19NP4025R0006 _Pipelines Upgradation and Installation Works.pdf

PDF 815 KB Posted

Attached to
Pipelines Upgradation and Installation Works
Solicitation number
19NP4025R0006
Issued by

About this file

This document is a Request for Quote (RFQ) for Pipelines Upgradation and Installation Works at the U.S. Embassy in Kathmandu, Nepal. The project involves designing, supplying, and installing two distinct potable water pipeline systems: a 350-meter raw water pipeline from Well 1 to the Singh House Raw Water Tank using 3-inch SCH 80 NSF-certified PVC pipes, and a 175-meter treated water pipeline from the Singh House Treated Water Tank to the Utility Building Treated Water Tank using 2-inch SCH 80 NSF-certified PVC pipes. The installation includes wall-mounted pipe supports, minimal excavation, gate and check valves, and two centrifugal pumps with automated controls.

The solicitation (RFQ 19NP4025R0006) is issued by the American Embassy Kathmandu with a site visit scheduled for August 5, 2025, and offers due by August 20, 2025. The contract will be for a one-year period, with work to be completed within 60 calendar days of award. The procurement is unrestricted, and the contract will be awarded to the lowest-priced, acceptable, and responsible offeror. Contractors must comply with specific technical standards including NSF/ANSI 61 for potable water systems, ASME B31.3 for process piping, and provide a one-year warranty on materials and workmanship. A pre-bid site inspection is mandatory for interested contractors.

View the file

Other files

File Type Posted
19NP4025R0006 _Cover Letter PUIW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SBU - CONTRACTING AND ACQUISITIONS

TABLE OF CONTENTS

SECTION 1 - THE SCHEDULE

• SF 1449 cover sheet

• Continuation To SF-1449, RFQ Number 19NP4025R0006, Prices, Block 23

• Continuation To SF-1449, RFQ Number 19NP4025R0006, Schedule Of

Supplies/Services, Block 20 Description/Specifications/Work Statement

• Attachment 1 to Description/Specifications/Performance Work Statement, Government Furnished Property

SECTION 2 - CONTRACT CLAUSES

• Contract Clauses

• Addendum to Contract Clauses - FAR and DOSAR Clauses not Prescribed in Part 12

SECTION 3 - SOLICITATION PROVISIONS

• Solicitation Provisions

• Addendum to Solicitation Provisions - FAR and DOSAR Provisions not Prescribed in

Part 12

SECTION 4 - EVALUATION FACTORS

• Evaluation Factors

• Addendum to Evaluation Factors - FAR and DOSAR Provisions not Prescribed in

Part 12

SECTION 5 - REPRESENTATIONS AND CERTIFICATIONS

• Offeror Representations and Certifications

• Addendum to Offeror Representations and Certifications - FAR and DOSAR

Provisions not Prescribed in Part 12

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

PR15453863

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

19NP4025R0006

6. SOLICITATION ISSUE DATE

Jul/21/2025

7. FOR SOLICITATION

INFORMATION CALL

a. NAME Sanju Gurung

b. TELEPHONE NUMBER (No collect calls)

014234000

8. OFFER DUE DATE/

LOCAL TIME

Aug/20/2025

9. ISSUED BY CODE

10. THIS ACQUISITION IS

American Embassy Kathmandu Bramha Cottage, Narayan Gopal Sadak, Maharajgunj, Kathmandu

X UNRESTRICTED

SET ASIDE: % FOR

SMALL BUSINESS EMERGING SMALL BUSINESS

HUBZONE SMALL BUSINESS SMALL BUSINESS

SERVICE-DISABLED VETERAN OWNED 8(A)

NAICS: 924110

SIZE STD:

11. DELIVERY FOR FOB 12. DISCOUNT

13a. THIS CONTRACT IS A RATED ORDER

DESTINATION UNLESS BLOCK IS MARKED

SEE SCHEDULE

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO: Code 16. Administered by:

American Embassy Kathmandu Attn: General Services Officer Maharajgunj, Kathmandu ktmcontracts@state.gov

General Services Officer American Embassy Kathmandu Bramha Cottage, Narayan Gopal Sadak, Maharajgunj, Kathmandu

17.a. CONTRACTOR/OFFEROR CODE FACILITY CODE

18a. PAYMENT WILL BE MADE BY Financial Management Officer American Embassy Kathmandu Bramha Cottage, Narayan Gopal Sadak, Maharajgunj, Kathmandu

17b CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS

BLOCK BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT in US$

Pipelines Upgradation and Installation Works in U.S.

Embassy, Kathmandu, Nepal in accordance with Scope of Work (SOW).

(Use Reverse and/or Attach Additional Sheets as Necessary) all

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a.SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA X ARE ARE NOT ATTACHED.

27b.CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA X ARE ARE NOT ATTACHED.

X 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN __2___

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

HEREIN.

29. AWARD OF CONTRACT: REF. _________________ OFFER

DATED _______________. YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH

ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT)

30c. DATE SIGNED

31b. NAME OF CONTRACTING OFFICER (Type or Print)

William J Miskelly

31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FOR 1449 (REV3/2005)

PREVIOUS EDITION IS NOT USABLE Computer Generated Prescribed by GSA - FAR (48

CFR)

mailto:ktmcontracts@state.gov

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

1.

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ____________________________

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED

CORRECT FOR

36. PAYMENT 37. CHECK NUMBER

PARTIAL FINAL

COMPLETE PARTIAL FINAL

38. S/R ACCOUNT NO.

39. S/R VOUCHER NO. 40. PAID BY

41.a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 42a. RECEIVED BY (PRINT) 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41C. DATE

42b. RECEIVED AT (Location) 42c. DATE REC’D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 3/2005) BACK

SECTION 1 - THE SCHEDULE

CONTINUATION TO SF-1449

RFQ NUMBER SNP 19NP4025R0006

PRICES, BLOCK 23

I. PERFORMANCE WORK STATEMENT

A. The purpose of this solicitation is for to provide Pipelines Upgradation and Installation

Works Services in U.S. Embassy, Kathmandu, Nepal in accordance with Attachment A Scope of Work (SOW).

B. The contract will be for a one-year period from the date of the contract award.

QUALITY ASSURANCE AND SURVEILLANCE PLAN (QASP)

This plan provides an effective method to promote satisfactory contractor performance. The QASP provides a method for the Contracting Officer's Representative (COR) to monitor Contractor performance, advise the Contractor of unsatisfactory performance, and notify the Contracting Officer of continued unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the contract.

The role of the Government is to monitor quality to ensure that contract standards are achieved.

Performance Objective Scope of Work

Paragraphs Performance Threshold

Services.

Pipelines Upgradation and Installation Works Services in U.S.

Embassy, Kathmandu, Nepal in accordance with Scope of Work

(SOW).

Whole SOW

All required services are performed and no more than one

(1) customer complaint is received per month.

II. PRICING

SCHEDULE, SUPPLIES/SERVICES, SF-1449 Continuation Page

III. VALUE ADDED TAX

VAT VERSION A

VALUE ADDED TAX. Value Added Tax (VAT) is not included in the CLIN rates. Instead, it will be priced as a separate Line Item in the contract and on Invoices. Local law dictates the portion of the contract price that is subject to VAT; this percentage is multiplied only against that portion. It is reflected for each performance period. The portions of the solicitation subject to VAT are:

OR

NOTICE TO PROCEED

After Contract award and submission of acceptable insurance certificates and copies of all applicable licenses and permits have been provided, the Contracting Officer will issue a Notice to Proceed. The Notice to Proceed will establish a date (a minimum of ten (10) calendar days from date of Contract award unless the Contractor agrees to an earlier date) on which performance shall start.

CLIN Description Quantity of Equipment

Type of services

No. of service

Unit price / service

Total ($)

Pipelines Upgradation and

Installation Works Services

002 Applicable 13%

VAT

Total

CONTINUATION TO SF-1449,

RFQ NUMBER 19NP4025R0006

SCHEDULE OF SUPPLIES/SERVICES, BLOCK 20

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

Scope of Work (SOW).

PROJECT: PIPELINES UPGRADATION AND INSTALLATION WORKS AT US

EMBASSY (KATHMANDU)

PROJECT DESCRIPTION

The Chancery Water Pipeline Installation project aims to establish a reliable and efficient potable water distribution system at the Chancery site. The project encompasses the design, supply, installation, and commissioning of two distinct piping systems to ensure the seamless transport of water to meet the facility's operational needs.

The first component involves the installation of a raw water pipeline from Well 1 to the Singh House Raw Water Tank, spanning approximately 350 meters. This system will utilize 3-inch SCH 80, NSF-certified PVC pipes and fittings, anchored to existing walls or structures with robust supports to minimize excavation. Excavation will be limited to areas where wall anchoring is not feasible, such as road crossings, ensuring minimal disruption to the site.

