19GE5021R0011.pdf
PDF 388 KB Posted
- Attached to
- Croatia - CMR HVAC and Plumbing Renovation
- Solicitation number
- 19GE5021R0011
About this file
This is a solicitation for construction services to renovate the HVAC and plumbing systems at the Chief of Mission Residence of the U.S. Embassy in Zagreb, Croatia. The successful offeror will replace the heating system including piping, radiators, boiler and accessories; install a new Variable Refrigerant Flow system in the basement and attic; replace the domestic hot water storage tank and all associated accessories and piping; replace all domestic and sanitary water piping from the meter to each fixture; update piping and fixtures to current codes; remodel selected bathroom finishes and fixtures; and perform all other work as required. Offers are due by March 2, 2021. The contract will be a firm fixed-price award with a performance period of approximately four months from notice to proceed. The Department of State is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19GE5021R0011 Q and A.pdf | ||
| 19GE5021R0011 0001.pdf | ||
| 19GE5021R0011 RFP Cover Letter.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION
DOCUMENT
CMR HVAC/Plumbing Renovation Project
US Embassy Zagreb, Croatia
Solicitation No. 19GE50-21-R-0011
US Consulate General Regional Procurement Support Office Frankfurt [RPSOFR]
Giessenerstrasse 30
60435 Frankfurt am Main, Germany
19GE5021R0011
SOLICITATION,OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
19GE5021R0011 SEALED BID (IFB)
X NEGOTIATED (RFP)
2. TYPE OF SOLICITATION 3. DATE ISSUED
01/26/2021
RATING
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
CODE FRANK
AMERICAN CONSULATE GENERAL FRANKFURT
GIESSENER STRASSE 30
ATTN: RPSO
60435, FRANKFURT, GERMANY
7. ISSUED BY 8. ADDRESS OFFER TO
9. FOR INFORMATION
CALL:
a. NAME
David D. Machen
b. TELEPHONE NO. (Include area code)(NO COLLECT CALLS) c. EMAIL machendd@state.gov
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Section A - Solicitation, Offer, and Award Section B - Supplies or Services and Price/Costs Section C - Description/Specifications/Statement of Work Section D - Packing and Marking Section E - Inspection and Acceptance Section F - Deliverables and Performance Section G - Contract Administration Data Section H - Special Contract Requirements Section I - Contract Clauses Section J - List of Attachments
J.1 Project Specifications J.2 Sample Administrative Documentation J.3 Supplementary Documents
Section K - Representations, Certifications and other Statements of Offerors Section L - Instructions, Conditions,and Notices to Offerors Section M - Evaluation factors for Award
11. The Contractor shall begin performance calendar days and complete it within calendar days after receiving15 F.1
Section F.1award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
2 15:00a.
03/02/2021
b. An offer guarantee is, X is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
CGFS : : CGFS
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CONTACT: DUNS:
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
G.4.2
ITEM
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY FRANK
AMERICAN CONSULATE GENERAL FRANKFURT
GIESSENER STRASSE 30
ATTN: RPSO
60435, FRANKFURT, GERMANY
AMERICAN EMBASSY ZAGREB
THOMASA JEFFERSONA 2
ATTN: FMO
ZAGREB 10010
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Eric N. Moore
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 4-85)BACK
Table of Contents
Section Description Page Number
B Supplies or Services and Prices/Costs
SECTION B - SUPPLIES OR SERVICES AND PRICES / COSTS
B.1 SERVICES
B.2 TYPE OF CONTRACT
B.3 CONTRACT PRICE
B.4 VALUE ADDED TAX (VAT)
B.5 DEFENSE BASE ACT (DBA) INSURANCE
B.6 ABBREVIATIONS
C Descriptions/Specifications/Statement of Work
652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)
C.1 PROJECT NAME & LOCATION
C.2 STATEMENT OF WORK
C.3 PROJECT SPECIFICATIONS
C.4 PROJECT DRAWINGS
D Packaging and Marking
652.229-70 EXCISE TAX EXEMPTION STATEMENT FOR CONTRACTORS WITHIN THE
UNITED STATES (JUL 1988)
D.1 DUTY-FREE CLEARANCE
E Inspection and Acceptance 52.246-12 Inspection of Construction (Aug 1996)
E.1 INSPECTION OF CONSTRUCTION
E.2 SUBSTANTIAL COMPLETION
E.3 USE OF EQUIPMENT BY THE GOVERNMENT
E.4 QUALITY ASSURANCE AND CONTROL
E.5 FINAL COMPLETION AND ACCEPTANCE
F Deliveries or Performance
F.1 COMMENCEMENT, PROSECUTION & COMPLETION OF WORK (FAR 52.211-10 APR
1984)
F.2 LIQUIDATED DAMAGES (FAR 52.211-12 SEP 2000)
F.3 CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES
F.4 DELIVERABLES
F.5 ACCEPTANCE OF SCHEDULE
F.6 NOTICE OF DELAY
F.7 MONTHLY PROGRESS REPORT
F.8 NOTICE TO PROCEED
F.9 WORKING HOURS
F.10 EXCUSABLE DELAYS
