Summary of 2025-BRP-017 Port Vue Demolition - Terms and Conditions
This document contains the terms and conditions for a sealed bid request issued by the Steel Rivers Council of Governments (SRCOG) acting as administrative agent for Port Vue Borough, Pennsylvania. The project involves the demolition of three residential structures located at 1612 Trimble Ave, 1801 New York Ave, and 1889 Romine Ave in Port Vue Borough. The scope of work includes asbestos removal and abatement as required, backfill, grading, seeding of the lots, and all related work in compliance with Federal, State, County, and Local laws and regulations. Electronic sealed proposals must be submitted via PennBid at https://pennbid.bonfirehub.com until 10:00 am prevailing time on November 19, 2026, with public bid opening and reading to follow immediately thereafter. The project has a mandatory 30-day completion period from issuance of the written proceed order, which must be issued within 90 days of proposal acceptance. The contractor must commence work within 15 days after the proceed order and obtain final approval by the end of the 30-day period. The contract is subject to the Pennsylvania Prevailing Wage Act, and the engineer for the project is Glenn Engineering & Associates, Ltd., located at 14920 US-30, Irwin, PA 15642.
Bidders must submit a Bid Bond in an amount equal to 10 percent of the proposal value as a guarantee of contract performance. Upon contract award, the successful bidder must provide a Performance Bond and a Payment Bond each equivalent to 100 percent of the contract price within 10 days, along with certificates of insurance including Workmen's Compensation Insurance and Comprehensive General Liability Insurance with minimum coverage of $1,000,000 per occurrence. The project is funded through Act 152 Blight Removal Program grants from Allegheny County Economic Development office (ACED). Payment will be made within 60 days of invoice receipt for satisfactorily completed work, contingent upon receipt of Act 152 funds; if funds are not received within 60 days, SRCOG will pay within three working days of receiving funds from ACED. Liquidated damages of $350 per day apply for work not completed within the 30-day completion period. Compliance is required with the Pennsylvania Prevailing Wage Act, Title VI of the Civil Rights Act, the Department of Labor Equal Opportunity Clause, Executive Orders 11625 and 12138, Section 504 of the Rehabilitation Act, and the Americans with Disabilities Act. The Allegheny County MBE/WBE Program establishes goals of 13 percent Minority Business Enterprise, 2 percent Female Business Enterprise, and 5 percent Veteran-Owned Small Businesses participation. All contractors receiving federal funding must obtain a UEI number and CAGE number from the System for Award Management (SAM). The contractor must provide a one-year maintenance bond equal to 100 percent of the final contract payment price prior to issuance of final payment.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STEEL RIVERS COUNCIL OF GOVERNMENTS
Request for Bids
November 2026
2025-BRP-017
PORT VUE DEMOLITION
PORT VUE BOROUGH, PA
Steel Rivers Council of Governments
1705 Maple Street, Room 100
Homestead, PA 15120
412-462-7600 (phone)
412-462-3986 (fax)
Glenn Engineering & Associates, Ltd.
14920 US-30
Irwin, PA 15642
412-824-5672
Project Timeline: 30-Day Completion Period
NOTICE TO BIDDERS
REQUEST FOR PROPOSALS
Notice is hereby given that sealed proposals will be received by the Steel Rivers COG via PennBid at https://pennbid.bonfirehub.com. Bid Proposals will be received until 10:00 am prevailing time on November
19, 2026. At 10:00 am prevailing time, bids will be publicly opened and read immediately thereafter for the following projects:
2025-BRP-017 Port Vue Demolition. Consists of the demolition of three (3) residential structures in Port
Vue Borough, asbestos removal and abatement as required, backfill, grading, and seeding of lot, and all related work complete and in compliance with Federal, State, County, and Local laws & regulations, and
Contract Documents. 1612 Trimble Ave, 1801 New York Ave, 1889 Romine Ave, 30-day completion.
Pennsylvania Prevailing Wage Act applies to all above projects. Contract Specifications, Instructions to
Bidders, General Conditions, Form of Proposal and Agreement can be obtained via PennBid at https://pennbid.bonfirehub.com. Proposals to receive consideration must include a Bid Bond in an amount equal to ten percent (10%) of the Proposal as a guarantee that, if the Proposal is accepted, the successful Bidder will immediately enter into Agreement after the Notice of Award of the Contract and commence start of construction immediately thereafter.
“Compliance is required with the Pennsylvania Prevailing Wage Act of 1961, P.L. 987, No. 442; Title VI and other applicable provisions of the Civil Rights Act of 1964; the Department of Labor Equal Opportunity Clause
(41 CFR 60-1.4); Executive Order 11625 (Utilization of Minority Business Enterprise); Executive Order 12138
(Utilization of Female Business Enterprise); in compliance with Section 504 of Rehabilitation Act of 1973 and
Americans with Disabilities Act of 1990; the Allegheny County MBE/WBE Program enacted July, 1981, which sets forth goals of 13 percent Minority and 2 percent Female Business Enterprise; and the Allegheny
County Ordinance #6867-12, setting forth goals of 5 percent Veteran-Owned Small Businesses.”
The Steel Rivers Council of Governments reserves the right to waive any informalities or to reject any or all proposals, or any part thereof. No Bidder may reject his/her bid for the period as specified in the project bid documents after the scheduled closing time for receipt of bids.