The second component entails the installation of a treated water pipeline from the Singh House Treated Water Tank to the Utility Building Treated Water Tank, covering approximately 175 meters. This system will employ 2-inch SCH 80, NSF-certified PVC pipes and fittings, also anchored to walls with appropriate supports. The treated water system includes the installation of two centrifugal pumps (one operational and one standby) with automated controls, including pressure switches, flow meters, and a control panel, to ensure consistent and efficient water delivery.

Both pipelines will adhere to NSF/ANSI 61 standards for potable water systems and ASME B31.3 for process piping, with comprehensive pressure testing and quality assurance measures to guarantee leak-free operation. The project prioritizes minimal environmental impact through reduced excavation and leverages existing infrastructure for pipe anchoring. The installation will be completed within 60 calendar days from contract award, subject to weather and site conditions, and includes a one-year warranty on materials and workmanship.

This project will enhance the Chancery's water supply infrastructure, ensuring reliable access to both raw and treated water for operational and utility purposes, while maintaining compliance with industry standards and local regulations.

PRE-BIDDING SITE VISIT

Prior to submitting quotes, all interested contractors are required to attend a site inspection and visit. The site visit shall be held on Aug/5/2025 at 14:00 hours at US Embassy, Kathmandu.

SCOPE OF WORK

The Contractor shall be responsible for providing all the materials, labor and equipment necessary to construct, install, build and complete each phase according to the project description, drawings, specifications and requirements.

Pipe Installation from Well 1 to Singh House Raw Water Tank

• Objective: Supply and install a potable water piping system to transport raw water from Well 1 to Singh House Raw Water Tank.

• Pipe Specifications: SCH 80, NSF-certified, minimum 3-inch diameter.

• Distance: Approximately 350 meters, based on field measurements.

• Scope of Work:

o Supply and install 3-inch SCH 80 NSF-certified pipes and necessary fittings (e.g., elbows, tees, couplings, reducers).

o Anchor pipes to existing walls or structures using proper supports (e.g., pipe clamps, brackets, and structural steel) designed to withstand operational loads.

o Minimize excavation, performing it only in areas where wall anchoring is not feasible or where underground routing is required (e.g., road crossings).

Excavation, when necessary, shall be to a minimum depth of 0.6 meters or as per local codes.

o Install pipes with proper alignment, slope, and support as per industry standards (e.g., ASME B31.3).

o Perform pressure testing and flushing to ensure leak-free operation.

o Restore any excavated areas with backfill and surface reinstatement as required.

o Provide necessary valves (e.g., gate valves, check valves) for system isolation and control.

Pipe Installation from Singh House Treated Water Tank to Utility Building Treated Water

Tank

• Objective: Supply and install a treated water piping system, including pumps and controls, from Singh House Treated Water Tank to the Utility Building Treated Water Tank.

• Pipe Specifications: SCH 80, NSF-certified, 2-inch diameter.

• Distance: Approximately 175 meters, based on field measurements.

• Scope of Work:

o Supply and install 2-inch SCH 80 NSF-certified pipes and fittings (e.g., elbows, tees, couplings, reducers).

o Anchor pipes to existing walls or structures using proper supports (e.g., pipe clamps, brackets, and structural steel) designed to withstand operational loads.

o Minimize excavation, performing it only in areas where wall anchoring is not feasible or where underground routing is required (e.g., road crossings).

Excavation, when necessary, shall be to a minimum depth of 0.6 meters or as per local codes.

o Install pipes with proper alignment, slope, and support as per industry standards (e.g., ASME B31.3).

o Supply and install centrifugal pumps (minimum 2 units, including one standby) with necessary controls (e.g., pressure switches, flow meters, control panels).

o Perform pressure testing and flushing to ensure leak-free operation.

o Restore any excavated areas with backfill and surface reinstatement as required.

o Provide necessary valves (e.g., gate valves, check valves) for system isolation and control.

o Commission the pumping system and integrate controls for automated operation.

Protection and Clean-up of Site

• The Contractor shall at all times protect and preserve all materials, supplies and equipment of every description, including USG property. All reasonable requests of the Contracting Officer to enclose to specially protect such property shall be complied with.

If, as determined by the COR, material, equipment, supplies and work performed are not adequately protected by the contractor, such property may be protected by the USG and the cost thereof may be charged to the contractor or deducted from any payments due to him.

GENERAL REQUIREMENTS

Standards and Compliance:

o All materials shall comply with NSF/ANSI 61 standards for potable water systems.

o Installation shall adhere to ASME B31.3 (Process Piping) and local plumbing codes.

o For outdoor installations, all pipes must be protected against UV radiation using one or more of the following methods: UV-resistant paint, pipe wrapping, insulation jackets, protective coatings, or pipe enclosures. The contractor shall select the most appropriate method based on site conditions and submit the proposed protection plan for approval prior to installation.

o Pipe supports and anchors shall be designed per relevant standards o The piping system design shall prioritize minimizing the use of 90-degree bends.

Contractors are encouraged to use gradual bends or multiple smaller angle bends (e.g., 45-degree bends) to optimize flow efficiency. Any use of 90-degree bends must be justified with technical reasoning or site constraints.

o All work shall comply with OSHA safety standards.

Quality Assurance:

o Provide material certifications for all pipes, fittings, pumps, controls, and support structures.

o Conduct pressure tests at 1.5 times the operating pressure for a minimum of 4 hours.

o Submit as-built drawings, including support and anchor details, and test reports upon completion.

Schedule:

o Complete all work within 60 calendar days from the date of contract award, subject to weather and site conditions.

Warranty:

o Provide a minimum 1-year warranty on materials and workmanship.

Submittals:

o Submit shop drawings, material specifications, and support design calculations for approval prior to installation.

o Submit draft pressure loss calculations and a preliminary piping layout during the proposal submission phase. These documents should include major and minor losses, pipe routing, fittings, and flow rates. Upon contract award, detailed pressure loss calculations, control schemes and finalized piping layouts, including elevations, dimensions, and adjustments based on site conditions, must be submitted for approval.

o Provide operation and maintenance manuals upon project completion.

Exclusions o Utility connections (power, water) beyond the scope of the piping system.

o Major landscaping or structural modifications not directly related to pipe installation.

SCHEDULE OF REQUIREMENTS

Pipe Installation from Well 1 to Singh House Raw Water Tank

Item No.

Description Unit Quantity

1 3" SCH 80 NSF-certified PVC pipe m 385 (350 + 10% contingency)

2 3" SCH 80 NSF-certified fittings (elbows, tees, couplings, etc.)

lot 1

3 3" Gate valves (NSF-certified) no. 4

4 3" Check valves (NSF-certified) no. 2

5 Excavation and backfilling (0.6 m depth, 10% of route) m 35

6 Pipe supports and anchors (wall-mounted, including clamps and structural steel) lot 1

7 Pressure testing and flushing lot 1

Pipe Installation from Singh House Treated Water Tank to Utility Building Treated Water

Tank

Item No.

Description Unit Quantity

1 2" SCH 80 NSF-certified PVC pipe m 193 (175 + 10% contingency)

2 2" SCH 80 NSF-certified fittings (elbows, tees, couplings, etc.)

lot 1

3 2" Gate valves (NSF-certified) no. 3

4 2" Check valves (NSF-certified) no. 2

5 Centrifugal pump (7.5 HP, NSF-compliant, including standby)

no. 2

6 Control panel (pressure switches, motorized valves, flow meters, control cable, automation) lot 1

7 Excavation and backfilling (0.6 m depth, 10% of route) m 17.5

8 Pipe supports and anchors (wall-mounted, including clamps and structural steel) lot 1

9 Pressure testing and flushing lot 1

10 Commissioning of pumps and controls lot 1

Notes

• Quantities are approximate and subject to verification during detailed engineering.

• The schedule assumes straight-line distances; actual pipe routes may require additional fittings.

• Excavation is minimized to 10% of the pipe length, with wall-mounted supports used for the majority of the route.

• All materials and installations shall comply with specified standards and be subject to quality assurance checks.

WARRANTY

• The contractor shall provide at least one year fully documented warranties on all equipment, materials and workmanship.

BID PRICING

• The Lump Sum Bid price has to be presented in a unit price breakdown format to facilitate the comparison of bids by the procurement officer. If any change orders are necessary due to changes in conditions or quantity reduction or increases the prices presented in a unit price format will be used as a reference price. Any item not included in the unit price list that is required by the project description, drawings or the specifications shall be included as a prorated part of all the listed items.

ATTACHMENT AND REFERENCES

S. N Details of Attachment Remarks 1 Layout Plan

RESPONSIBILITY OF THE CONTRACTOR

• The Contractor shall provide and get approvals Working methodology, Safety plan, Activity Hazard Analysis (AHA) and work schedule.