F.11 PRE-CONSTRUCTION CONFERENCE (FAR 52.236-26 FEB 1995)
52.242-14 Suspension of Work (Apr 1984) 52.242-15 Stop-Work Order (Aug 1989) 52.242-17 Government Delay of Work (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984)
G Contract Administration Data
G.1 AUTHORITY OF CONTRACTING OFFICER
G.2 CONTRACT ADMINISTRATION DATA
G.3 SUPERINTENDENCE BY THE CONTRACTOR (FAR 52.236-6 APR 1984)
G.4 PAYMENT FOR CONSTRUCTION SERVICES
G.5 ADVANCE PAYMENT
H Special Contract Requirements
H.1 BOND REQUIREMENTS
H.2 INSURANCE
H.3 DEFINITIONS
H.4 OWNERSHIP AND USE OF DOCUMENTS
H.5 SECURITY
H.6 GOVERNING LAW
H.7 LANGUAGE PROFICIENCY
H.8 LAWS AND REGULATIONS
H.9 RESPONSIBILITY OF CONTRACTOR
H.10. CONSTRUCTION OPERATIONS
H.11 TEMPORARY FACILITIES AND SERVICES
H.12 SAFETY
H.13 SUBCONTRACTORS AND SUPPLIERS
H.14 CONSTRUCTION PERSONNEL
H.15 MATERIALS AND EQUIPMENT
H.16 IMPORTED MATERIALS, EQUIPMENT, AND PERSONNEL
H.17 SPECIAL WARRANTIES
H.18 EQUITABLE ADJUSTMENTS
H.19 NONCOMPLIANCE WITH CONTRACT REQUIREMENTS
H.20 ZONING APPROVALS & BUILDING PERMITS
H.21 ASSIGNMENT
H.22 AVAILABILITY OF FUNDS
H.23 ASBESTOS-CONTAINING MATERIALS RESTRICTION
H.24 PERFORMANCE OF WORK BY THE CONTRACTOR (FAR 52.236-1 APR 1984)
H.25 CONTRACTOR RECRUITMENT OF THIRD-COUNTRY NATIONALS
I Contract Clauses 52.252-2 Clauses Incorporated by Reference (Feb 1998) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I (Sept 1996) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Aug 2020) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Jun 2020) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (Jun 2020) - Alternate IV (Oct 2010) 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Mar 2020) 52.222-19 Child Labor--Cooperation with Authorities and Remedies (Jan 2020) 52.225-13 Restrictions on Certain Foreign Purchases (June 2008) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Dec 2013) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.222-50 Combating Trafficking in Persons (Oct 2020) 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Oct 2020) 52.228-3 Workers' Compensation Insurance (Defense Base Act) (July 2014) 52.229-12 Tax on Certain Foreign Procurements (Jun 2020) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.247-63 Preference for U.S.-Flag Air Carriers (June 2003) 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006)
652.204-70 DEPARTMENT OF STATE PERSONAL IDENTIFICATION CARD POLICY AND
PROCEDURES (FEB 2015)
652.225-71 SECTION 8(a) OF THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED
(AUG 1999)
652.229-71 PERSONAL PROPERTY DISPOSITION AT POSTS ABROAD (AUG 1999)
652.242-73 AUTHORIZATION AND PERFORMANCE (AUG 1999)
652.243-70 NOTICES (AUG 1999)
J List of Attachments
J.1 PROJECT SPECIFICATIONS
J.2 SAMPLE ADMINISTRATIVE DOCUMENTATION
J.3 SUPPLEMENTARY DOCUMENTS
K Representations, Certifications, and Other Statements of Offerors or Respondents
652.225-70 ARAB LEAGUE BOYCOTT OF ISRAEL (AUG 1999)
K.1 AUTHORIZED CONTRACT ADMINISTRATOR
K.2 CONTRACTOR RECRUITMENT OF THIRD COUNTRY NATIONALS (TCNs)
K.3 CERTIFICATION
52.204-8 Annual Representations and Certifications (Mar 2020) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Oct 2020) 52.209-7 Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Jul 2020) 52.229-11 Tax on Certain Foreign Procurements--Notice and Representation (Jun 2020)
L Instructions, Conditions, and Notices to Offerors and Respondents 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.215-1 Instructions to Offerors-Competitive Acquisition (Jan 2017) 52.232-38 Submission of Electronic Funds Transfer Information with Offer (Jul 2013) 52.236-27 Site Visit (Construction) (Feb 1995) 52.236-28 Preparation of Proposals-Construction (September 2019) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.204-7 System for Award Management (Oct 2018) 52.215-20 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data (Oct 2010) - Alternate IV (Oct 2010) 52.216-1 Type of Contract (Apr 1984) 52.233-2 Service of Protest (Sept 2006)
652.206-70 ADVOCATE FOR COMPETITION/OMBUDSMAN (FEB 2015)
L.1 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)
L.2 SOLICITATION PROVISIONS IN FULL TEXT
L.3 MAGNITUDE OF CONSTRUCTION PROJECT
L.4 REVIEW OF DOCUMENTS
L.5 SUBMISSION OF OFFERS
L.5.4 SUMMARY OF PROPOSAL INSTRUCTIONS
L.5.5 DETAILED INSTRUCTIONS
L.6 SITE VISIT (FAR 52.236-27 Alt I FEB 1995)
L.7 PROPOSAL DUE DATE
M Evaluation Factors for Award
M.1 EVALUATION OF PROPOSALS
M.2 AWARD WITHOUT DISCUSSIONS
M.3 CONTRACT AWARD
52.225-17 Evaluation of Foreign Currency Offers (Feb 2000)
Line Item Summary
Solicitation Number:
19GE5021R0011
Contract Number: Title: Zagreb - CMR Heating Date of Solicitation:
01/26/2021
Line Item No.
