This is a bid form and price schedule attachment for an Invitation for Bid (IFB 26-22B) issued by Murray City, Utah for the Park Center Roof Replacement project. The project requires qualified roofing contractors to provide complete roof system replacement services, including removal and disposal of existing roofing materials, deck and substrate repairs, insulation installation, placement of a new 60 mil TPO roofing system, drainage improvements, flashings, coping and parapet work, and related accessories. The work is organized into twelve distinct roof sections (identified by color coding) plus project-wide shared work. Bidders must submit a Total Base Bid that encompasses all labor, materials, equipment, demolition, disposal, permits and fees, temporary facilities, site protection, cleanup, warranties, insurance, bonding, overhead, and profit necessary for complete performance of the work. The bid form requires bidders to provide unit prices for potential change order work, including insulation replacement, steel deck replacement, coping, wood nailer, and walk pads, though these unit prices are separate from and will not be used to determine the low bid.
Award will be made based on responsiveness, responsibility, and the construction preference system established under Murray City Code 3.10.370. Bidders may claim preferences in the following categories: qualified health insurance coverage, drug and alcohol testing policies including random testing, veteran recruitment and employment programs, job training programs, safety programs, and formal nondiscrimination policies. Each claimed preference must be supported by documentation submitted with the bid, and the City will verify preferences after bid opening. Bidders are not required to qualify for any preference to submit a responsive bid, and construction preferences do not alter the actual Total Base Bid amount. Bidders must complete a Construction Preference Certification by selecting yes or no for each preference category and providing supporting documentation for all affirmative responses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-26-22B Park Center Roof Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form
| MURRAY CITY, UTAH |
| IFB 26-22B – PARK CENTER ROOF REPLACEMENT |
| ATTACHMENT A – BID FORM AND PRICE SCHEDULE |
| Bidder Legal Name | Contact Name |
| Address | Phone |
| City / State / ZIP |
| The Total Base Bid is the sole price used for bid comparison. It shall include all work required by the IFB, drawings, specifications, attachments, and addenda. Unit prices are separate and will not be used to determine the low bid. Award remains subject to responsiveness, responsibility, and the construction preference system stated in the IFB. | |||||||
| A. TOTAL BASE BID – COST BY ROOF SECTION | |||||||
| Roof Area | Labor ($) | Materials ($) | Equipment ($) | Disposal ($) | Permits & Fees ($) | Other / O&P ($) | Area Total ($) |
| Roof Section 1 – Red | - | ||||||
| Roof Section 2 – Blue | - | ||||||
| Roof Section 3 – Purple | - | ||||||
| Roof Section 4 – Orange | - | ||||||
| Roof Section 5 – Light Green | - | ||||||
| Roof Section 6 – Dark Pink | - | ||||||
| Roof Section 7 – Green | - | ||||||
| Roof Section 8 – Light Purple | - | ||||||
| Roof Section 9 – Light Yellow | - | ||||||
| Roof Section 10 – Pink | - | ||||||
| Roof Section 11 – Light Red | - | ||||||
| Roof Section 12 – Yellow | - | ||||||
| Project-Wide / Shared Work | - | ||||||
| TOTAL BASE BID | - | ||||||
| Base Bid shall include all labor, materials, equipment, demolition, disposal, permits and fees, cranes, temporary facilities, site protection, cleanup, warranties, insurance, bonding, overhead, profit, and all other costs necessary for complete performance of the Work. Roof Sections 1–12 correspond to Figures 1 and 2. Include vapor barrier work shown in Figure 3 in the applicable section price. Include ladder access and other shared work required by the IFB in the applicable section price or the Project-Wide / Shared Work line. | |||||||
| B. UNIT PRICE SCHEDULE | |||||||
| Item | Unit | Unit Price ($) | Basis / Notes | ||||
| Insulation replacement | SF | Per square foot. | |||||
| Steel deck replacement | SF | Per square foot. See IFB scope for required Base Bid work. | |||||
| Coping | LF | Per linear foot. | |||||
| Wood nailer | LF | Per linear foot. | |||||
| Walk pads | LF | Per linear foot. See IFB §3.10 for walk-pad location and approximate quantity. | |||||
| Unit prices shall be fully burdened and include all labor, materials, equipment, overhead, profit, and incidentals required for the applicable unit of work. Unit prices do not alter the Total Base Bid used for bid comparison. | |||||||
| C. ROOF SECTION / DRAWING PRICING NOTES | |||||||
| Use the numbered roof sections shown in Figure 1 and the matching color key shown in Figure 2 when completing Section A. Each section price shall include all work required for that roof section. | |||||||
| Figure 3 identifies the roof areas requiring the vapor barrier assembly. Include that work in the applicable roof section price. Ladder access locations are identified by “+L” on Figure 1. Include all ladder work in the applicable section price or the Project-Wide / Shared Work line. Do not exclude required work merely because it is shown on a drawing rather than repeated on this pricing sheet. |
D. CONSTRUCTION PREFERENCE CERTIFICATION – REQUIRED
OpenAI: Preference categories are based on Murray City Code §3.10.370(E), excluding apprentice utilization because this project is below the qualifying-project threshold stated in the IFB/project direction.
| Each Bidder shall complete this section by selecting Yes or No for every preference listed below. A Bidder is not required to qualify for any preference in order to submit a responsive Bid. For each Yes response, the Bidder and every subcontractor, if any, shall provide sufficient supporting documentation with the Bid to demonstrate the claimed preference in accordance with IFB Section 9 and Murray City Code §3.10.370. | |||
| Preference | Yes / No | Supporting Documentation / Reference | |
| Qualified health insurance coverage (see IFB Section 9) | |||
| Drug and alcohol testing policy, including random testing | |||
| Veteran recruitment and/or employment program | |||
| Job training program | |||
| Safety program | |||
| Formal nondiscrimination policy | |||
| The City will verify each claimed preference after Bid opening and apply all verified preferences during evaluation in accordance with IFB Sections 9 and 10 and Murray City Code §3.10.370. A Bidder that does not qualify for any preference may still submit a responsive Bid. Construction preferences do not change the Bidder’s actual Total Base Bid. | |||
| E. BID SUMMARY AND CERTIFICATION | |||
| TOTAL BASE BID | - |
| By submitting this Bid Form, the Bidder certifies that the Total Base Bid is complete and includes all costs necessary to perform the Work required by IFB 26-22B and its drawings, attachments, and addenda. The Bidder acknowledges that unit prices are separate from the Total Base Bid and will not be used to determine the low bid. The Bidder further certifies that it has completed the Construction Preference Certification by selecting Yes or No for each preference and that each Yes response is supported by information submitted with the Bid and is subject to the City’s determination under Murray City Code §3.10.370. | |
| Authorized Rep. | Signature |
| Title | Date |
Source basis: IFB 26-22B Park Center Roof Replacement; Figure 1 – Roof Replacement Area Plan; Figure 2 – Roof Sections & Color Key; Figure 3 – Vapor Barrier Sections; Murray City Code §3.10.370: https://codelibrary.amlegal.com/codes/murrayut/latest/murray_ut/0-0-0-2966 OpenAI: Murray City Procurement Code source: https://codelibrary.amlegal.com/codes/murrayut/latest/murray_ut
&8 IFB 26-22 – Attachment A – Bid Form and Price Schedule &8 Page &P of &N
File details come from the government source that posted it. Updated .