• The Contractor shall provide a quantity of personnel, transportation, equipment, materials, tools, and supervision as needed to complete the services and technical requirements in the Statement of Work (SOW).

• The Contractor shall provide to the COR a project schedule within 3 days of contract award date.

• The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period. The work shall be completed in 60 days from the contract award date. The start date shall be within 10 days after the contract is awarded.

• The Contractor shall be required to prepare and submit reports, bill of materials, drawings, specifications, quality control schedules, safety plan and construction costs.

• Work Hours: Shall be as per the local labor law.

• The Contractor shall designate and make available a representative to meet with the

Contracting Officer’s Representative (COR) weekly to discuss the Progress of the Project.

• The Contractor shall ensure that the overall program is executed smoothly, delivered on schedule, and within the project budget.

• It is the Contractor's responsibility to ensure the safe handling, application, removal, and environmentally sound disposal of all hazardous or potentially hazardous chemicals used under this contract.

SAFETY:

• After the contract is awarded, Contractor shall submit Specific Safety Plan for this project which includes work methodology, list of tools and equipment, PPE, work schedule, emergency contact numbers and Activity Hazard Analysis (AHA). Post Occupational Safety and Health Officer (POSHO) and Assistant Post Occupational Safety and Health Officer) A-POSHO shall review and approve contractor’s Safety Plan and AHA. AHA is required for operating power tool - stone cutter.

• The Contractor shall be responsible for conducting the work in a manner that ensures the safety of its employees and USG employees/personnel at the project site during the entire project.

• The Contractor shall be responsible for any mishaps, injuries or accidents which occur during the project. Any mishaps and near misses involving the contractor’s employees must be reported to the COR, the POSHO and APOSHO at the earliest on the same day.

• Based on hazard assessments, the Contractor must provide or afford each affected employee Personal Protective Equipment (PPE) that shall protect the employee from hazards. At a minimum PPE should consist of safety glasses and/or goggles for eye protection, hard hats for head protection, appropriate gloves, and closed-toe shoes.

Closed shoes with steel toe are mandatory for employees using power actuated tools (e.g., a jack hammer, pick for excavation, axe for cutting trees, and for work that requires lifting heavy materials, etc.). Sandals or athletic shoes are not acceptable. PPE such as gloves, dust masks, earplugs, hard hats, safety shoes, and coveralls and face shields are recommended for contracted personnel. These items must be provided at the Contractor’s expense. All contractor personnel shall wear PPEs as identified in the Safety Plan, and/or deemed necessary by the COR, (Facility Manager) FM/POSHO or A-POSHO. Workers may use discretion if they feel unsafe in using the equipment. The Contractor must not create an unsafe or hostile work environment for its personnel.

• Any worker at an elevated and unprotected location above 1.8 meters (6 feet), except for a portable ladder or balcony with railings, must be provided and utilize a safety harness with lanyard. These items must be in good condition and free from cuts and damages.

• Scaffoldings should be provided by Contractors for working at heights where ladder use is unsafe. Full body fall harness with lanyard should also be used by the Contractor.

Bamboo scaffolding is not allowed to be used at USG properties and leased residences.

The Contractor shall use only COR and/or POSHO/APOSHO approved metal scaffoldings with platforms and bracing.

• Welders must have proper PPE: welding goggles/mask, leather gloves, apron or welding jacket that is fire rated. Fire Watch with dedicated fire extinguisher should be on the vicinity of work site. Fire curtain should be used not to expose welding sparks to others.

Contractor must obtain Embassy’s Hot Work Permit (see attachment) daily before commencing any hot work (cutting, grinding, welding). Hot work equipment must be in good condition. Fire safe materials shall be placed under any welding or hot work to protect the surface under the work and prevent ignition of surfaces.

• Safe Electrical Work Practices: The Contractor must follow safe electrical work practices to prevent electric shock, arc flash, or other injuries resulting from either direct or indirect contact with electrical circuits or equipment which are or may be energized.

• Respiratory Protection: Approved respirator mask (half face/full face) shall be used while performing work that produces toxic organic vapors. For example: epoxy or spray-painting work, using adhesives, using coil cleaners, using Hydrochloric acid (HCl) for cleaning, etc. The Contractor must provide respirator(s) with the correct type of cartridge to every employee (respirator should not be shared between employees); and masks/ respirators must pass the fit test for workers using them. The room/area where vaporous work is being conducted shall be well ventilated to prevent excess and prolonged exposure to vapors. Dust masks are not an acceptable replacement for respirators.

