This is a cost breakdown template for a federal construction project involving ceiling replacement and office renovation work at the US Embassy Madrid Chancery Building. The document outlines three separate Contract Line Items (CLINs) with detailed scope items and quantities for measuring and estimating costs.
CLIN 1 encompasses 63 square meters of work including demolition of false ceilings with plaster and existing luminaires, removal and reinstallation of installations, furniture relocation, removal of Armstrong Sahara 60x60 cm false ceiling panels, installation of LED screens (20 units), painting of vertical walls with two coats of RAL 9010 washable plastic paint covering 112 square meters, and ancillary services such as waste management and safety/security measures. CLIN 2 represents the largest scope at 684 square meters of false ceiling demolition, includes supply and installation of 684 square meters of Armstrong Sahara false ceiling, adaptation of electrical installations to double lighting points (138 units), formation of 300 linear meters of partition walls, installation of 138 LED screens, creation of 100 linear meters of masonry ruts, smoothing and painting of 321 square meters of vertical walls, supply and installation of 9 new doors, and 125 linear meters of baseboard installation. CLIN 3 covers 30 square meters of false ceiling work with similar scope elements including demolition, supply and installation of Armstrong Sahara ceiling, electrical adaptation for 15 light points, 30 linear meters of partitions, 15 LED screen installations, 30 linear meters of masonry ruts, and painting/finishing of 70 square meters of wall space and 70 linear meters of baseboard. All measurements are noted as estimates with offerors responsible for independent verification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1.docx | DOCX document | |
| Attachment 8 Drawings V1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 All measurements included here are estimates. Each Offeror is responsible for taking its own measurements.
| Presupuesto | |||||
| Código | Ud | Item | Mes | CanPres | Pres |
| CLIN 1 : TSS RELOCATION | |||||
| 1.01 | ud | Cover of all area | 1 | ||
| 1.02 | m2 | Demolition of false ceiling with plaster including disconnection and removal of existing screen-type luminaires, PCI , exhaust grills. | 63 | ||
| 1.03 | pa | Removal of installations in the affected area and reinstallation once works are finished. | 1 | ||
| 1.04 | pa | Removal of furniture. | 1 | ||
| 1.05 | m2 | Removal of false ceiling type Armstrong Sahara 60x60 cm or similar Auxiliary anchors included. Fully assembled. | 63 | ||
| 1.06 | m2 | Installation of retired false ceiling type Armstrong Sahara 60x60 cm Auxiliary anchors included. Fully assembled. | 63 | ||
| 1.07 | ud | Installation of LED screens 60x60 series according to the technical specifications provided by the Embassy in false ceiling type Armstrong 60x60. | 20 | ||
| 1.08 | m2 | Supply of paint and application of 2 coats of plastic paint washable on vertical walls inside the offices. RAL 9010. | 112 | ||
| 1.09 | pa | Removal and relocation of heavy furniture inside the office itself, in order to smooth and paint. Includes protection. | 1 | ||
| 1.1 | PA | Reinstallation of disconnected installation. | 1 | ||
| 1.11 | pa | Waste mangement. | 1 | ||
| 1.12 | pa | Safety and security. | 1 | ||
| 1.13 | pa | Miscellaneous. | 1 | ||
| CLIN2 | |||||
| 1.01 | ud | Protection of all working area | 1 | ||
| 1.02 | m2 | Demolition of false ceiling with plaster including disconnection and removal of existing screen-type luminaires, PCI , exhaust grills. | 684 | ||
| 1.03 | pa | Removal of installations in the affected area and reinstallation once works are finished. | 1 | ||
| 1.04 | pa | Removal furniture | 1 | ||
| 1.05 | pa | Removal baseboard and doors | 1 | ||
| 1.06 | m2 | Supply and installation of false ceiling type Armstrong Sahara 60x60 cm or similar Auxiliary anchors included. Fully assembled. | 684 | ||
| 1.07 | ud | Adapt the current electrical installation to double the current points of light. | 138 | ||
| 1.08 | ml | Formation of partition of h=40 cm in false ceiling type Armstrong 60x60 Sahara or similar. | 300 | ||
| 1.09 | ud | Supply and installation of LED screens 60x60 series according to the technical specifications provided by the Embassy in false ceiling type Armstrong 60x60. | 138 | ||
| 1.1 | ml | Creation of masonry ruts to hide current installations. Includes demolition, removal of debris, and plastering prior to painting work | 100 | ||
| 1.11 | m2 | Smoothing of the vertical walls inside the offices. | 321 | ||
| 1.12 | m2 | Supply and application of 2 coats of plastic paint washable on the vertical walls inside the offices. RAL 9010. | 321 | ||
| 1.13 | m2 | Supply and installation of new doors | 9 | ||
| 1.14 | ml | Supply and installation baseboard | 125 | ||
| 1.15 | PA | Reinstallation of installation disconnected | 1 | ||
| 1.16 | pa | Removal and relocation of heavy furniture inside the office itself, in order to smooth and paint. Includes protection. | 1 | ||
| 1.17 | pa | Waste mangement. | 1 | ||
| 1.18 | pa | Safety and security. | 1 | ||
| 1.19 | pa | Miscellaneous. | 1 | ||
| CLIN3 | |||||
| 1.01 | ud | Cover of all area | 1 | ||
| 1.02 | m2 | Demolition of false ceiling with plaster including disconnection and removal of existing screen-type luminaires, PCI , exhaust grills. | 30 | ||
| 1.03 | pa | Removal of installations in the affected area and reinstallation once works are finished. | 1 | ||
| 1.04 | pa | Removal furniture inside the office itself, in order to smooth and paint. Includes protection. | 1 | ||
| 1.05 | pa | Removal baseboard. | 1 | ||
| 1.06 | m2 | Supply and installation of false ceiling type Armstrong Sahara 60x60 cm or similar Auxiliary anchors included. Fully assembled. | 30 | ||
| 1.07 | ud | Adapt the current electrical installation to double the existing points of light. | 15 | ||
| 1.08 | ml | Formation of partition of h=40 cm in false ceiling type Armstrong 60x60 Sahara or similar. | 30 | ||
| 1.09 | ud | Supply and installation of LED screens 60x60 series according to the technical specifications provided by the Embassy in false ceiling type Armstrong 60x60. | 15 | ||
| 1.1 | ml | Creation of masonry ruts to hide the current installations. Includes demolition, removal of debris, and plastering prior to painting work | 30 | ||
| 1.11 | m2 | Smoothing of vertical walls inside the offices. | 70 | ||
| 1.12 | m2 | Supply of paint and application of 2 coats of plastic paint washable on vertical walls inside the offices. RAL 9010. | 70 | ||
| 1.13 | ml | Supply and installation baseboard. | 70 | ||
| 1.14 | PA | Reinstallation of disconnected installation. | 1 | ||
| 1.15 | pa | Removal and relocation of heavy furniture inside the office itself, in order to smooth and paint. Includes protection. | 1 | ||
| 1.16 | pa | Waste mangement. | 1 | ||
| 1.17 | pa | Safety and security. | 1 | ||
| 1.18 | pa | Miscellaneous. | 1 |