Q and A_19JA7026Q0084 (2026-05-27).pdf
PDF 153 KB Posted
- Solicitation number
- 19JA7026Q0084
- Issued by
-
Department of State
About this file
This file is a Questions and Answers document for Request for Quotations (RFQ) No. 19JA7026Q0084 issued by the U.S. Consulate General in Sapporo, Japan on May 27, 2026. The RFQ concerns A/C and Ceiling/Lighting Renewal work for the CAC (Community Advisory Committee area or similar facility) at the consulate.
The Q&A addresses technical and procedural matters relevant to the renovation work. Key clarifications include: electrical conduits may be supported by anchoring into steel frames with bolts, following manufacturer guidance for installation methods; separate total heat exchangers are acceptable for the Security Booth and Guard Booth ventilation; LED restroom lighting does not require dimmers; passageway lighting must remain operational 24 hours daily; asbestos has not been identified in ceiling or exterior wall materials; contractors may use consulate utilities (electricity, water, restrooms) free of charge during construction. Regarding AC replacement, contractors may reuse existing ducts, refrigerant piping, and electrical wiring if in suitable condition, provided they offer warranty equivalent to new materials and thoroughly clean any reused ducts internally; however, inspection area refrigerant piping may require replacement due to size incompatibility (existing 3/8" and 5/8" versus current 1/4" and 1/2" standards). The document provides a table with AC indoor and outdoor unit models and serial numbers for three locations: CAC Security Room, CAC Inspection Station, and Police Box. Emergency light batteries should be replaced as necessary to restore operation; full replacement of emergency lights was not approved.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 27, 2026
Questions and Answers
Request for Quotations (RFQ) No. 19JA7026Q0084 A/C and Ceiling/Lighting Renewal for the CAC at the U.S. Consulate General Sapporo
Question 1:
Is it acceptable to support the electrical conduits by fixing anchors into the steel frame and securing them with bolts?
Answer 1:
Yes.
Question 2:
Regarding air conditioners and lighting fixtures, is it also acceptable to support the electrical conduits by fixing anchors into the steel frame and securing them with bolts?
Answer 2:
Question 3:
If there are any specifications or requirements for the anchor installation method, please provide them.
Answer 3:
Please follow the manufacture’s guidance for the anchor installation method.
Question 4:
Regarding the ventilation of the Security Booth and Guard Booth, would it be acceptable to install a separate total heat exchanger for each room?
Sapporo, Japan
Consulate General of the United States of America
Answer 4:
Question 5:
Are there asbestos or similar materials included in the ceiling and exterior wall materials?
Answer 5:
No asbestos has been identified in the ceiling or exterior wall materials.
Question 6
During the construction work, will it be possible to use electricity, water, and restroom facilities free of charge?
Answer 6:
Yes
Question 7:
For the LED lighting in the restrooms, is it correct to understand that dimmers are not required?
Answer 7:
For the LED lighting in the restrooms, is it correct to understand that dimmers are not required?
Question 8:
Similar to the entryway, is the passageway intended to remain lit 24 hours a day?
Answer 8:
Yes
Question 9:
Regarding AC indoor units, we could not find the product number at Inspection area and
Gurd booth. If the product/model number can be confirmed from any stored documents or records, we would appreciate it if you could share it with us.
Answer 9:
Please see below.
Question 10:
Regarding the AC replacement, would it be acceptable to reuse the existing ducts, refrigerant pipes, and power wiring if they are still in reusable condition?
However, it appears that only the refrigerant piping in the inspection area may need to be replaced. The existing system currently uses 3/8" and 5/8" refrigerant piping, whereas current products are 1/4" and 1/2" piping sizes. (Smaller) For the guard booth and security booth, both the existing and current systems use the same 1/ 4" and 1/2" piping sizes, so we believe reuse should be possible.
Answer 10:
The reuse of existing ducts, refrigerant piping, and electrical wiring is permitted at the contractor’s discretion, provided that they are in suitable condition. If such components are reused, the contractor shall provide a warranty equivalent to that of new materials.
In addition, any reused ducts must be thoroughly cleaned internally prior to use.
Question 11:
Several emergency lights are currently not functioning, and we believe the cause is defective batteries. Since this would be a good opportunity, we were wondering if it might be better to replace all of the emergency lights at the same time. What are your thoughts on this?
Answer 11:
Please replace the batteries as necessary to restore proper operation of the emergency lights.
- End of Q & A -
File details come from the government source that posted it. Updated .