• Housekeeping: The Contractor shall keep the site clean and organized daily to prevent slip, trip, and fall hazards.

• The COR, GTM, SME, POSHO or APOSHO can stop work at any time if unsafe working conditions are observed or encountered. The Embassy Escort can also temporarily stop work for any unsafe action while one of the above responds to the worksite to examine the situation and make a final determination as to the safety of contracted personnel.

• The Contractor’s and its employees shall attend mandatory safety briefings and training provided by the US Embassy Safety team before the start of, or any phase thereof, the project.

• The Contactor must have a competent person on-site for inspection of equipment, training workers in the safe use of equipment and the recognition of hazards related to their use, supervision, and identifying and correcting unsafe work practices for high hazard work.

• Contractors, construction managers, and subcontractors engaged in replacement operations shall institute and maintain all safety measures required by the local law and provide all equipment or temporary construction installations necessary to safeguard the public and property affected by such contractor’s operations.

SECURITY

• After award of contract, contractor must submit names of their personnel, list of tools, equipment, vehicles information to complete the entire work within 60 working days after signing of contract.

PROJECT SCHEDULE

The Contractor shall commence work under this contract promptly upon Contract Award, execute the work diligently, and achieve final completion and acceptance of the project, including final cleanup of the premises, within the contr

SECTION 2 - CONTRACT CLAUSES

52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS

(NOV 2023) IS INCORPORATED BY REFERENCE. (SEE SF-1449,

BLOCK 27A)

FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Products and Commercial Services (JAN 2025) (DEVIATION FEB 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) ( 31 U.S.C. 3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Jun 2020), with Alternate I (Nov 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).

__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

__ (4) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) ( 41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).

_X_(5) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (6) [Reserved].

https://www.acquisition.gov/far/52.203-19#FAR_52_203_19 https://www.acquisition.gov/far/52.204-23#FAR_52_204_23 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.acquisition.gov/far/52.209-10#FAR_52_209_10 https://www.acquisition.gov/far/52.232-40#FAR_52_232_40 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3801&num=0&edition=prelim https://www.acquisition.gov/far/52.233-3#FAR_52_233_3 https://www.acquisition.gov/far/52.233-4#FAR_52_233_4 https://www.acquisition.gov/far/52.203-6#FAR_52_203_6 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section4655&num=0&edition=prelim https://www.acquisition.gov/far/52.203-13#FAR_52_203_13 https://www.acquisition.gov/far/52.203-15#FAR_52_203_15 https://www.acquisition.gov/far/52.203-17#FAR_52_203_17 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section4712&num=0&edition=prelim https://www.acquisition.gov/far/3.900#FAR_3_900 https://www.acquisition.gov/far/52.204-10#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim

_X_(7) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_(9) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division R of Pub. L. 117-328).

__ (10) 52.204-28, Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (Dec 2023) ( Pub. L. 115–390, title II).

__ (11)

(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (Dec 2023) ( Pub. L. 115–390, title II).

__ (ii) Alternate I (Dec 2023) of 52.204-30.

_X_(12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025) ( 31 U.S.C. 6101 note).

__ (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) ( 41 U.S.C. 2313).

__ (14) [Reserved].

__ (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Oct 2022) ( 15 U.S.C. 657a).

__ (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (17) [Reserved] __ (18)

(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-6.

__ (19)

(i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-7.

__ (20) 52.219-8, Utilization of Small Business Concerns (Jan 2025)( 15 U.S.C. 637(d)(2) and (3)).

__ (21)

(i) 52.219-9, Small Business Subcontracting Plan (Jan 2025) ( 15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Nov 2016) of 52.219-9.

