This is a Maintenance Protocol form for hydraulic barrier systems located at the U.S. Chancery in Vienna, Austria (1090 Vienna, Boltzmanngasse 16). The document serves as a standardized checklist and work log for maintenance contractors and Facilities & Administrative Coordinator (FAC) representatives to track the performance and condition of security barriers.

The protocol is divided into monthly maintenance tasks and additional yearly inspection items. Monthly duties include logging pressure settings, inspecting hydraulic hoses and fittings for leaks or damage, checking oil levels in the site glass, managing filter replacements based on cycle frequency (every third month for systems cycled less than 100 times daily, or monthly for high-cycle or dusty environments), verifying accumulator pressure using Delta Charging Kit 2469-31, confirming smooth barrier operation, checking for debris and oil leaks around cylinders and foundation frames, testing barrier heaters, verifying all control functions, and maintaining cleanliness around the HPU tank and hydraulic lines. Yearly inspection tasks include draining and flushing the oil reservoir with mineral spirits, inspecting cylinder clevis pins for wear, examining foundation frames and drain systems, tightening or replacing loose bolts, assessing paint condition and reflective tape, inspecting hydraulic interconnect lines, thoroughly cleaning the HPU, testing motor starter overloads, checking the pressure relief valve (which should be set to 2200 psig or 152 bar), and examining hydraulic cylinders for internal leaks. The form includes fields for documenting the date and time of maintenance, contractor information, FAC representative oversight, work completion status, parameters and comments, additional repairs performed, uncorrected deficiencies, and signatures from both the contractor and FAC representative.

View the file

Other files

File Type Posted
19AU9026Q0014_cover letter.pdf PDF
19AU9026Q0014_Solicitation.pdf PDF
19AU9026Q0014_SF-1449.pdf PDF
19AU9026Q0014_SOW.pdf PDF
S19AU9026Q0014_Service manual.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RANGE OF WORK TO BE PERFORMED

PLEASE WATCH ATTACHED SAFETY RECOMMONDATIONS

Monthly:

done not done parameter / comments

Log pressure settings on sheet supplied in this section.

Check for leaks around all fittings. Tighten when necessary.

Check that hydraulic hoses (if used) are not rubbing on any hard or sharp surfaces. Especially check where hose enters conduit or where it may contact the ground.

Check oil level in the site glass after the pump/motor has run to full pressure and shutoff. If level appears to be falling, investigate the HPU and Darner fittings and the hydraulic ‘lines.

Shut system off and drop system pressure to zero.

For systems that are cycled less than 100 cycles per day, replace every third month thereafter. If system is cycled above this rate, or the location is in a high dust environment, replace filter monthly.

Check the accumulator pressure while the system is at zero pressure using Delta Charging Kit 2469‐31 or equal. If tool is not available, observe the value that the pressure gage jumps to when power is again turned on. (See hydraulic Section for details.) Log value and pressure setting on Log sheet provided

Confirm that the Barrier operates smoothly during the raise and lower cycle Adjust speeds as desired.

Remove Barrier top plates and check for debris build up in the bottom of the foundation frame Check for indications

MAINTENANCE PROTOCOLL FOR

BARRIERS CHANCERY (1090 Vienna, Boltzmanngasse 16)

Maintenance done at (date, time):

By (Company/Name(s) of the performer):

Control done by FAC representative (Name):

of oil leaks around the cylinders and Barrier header fittings. Tighten fittings and clean debris as necessary.

Check the operation of the Barrier heaters if so equipped.

They should get warm approximately one minute after energizing.

Check all control functions for complete operation of all features.

Turn off pump/motor power, bleed system pressure to zero and add dean, filtered oil to the top of the site glass.

Clean dust and debris from around HPU tank and hydraulic lines. Wipe up any spilled oil

Turn power on and bring system back to operation.

Additional at the yearly inspection:

done Not done parameter / comments

Drain the oil from the reservoir and flush with mineral spirits or clean oil. Alter wiping down the tank sides and bottom to assure that no contamination remains, replace with clean filtered oil.

Check cylinder clevis pins for wear, replace as necessary.

Examine the foundation frame for debris buildup, check drain lines and sump wells for drainage. Clean debris

Tighten or replace any loose top plate bolts Drill and tap to next size or use inserts if threads are stripped.

Check condition of the Barrier paint surface. Prepare, prime and touch up areas where the paint has be chipped or worn away Apply new reflective tape as necessary

Checks hydraulic interconnect lines for kinks, contact wear or bulging. Replace or protect hoses as required.

Thoroughly clean the HPU, removing dust and spilled oil.

Remove any rust build up on components. Touch up paint where necessary.

Check the accumulator pressure while the system is at zero pressure using Delta Charging Kit 2489‐31 or equal, If tool is not available; observe the value that the pressure gage jumps to when power is again turned on. (See Hydraulic Section for details.) Log value and pressure setting on Log sheet provided.

Test motor starter overloads by pressing the test button.

Replace if necessary or press reset. Auto/Manual switch should be in the Manual position

Check the pressure relief valve by depressing the starter armature and allowing unit to run to the relief pressure value of 2200 psig (152 bar]. Adjust as necessary.

Remove Barrier top plates, check that the hydraulic cylinders are not leaking internally. Replace cylinder seals or cylinder as necessary.

Other repairs/work being carried out:

Noticed, but not corrected deficiencies: