QUESTIONS AND ANSWERS_19RP3825Q0117.pdf

PDF 102 KB Posted

Attached to
EXTERIOR REPAINTING OF NOX 1 BLDG.
Solicitation number
19RP3825Q0117
Issued by

About this file

This document is a Questions and Answers (Q&A) file for Request for Quote (RFQ) No. 19RP3825Q0117 for the Exterior Repainting of NOX 1 Building. The Q&A addresses four key questions from potential contractors regarding work logistics, including personnel limitations, work location flexibility, painting procedures during rain, and equipment usage. For each question, the responses direct bidders to refer to specific sections in Amendment 001 and Attachment 5 - Scope of Work, indicating that detailed instructions and requirements are contained in those referenced documents. The RFQ appears to be for a painting project at an embassy location, with specific procedural and safety protocols that contractors must follow.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P a g e | 1

QUESTIONS AND ANSWERS

RFQ No. 19RP3825Q0117

EXTERIOR REPANTING OF NOX 1 BLDG.

Q1: Is there a limit of personnel to work at the embassy due to escort availability?

A1: Refer to Amendment 001 and ATTACHMENT 5 – SCOPE OF WORK, Subparagraph 12.4

Q2: Is it possible to work on separate places, for example some personnel at the rooftop doing scraping jobs while the other personnels doing sealant of windows?

A2: Refer to Amendment 001 and ATTACHMENT 5 – SCOPE OF WORK, Subparagraphs 11.1 and 12.4

Q3: While painting or after painting, it suddenly rains, what will be the consequence of our painting? Do we have to do it again?

A3: Refer to ATTACHMENT 5 – SCOPE OF WORK, Subparagraph 8.3.

Q4: Can we use any equipment as long as it follows safety protocol?

A4: Refer to Amendment 001 and ATTACHMENT 5 – SCOPE OF WORK, Subparagraph 13.5