�kxj��jqjh�hfo�zlrkv�kxlk� kxj�yrlfpwhkkhfo�zlrkv�hp�kxj�qeuvrhoxk�e�fjr�eg�kxj�nhohklm�nlkl��er�ekxjr�hpj�xlp�ujrwhpphef�ke�krlfpwhk�kxj�nhohklm� nlkl�ke�kxj��jqjh�hfo�zlrkv�ger�hkp�tpj�ef�kxj�zre�jqk�hf�lqqerilfqj��hkx�kxj�kjrwp�lfi�qefihkhefp�eg�kxhp��orjjwjfk}� _̀�bc��g�kxj�yrlfpwhkkhfo�zlrkv�krlfpwhkp�defghijfkhlm�nhohklm�nlkl��kxj�krlfpwhpphef�eg�ptqx�defghijfkhlm�nhohklm� nlkl�qefpkhktkjp�l��lrrlfkv�ke�kxj��jqjh�hfo�zlrkv�kxlk�kxj�yrlfpwhkkhfo�zlrkv�hp�ltkxerh�ji�ke�krlfpwhk�kxj� defghijfkhlm�nhohklm�nlkl}��g�kxj��jqjh�hfo�zlrkv�rjqjh�jp�defghijfkhlm�nhohklm�nlkl��kxj��jqjh�hfo�zlrkv�pxlmm�{jju� kxj�defghijfkhlm�nhohklm�nlkl�pkrhqkmv�qefghijfkhlm�lfi�pxlmm�fek�ihpqmepj�hk�ke�lfv�ekxjr�ujrpef�er�jfkhkv�j�qjuk�lp�pjk� gerkx�hf��jqkhef��}�}�}� _̀�bcba�yxj��jqjh�hfo�zlrkv�wlv�ihpqmepj�kxj�defghijfkhlm�nhohklm�nlkl�lp�rj�thrji�sv�ml��er�qetrk�erijr��hfqmtihfo� l�ptsuejfl�er�ekxjr�gerw�eg�qewutmperv�mjolm�ureqjpp�hpptji�sv�l�qetrk�er�oe�jrfwjfklm�jfkhkv}�yxj��jqjh�hfo�zlrkv� wlv�lmpe�ihpqmepj�kxj�defghijfkhlm�nhohklm�nlkl�ke�hkp�jwumevjjp��qefptmklfkp�er�qefkrlqkerp�hf�erijr�ke�ujrgerw� pjr�hqjp�er��er{�pemjmv�lfi�j�qmtph�jmv�ger�kxj�zre�jqk��ure�hiji�kxepj�jwumevjjp��qefptmklfkp�lfi�qefkrlqkerp�lrj� pts�jqk�ke�kxj�rjpkrhqkhefp�ef�kxj�ihpqmeptrj�lfi�tpj�eg�defghijfkhlm�nhohklm�nlkl�lp�pjk�gerkx�hf�kxhp��orjjwjfk}�� _̀�b�̀yxj�yrlfpwhkkhfo�zlrkv�rjklhfp�hkp�rhoxkp�hf�kxj�nhohklm�nlkl}��v�krlfpwhkkhfo�kxj�nhohklm�nlkl��kxj�yrlfpwhkkhfo� zlrkv�iejp�fek�orlfk�ke�kxj��jqjh�hfo�zlrkv�lf�lpphofwjfk�eg�kxepj�rhoxkp��fer�iejp�kxj�yrlfpwhkkhfo�zlrkv�qef�jv�ke� kxj��jqjh�hfo�zlrkv�lfv�rhoxk�hf�kxj�pegk�lrj�tpji�ke�ojfjrlkj�kxj�nhohklm�nlkl}�� _̀�b�̀ye�kxj�gtmmjpk�j�kjfk�ujrwhkkji�sv�ml���kxj��jqjh�hfo�zlrkv�pxlmm�hfijwfhgv�lfi�ijgjfi�kxj�yrlfpwhkkhfo�zlrkv� grew�lfi�lolhfpk�lmm�qmlhwp�lrhphfo�grew�er�rjmlkji�ke�kxj��jqjh�hfo�zlrkv p�weihghqlkhef�ke��er�tfmhqjfpji�tpj�eg��kxj� nhohklm�nlkl}�� ~������̀c̀`̀�������̀����������̀ yxj�ulrkhjp�lorjj�ke�kxj�gemme�hfo�qefihkhefp�ef�kxj�mhwhkji�mhqjfpj�orlfkji�hf��jqkhef��}�¡�� ¢£¤¥¤¦§̈¦©ª«§¬®̄¤°§ª¬§¬¦°¤¬±¤ª²°§¥³³©±¥̈©¦§¤ª§¤̄¦§́¦±¦µ²®§¶¥¬¤·̧°§¹°¦§ªº§¤̄¦§»®¤¥©§»¥¤¥¼§¬¦½¹¬¦¾¦²¤°§ºª¬§¿¥¤¥§