__ (iii) Alternate II (Nov 2016) of 52.219-9.

__ (iv) Alternate III (Jun 2020) of 52.219-9.

__ (v) Alternate IV (Jan 2025) of 52.219-9.

__ (22)

(i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

__ (ii) Alternate I (Mar 2020) of 52.219-13.

__ (23) 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s).

__ (24) 52.219-16, Liquidated Damages—Subcontracting Plan (Sep 2021) (15 U.S.C. 637(d)(4)(F)(i)).

https://www.acquisition.gov/far/52.204-14#FAR_52_204_14 https://www.acquisition.gov/far/52.204-15#FAR_52_204_15 https://www.acquisition.gov/far/52.204-27#FAR_52_204_27 https://www.acquisition.gov/far/52.204-28#FAR_52_204_28 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.acquisition.gov/far/52.209-6#FAR_52_209_6 https://www.govinfo.gov/link/uscode/31/6101 https://www.acquisition.gov/far/52.209-9#FAR_52_209_9 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section2313&num=0&edition=prelim https://www.acquisition.gov/far/52.219-3#FAR_52_219_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim https://www.acquisition.gov/far/52.219-4#FAR_52_219_4 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 https://www.acquisition.gov/far/52.219-8#FAR_52_219_8 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 https://www.acquisition.gov/far/52.219-14#FAR_52_219_14 https://www.acquisition.gov/far/52.219-16#FAR_52_219_16

__ (25) 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran- Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024) (15 U.S.C. 657f).

__ (26)

(i) 52.219-28, Postaward Small Business Program Representation (Jan 2025) (15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (Mar 2020) of 52.219-28.

__ (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Oct 2022) (15 U.S.C. 637(m)).

__ (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Oct 2022) (15 U.S.C. 637(m)).

__ (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) ( 15 U.S.C. 644(r)).

__ (30) 52.219-33, Nonmanufacturer Rule (Sep 2021) ( 15 U.S.C. 637(a)(17)).

__ (31) 52.222-3, Convict Labor (Jun 2003) (E.O.11755).

_X_(32) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Jan 2025)( E.O.

13126).

__ (33) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

__ (34)

(i) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).

__ (ii) Alternate I (Feb 1999) of 52.222-26.

__ (35)

(i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) ( 38 U.S.C. 4212).

__ (ii) Alternate I (Jul 2014) of 52.222-35.

__ (36)

(i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) ( 29 U.S.C. 793).

__ (ii) Alternate I (Jul 2014) of 52.222-36.

_X_(37) 52.222-37, Employment Reports on Veterans (Jun 2020) ( 38 U.S.C. 4212).

__ (38) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

_X_(39)

(i) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C. chapter 78 and E.O.

13627).

__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

__ (40) 52.222-54, Employment Eligibility Verification (Jan 2025) ( Executive Order 12989).

(Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

__ (41)

(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (42) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (May 2024) ( 42 U.S.C. 7671, et seq.).

https://www.acquisition.gov/far/52.219-27#FAR_52_219_27 https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 https://www.acquisition.gov/far/52.219-29#FAR_52_219_29 https://www.acquisition.gov/far/52.219-30#FAR_52_219_30 https://www.acquisition.gov/far/52.219-32#FAR_52_219_32 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section644&num=0&edition=prelim https://www.acquisition.gov/far/52.219-33#FAR_52_219_33 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.222-3#FAR_52_222_3 https://www.acquisition.gov/far/52.222-19#FAR_52_222_19 https://www.federalregister.gov/executive-order/13126 https://www.federalregister.gov/executive-order/13126 https://www.acquisition.gov/far/52.222-21#FAR_52_222_21 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title29-section793&num=0&edition=prelim https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 https://www.acquisition.gov/far/52.222-37#FAR_52_222_37 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-40#FAR_52_222_40 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 https://www.acquisition.gov/far/52.222-54#FAR_52_222_54 https://www.federalregister.gov/executive-order/12989 https://www.acquisition.gov/far/22.1803#FAR_22_1803 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 https://www.acquisition.gov/far/52.223-11#FAR_52_223_11 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim

__ (43) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (44) 52.223-20, Aerosols (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (45) 52.223-21, Foams (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (46) 52.223-23, Sustainable Products and Services (May 2024) ( E.O. 14057, 7 U.S.C.

8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l).

__ (47)

(i) 52.224-3 Privacy Training (Jan 2017) ( 5 U.S.C. 552 a).

__ (ii) Alternate I (Jan 2017) of 52.224-3.

__ (48)

(i) 52.225-1, Buy American-Supplies (Oct 2022) (41 U.S.C. chapter 83).

__ (ii) Alternate I (Oct 2022) of 52.225-1.

__ (49)

(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (NOV 2023) ( 19 U.S.C.

3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109- 169, 109-283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I [Reserved].

__ (iii) Alternate II (Jan 2025) of 52.225-3.

__ (iv) Alternate III (Feb 2024) of 52.225-3.

__ (v) Alternate IV (Oct 2022) of 52.225-3.

_X_(50) 52.225-5, Trade Agreements (NOV 2023) ( 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

_X_(51) 52.225-13, Restrictions on Certain Foreign Purchases (Feb 2021) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

__ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).

__ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).

_X_(55) 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) ( E.O. 13513).