Jennifer Kwiatek, Government Grants Manager, Steel Rivers COG
Advertisement Dates:
Pittsburgh Post Gazette Local Xtra East Advertisement Dates: October 29 and November 5, 2026 https://pennbid.bonfirehub.com/
INSTRUCTIONS TO BIDDERS
Bids to be entitled to consideration must be made in accordance with the following:
1. Bids shall be made upon the online form provided on the PennBid website, https://pennbid.bonfirehub.com, and the blank spaces in such forms shall be fully filled; numbers shall be stated in figures where indicated; the signature shall be included where required.
2. No oral, telegraphic, or telephonic modifications shall be considered.
3. Should a bidder find discrepancies in, or omissions from, the documents, or be in doubt as to their meaning, clarification should be requested of the Steel Rivers
Council of Governments.
4. Erasures or other changes in the Bid must be explained or noted over the signature of the Bidder.
5. Bids may be withdrawn via the PennBid website, https://pennbid.bonfirehub.com, prior to the time set for Bid opening.
6. Before submitting a Bid, Bidders should carefully examine the specifications, visit the sites, fully inform themselves as to the existing conditions, and included in, or required by, the contract.
7. The competency and responsibility of Bidders and of their proposed subcontractors will be considered in making the award. The Steel Rivers Council of Governments reserves the right to reject any and all bids.
8. Bidders and other persons properly interested may view the bid results online at https://pennbid.bonfirehub.com.
9. The Bidder to whom the award is made will be notified within ninety (90) days after the bid opening. However, the Steel Rivers Council of Governments reserves the right to reject any and all Bids and to waive any informality in
Bids received whenever such rejection or waiver is in its interest. The contract will be awarded according to the Contract Selection Procedures adopted by the
Steel Rivers Council of Governments and included in this Bid Package (refer to
Table of Contents)
10. Attention is called to the fact that not less than the minimum salaries and wages as determined by the PA Department of Labor must be paid for this project; that the
Contractor must insure that employees and applicants for employment are not discriminated against because of their race, color, age, religion, sex, or national origin and that the Executive Order #11625 (Utilization of Minority Enterprise), Executive Order #12138 (Utilization of Female Business Enterprise), compliance with Section 504 of the Rehabilitation Act of 1973 and the Americans with
Disabilities Act of 1990, the Allegheny County MBE/WBE Program, Section 109 of the housing and Community Development Act of 1974, any/all civil rights legislation, and applicable federal labor standards provisions must be observed.
Attention will also be paid to the Section 3 clause of the Housing and Urban
Development Act of 1968, as it applies to employment and training goals for lower income residents of the project area, and to the extension of all feasible efforts to contract with business located in or owned in substantial part by persons residing in the project area. Finally, bidding contractors must utilize to the greatest extent feasible, minority business concerns located in the program area.
11. Notice to Contractors - UEI & CAGE Numbers: In accordance with new HUD regulations, ALL CONTRACTORS receiving federal funding are required to obtain a CAGE number from the System for Award Management (SAM) formerly known as Central Contractor Registry (CCR) as well as a Unique
Entity IDS (UEI) number. In order to get a CAGE number, you must first obtain a UEI number. To obtain a UEI number, go to the following website:
https://sam.gov or by calling 1-800-264-1318. If you are a contractor bidding on projects funded with federal CDBG grants and do not currently have a DUNS and
CAGE number, you must register and obtain these numbers. Proof of registration is mandatory to be considered for funding. ACED compliance documents have been revised for contractors to enter their UEI number, CAGE number and CAGE expiration date (Award Verification for Prime/Subcontractors– PL3/PL4).
12. The bidder agrees to provide for Minority/Women/Disadvantaged Business
Enterprise, and Veteran Owned Small Businesses (M/W/DBE/VOSB) requirements/participation in accordance with the following:
• M/W/DBE/VOSB Goals - The County of Allegheny, who is funding this contract, has established in connection with this contract, the goal of 13 percent of the contract price for the utilization of firms owned and controlled by Minority Business
Enterprises (MBEs), 2 percent of the contract price for firms owned and controlled by
Women's Business Enterprises (WBEs), and a 5 percent goal for Veteran Owned
Small Businesses (VOSB).
• M/W/DBE/VOSB Obligation - Bidders shall take necessary and reasonable steps to ensure that M/W/DBE/VOSB(s) have the maximum opportunity to compete for and perform contracts. The vendor shall not discriminate on the basis of race, color, national origin, or sex in the award and performance of County contracts.
• Proposals containing an M/W/DBE/VOSB sub-contracting component must include the percentage involvement of all MBE, WBE, DBE and VOSB businesses along with the names of the firms involved. The overall goals may be exceeded.
• List of approved M/W/DBE firms may be obtained from the County’s M/W/DBE
Office.
13. Bidders shall state, on the Bid Form provided, a Base Bid price for all labor, materials, and equipment required to complete the total work shown on the
Drawings and required by the Specifications.
14. Bidders shall include on the Bid Form provided, unit prices and separate prices for all items listed on the Proposal Form.
15. Following the award and within fifteen (15) days after the "Notice of Contract
Award" has been issued by the SRCOG, the successful bidder will be required to execute said contract, post all bonds and deliver certificates of insurance to the SRCOG. The successful bidder shall abide by the following requirements:
• Performance Bond - A Performance Bond equivalent to 100% of the contract price will be supplied by the successful bidder within ten (10) days of the award by the
Steel Rivers Council of Governments.
https://sam.gov/
• Payment Bond - A Payment Bond equivalent to 100% of the contract price will be supplied by the successful bidder within ten (10) days of the award by the Steel
Rivers Council of Governments.
• Workmen's Compensation Insurance - The successful bidder shall carry
Workmen's Compensation Insurance as required by law or shall submit evidence that it has qualified with the Pennsylvania Department of Labor and
Industry as a self-insurer. No program of self-insured retention shall apply to the above coverage without prior approval of Allegheny County.
In the event that the bidder fails to do so, he will be deemed to have abandoned the contract and the SRCOG at its option may either re-advertise or otherwise award said contract to the next lowest bidder meeting specifications and the
SRCOG may move to recover the losses sustained by such abandonment out of the bidders Surety Bond or Certified Check.
16. Bidders shall not remove any pages from this volume of Contract documents.
Proposals shall be submitted intact with this volume together with all drawings and addenda. All additional sheets or special forms used shall be inserted into the PDF upload to which it applies.
17. Bids will be received by SRCOG via PennBid at https://pennbid.bonfirehub.com until _10:00 A.M. prevailing time on November 19, 2026 , and will be publicly opened and read immediately thereafter.
PORT VUE DEMOLITION
PORT VUE BOROUGH
2025-BRP-017
STEEL RIVERS COG
GENERAL REQUIREMENTS
MANAGEMENT RESPONSIBILITIES
The Steel Rivers Council of Governments (SRCOG) is recognized as the agent for the
Municipality in soliciting the proposal, accepting the bid, awarding the contract and administering the ACT 152 program on behalf of Municipality for the project hereinafter described. Engineering guidance and technical supervision will be furnished by the
Municipality. All work on the project must be performed to the satisfaction of
Municipality. Any contract problems or disputes must be resolved between Contractor and Municipality.
1. LOCATION OF SITE:
1.1 The project is located within: Borough of Port Vue
1.1.1 1612 Trimble Ave.
1.1.2 1801 New York Ave.
1.1.3 1889 Romine Ave
1.2 Every Contractor and subcontractor who proposes to be engaged in this work shall visit the site and acquaint himself/ herself with the conditions that exist. The Contractor and each subcontractor shall be presumed to have fully appraised himself of all site conditions pertaining to the contract work and to have accepted the conditions as they do or will exist under the intent of the Contract documents and will be responsible for the completion of the project in the manner and within the time stated in the
Contract Documents.
2. ESTIMATED QUANITIES
2.1 The bidders’ attention is drawn to the fact that the estimate of quantities of work to be done and/or materials to be furnished under these specifications, as shown on the proposal form, and in the contract, are approximate and are given only as a basis of calculation upon which the award of the contract is to be made. The SRCOG does not assume any responsibility that the quantities shall materialize strictly in the construction of the project, nor shall the contractor plead misunderstanding or deception because of such estimate of quantities or of the character of the work, location, or other conditions pertaining thereto.
2.2 The SRCOG reserves the right to increase or decrease any or all of the above mentioned quantities of the work, or to omit any of them, as it may deem necessary, and such increase or decrease of the quantities given for any of the items shall not be considered as sufficient grounds for granting an increase in the unit prices Bid.
3. PROCEED ORDER
3.1 The SRCOG shall issue a written proceed order within ninety (90) days from the date of the acceptance of the Contractor’s proposal. No work shall be commenced by the Contractor until such written proceed order from the SRCOG has been received. If the order to proceed is not received by the Contractor within this 90-day period, the Contractor has the option of withdrawing his Proposal.
3.2 The Contractor must commence the work within fifteen (15) days after the issuance of the Proceed Order. At the option of the SRCOG, this contract may be cancelled by failure of the Contractor to begin work within this time period. A Contractor may submit a written request to
SRCOG to extend the commencement date beyond this period. All requests must be made in writing within the fifteen (15) day period and are granted at the discretion of the SRCOG.
4. PROJECT COMPLETION AND SCHEDULING
4.1 The Contractor must satisfactorily complete this project by
30-day completion period. Notwithstanding the aforesaid, the Contractor is excused from the performance time requirement if, during the process of the work, delay is authorized in writing by the SRCOG designated personnel; because of any act of neglect of the SRCOG or its member municipalities or by authorized changes in the work or by strikes, lockouts, fire, unusual delay in the transportation, unavoidable casualties or any causes completely beyond the Contractor's control. SRCOG designated personnel, in consultation with affected municipalities, shall be empowered to make final decisions on justifiability of causes offered as a basis for extension of time.
4.2 It is expressly understood and agreed by and between the parties hereto that the Contractor must complete all of the above-enumerated Services and, as shown in detail on the Proposal, by 30-day completion period and that the contractor shall obtain final approval of work conducted by 30-day completion period. It is further understood that 30-day completion period indicates the end of the grant funding period for this project.
Therefore, if the contractor fails to complete all of the above-enumerated
Services, these services will be still be required by the contract, but will not be eligible for payment. Additionally, if the work is not completed by
30-day completion period, and a written extension by SRCOG is not granted, then it will be assumed that the contractor has abandoned the contract and as such the SRCOG may secure another contractor to complete the work and charge the original Contractor for this work, deduct it from payment to the Contractor, and/or submit a claim against the
Contractor’s bond.
4.3 Additionally, for each day over 30-day completion period, said
Contractor shall be subject and liable for liquidated damages in the sum of
Three-Hundred Fifty Dollars ($350.00) per day with said liquidated damages to be deducted in the settlement of its accounts with the SRCOG upon completion of the work, and its acceptance on the part of the
SRCOG and the affected municipality.