ºª¬¾¥¤¼§¤¬¥²°¾°°ª²§¾¦¤̄ª¿§ª¬§ª¤̄¦¬§±ª²¿¤ª²°§ª²§¿¥¤¥§¤ª§̈¦§¤¬¥²°¾¤¤¦¿ÀÁ§

~������̀�̀`̀���������̀���̀��̀��Â��̀���Ã���~����̀ yxj��jqjh�hfo�zlrkv�lorjjp�ke�ulv�kxj�yrlfpwhkkhfo�zlrkv�kxj�gemme�hfo�gjj�er�ekxjr�qewujfplkhef�ger�kxj��jqjh�hfo� zlrkv p�tpj�eg�kxj�nhohklm�nlkl¡� ¢£¤¥¤¦§¤̄¦§º¦¦¼§²§¿ª©©¥¬°¼§ª¬§ª¤̄¦¬§¾¦¤̄ª¿§̈·§«̄±̄§¤̄¦§́¦±¦µ²®§¶¥¬¤·§«©©§±ª¾³¦²°¥¤¦§¤̄¦§Ä¬¥²°¾¤¤²®§¶¥¬¤·§ºª¬§ ¤̄¦§́¦±¦µ²®§¶¥¬¤·̧°§¹°¦§ªº§¤̄¦§»®¤¥©§»¥¤¥ÀÁ§ yxj�zlrkhjp�lorjj�kxlk�kxj�gemme�hfo�hkjwp�qefpkhktkj�kxj�nhohklm�nlkl�pts�jqk�ke�kxj�mhqjfpj�orlfkji�hf��jqkhef��}�¡̀ ¢Å¿¦²¤º·§̈¦©ª«¼§²§¿¦¤¥©¼§¤̄¦§²ºª¬¾¥¤ª²§±¬¦¥¤¦¿§ª¬§°¤ª¬¦¿§²§¿®¤¥©§ºª¬¾§¤̄¦§³¥¬¤¦°§²¤¦²¿§¤ª§̈¦§°¹̈Ʀ±¤§¤ª§¤̄°§

Ç®¬¦¦¾¦²¤ÀÁ§

��������������������������� ! "##$ %&' "#() *� +�, -.,��/%& 0&1���2�, �3 -�/���,/�1���44�5�67�8�5�8�59�:��;�<=�=>?�@7�8����A�� �����8� B5

�����:�CD�E�F���

BD5�67��GHI�H�:�����5�H��

�H4�@5�H���8��E�H��7 5�J�:�5�B5 5�:�8�5�C��� K��7�8����A�� ���L� 5�H�D�B 5�� K���L�

HD�5�8�4�����8�9�5����9�4�H�:��5�

��H4�B��H4���8L�H�:�I�44�C��B5 8�����:�� ��7��

HM�

��M�����B

88�C4����:�5��7��4HI� +��1 '�/2.,&� N%1 ���'2/,' *�

-0- 1�3�N%�, %� (#O)PO($ �& #QR("R"#($ 2&',� S�',� T�UVW(("$XP$XY( N��/� ,Z���,1 �& #(R#(R"#(W[ %&' �1 &�� 3�� �,1%\,U E8�5�=