__ (56) 52.229-12, Tax on Certain Foreign Procurements (Feb 2021).

_X_(57) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

__ (58) 52.232-30, Installment Payments for Commercial Products and Commercial Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

_X_(59) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (Oct2018) ( 31 U.S.C. 3332).

_X_(60) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).

__ (61) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).

__ (62) 52.239-1, Privacy or Security Safeguards (Aug 1996) ( 5 U.S.C. 552a).

https://www.acquisition.gov/far/52.223-12#FAR_52_223_12 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-20#FAR_52_223_20 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-21#FAR_52_223_21 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-23#FAR_52_223_23 https://www.federalregister.gov/executive-order/14057 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8102&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8102&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section6962&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section8259&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section552&num=0&edition=prelim https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section2112&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3805&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section4001&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title19-chapter29&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title19-chapter29&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-5#FAR_52_225_5 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section2501&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://www.acquisition.gov/far/52.225-13#FAR_52_225_13 https://www.acquisition.gov/far/52.225-26#FAR_52_225_26 https://www.acquisition.gov/far/52.226-4#FAR_52_226_4 https://www.acquisition.gov/far/52.226-5#FAR_52_226_5 https://www.acquisition.gov/far/52.226-8#FAR_52_226_8 https://www.federalregister.gov/executive-order/13513 https://www.acquisition.gov/far/52.229-12#FAR_52_229_12 https://www.acquisition.gov/far/52.232-29#FAR_52_232_29 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3805&num=0&edition=prelim https://www.acquisition.gov/far/52.232-30#FAR_52_232_30 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3805&num=0&edition=prelim https://www.acquisition.gov/far/52.232-33#FAR_52_232_33 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3332&num=0&edition=prelim https://www.acquisition.gov/far/52.232-34#FAR_52_232_34 https://www.acquisition.gov/far/52.232-36#FAR_52_232_36 https://www.acquisition.gov/far/52.239-1#FAR_52_239_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section552a&num=0&edition=prelim

__ (63) 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) (Sections 1821-1826, Pub. L.

118-31, 41 U.S.C. 3901 note prec.).

__ (64) 52.242-5, Payments to Small Business Subcontractors (Jan 2017) (15 U.S.C. 637(d)(13)).

__ (65)

(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2021) ( 46 U.S.C. 55305 and 10 U.S.C. 2631).

__ (ii) Alternate I (Apr 2003) of 52.247-64.

__ (iii) Alternate II (Nov 2021) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.] __ (1) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter67).

__ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) ( 29U.S.C.206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (May 2014) (41 U.S.C. chapter 67).

__ (7) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan 2022).

__ (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2022) (E.O. 13706).

__ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) (42 U.S.C. 1792).

__ (10) 52.247-69, Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking (Jan 2025) ( 49 U.S.C. 40118(g)).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract, and does not contain the clause at 52.215-2, Audit and Records-Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the https://www.acquisition.gov/far/52.240-1#FAR_52_240_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section3901&num=0&edition=prelim https://www.acquisition.gov/far/52.242-5#FAR_52_242_5 https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section55305&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section55305&num=0&edition=prelim https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://www.acquisition.gov/far/52.222-41#FAR_52_222_41 https://www.acquisition.gov/far/52.222-42#FAR_52_222_42 https://www.acquisition.gov/far/52.222-43#FAR_52_222_43 https://www.acquisition.gov/far/52.222-44#FAR_52_222_44 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title29-section206&num=0&edition=prelim https://www.acquisition.gov/far/52.222-51#FAR_52_222_51 https://www.acquisition.gov/far/52.222-53#FAR_52_222_53 https://www.acquisition.gov/far/52.222-55#FAR_52_222_55 https://www.acquisition.gov/far/52.222-62#FAR_52_222_62 https://www.acquisition.gov/far/52.226-6#FAR_52_226_6 https://www.acquisition.gov/far/52.247-69#FAR_52_247_69 https://www.govinfo.gov/link/uscode/49/40118 https://www.acquisition.gov/far/2.101#FAR_2_101 https://www.acquisition.gov/far/52.215-2#FAR_52_215_2 https://www.acquisition.gov/far/subpart-4.7#FAR_Subpart_4_7 records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement.