This is an Amendment of Solicitation (SF-30) for a generator repair contract at the US Embassy in Paris, France. The amendment extends the bid due date to April 16, 2025, at 6:00 PM local time and revises requirements in the Scope of Work. The solicitation requires repairing and replacing components for four generators located in three different buildings: Chancery A Building (660 kva CATERPILLAR C18), Chancery A Building (500 kva CATERPILLAR C15), CMR (275 kva CATERPILLAR 3306 B-D1), and Raphael Building (250 kva VOLVO TAD740GE).
The contractor must be referred by CATERPILLAR with minimum 10 years of generator maintenance experience, provide original manufacturer parts, submit qualifications demonstrating at least 5 similar project references, and comply with safety regulations including OSHA standards and French occupational safety requirements. Specific repair tasks include replacing batteries, belts, filters, coolant, radiators, hoses, and other components across the four generators. The work is scheduled to be performed from November 2024 to April 2025, with working hours set from 9:00 to 12:00 and 13:00 to 17:00, Monday through Friday, excluding American and French holidays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
19FR6325Q0009-A0002
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 24
2. AMENDMENT/MODIFICATION
NO.
19FR6325Q0009-A0002
3. EFFECTIVE DATE
March 28, 2025
4. REQUISITION/PURCHASE REQ. NO.
PR15023494
5. PROJECT NO. (If applicable)
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE
Contracts Office A-M8, American Embassy, 2 Ave Gabriel, 75008 Paris
8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)
X
9a. AMENDMENT OF SOLICITATION NO.
19FR6325Q0009
9b. DATED (SEE ITEM 11)
March 5, 2024
10a. MODIFICATION OF CONTRACT/ORDER NO.
10b. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ x ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ X ] is extended until April 16, 2025 no later than 6:00 P.M (local time) [ ] is not extended Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ____1___ copies of the amendment;(b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.
FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [ ] is not, [ X ] is required to sign this document and return ___ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to:
- Extend the bid due date until April 16, 2025, no later than 6:00 P.M (local time).
- Revise requirements in the “Attachment 1 – Scope of work” as shown in blue in this document
- Provide additional pictures.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME OF CONTRACTING OFFICER
CRAIG N DEATRICK
15B. NAME OF CONTRACTOR/OFFEROR
BY
(Signature of person authorized to sign)
15C.DATE
SIGNED
16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C.DATE SIGNED
NSN 7540-01-152-8070 Standard Form 30 (revised 10/83) Previous edition unusable Prescribed by GSA FAR (48 CFR
SCOPE OF WORK
REPAIR GENERATORS
CHANCERY, CMR & RAPHAEL BUILDINGS
Contents
1. General
2. General description and mandatory requirements
3. Details of installation
3.1. Chancery - A Building
3.2. Chancery - A Building
3.3. CMR
3.4. Raphael Building
SCOPE OF WORK
Repair generators – Chancery, CMR and Raphael Buildings
1. General
The Scope of Work (SOW) detailed herein is designed to articulate the necessary requirements and tasks involved in replacing worn parts on our generators following an inspection report by a team specializing.
This project necessitates the engagement of a specialized and experienced contractor.
The contractor is responsible for furnishing all labor, materials, tools, equipment, supervision, and any other necessary items to carry out the work in accordance with the defined scope of work and specifications.
Contractors are strongly encouraged to conduct on-site visits to verify the existing site conditions before developing their proposals. This firsthand assessment is crucial for ensuring accuracy and completeness in the proposal development process.
The Contractor is responsible for verifying all dimensions and site conditions before ordering any materials or commencing any work.
All materials and equipment incorporated into the project shall be new unless otherwise noted. The
Contractor is responsible for transporting and safeguarding all materials and equipment required for the project.
Any variations must be priced and approved in writing by the COR before proceeding with the work and all costs associated with subcontracted services shall be borne by and be the complete responsibility of the Contractor under the fixed price of this contract.
Working hours are set from 9:00 to 12:00 and from 13:00 to 17:00, Monday through Friday. During
American and French holidays, the Property shall be closed to allow for uninterrupted work.
If necessary and with a request made 48 hours in advance, schedules can be adapted. Any work required outside of these hours must be requested in writing and approved by the COR.
The following is a list of the U.S. national holidays and the legally observed local holidays for calendar year 2024. Please keep for reference.
DATE DAY OF THE
WEEK
HOLIDAY TYPE
Jan. 1 Monday New Year’s Day American/French
Jan. 15 Monday Martin Luther King Jr’s Birthday American
Feb. 19 Monday Presidents Day American
April 1 Monday Easter Monday French
May 1 Wednesday Labor Day French
May 8 Wednesday Veterans Day French
May 9 Thursday Ascension Day French
May 20 Monday Whit Monday American
May 27 Monday Memorial Day French
June 19 Wednesday Juneteenth American
July 4 Thursday Independence Day American
July 14 Sunday French National Day French
Aug. 15 Thursday Assumption Day French
Sept. 2 Monday Labor Day American
Oct. 14 Monday Columbus Day American
Nov. 1 Friday All Saints’ Day French
Nov. 11 Monday Veterans Day (WWI) American/French
Nov. 28 Thursday Thanksgiving American
Dec. 25 Wednesday Christmas American/French
And the following is a list of the U.S. national holidays and the legally observed local holidays for calendar year 2025. Please keep for reference.
All work shall be performed in accordance with:
A. The safety requirements of the EM-385-1-1 http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-
1.pdf;
B. The safety requirements within the Occupational Safety and Health Standards https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_ number=1910;
C. Local French occupational safety and health requirement laws and regulations.
D. When there is a difference with the minimum requirements the more stringent requirement shall be followed.
2. General description and mandatory requirements
This installation will be performed from November 2024 to April 2025
This contractor is expected to:
Supply and installing replacement parts for our four generators as detailed below, located in Paris
75008 and 75016.
Spare parts will be original manufacturer parts depending on the make of the generators.
The contractor must be referred by the manufacturer CATERPILLAR, have significant experience in generators maintenance with a minimum of 10 years’ experience.
Submit the necessary qualifications for this type of work and provide proof of experience. This may include a minimum of 5 jobs and references demonstrating experience in similar generator repair/maintenance projects.
Provide all necessary materials and resources for the execution and completion of the work.
Additionally, the Contractor must furnish written proof of liability insurance before commencing any work.
Furnish written assurance to the Contracting Officer that all subcontractors and workers involved in the project possess the necessary licenses and permits.
Include a comprehensive PP SPS – Plan particulier de sécurité et de protection de la santé (Safety and Health Protection Plan) with their proposal, which conforms to the latest version of the Health, Safety, and Welfare at Work Act. This plan should be well-thought-out and detailed enough to demonstrate that the contractor is proficient in conducting safe and professional operations and has prioritized a culture of safety in their business practices.
Comply with all OSHA standards relevant to the work being performed. They must also adhere to the requirements of the National Electric Code, all applicable rules and regulations of the National Fire
Protection Association regarding the handling of flammable materials or mixtures, and any state or local health and safety requirements, whichever is more stringent.
Before commencing site work, the Contractor must submit a health and safety plan to the SHEM inspector and the COR. This plan should address all applicable OSHA requirements for the project's duration. Throughout the project, the Contractor must follow the procedures outlined in the health and safety plan to ensure the protection of the health and safety of all individuals and property near the project site. The Contractor must always keep a copy of the health and safety plan on-site and ensure that all on-site personnel have reviewed and are familiar with it. Furthermore, all safety equipment referenced in the health and safety plan must be present on-site and calibrated (if applicable) before any activities commence.
Must adhere to the following work coordination requirement:
All work must be carried out in coordination with the Contracting Officer's Representative (COR) at the specified locations.
For substantive technical clarification on the scope of work, technical guidance, or questions, the
FAC COR should be consulted.
Any official changes or financial commitments must be authorized by the Contracting Officer
(CO). No financial or major substantive changes to the scope of work can occur without written direction from the government procurement office and the CO.
Provide a resource-loaded work schedule that clearly delineates the sequence of work, along with the associated resources and timeframes for each task.
Submit identification information for all employees meant to work on site to the COR to be placed on the approved Visitors Roster. Details should include full name and vehicle make, model, and registration number.
3. Details of installation
The contractor shall provide and replace
3.1. Chancery - A Building
Generator CATERPILLAR C18 model ELM070 – 660 kva.
o Supply and replace of batteries (X2).
o Supply and replace of belts according to type on generator set.
o Supply and replace the air filters (X2).
o Supply and replace of coolant.
3.2. Chancery - A Building
Generator CATERPILLAR C15 model FTH00843 – 500 kva.
o Supply and replace the exchanger next to the resistances.
o Supply and replace of coolant.
o Repair the Oil leak between engine/ alternator coupling.
o Repair the Oil leak on upper motor housing.
o Supply and replace the thermostat for the water exchanger temperature.
o Supply and replace one fusible A6T100 – 100 Amp.
o Supply and replace of belts according to type on generator set.
o Bearing lubrification.
3.3. CMR
Generator CATERPILLAR 3306 B-D1 model 85Z08762 – 275 kva.
o Generator set need completed cleaning.
o Supply and replace of batteries (X2).
o Supply and replace of belts according to type on generator set.
o Supply and replace the radiator.
o Supply and replace the hose from the radiator to engine.
o Supply and replace of coolant.
o Supply and replace the Both air / safety filter.
o Supply and replace the battery charging cable.
o Supply and replace the vibration isolators have deteriorated.
3.4. Raphael Building
Generator VOLVO TAD740GE model 868825 – 250 kva.
o Supply and replace of belts according to type on generator set.
o Supply and install one valve on the exhaust pipe.
o Supply and install a new day tank with a double-skinned one.
o Supply and replace of coolant.
o Supply and replace the Control Unit = “Unité de Commande” IHM.