��8? ]((PV)XW(PQ̂

_̀ab�cdeffgfhi�ab�fhifefj�ahik�lb�km�ìf�jln�lhj�nfle�maebi�oeaiifh�lpkqf�lhj�oarr�ifegahlif�stkh�uspbilhialr� vkgtrfiakh�km�ìf�wekxfyiz�lb�ìli�ifeg�ab�jfmahfj�ah�c{c�|kysgfhi�c}~���}~~�z��fhfelr�vkhjaiakhb�km�ìf� vkhielyi�mke�vkhbiesyiakhz�shrfbb�kìfeoabf�ldeffj�pn�ìf�tleiafb�lhj�bfi�mkeì�pfrko��

¡¢£¤¥¦§¡¡§¤̈©ª£¢¡«����������� � � ¢¬¬§®§¤̈©ª£¢¡«©���������� �

LDG 2025-180 ALTERATION PROJECT PROCEDURES 01 35 16 - 1

SECTION 01 35 16 - ALTERATION PROJECT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes special procedures for alteration work.

1.2 DEFINITIONS

A. Alteration Work: This term includes remodeling, renovation, repair, and maintenance work performed within existing spaces or on existing surfaces as part of the Project.

B. Consolidate: To strengthen loose or deteriorated materials in place.

C. Design Reference Sample: A sample that represents the Architect's prebid selection of work to be matched; it may be existing work or work specially produced for the Project.

D. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

E. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, or finish; as approved by Architect.

F. Refinish: To remove existing finishes to base material and apply new finish to match original, or as otherwise indicated.

G. Repair: To correct damage and defects, retaining existing materials, features, and finishes. This includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials.

H. Replace: To remove, duplicate, and reinstall entire item with new material. The original item is the pattern for creating duplicates unless otherwise indicated.

I. Replicate: To reproduce in exact detail, materials, and finish unless otherwise indicated.

J. Reproduce: To fabricate a new item, accurate in detail to the original, and from either the same or a similar material as the original, unless otherwise indicated.

K. Retain: To keep an element or detail secure and intact.

L. Strip: To remove existing finish down to base material unless otherwise indicated.

M. Furnish: to provide purchase and deliver to site, materials to be installed.

N. Provide: To furnish and install materials items as indicated.

1.3 MATERIALS OWNERSHIP

A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may

LDG 2025-180 ALTERATION PROJECT PROCEDURES 01 35 16 - 2

be encountered or uncovered during the Work, regardless of whether they were previously documented, remain Owner's property.

1.4 QUALITY ASSURANCE

A. Title X Requirement: Each firm conducting activities that disturb painted surfaces shall be a "Lead-Safe Certified Firm" according to 40 CFR 745, Subpart E, and use only workers that are trained in lead-safe work practices.

B. Fire-Prevention Plan: Prepare a written plan for preventing fires during the Work, including placement of fire extinguishers, fire blankets, rag buckets, and other fire-control devices during each phase or process. Coordinate plan with Owner's fire-protection equipment and requirements. Include fire-watch personnel's training, duties, and authority to enforce fire safety.

C. Safety and Health Standard: Comply with ANSI/ASSP A10.6.

1.5 STORAGE AND HANDLING OF SALVAGED MATERIALS

A. Salvaged Materials:

1. Clean loose dirt and debris from salvaged items unless more extensive cleaning is indicated.

2. Pack or crate items after cleaning; cushion against damage during handling. Label contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area designated by Owner.