5. WORK CHANGES
5.1 The Project Engineer/Street Commissioners of each municipality/ municipalities may make such minor changes in the specifications as are deemed necessary by him to complete the project or any part thereof, provided, however that they are of a character as not to affect materially the unit cost of the work involved. The Contractor will be paid for said work at the Contract unit prices. Any changes contemplated by the
Project Engineer and/or Contractor, which may result in deviation from the standards on the drawings shall be made in writing before same shall be made. Compensation for the work shall be at unit prices for the time involved. The SRCOG reserves the right to add or delete any items listed on the bidding schedule.
6. PROPERTY DAMAGES
6.1 The Contractor is liable for damage to gas, water, power, telephone, and television lines as they exist on the site of the work. The Contractor shall notify the utility company concerned when damage occurs. If the
Contractor determines that an existing utility facility may pose a problem, he will contact the Municipal Engineer or his designate as to the nature of the problem. Written certification of the Engineer’s approval to commence work will be presented to the SRCOG before excavation begins.
6.2 When buildings, fences hedges, gardens, trees, etc., border on the line of the work, the Contractor shall be held liable for damage resulting from careless work.
6.3 Repair of street, after placement of a new catch basin, is incidental to its installation, and must conform to the existing condition of the street.
7. WORK AND WORKMANSHIP
7.1 The work specified herein shall include the furnishings of all labor, materials, supervision equipment, and services required for, or necessary for, or incidental to, the performance of all work required. Workmanship shall be performed in accordance with the standards of the several trades known as “GOOD WORKMANLIKE MANNER.” All work shall be done in strict accordance with all applicable Building Fire Codes, and municipal ordinance requirements. Sub-contractors shall be bound by terms and conditions of this Agreement, insofar as they apply to their work, but this shall not relieve the Contractor from the full responsibility to the SRCOG and the Municipality for the proper completion of all work to be executed under this Agreement, and he shall not be released from this responsibility by any sub-contractual agreement he may make with others.
8. SAFETY
8.1 The Contractor shall comply with all parts of the Williams-Steiger
Occupational Safety and Health Act of 1970 (OSHA) and shall require that all subcontractors on the site also comply. He shall be responsible for posting all OSHA regulations and report forms and shall maintain logs and records as required by the OSHA regulations.
8.2 Non-compliance with OSHA regulations by any Contractor or his employees shall be cause for excluding that Contractor or his employees from the construction site until the OSHA requirement have been met.
8.3 Visits by the SRCOG personnel or the Municipal Engineer to conduct construction review of the Contractor’s performance are not intended to include review of the adequacy of the Contractor’s safety measures in, on, or near the construction site.
9. BARRICADES
9.1 The contractor shall furnish, erect, and maintain at closures, intersections, and throughout the project all necessary approved devices (i.e., barricades, lashing, warning lights, steady burn lights, reflectors, and signs) and he shall take all necessary and legal precautions for the protection of the work and safety of the public. If required by the municipality, the standard
"Road Closed" signs furnished by the contractor shall be securely fastened to the barricade by the Contractor in a position to be seen plainly at all times. All obstructions or hazardous conditions shall be set off by the use of the barricades and signs shall be reflectorized or equipped with approved flashing warning lights. The low intensity flashing warning lights and steady burn lights shall be kept in operation from sunset until sunrise and/or other periods of time when the barricades and/or other obstructions are not clearly visible in natural light. High intensity flashing warning lights shall be kept in operation 24 hours a day. The types of barricades and methods of installation shall be subject to the approval of the member municipality/municipalities or their respective engineers.
10. SITE INSPECTION
10.1 The contractor shall permit the Municipal Engineer or his designated representative, SRCOG personnel, insurance estimators, and evaluators from funding agencies access to the site to inspect the work at any time.
10.2 The Municipal Engineer/Street Commissioner, SRCOG designated personnel/Project Engineer shall have the authority to deny payment if the
Contractor fails to comply with the specifications or if a hazard to the public safety occurs (refer to Section 8 – Safety, and Section 13- Hold
Harmless) chosen by the Municipal Engineer/Street Commissioner/project
Engineer/SRCOG designated personnel. No crew may proceed to other sites without the approval of one of the above-mentioned individuals.
11. CONTRACT ASSIGNMENT
11.1 The Contractor shall not assign any part of this Contract without the written consent of the SRCOG.
12. PATENT SECURITY
12.1 The Contractor shall hold and save the SRCOG and its officers, agents, servants, and employees harmless from liability of any nature or kind, including cost and expenses for, or on account of, any patent or un-patented invention, process, article, or appliance manufactured or used in the performance of the Contract, including its use by the owner by the owner unless otherwise specifically stipulated in the Contract Documents.
12.2 License or Royalty Fees for the use of a process which is authorized by the
SRCOG must be reasonable, and paid to the holder of the patent, of his authorized license, direct by the SRCOG and not by or through the
Contractor.
12.3 If the Contractor uses any design, device, or materials covered by letters, patent, or copyright, he shall provide for such use by suitable agreement with the SRCOG of such patented or copyrighted design, device, or material. It is mutually agreed and understood that, without exception, the
Contract prices shall include all royalties or costs arising from the use of such design, device, or materials in any way involved in the work. The
Contractor and /or his sureties shall indemnify him and save harmless the
SRCOG and its member municipalities/municipality from any and all claims for infringement by reason of the use of such patented or copyrighted design, or materials or any trademark or copyright, in connection with work agreed to be performed under this Contract, and shall indemnify the SRCOG for any cost, expense, or damage which it may be obligated to pay by reason of such infringement at any time during the execution of the work or after completion of the work.
13. HOLD HARMLESS
13.1 The Contractor shall carry, during the life of the Contract, contractual liability insurance to protect and hold harmless the Redevelopment Authority of
Allegheny County and Allegheny County Economic Development and its officers, directors, agents and employees, the SRCOG, and its member municipality/municipalities, and shall furnish evidence of such insurance to both the SRCOG and the municipality/municipalities.
14. QUALIFICATION OF CONTRACTORS
14.1 All Contractors will be required to qualify by establishing proof of their competency and responsibility at the fixed date for the opening of bids for construction work.
14.2 Each Contractor shall submit a qualification statement on the form provided in this bid package and may include as attachments any essential extensions and/or supplementary information, details of financial ability, adequacy of organization, experience, plant and equipment, and related pertinent and material information necessary to establish qualification.
14.3 At the request of the SRCOG, the Contractor agrees to provide his most recent financial statement. From the data and information provided, the
SRCOG will establish qualification, determining the maximum amount of work on which a Contractor will be eligible to bid.
15. INSURANCE
15.1 The Contractor shall furnish evidences of Workman’s Compensation coverage to the SRCOG. The Contractor shall furnish evidence of
Comprehensive General Liability Insurance Coverage to include the following: comprehensive form, premises operations, products completed operations hazards, contractual insurance and independent contractors, (underground hazard is required for demolition, sewer and water projects).
Coverage is to be no less than $1,000,000.00 for each occurrence and
$1,000,000.00 aggregate for bodily injury and property damage combined.
15.2 The Contractor shall also furnish evidence of Automobile Liability
Insurance Coverage to include the following: Comprehensive form, owned, hired and non-owned. Coverage is to be no less than, for each occurrence, $500,000.00 for property damage, and $1,000,000.00 bodily injury and property damage combined.
15.3 Such certificates shall contain a clause that the Redevelopment Authority of Allegheny County and its officers, directors, agents and employees, as well as Allegheny County and its elected officials, officers, appointees and employees; the SRCOG; the Municipality and the municipal engineer shall be additional insured with the right of thirty (30) days’ notice of cancellation.
16. LIABILITY
16.1 The Contractor shall assume responsibility for any damages to persons or public or private, caused by reason of insufficient protection. This shall include, but is not limited to, damage done by heavy equipment to streets sidewalks, curbs, and utility devices. The Contractor shall repair any and all damages caused by him to neighboring property before leaving the site, except where weather conditions or other extenuating circumstances present an unreasonable hardship. In such cases, SRCOG designated personnel and/or other inspectors shall determine a suitable time frame for repairing the damages. Any repairs not completed within two weeks of that time shall be reported by the SRCOG to the Contractor’s Insurance
Agent.
17. MAINTENANCE OF STREETS
17.1 The Contractor shall clean and keep clean the streets, the work on public or private property occupied by him, free from waste or refuse resulting from his operations. Trucks hauling excavated material, cement, sand, stone, or other loose materials from or to the site shall be tight, so that no spillage will occur on adjacent streets. Before trucks start away from the site, their loads shall be trimmed.
17.2 The Contractor shall comply with all requirements relative to the maintenance of traffic as stipulated by municipal subdivisions.
18. MAINTENANCE OF EXISTING DRAINAGE
18.1 Drainage through existing sewers and drains shall be maintained at all times during construction, and all gutters shall be kept open for drainage.
Where existing sewers which interfere with the construction are encountered in the line of work, the flow in the sewers, including both dry weather flow and storm flow, shall be maintained either by constructing a satisfactory flume or by-pass sewer or by pumping, or by both.
19 UTILITIES
19.1 The Contractor is responsible for notifying all utility companies prior to commencing work in any municipality. The Contractor shall carefully support and protect from injury all existing gas pipes, water pipes, steam pipes, electrical conduits, sewers, drains hydrants, valve boxes, telephone cables, and other structures which do not have to be changed in their location. In case of injury or temporary removal, these facilities shall be restored to as satisfactory a condition as that in which they were found. Where dead ends shall exist following removal of pipes, conduits, or sewers, such ends shall be carefully plugged or bulk headed with brick or mortar. The said method of utility protection shall be subject to the approval of the member municipality/municipalities or their respective Engineer (s). The Contractor shall notify all utility companies affected by said construction, and shall determine the exact location of all existing utilities, prior to any construction.
20. ENGINEERING WORK
20.1 The Contractor shall furnish an Engineer, and shall be responsible for the general layout of all project sites, for the maintenance of all monuments, bench marks, and reference points, and shall maintain these points until completion of the work, and shall make all necessary extensions therefrom for all work under this Contract. The SRCOG reserves the right to check any and all such work under this Contract. The Contractor will be held responsible for the accuracy of such extensions, whether or not they are checked by the SRCOG.
21. PHOTOGRAPHS
21.1 Prior to any construction activities, the Contractor shall take color photographs of each project site and adjacent area. The photographs shall clearly show the extent and condition of the existing project site and landscaping adjacent to the project area. The Contractor shall present one complete set of photographs of the project site to the SRCOG for their records. Additional sets of photographs showing the completed project in each municipality shall be furnished SRCOG upon completion of the
Contract.
22. USE OF STREET, PRIVATE OR PUBLIC PROPERTY
22.1 The operations of the Contractor in public streets, public highways, or alleys, as regulated more in detail herein, shall be confined to as small a space as is practical so as not to cause undue inconvenience to the public or abutting properties and shall be subject to the approval of the Municipal
Engineer or Street Commissioner.
22.2 The operations shall be confined to the limits of rights-of- way over private property unless otherwise indicated, and, if additional area is required at no additional cost to the SRCOG. The Contractor shall take cognizance of his responsibility to protect the property on each side of the right-of-way.
22.3 The Contractor shall submit, prior to any construction, evidence, in writing signed by both Contractor and individual property owner, of acquisition of any rights-of-way, which may be required for construction and/or storage of Materials / equipment within private property, to the
Engineer’s office of the municipality involved.
23. MAINTENANCE OF TRAFFIC
23.1 During the progress of the work, the Contractor shall accommodate both vehicular and foot traffic, and shall provide free access to abutting property, fire hydrants, water and gas valves, and such other facilities, Street intersection may be blocked, but one-half at a time, and the
Contractor shall lay and maintain temporary driveways and crossings, such as in the opinion of the Municipal Engineer or Street Commissioner are necessary to accommodate the public. In the event of the Contractor’s failure to comply with the foregoing provisions, the SRCOG may, with or without notice, cause the same to be done and deduct the costs of such work from monies due the Contractor under this Contract; but the performance of such work by the SRCOG or at its insistence, shall serve in no way to release the Contractor from his general or particular liability for the safety of the public or the work.
23.2 The Contractor shall comply with all requirements/ordinances relative to the maintenance of traffic, as stipulated by the State and County Highway
Departments and local municipalities.
24. GUARANTEE
24.1 The Contractor shall guarantee all work done under this Contract for a period of one year from date of completion. A joint inspection shall be made by the Contractor, Municipal Representative(s), and SRCOG designated personnel to determine whether any corrective work is necessary. Any necessary corrective work to be done within that one year period by the Contractor, with no additional compensation therefore.
24.2 After all Contract work is completed and accepted, the Contractor shall present SRCOG with a one-year maintenance bond in the name of the
Steel Rivers Council of Governments, and in an amount equal to the one hundred percent (100%) of the final Contract payment price. This bond shall be presented prior to issuance of final payment.
25. PAYMENT
25.1 The SRCOG shall pay the Contractor within sixty (60) days of receiving any invoice for work satisfactorily completed pending receipt of Act 152 funds from Allegheny. If ACT 152 funds are not received within sixty
(60) days, SRCOG shall pay the full amount approved by the Department of Economic Development within three (3) working days following receipt of same from the Department of Economic Development.
Invoices shall be submitted monthly by the Contractor on or before the last day of the month. Final payment for work contracted will only be made after a final inspection and acceptance of the work by the Project
Engineer/Municipal Representative/Street Commissioner/SRCOG designated personnel.
25.2 If the Contractor is unable to complete any portion of the work by the 30-day completion period, a written request for an extension must be submitted to the SRCOG prior to 30 days before the 30-day completion period. This request must detail the reasons for the delay and for the extension and the date that the project will be completed. If the extension is granted, the SRCOG will respond in writing with a new 30-day completion period for the contract. Not all requests for extensions shall be granted; therefore the Contractor should not assume that any extension has been granted until s/he receives such notice in writing.
25.3 The Contractor understands that this project is funded through a county grant which is only available for a limited amount of time. Therefore, costs incurred and services performed past 30-day completion period will not be paid. Therefore, Contractors should be advised that all work must be completed and inspected by 30-day completion period.
26. SUB-CONTRACTS
26.1 Contractor shall not contract with any proposed subcontractor who has not been accepted, in writing, by the SRCOG.
26.2 The SRCOG may, without claim for extra cost by the Contractor, disapprove any subcontractor for cause on the basis of its own determination or because of the fact that the proposed subcontractor is listed as ineligible to receive awards of contracts from the United States.
26.3 Nothing contained in the contract shall create any contractual relation between the subcontractor and the SRCOG.
26.4 The Contractor shall be as fully responsible for the acts and omissions of his subcontractors, and of persons either directly or directly employed by them as he is for the acts and omissions of persons directly employed by him.
27. PERMITS, CODES AND STANDARDS
27.1 Contractor shall give all notices and comply with all laws, codes, ordinances, rules regulations, standards and specifications, except as otherwise shown or specified.
27.2 It is the intent of this Contract that the Contractor shall base his bid upon the drawings and specifications, but that all work installed shall comply with all applicable codes and regulations as amended by any waiver.
Before installing the work, the Contractor shall examine the drawings and specifications for compliance with applicable codes and regulations bearing on the work, and shall immediately report any discrepancy to the
SRCOG. Where the requirements of the drawings and specifications fail to conform to the applicable code, they shall be adjusted to conform to the code or regulations.
27.3 The Contractor shall secure and pay for all permits, fees, and licenses/taxes necessary for the proper execution and completion of the work.
28. BID SELECTION /REJECTION
28.1 Bid must include prices for all items listed in addition to the Base Bid
Price. Exclusion of any item will be considered grounds for rejection of the bid. The SRCOG reserves the right to reject any and all bids. (refer to
SRCOG Contract Selection Procedure)
28.2 The Steel Rivers Council of Governments reserves the right to award the contract in total or upon consultation with the member municipality, choose individual items based upon local priorities and/or funding availability.
29. CONTRACT BONDS
29.1 The Contractor to whom the Contract is awarded shall enter into a written
Agreement with the SRCOG and shall furnish a bond with surety in the full amount of the Contract price, conditioned for the faithful performance of the Contract in accordance with all the terms and provisions thereof, and a separate labor and Materials Bond with surety in the same amount, conditioned as provided by the ACT of Assembly of the Commonwealth of Pennsylvanian and containing the specified provisions therein set forth.
The SRCOG shall require that the Contractor observe the bonding requirements provided in Appendix B of Federal Management Circular
74-7; Uniform Administrative Requirements for Grants-in Aid to state and local governments. The surety of such bonds shall be a duly authorized surety company, subject to the approval of the SRCOG.
30. TERMINATION
30.1 In the case that the Contractor fails to furnish materials and equipment or execute work in accordance with the provisions of this Contract, or fails to proceed with or complete work within the time limit specified in this
Contract, or if the provisions of the Contract are otherwise violated by the
Contractor, the SRCOG shall have the right to declare the Contractor in default in the performance of his obligations under the Contract. The
SRCOG may proceed to have the work completed, and shall apply to the cost of having the work completed, any money due to the Contractor, and the Contractor shall be responsible for any damages resulting to the
SRCOG by reason of said default.
31. PROHIBITED INTEREST
31.1 No member, officer, or employee of the County or its designees or agents, no member of the governing body of the locality in which the program is situated, and no other public official of such to the Program during his tenure or for one year thereafter shall have any locality or localities who exercises any functions or responsibilities with respect to any interest, direct or indirect, in any Contract or subcontract or the proceeds thereof, for the work to be performed in connections with the Program assisted under this Contract.
32 PREVAILING WAGE RATES
32.1 The Contractor must pay the prevailing PA Wage Rate for all positions under this contract.
32.2 Contractor must submit certified payment sheets on a weekly basis to the
SRCOG CD Department. Failure to do so will result in a hold-up in the payment process.
Note: Payment of PA Prevailing Wage Rates DOES apply to this agreement.
Steel Rivers Council of Governments
Contract Selection Procedure
1. In all cases, solicitations of offers, whether by competitive sealed bids or competitive negotiation, shall:
A. Incorporate a clear and accurate description of the technical requirements for the material(s); product(s) or service(s) to be procured. Such description shall not, in competitive procurements, contain features that unduly restrict competition.
B. Clearly set forth all requirements which bidders must fulfill and all other factors to be used in evaluating bids or proposals.
2. Awards shall be made only to responsible contractors that possess the potential ability to perform successfully under the terms and conditions of the contract. Consideration shall be given to such matters as contractor integrity; compliance with specifications and public policy; record of past performance and experience and financial and technical resources.
3. Reasons for rejection of bids or proposals shall include, but not be limited to :
A. Failure to submit the proposal in the format required by the SRCOG;
B. Failure to sign and complete the bid proposal or any of the required affidavits, fringe benefits letter, and other certificates attached thereto;
C. Failure to furnish the required proposal guarantee;
D. The inclusion of conditions or qualifications not provided for in the bid proposal form;
E. Any part of the proposal form is detached;
F. If the proposal contains any omissions, erasures, alterations, additions not called for or irregularities of any other kind;
G. Any bid prices are obviously unbalanced;
H. Failure to submit with bid or proposal such statements which may be necessary to determine the adequacy and/or stability of a firm. Such statements shall include but are not limited to:
i. Financial Statement
ii. Qualification / Experience Statement
iii. List of Available Equipment
CONTRACT NO. _________
SAMPLE AGREEMENT
THIS AGREEMENT, made this _____ day of ______________ in the year Two Thousand Twenty-Six
BY AND BETWEEN
Steel Rivers Council of Governments (SRCOG)
1705 Maple Street
Homestead PA 15120
Acting as Administrative Agent as established under separate Project Administration Agreement for the Municipality of: __________________________ hereinafter referred to as “Municipality” and hereinafter referred to as “Contractor.”
WITNESSETH,
WHEREAS, Municipality requires the services of a Contractor to perform all work, to provide and furnish all labor, all necessary tools and equipment, all utility and transportation services and materials, both expendable and permanent, all as required in complete accordance with the Contract Specifications and other Documents for the successful completion of the project known as: .
WHEREAS, Contractor possesses experience and is skilled in the work to be performed; and
WHEREAS, Contractor has submitted a bid for the project, which bid has been accepted by the Municipality.
NOW, THEREFORE, in consideration of the mutual covenants contained hereafter and intending to be legally bound hereby, Municipality and Contractor mutually agree as follows:
ARTICLE 1. LOCATION AND OWNERSHIP OF PROJECT
Contractor understands that this project is located within the municipal boundaries of _________________.
ARTICLE 2. MANAGEMENT RESPONSIBILITIES
The Steel Rivers Council of Governments (SRCOG hereinafter) is recognized as the agent for Municipality in soliciting the proposal, accepting the bid, awarding the contract and administering the Act 152 Blight Removal program on behalf of Municipality for the project hereinafter described. Engineering guidance and technical supervision will be furnished by
Municipality. All work on the project must be performed to the satisfaction of Municipality. Any contract problems or disputes must be resolved between Contractor and Municipality.
ARTICLE 3. STATE-ASSISTED PROJECT
Contractor understands that this project is being assisted Act 152 funds provided through Allegheny County Economic
Development office, ACED hereinafter. Contractor therefore agrees to comply with any and all applicable regulations, conditions, and policies established by the Act 152 Program and the ACED.
ARTICLE 4. SCOPE OF WORK
The Contractor shall furnish all supervision, technical personnel, labor, materials, machinery tools, equipment, tests and services, including utility and transportation service and perform and complete all work required which consists of
All items shall be complete in place as fully specified and in accordance with the Drawings and Specifications for the project entitled:
Project Number - Project Name and, in strict accordance with the contract documents for this project, which are incorporated herein and made a part of this
Agreement, including all addenda thereto, as prepared by: (municipal engineer) .
ARTICLE 5. TIME OF COMPLETION
Work shall commence upon receipt of notice to proceed issued by Agent, Municipality’s engineer, architect or official managing the project and shall be completed within the time specified in the Contract Documents. All work shall be completed no later than thirty (30) calendar days from the date of written notice to proceed.
ARTICLE 6. CONTRACT SUM
Municipality will pay Contractor through SRCOG for performance of the Contract, for total quantities of work performed at the prices stipulated in the bid, subject to any additions and modifications provided therein and established in award, in current funds, the sum of
($__________). This sum is the Total Bid Amount.
It is understood and agreed to by the parties to this Agreement that the Municipality shall be solely obligated, and not the SRCOG, to pay any and all authorized costs in excess of those covered by the grant funds allocated for the project, said costs being the difference between the sum total of any and all construction/program related expenses as identified by the bid, together with applicable change orders, and the grant amount allocated to the project. SRCOG shall have no liability for any funds over and above those grant funds that are allocated and awarded to a project, and Municipality agrees to indemnify, defend and hold SRCOG harmless from any such liability.
ARTICLE 7. PAYMENTS
Contractor shall recognize that payment to Contractor by SRCOG is contingent upon receipt of funds from either Municipality or the
ACED. Funds are guaranteed, but a drawdown process shall be followed. Therefore, payments shall be subject to the following conditions and stipulations:
A. Contractor shall process all requests for payment through Municipality and its engineer, architect or official managing the project. No payments will be made unless first approved by Municipality and its engineer, architect or official managing the project. Payment will be in the amount approved by Municipality and its engineer, architect or official managing the project.
Any problems or disputes concerning the approved amount must be resolved between Contractor and Municipality. It is understood and agreed to by the parties to this Agreement that the Municipality shall be solely obligated, and not the
SRCOG, to pay any and all authorized costs in excess of those covered by the grant funds allocated for the project, said costs being the difference between the sum total of any and all construction/program related expenses as identified by the bid, together with applicable change orders, and the grant amount allocated to the project. SRCOG shall have no liability for any funds over and above those grant funds that are allocated and awarded to a project, and Municipality agrees to indemnify, defend and hold SRCOG harmless from any such liability.
B. When the written approval of Contractor’s request for payment is received from Municipality and its engineer, architect or official managing the project, SRCOG will commence the drawdown process for funds from the appropriate paying source within five (5) working days of receipt of same, provided that Contractor has submitted all documents required by the Act
152 Program. If all required documents have not been submitted, the drawdown process will not commence until said documents are received by SRCOG. In such case, the drawdown process will then commence within five (5) working days of receipt of the required Act 152 program documents.
C. If ACT 152 funds are involved, a request for those funds will be made from ACED. SRCOG shall pay the full amount of
ACT 152 funds received within three (3) working days following receipt of same from ACED. Same shall apply to final payment provided all provisions of the Contract Documents have been complied with. Contractor shall note that payment to
SRCOG from ACED may take up to eight (8) weeks for progress payments and ten (10) weeks for final payment. Contractor understands and agrees that neither SRCOG nor Municipality shall be responsible or liable for any delay in receiving payments from ACED. Contractor understands and agrees that SRCOG cannot and will not make payment of any portions of the project payable by ACED until those funds are received from ACED.
D. Contractor shall be responsible for submitting, in a timely fashion, on Contractor’s behalf and on behalf of any and all subcontractors retained by Contractor, as well as any lower tier subcontractors retained by Contractor’s subcontractors, all payrolls, monthly reports and any other documents required by the ACT 152 program. Failure to submit these items, or failure to submit properly completed documents may be cause for delay in Contractor receiving payment.
E. If Municipality’s funds are involved, SRCOG shall make a request for those funds from Municipality. SRCOG shall pay the full amount approved by Municipality following receipt from Municipality. Contractor understands and agrees that SRCOG cannot and will not make payment of any portions of the project payable by Municipality until those funds are received from
Municipality. SRCOG’s responsibility for securing these funds shall be limited to making the initial request for those funds from Municipality. Contractor further understands and agrees that SRCOG shall not be held responsible or liable for any delay in receiving payments from Municipality. It is understood and agreed to by the parties to this Agreement that the
Municipality shall be solely obligated, and not the SRCOG, to pay any and all authorized costs in excess of those covered by the grant funds allocated for the project, said costs being the difference between the sum total of any and all construction/program related expenses as identified by the bid, together with applicable change orders, and the grant amount allocated to the project. SRCOG shall have no liability for any funds over and above those grant funds that are allocated and awarded to a project, and Municipality agrees to indemnify, defend and hold SRCOG harmless from any such liability.
F. When submitting requests for payment, Contractor shall anticipate the approval time required by ACED and Municipality.
Contractor shall not impose or attempt to impose any time frame, number of days or dates by which payment shall be due.
Since this is a project assisted with Pennsylvania State Funds through the ACT 152 program, no local law is applicable to or governs this project, no interest charges shall be permitted on outstanding requests for payment, and no interest, fees or penalties shall accrue on any requests for payment made by Contractor.
G. All payments will be made through the SRCOG office.
H. Acceptance of final payment and negotiation of the check representing final payment by Contractor shall act as a release by
Contractor of any and all claims Contractor may have…