Description Quantity Unit Unit Price Total Cost
001 CLIN 0001 - CONSTRUCTION SERVICES
Construction Services for the HVAC/Plumbing renovation of the Chief of Mission Residence of the US Embassy Zagreb, as described in the Statement of Work, to include the supply and delivery of all equipment, all labor, materials, overhead, other indirect costs, costs for insurance (other than DBA), Letters of Credit, and profit;
Type of Contract Pricing:
Doc Ref No:
Delivery Date FOB:
1.00 LT
002 CLIN 0002 - DEFENSE BASE ACT (DBA)
INSURANCE
Type of Contract Pricing:
Doc Ref No:
Delivery Date FOB:
1.00 LT
003 CLIN 0003 - VALUE ADDED TAX (VAT)
25% of the Price of CLIN 0001 (as applicable) Type of Contract Pricing:
Doc Ref No:
Delivery Date FOB:
1.00 EA
SECTION B - - SUPPLIES OR SERVICES AND PRICES / COSTS
B.1 - SERVICES
The Contractor shall provide construction services necessary for the HVAC/plumbing renovation of the Chief of Mission Residence (hereafter, referred to as CMR) of the U.S. Embassy Zagreb, Croatia.
All work shall be performed in accordance with the specifications contained at Section J, List of Attachments, and all other documents incorporated into this contract. The Contractor is to perform the services in accordance with the terms and conditions of this contract/ solicitation, and in strict conformance with the contract clauses and any special conditions contained herein.
B.2 - TYPE OF CONTRACT
This is a firm fixed-price contract payable entirely in the currency indicated by the Contractor in Sub-Section B.3. No additional sums will be payable on account of any escalation in the cost of materials, equipment or labor, or because of the Contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract.
Nor will the contract price be adjusted on account of fluctuations in the currency exchange rates. Changes in the contract price or time to complete will be made only due to changes made by the Government in the work to be performed, or by delays caused by the Government (see Sub-Section F.10, Excusable Delays), as determined and approved by the Contracting Officer.
B.3 - CONTRACT PRICE
The Contractor shall complete all work (including furnishing all labor, material, equipment, and services) required under this contract for the following firm fixed-price and within the time specified herein. This price shall include all labor, services, materials, equipment, overhead, costs for insurance, costs of obtaining Irrevocable Letters of Credit, profit, travel, DBA Insurance, and any other costs required to perform and complete all construction services, in accordance with the Statement of Work (SOW), drawings, specifications, and all other contract terms and conditions stated within the contract.
The cost of any materials or equipment required in conjunction with the services rendered herein shall be included in the proposed firm fixed-price.
A Price Proposal Breakdown is provided under Section J, Attachment J.3.1 - Breakdown of Price Proposal. The Contractor shall complete the attachment and ensure that the total amount matches that of the total firm fixed-price proposal in the offeror’s price proposal in Section B.3.1.
Insurance required by FAR 52.228-3, Workers’ Compensation Insurance (Defense Base Act), shall be part of the firm fixed-price.
Any costs not priced will be included in overhead and other indirect costs.
B.3.1 Total Contract Price The Offeror shall insert their total price proposal costs as follows:
CLIN Description Price
0001 CONSTRUCTION SERVICES
Construction services as specified in the Statement of Work
0002 DEFENSE BASE ACT (DBA)
INSURANCE
0003 VALUE ADDED TAX (VAT)
(if applicable) Total Contract Price
(CLIN 0001 - CLIN 0003)
State Currency: __________________________________________
The offeror shall clearly identify and state the currency for all costs in their price proposal. After award, the Contractor shall invoice in and payment will be made according to the currency identified in the offerror's proposal, unless otherwise specified by the Contracting Officer.
B.4 - VALUE ADDED TAX (VAT)
Offerors shall identify Value Added Tax (VAT) as a separate line item in Section B.3 CONTRACT PRICE, and additionally in the required breakdown of the price proposal.
The rate of VAT in Croatia is 25%. VAT shall not be charged against DBA (CLIN 0002).
Any refund of VAT to the Contractor shall be paid to the Government to the extent the Government reimbursed the contractor for the VAT payment.
Value Added Tax shall also be reflected as a separate cost item on all invoices submitted under the resulting contract.
B.5 - DEFENSE BASE ACT (DBA) INSURANCE
B.5.1 DBA insurance is required for all United States citizens or residents and individuals hired in the United States, regardless of citizenship for any construction and services for U. S. overseas contracts over US$3,500.00. DBA insurance is also required for all Host Country Nationals (HCNs) and Third Country Nationals (TCNs) working overseas unless waved by the Department of Labor (DOL). Only the countries listed currently on the DOL’s Active DBA Waivers are not required to have DBA insurance for Host Country Nationals (HCNs) and Third Country Nationals (TCNs). See website for country waivers:https://www.dol.gov/owcp/dlhwc/ dbawaivers/dbawaivers.htm). The waiver is only valid if alternative worker’s compensation benefits are provided to the waived employees pursuant to applicable local law. If there are no local worker’s compensation laws, the waiver has no effect and HCN and TCN (if applicable by local law) working under a U. S. contract shall be included and covered under the DBA.
B.5.2 The DBA insurance may be obtained from any authorized DBA insurance broker, see Sub-Section I.14, FAR 52.228-3 WORKER’S COMPENSATION INSURANCE (DEFENSE BASE ACT) (APR 1984). New DBA insurances policies can be purchased directly from any DOL approved insurance carrier. A list of DOL approved carriers may be found athttp://www.dol.gov/ owcp/dlhwc/lscarrier.htm.
B.5.3 The Contractor will be reimbursed for DBA only to the extent the contractor provides documentary proof that DBA has been paid and only to the extent quoted in the Pricing Schedule.
B.5.4 DBA insurance cost will be evaluated as part of the total evaluated fixed price and included in the fixed price of the contract. Where DBA is applicable, the Contractor will be required to provide evidence of insurance (certification of coverage and a paid invoice) within 15 calendar days from the date of award.
B.5.5 Croatia is currently not included on the DOL’s active waiver list, therefore DBA insurance is required for all employees performing work on this contract.
B.6 - ABBREVIATIONS
CLIN Contract Line Item Number CO Contracting Officer COR Contracting Officer's Representative DOSAR Department of State Acquisition Regulations FAR Federal Acquisition Regulations ILOC Irrevocable Letter of Credit INL Internatioal Narcotics and Law Enforcement (US Department of
State) LNTP Limited Notice to Proceed OBO Overseas Buildings Operations SOW Statement of Work QTY Quantity
Section C - Descriptions/Specifications/Statement of Work
652.242-70 - CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)
(a) The Contracting Officer may designate in writing one or more Government employees, by name and position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer's Representative (COR). Such designation(s) shall specify the scope and limitations of the authority so delegated; provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer and this authority is delegated in the designation.
(b) The COR, who will be appointed at the time of contract award, is responsible for inspection and acceptance of services. These duties include review of Contractor invoices, including the supporting documentation required by the contract. The COR may provide technical advice, substantive guidance, inspections, invoice approval (except for the final invoice, which must be approved by the Contracting Officer), and other purposes as deemed necessary under the contract. The COR is designated as the authority to act for the Contracting Officer in matters concerning technical clarification, random inspection of Contractor performance to ensure compliance with contract specifications and acceptance of the Contractor's performance under this contract. The COR will coordinate all work with the Contractor during the term of this contract. The COR is not authorized to alter the contract's terms, or conditions, including the design to budget parameter. Such changes must be authorized by the Contracting Officer in a written modification to the contract.
C.1 - PROJECT NAME & LOCATION
The Contractor shall furnish and install all materials required by this contract for construction services in support of the Department of State's (DoS) Mission:
- Project Id: CMR HVAC/Plumbing Renovation
- Location: Chief of Mission Residence
Zagreb, Croatia
C.2 - STATEMENT OF WORK
C.2.1 General
The Scope of Work comprises of the Supply, Installation, and Testing & Commissioning of:
C.2.1.1 Basement: Variable Refrigerant Flow (VRF) types HVAC System with reheat capability to replace existing DX split system heat pump units, through the basement floor. All exiting condensing units located on wall shelfs shall be removed and the exterior walls shall be patched to match existing façade.
C.2.1.2 Attic: Replacement of existing DX split system heat pump units, through the attic. “Replace one-in-kind or closest model is acceptable.
C.2.1.3 The outdoor condensing units for the VRF systems shall be capable of providing cooling and heating within ambient range of -20°C to 40°C DB
C.2.1.4 All floors - Replace Heating Pipes, including risers and horizontals run outs and Radiators (remove heating piping where exposed, including above the drop/false ceilings, and abandon where concealed in masonry structures): The project shall replace all Heating Hot Water (HHW) accessories and appurtenances with new. The project shall include complete replacement of HHW equipment (radiators, valves and associated equipment and controls) in the hydronic distribution system. All indoor HHW piping shall be K type copper. Use welded schedule 40 copper, or equivalent European specification sizes. Provide individual Siemens SSA955 radiator control actuator and Synco Living at each radiator (or radiator zone) with wireless control.
C.2.1.5 Provide new condensing hot water boiler (gas), pumps, valves, piping and accessories. Replace all gas piping downstream from the main meter to the boiler. This includes valves and connections.
C.2.1.6 Replace all existing domestic hot and cold-water piping and equipment through the building; except in the two (2) bathrooms located on the first floor, recently renovated. Abandon pipes in place if necessary and they are located in the masonry structure. All indoor domestic water distribution piping shall be “K” copper type.
C.2.1.7 Replace all bathroom fixtures and toilets in all bathrooms (exception listed under 2.1.6).
C.2.1.8 Replace all bathrooms floors and wall finishes (tiles). Exception listed under 2.1.6.
C.2.1.9 Replace all kitchen floor tiles.
C.2.1.10 Replace all sewer and sanitary drain piping in the building, including piping in all bathrooms (exception listed under 2.1.6) and kitchen spaces.
C.2.1.11 Provide new domestic hot water storage tank (DHW) with double wall, SS, heat exchanger with air gap. Replace all existing domestic hot pumps, valves, piping and accessories.
C.2.1.12 The Contractor shall evaluate and replace if necessary all roof drainage piping and system. Segregate storm water from sanitary sewer to the main. Include “duck bill” backwater valves.
C.2.1.13 Air handling unit (AHU) located in the attic shall remain in place.
C.2.1.14 Condensing Unit (CU) located outside on ground, serving AHU shall be replaced with a new one with matching capacity.
C.2.1.15 Provide wireless temperature control for the radiators and the VRF systems.
C.2.1.16 All exposed refrigerant piping shall be covered with heavy duty flexible pipe for protection. Special precaution to be taken during installation of the drain piping.
C.2.1.17 The contractor shall be responsible for any leakage /seepage due to poor installation of the drain system throughout the warranty period. Drain point to be tested for 24 hours after blocking one end. Drain piping will be plugged at both ends by an appropriate method after completing the drain test to avoid chocking due to foreign material.
C.2.1.18 Execute all incidental work at site including all material supply at site required in the technical specifications. Drain and refrigerant piping work with insulation, control wiring from outdoor units to indoor units, VRF control panel etc., and erection at site for all manufactured items at works and also items fabricated at site.
C.2.1.19 Routine testing, pressure testing of refrigerant and drain piping, and complete commissioning including performance testing of the entire VRF system.
C.2.1.20 Responsible for the disposal of all material and equipment, unless appropriately abandon in the masonry structure.
C.2.1.21 Replace all ceiling tiles in basement corridor.
C.2.2 GENERAL REQUIREMENTS
The Contractor shall provide construction services to provide complete operating systems. All work shall comply with the Design Documents listed in Attachment A and 2020 OBO Supplements to the current International Building Code (IBC), National Electrical Code (NEC), International Mechanical Code (IMC), and the International Plumbing Code (IPC), in addition to the approved specifications.
C.2.3 CONSTRUCTION SERVICES
C.2.3.1 Construction: The Contractor shall execute the construction per the Design Documents provided at J.1
C.2.3.2 Commissioning Services: All systems shall be tested and commissioned per the specifications. The final commissioning of the new equipment shall be performed with an OBO/PDCS/DE/ME representative present. The Contractor shall be responsible for the following construction inspections and tests:
3.0 C.
A. All new VRF indoor and outdoor units testing and commissioning.
B. All new piping (domestic and heating) pressure and leak tests.
C. Boiler, domestic hot water storage tank, pumps testing and commissioning.
D. All radiators testing and commissioning.
E. Manufacturer’s Warranty Inspection.
C.3 - PROJECT SPECIFICATIONS
The Project Specifications and Statement of Work are attached in Section J. Any inconsistency in the contract requirements shall be resolved by giving precedence in the order outlined in Section I, FAR 52.215-8 - Order of Precedence - Uniform Contract Format;
however, any inconsistencies in respect to the Project Drawings and Specifications shall be governed by FAR 52.236-21.
C.4 - PROJECT DRAWINGS
Project Drawings are provided in Section J, Attachment J.1.3. In case of differences between small and large-scale drawings, the latter shall govern. Where a portion of the work is drawn in detail and the remainder of the work is indicated in outline, the parts drawn in detail shall apply also to all portions of the work.
Section D - Packaging and Marking
652.229-70 - EXCISE TAX EXEMPTION STATEMENT FOR CONTRACTORS WITHIN THE UNITED STATES (JUL 1988)
This is to certify that the item(s) covered by this contract is/are for export solely for the use of the U.S. Foreign Service Post identified in the contract schedule.
The Contractor shall use a photocopy of this contract as evidence of intent to export. Final proof of exportation may be obtained from the agent handling the shipment. Such proof shall be accepted in lieu of payment of excise tax.
(End of clause)
D.1 - DUTY-FREE CLEARANCE
In accordance with procedures described in Section H.16, if applicable, duty-free clearance shall include all imported materials, equipment. All shipping containers or otherwise, shall be labeled as follows:
ATTN: Customs & Shipping (CONTRACT 19GE50-21-C-XXXX) to be completed by the Contractor Items shall be marked as “Diplomatic Cargo”.
D.1.1 Material Shipping/Customs Clearance
Material Shipping/Customs Clearance Materials for the CMR HVAC/Plumbing Renovation Project shall be shipped to:
U.S. Embassy Zagreb ATTN: Facilities Thomasa Jeffersona 2 10010 Zagreb Croatia
D.1.2 Free Entry of Goods
To obtain a free entry for the goods the contractor shall provide the COR with the following documentation twenty (20) days prior to the arrival of goods:
- Detailed description of goods (including number of crates)
- Approximate weight
- Approximate value of goods
- Mode of shipment
The Contractor shall provide an Advance Notice to the U.S. Embassy shipping office twenty (20) calender days before any shipment is to be made.
D.1.3 Customs Clearance and Delivery
The Contractor shall estimate a reasonable number of days for custom clearances and delivery. Should the contractor fail to provide any required paperwork for the custom clearance process to the U.S. Embassy Zagreb shipping office and the custom clearances procedure is delayed, the contractor shall be required to pay any additional costs occurred (storage fees).
Section E - Inspection and Acceptance
52.246-12 - Inspection of Construction (Aug 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may--
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately.
Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(End of clause)
E.1 - INSPECTION OF CONSTRUCTION
The Contractor is required to maintain an adequate inspection system that ensures all contractual obligations are meet under the terms and conditions of the contract. The Contractor must maintain inspection records and make them readily available to the Government upon request of the Contracting Officer or the Contracting Officer's Representative (COR), in accordance with FAR 52.246-12.
E.2 - SUBSTANTIAL COMPLETION
Please see the following definitions below:
E.2.1 Substantial Completion The stage in the progress of the work as determined and certified by the Contracting Officer or Contracting Officer’s Representative (COR) in writing to the Contractor, on which the work or a portion thereof designated by the Government is sufficiently complete and satisfactory, in accordance with the requirements of the Contract Documents, that it may be occupied or utilized for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:
(1) Do not interfere with the intended occupancy or utilization of the work, and;
(2) Can be completed or corrected within the time period required for final completion.
E.2.2 Date of Substantial Completion Inspection The date determined by the Contracting Officer or Contracting Officer’s Representative (COR) of which substantial completion of the work has been achieved.
E.2.3 Request for Substantial Completion Inspection
The Contractor shall give the COR at least 15 days advance written notice of the date the work will be substantially completed and ready for inspection and tests. The inspection and tests will be started not later than the date specified in the aforesaid notice unless the COR determines that the work is not ready for inspection and so informs the Contractor.
E.2.4 Use and Possesion upon Substantial Completion The Government shall have the right to take possession of and use the work upon substantial completion thereof. Upon notice by the Contractor that the work is substantially complete and verification thereof on the basis of an inspection by the COR and any required tests, the COR shall furnish the Contractor a Certificate of Substantial Completion, accompanied by the Schedule of Defects enumerating items of work remaining to be performed, completed or corrected before final completion and acceptance. However, failure of the COR to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use upon substantial completion shall not be deemed an acceptance of any work under the contract.
E.3 - USE OF EQUIPMENT BY THE GOVERNMENT
The following sections below describe the use of equipment by the Government in performance of the contract requirements.
E.3.1 Right to Use The Government may take over and operate, with Government employees, such equipment as is necessary for heating or cooling such areas of the building as require the service, and other equipment such as elevators, electrical, plumbing and mechanical systems, as soon as the installation is sufficiently complete to permit operation.
E.3.2 Notice The COR will advise the Contractor in writing, prior to the use of the equipment, which items of equipment will be operated, and the date and time such operation shall begin.
E.3.3 Effect on Warranties The COR will advise the Contractor in writing, prior to the use of the equipment, which items of equipment will be operated, and the date and time such operation shall begin.
E.4 - QUALITY ASSURANCE AND CONTROL
A principal factor of performance on a project is the Contractor’s control of the quality of workmanship. The Contractor shall establish and maintain a project-specific Quality Management Program (QMP) which defines and implements a quality system. The quality system is a documented organizational process which describes responsibilities, procedures, and resources for providing quality control and quality assurance on a project. Effectiveness of the QMP is achieved through adequate planning, forceful direction, and checking in the sense of measurement and evaluation. The QMP applies to the control of quality throughout all areas of contract performance.
E.4.1 Quality Management Program The Contractor’s QMP shall be Facility Management Office (COR)-approved to provide employees, consultants, and/or joint-venture partners with established, uniform procedures for production of project data and documents throughout the construction process.
Principal functions of the QMP are the following:
E.4.1.1 Quality Control (QC) Operational techniques and activities that are used to fulfill requirements for construction quality.
E.4.1.2 Quality Assurance (QA) Documentation of planned and systematic actions required to provide confidence that construction services provided are based on project requirements and satisfy stated requirements for quality.
E.4.2 Audits After award of the Contract The Government may perform audits of the Contractor’s QMP to periodically assess conformance with the QMP in accordance with the provisions of Section E of the contract. Disapproval of the program, or major portions, may be cause for a delay in progress of the project’s development or, in some cases, withholding acceptance of the Contractor’s performed services. The Government may examine the Contractor’s existing quality system prior to award of this contract as part of a pre-contract assessment, in order to determine the ability of the Contractor to satisfy the “quality” requirements of this contract.
E.4.3 Agreement on Quality Assurance The Contractor shall develop a clear understanding with all his consultants on quality assurance matters for which the contractor are responsible, and the quality assurance program of the contractor shall be integrated with that of the Contractor of record.
E.4.4 QMP Submittal Requirements The QMP shall be structured and developed to include the following minimum requirements:
E.4.4.1 Organizational Structure The Contractor shall define and submit a QMP organizational structure within 15 days of contract award, including charts and a description of responsibilities of key persons who will perform the services. Persons responsible for interface with the Government, including the security manager and QMP Manager must be identified. A separate list should also include all team members, including consultants with telephone and email addresses.
In addition to the submittal of a Quality Management Plan within fifteen (15) calendar days after con- tract award, the Contractor shall also submit a preliminary Quality Management Program as part of their proposal (See L.5.5.3 (E)).
E.4.4.2 Quality Policy The Contractor shall have a stated corporate quality policy. This policy shall be consistent with the Contractor’s quality policy in the QMP. Necessary measures shall be taken by the Contractor to ensure that the corporate quality policy is understood, implemented, and maintained by all employees of the Contractor and the Contractor’s subcontractors.
E.4.4.3 Building Standards Construction must comply with the building codes and standards as detailed within the project drawings and specifications in addition to conforming to each volume, as applicable, of the 2009 International Code Council body of codes. Inconsistencies among codes and standards shall be brought in writing to the attention of the COR. The COR will resolve any inconsistencies.
E.4.4.4 Other Procedures Other procedures shall address construction management, procurement activities, construction management, quality records, and audits.
E.4.4.5 Security and Communications Interface The Contractor’s QMP shall provide for integration of security and communications requirements into the project.
E.4.4.6 Checking, Coordinating, and Integrating Drawings Quality Control procedures shall be established to ensure individual drawings and other documentation have been checked and that all documentation, including that of the supporting disciplines (e.g., civil, structural, mechanical, electrical) have been coordinated and integrated. Deficiencies, ambiguities, conflicts, and inconsistencies shall be corrected prior to construction. Similar procedures shall be established to ensure that work in place complies with code requirements without the need for the USG to identify defects and initiate corrective action.
E.4.4.7 Document Control The QMP shall ensure that documents, including subsequent changes, will be reviewed for adequacy, approved for release by authorized personnel, and properly conveyed to the Government. Persons responsible for reviewing, approving, and releasing new and revised documents shall be identified.
E.4.4.8 Reserved
E.4.4.9 Corrective Action The QMP shall clearly define responsibilities and procedures for corrective action in the event that deficiencies in D/B services or resulting deliverables are found to exist.
E.4.5 QMP Reporting The Contractor shall prepare a sample Quality Assurance (QA) Report to be submitted as part of the solicitation package this sample report shall be updated and submitted with 15 calendar days from contract award. This report shall identify the QMP procedures used to review drawings and data for these submissions identifying steps taken to coordinate all drawings and documents provided by the Government and shall show contractors coordination with the subcontractors. The report shall include:
1. QC Status of the project include evidence of QC effort by inclusion of notes, comments, dialogue and discussion among and between disciplines of QC input and adjudication;
2. Significant Program Problems and their solutions/corrective actions;
3. Organization and Key Personnel Changes to be submitted within 5 working days in advance of the proposed change;
4. Certification of completion of QMP procedures and submission completeness;
5. Construction Documents Compliance Letter for the construction works
E.5 - FINAL COMPLETION AND ACCEPTANCE
The following sections below describe the terms and conditions for the final completion and acceptance of construction services.
E.5.1 Definitions The "Final completion and acceptance" means the stage in the progress of the work as determined by the COR and confirmed in writing to the Contractor, on which all work required under the contract has been completed in a satisfactory manner in accordance with the requirements thereof, subject to the discovery of defects after final completion, and except for items specifically excluded in the notice of final acceptance.
The "date of final completion and acceptance" means the date determined by the COR as of which final completion of the work has been achieved, as indicated by written notice to the Contractor.
E.5.2 Request for Final Inspection and Tests The Contractor shall give the COR at least 15 days advance written notice of the date the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started not later than the date specified in the aforesaid notice unless the COR determines that the work is not ready for final inspection and so informs the Contractor.
E.5.3 Final Acceptance Upon (a) satisfactory completion of all required tests, (b) verification by the COR on the basis of a final inspection that all items listed in the Schedule of Defects have been completed or corrected and that the work is finally complete, subject to the discovery of defects after final completion, and (c) submittal by the Contractor of all documents including contractor close-out documents, and other items required upon completion of the work, in- cluding a final request for payment, and if the COR is satisfied that the work under the contract is complete and the contract has been fully performed, with the exception of continuing obligations there under, the COR shall issue to the Contractor a notice of final acceptance and process final payment as required by the contract.
Section F - Deliveries or Performance
Clause Title Fill-ins
52.242-13 Bankruptcy (July 1995)
F.1 - COMMENCEMENT, PROSECUTION & COMPLETION OF WORK (FAR 52.211-10 APR 1984)
F.1.1 SUBMITTAL PROCEDURES
Effective from the date of contract award, the Contractor shall be required to commence with all administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples and other submittals, as described in the project specifications, attachment J.1. Specifications by divisions and the submittal procedures contained therein, and to provide to the Government all Submittal documents for review within 30 calendar days. The time stated for submission shall include the time required for mailing.
Submittal to the US Government of shop Drawings, 30 calendar days from date of Contract Award Product Data, Samples and other submittals TOTAL DURATION SUBMITTAL PROCEDURES: 30 calendar days
It is anticipated for the government to require a period of approximately 30 calendar days to review the submittal documentation.
F.1.2 EQUIPMENT AND MATERIAL PURCHASE
Upon approval of the submittals, the Contractor shall be required to purchase all necessary equipment and materials and arrange for transportation and shipment to the project site within 30 calendar days after issuance of a “Limited Notice to Proceed” (LNTP).
TOTAL DURATION EQUIPMENT/MATERIAL PURCHASE: 30 calendar days
F.1.3 CONSTRUCTION WORK
Construction portion of the contract: The Contractor shall be required to (a) commence on-site construction work under this contract within 14 days after the issuance date of the “Full Notice To Proceed” (FNTP), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after the issuance date of the FNTP. The time stated for the construction portion of the contract shall include final cleanup of the premises, completion of punch-list items and all other items specified in the contract.
TOTAL DURATION CONSTRUCTION WORK: 90 calendar days
F.2 - LIQUIDATED DAMAGES (FAR 52.211-12 SEP 2000)
The project schedule is a key parameter of this project, and completion of the construction effort within the allocated period is key to the project as a whole.
F.2.1 Liquidated Damages In accordance with FAR 52.211-12:
(a) If the Contractor fails to complete the work within the time specfied in the contrct, the Contractor shall pay liquated damages to the Government in the amount of USD $3440.00 for each calendar day of delay until the work is completed of accepted.
(b) If the Government terminated the Contractor's right to proceed, liquated damages will continue to accrue until the work is completed. The liquated damages are in addition to excess costs of repurchase under the Termination clause.
F.2.2 Assessment & Apportionment of Liquidated Damages Liquidated damages will be assessed from the completion date indicated in the contract or extensions thereof to the date of substantial completion as actually achieved by the Contractor, as determined by the Contracting Officer.
F.3 - CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES
(a) The time for submission of the schedules referenced in Section I, 52.236-15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect that the submission shall be within 15 calendar days after contract award.
(b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contract shall be submitted for approval.
(c) The Contractor shall revise such schedules:
(1) To account for the actual progress of the work,
(2) To reflect approved adjustments in the performance schedule, and,
(3) As required by the COR to achieve coordination with work by the Government and any separate contractors employed by the Government.
The Contractor shall submit a schedule, which sequences work to minimize disruption at the job-site.
(d) All deliverables shall be in the English language, unless…