5. Protect items from damage during transport and storage.

B. Salvaged Materials for Reinstallation:

1. Repair and clean items for reuse as indicated.

2. Pack or crate items after cleaning and repairing; cushion against damage during handling. Label contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment unless otherwise indicated. Provide connections, supports, and miscellaneous materials to make items functional for use indicated.

C. Existing Materials to Remain: Protect construction indicated to remain against damage and soiling from construction work.

D. Storage: Catalog and store items within a weathertight enclosure where they are protected from moisture, weather, condensation, and freezing temperatures.

1. Identify each item for reinstallation with a nonpermanent mark to document its original location.

Indicate original locations on plans, elevations, sections, or photographs by annotating the identifying marks.

2. Secure stored materials to protect from theft.

3. Control humidity so that it does not exceed 85 percent. Maintain temperatures 5 deg F or more above the dew point.

LDG 2025-180 ALTERATION PROJECT PROCEDURES 01 35 16 - 3

PART 2 - PRODUCTS - (Not Used)

PART 3 - EXECUTION

3.1 PROTECTION

A. Protect persons, motor vehicles, surrounding surfaces of building, building site, plants, and surrounding buildings from harm resulting from alteration work.

1. Use only proven protection methods, appropriate to each area and surface being protected.

2. Provide temporary barricades, barriers, and directional signage to exclude the public from areas where alteration work is being performed.

3. Erect temporary barriers to form and maintain fire-egress routes.

4. Erect temporary protective covers over walkways and at points of pedestrian and vehicular entrance and exit that must remain in service during alteration work.

5. Contain dust and debris generated by alteration work, and prevent it from reaching the public or adjacent surfaces.

6. Provide shoring, bracing, and supports as necessary. Do not overload structural elements.

7. Protect floors and other surfaces along hauling routes from damage, wear, and staining.

B. Temporary Protection of Materials to Remain:

1. Protect existing materials with temporary protections and construction. Do not remove existing materials unless otherwise indicated.

2. Do not attach temporary protection to existing surfaces except as indicated as part of the alteration work program.

C. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, components, and vegetation.

D. Utility and Communications Services:

1. Maintain existing services unless otherwise indicated; keep in service, and protect against damage during operations. Provide temporary services during interruptions to existing utilities.

3.2 PROTECTION FROM FIRE

A. General: Follow fire-prevention plan and the following:

1. Comply with NFPA 241 requirements unless otherwise indicated. Perform duties titled "Owner's

Responsibility for Fire Protection."

2. Remove and keep area free of combustibles, including rubbish, paper, waste, and chemicals, unless necessary for the immediate work.

a. If combustible material cannot be removed, provide fire blankets to cover such materials.

B. Heat-Generating Equipment and Combustible Materials: Comply with the following procedures while performing work with heat-generating equipment or combustible materials, including welding, torch-cutting, soldering, brazing, removing paint with heat, or other operations where open flames or implements using high heat or combustible solvents and chemicals are anticipated:

1. Obtain Owner's approval for operations involving use of welding or other high-heat equipment. Use of open-flame equipment is not permitted. Notify Owner at least 72 hours before each occurrence, indicating location of such work.

2. As far as practicable, restrict heat-generating equipment to shop areas or outside the building.

3. Do not perform work with heat-generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. Use a combustible gas indicator test to ensure that the area is safe.

LDG 2025-180 ALTERATION PROJECT PROCEDURES 01 35 16 - 4

4. Use fireproof baffles to prevent flames, sparks, hot gases, or other high-temperature material from reaching surrounding combustible material.

5. Prevent the spread of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings.

6. Fire Watch: Before working with heat-generating equipment or combustible materials, station personnel to serve as a fire watch at each location where such work is performed. Fire-watch personnel shall have the authority to enforce fire safety. Station fire watch according to NFPA 51B, NFPA 241, and as follows:

a. Train each fire watch in the proper operation of fire-control equipment and alarms.

b. Prohibit fire-watch personnel from other work that would be a distraction from fire-watch duties.

c. Cease work with heat-generating equipment whenever fire-watch personnel are not present.

d. Have fire-watch personnel perform final fire-safety inspection each day beginning no sooner than 30 minutes after conclusion of work in each area to detect hidden or smoldering fires and to ensure that proper fire prevention is maintained.

e. Maintain fire-watch personnel at each area of Project site until two hours after conclusion of daily work.

C. Fire-Control Devices: Provide and maintain fire extinguishers, fire blankets, and rag buckets for disposal of rags with combustible liquids. Maintain each as suitable for the type of fire risk in each work area.

Ensure that nearby personnel and the fire-watch personnel are trained in fire-extinguisher and blanket use.

D. Sprinklers: Where sprinkler protection exists and is functional, maintain it without interruption while operations are being performed. If operations are performed close to sprinklers, shield them temporarily with guards.

1. Remove temporary guards at the end of work shifts, whenever operations are paused, and when nearby work is complete.

3.3 GENERAL ALTERATION WORK

A. Record existing work before each procedure (preconstruction), and record progress during the work.

Use digital preconstruction documentation photographs or video recordings.

B. Perform surveys of Project site as the Work progresses to detect hazards resulting from alterations.

C. Notify Owner and Architect of visible changes in the integrity of material or components whether from environmental causes including biological attack, UV degradation, freezing, or thawing or from structural defects including cracks, movement, or distortion.

1. Do not proceed with the work in question until directed by Architect.

END OF SECTION 01 35 16

LDG 2025-180 TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 1

SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 SECTION REQUIREMENTS

A. Use Charges: Cost or use charges for temporary facilities shall be included in the Contract Sum.

B. Use water and electric power from Owner's existing system without metering and without payment of use charges.

C. Electrical Service: Comply with NEMA, NECA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 TEMPORARY UTILITIES

A. General: Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fixtures. Comply with regulations and health codes for type, number, location, operation, and maintenance of fixtures and facilities.

C. Heating and Cooling: Provide temporary heating and cooling required for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

D. Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

3.2 TEMPORARY SUPPORT FACILITIES

A. Provide field offices, storage and fabrication sheds, and other support facilities as necessary for construction operations.

B. Provide waste-collection containers in sizes adequate to handle waste from construction operations.

Collect waste daily and, when containers are full, legally dispose of waste off-site. Comply with requirements of authorities having jurisdiction.

3.3 TEMPORARY SECURITY AND PROTECTION FACILITIES

A. Provide temporary environmental protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by Owner from fumes and noise.

LDG 2025-180 TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 2

C. Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

D. Furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering site except by entrance gates.

E. Install and maintain temporary fire-protection facilities. Comply with NFPA 241.

3.4 TERMINATION AND REMOVAL

A. Remove temporary facilities and controls no later than Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

END OF SECTION 01 50 00

LDG 2025-180 PRODUCT REQUIREMENTS 01 60 00 - 1

SECTION 01 60 00 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION REQUIREMENTS

A. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

B. Product Substitutions: Substitutions include changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor after award of the Contract.

1. Submit requests within ten days after the Notice to Proceed.

2. Do not submit unapproved substitutions on Shop Drawings or other submittals.

3. Identify product to be replaced and show compliance with requirements for substitutions.

Include a detailed comparison of significant qualities of proposed substitution with those of the Work specified, a list of changes needed to other parts of the Work required to accommodate proposed substitution, and any proposed changes in the Contract Sum or the Contract Time should the substitution be accepted.

4. Architect will review the proposed substitution and notify Contractor of its acceptance or rejection.

C. Comparable Product Requests:

1. Do not submit unapproved products on Shop Drawings or other submittals.

2. Identify product to be replaced and show compliance with requirements for comparable product requests. Include a detailed comparison of significant qualities of proposed substitution with those of the Work specified.

3. Architect will review the proposed product and notify Contractor of its acceptance or rejection.

D. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

1. Schedule delivery…