RFQ19AS2026Q0025 Residential Bathroom Renovation and Drainage Upgrades.pdf
PDF 487 KB Posted
- Solicitation number
- 19AS2026Q0025
- Issued by
-
Department of State US Embassy Canberra
About this file
This is a Request for Quotes (RFQ) for residential bathroom renovation and drainage upgrades at 31 Couvreur Street, Canberra, Australia, issued by U.S. Embassy Canberra on July 24, 2026. The project involves renovation of bathroom, toilet, and powder room areas (18 square meters) including associated drainage and plumbing systems at a U.S. Government-owned residential property. The scope encompasses preliminary works with site inspection and documentation submission, asbestos testing, demolition and removal of existing fixtures, installation of new PVC drainage systems, slab reinstatement with concrete work per Australian Standards, bathroom/toilet/powder room renovation with electrical upgrades and waterproofing, laundry drainage replacement, finishing work, and final testing and handover with compliance certifications. Quotations are due by Tuesday, September 8, 2026, at 4:00 p.m. AEST, with a mandatory site visit scheduled for Thursday, August 6, 2026, at 10:00 a.m. AEST. The anticipated contract value ranges between $60,000 and $80,000 USD. Award will be made to the lowest-priced, acceptable, responsible quoter based on compliance with RFQ terms and FAR 9.1 responsibility criteria.
Offerors must be registered in the System for Award Management (SAM) with a valid Unique Entity Identifier (UEI) prior to submission. Required submissions include Standard Form 1442, completed pricing breakdown (Section A), performance schedule as a bar chart, business management/technical proposal with company information and three years of past performance references, SF-1442, Section L representations and certifications, and proof of SAM registration. Offerors must demonstrate minimum qualifications including three years of construction experience in Australia, English language capability, permanent business address, necessary licenses and permits, adequate personnel and equipment, no adverse criminal record, and ability to obtain performance security. Quotations must be submitted electronically to cnbgsoprocurement@state.gov in MS-Word, MS-Excel, or Adobe PDF format not exceeding 30MB. The contract includes a 75-day completion period from notice to proceed, with commencement required within 10 calendar days of award. Liquidated damages of $600 AUD or 1% of project award total per day apply for delays. General liability insurance of $10,000,000 AUD per occurrence is required, with the United States of America named as additional insured. Standard FAR clauses apply including provisions for commencement/prosecution/completion of work, payment under fixed-price construction contracts, inspection and acceptance, and termination for convenience or default.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Embassy Canberra Date: 24th July 2026
Dear Prospective Offeror:
Subject: Request for Quotes – 19AS2026Q0025
Enclosed is a Request for Quotes (RFQ) for Residential Bathroom Renovation and Drainage upgrades. If you would like to submit a quotation, follow the instructions in Section J of the solicitation, complete the required portions of the attached document, and submit it to the address shown on the Standard Form that follows this letter.
The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.
Quotations are due by Tuesday 8th September 2026 at 4:00pm AEST. No quotations will be accepted after this time. Quotations must be in English and incomplete quotations will not be accepted.
The Embassy will hold a site visit on Thursday 6th August, at 10:00 AM AEST at the Residence in Canberra. Prospective offerors/quoters should contact cnbgsoprocurement@state.gov by Tuesday 4th August 2026, at 4:00 PM for additional information or to arrange entry to the building site.
Your quotation must be submitted electronically to cnbgsoprocurement@state.gov It is important to make sure the submission is made in specific size and format; in MS-Word 2007/2010 or MS-Excel 2007/2010 or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed the 30MB, the submission must be made in separate files and attached to separate emails with less than 30MB each.
In order for a quotation to be considered, you must also complete and submit the following:
1. SF-1442
2. Section A, Pricing
3. Section L Representations and Certifications
4. Additional information as required in Section J
5. Proof of SAM Registration
Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102.
Failure to be registered at time of proposal submission may deem the offeror’s proposal to be considered non-responsible and no further consideration will be given. Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.
mailto:cnbgsoprocurement@state.gov https://www.sam.gov/
Sincerely, Malene G. Carr Contracting Officer
Enclosure:
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
19AS2026Q0025
2. TYPE OF
SOLICITATION
SEALED BID (IFB)
[x] NEGOTIATED (RFP)
3. DATE
ISSUED
24th July 2026
PAGE OF
PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE
REQUEST NO. PR16102246
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
GSO Procurement 21 Moonah Place Yarralumla ACT 2600 Australia
Your quotation must be submitted electronically to:
cnbgsoprocurement@state.gov
9. FOR INFORMATION
CALL:
A. NAME
Vicki Page
B. TELEPHONE NO. (Include area code) (NO COLLECT
CALLS) 02 6214 5972
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
The American Embassy in Canberra has a requirement for the renovation of a U.S. Government owned residential property (GOP) located at 31 Couvreur, Canberra, ACT, Australia.
Refer to Section B for the Statement of Work.
11. The Contractor shall begin performance within ____ calendar days and complete it within ____ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _______________.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND
PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and ____ copies to perform the work required are due at the place specified in Item 8 by _______ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within _____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D.
Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract.
The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
0B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
RFQ NUMBER: 19AS2026Q0025
TABLE OF CONTENTS
SF-1442 COVER SHEET
A. PRICING
B. STATEMENT OF WORK
C. PACKAGING AND MARKING
D. INSPECTION AND ACCEPTANCE
E. DELIVERIES AND PERFORMANCE
F. CONTRACT ADMINISTRATION DATA
G. SPECIAL TERMS AND CONDITIONS
H. CLAUSES
I. LIST OF ATTACHMENTS
Attachment 1: Site Visit Drawing
J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION
K. EVALUATION CRITERIA
L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS
SECTION A - PRICING
A. PRICE
The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurances, overhead and profit.
Total Price (including all labor, materials, overhead and profit)
Goods and Services Tax (GST)
Grand Total (Total Price + GST)
A.1 GOODS & SERVICES TAX (GST)
The Contractor shall show Goods and Services Tax (GST) as a separate item on invoices submitted for payment.
A.2 FIRM FIXED PRICES
The Offeror shall propose firm fixed prices for the deliverables listed in Section A and fixed loaded hourly rates for additional services. Proposals that do not include firm fixed prices cannot be evaluated and will be rejected.
A.3 SEPARATE CHARGES
Separate charges, in any form, are not solicited. The Government shall not be obligated to pay any charges other than the contract price.
A.4 52.225-17 EVALUATION OF FOREIGN CURRENCY OFFERS (FEB 2000):
If the Government receives offers in more than one currency, the Government will evaluate offers by converting the foreign currency to United States currency using the exchange rate used by the Embassy in effect as follows:
(a) For acquisitions conducted using sealed bidding procedures, on the date of bid opening.
(b) For acquisitions conducted using negotiation procedures—
(1) On the date specified for receipt of offers, if award is based on initial offers; otherwise
(2) On the date specified for receipt of proposal revisions.
SECTION B - STATEMENT OF WORK
B.1. BACKGROUND
The American Embassy in Canberra has a requirement for the renovation of a U.S. Government owned residential property (GOP) located at 31 Couvreur, Canberra, ACT, Australia. The purpose of this project is to undertake the rehabilitation of the bathroom, toilet, and powder room areas, including associated drainage and plumbing systems, in order to address identified deficiencies, rectify end-of-life building services, and restore the wet areas to current functional, safety, and building standards.
The scope includes the replacement of deteriorated finishes, fixtures, and infrastructure, as well as the upgrade of sub-surface drainage and slab elements where required due to existing failures.
The works are intended to improve water tightness, drainage performance, durability, and overall usability of the wet areas. This project does not include structural modifications to the dwelling or changes to the overall building layout, except where alterations are required to accommodate new services, drainage upgrades, or fixture replacement.
B.2. Bathroom, toilet and Powder Room Renovation (18 sqm)
B.2.1 Preliminary Works
a) The Contractor shall undertake a detailed site inspection and assessment of existing conditions, including plumbing, drainage, structural elements, and finishes, to verify the extent of works.
b) The Contractor shall prepare and submit all required documentation for review and approval by the COR, including but not limited to:
c) Hydraulic/plumbing layouts
d) Shop drawings and construction details
e) Engineering details (where applicable)
f) The Contractor shall obtain all necessary approvals, permits, and certifications required to execute the works in accordance with applicable regulations.
g) All works shall be carried out by licensed and qualified trades in accordance with relevant Australian Standards and project specifications.
2.2 Demolition and removal
a) The Contractor shall arrange for asbestos testing of all affected areas prior to commencement of demolition works (if applicable).
b) Contractor shall demolish and remove existing bathroom, toilet, and powder room fixtures, finishes, and associated elements as required to facilitate the renovation works.
c) Works shall include saw-cutting and controlled demolition of slab areas as required to access existing drainage infrastructure.
d) All redundant, damaged, or non-compliant plumbing infrastructure shall be removed and disposed of.
e) All demolition materials shall be removed from site and disposed of at an approved facility in accordance with local regulations.
2.3 Drainage & plumbing works
a) The Contractor shall supply and install new compliant PVC drainage systems servicing the bathroom, toilet, powder room, and existing laundry.
b) All new drainage works shall be connected to the existing sewer system or approved discharge points.
c) Plumbing installations shall comply with all applicable Australian Standards and NCC requirements.
d) Upon completion, all plumbing systems shall be tested, commissioned, and certified.
2.4 Slab reinstatement
a) The Contractor shall carry out saw cutting, demolition, and removal of the existing slab to the extent required for plumbing and structural rectification.
b) The exposed subgrade shall be trimmed, leveled, and compacted to provide a suitable founding surface.
c) A moisture/vapour barrier shall be installed in accordance with relevant Australian Standards.
d) Reinforcement, including mesh and any required bar reinforcement, shall be supplied and installed, adequately supported and tied.
e) Starter bars shall be dowelled into existing slab edges to ensure structural continuity.
f) Concrete shall be placed to match existing levels and falls, finished to tolerances suitable for subsequent waterproofing and finishes.
g) All concrete works shall comply with applicable Australian Standards, including AS
3600 and AS 2870.
h) Concrete shall be cured in accordance with standards and manufacturer recommendations, and sufficient curing time shall be allowed prior to waterproofing installation.
2.5 Bathroom, toilet and powder room renovation
a) The Contractor shall supply and install all fixtures and fittings, including toilets, bathtub, shower and mixer, vanities, screens, tapware, toilet and towel rails.
b) Electrical works shall include the installation and upgrade of lighting, exhaust systems, switches, power outlets, and under-tile heating systems, coordinated with the renovation works.
c) Waterproofing shall be applied to all wet areas in accordance with AS 3740 and AS/NZS
4858, and certification shall be provided upon completion.
d) Floor and wall tiling shall be installed in accordance with AS ISO 13006 and AS 3958.1, including substrate preparation, screeding, adhesives, grouting, and finishing.
e) Shower screens, mirrors, and accessories shall be supplied and installed as per the approved design and schedules.
2.6 Laundry drainage works
a) The Contractor shall replace the existing laundry drainage system with new compliant PVC pipework.
b) The new system shall be integrated with the upgraded drainage network and connected to the existing sewer system.
c) The system shall be tested and commissioned upon completion.
2.7 Finishing work
a) The Contractor shall complete final fit-off of all fixtures, fittings, and services.
b) All joints, penetrations, and interfaces shall be sealed and finished to a high standard.
c) All work areas shall be cleaned, and the site left in a safe and presentable condition.
2.8 Testing & handover
a) The Contractor shall carry out final inspections of all works, including plumbing, electrical, and finishes.
b) All required compliance certifications shall be provided.
c) Warranties, manuals, and as-built documentation shall be submitted to the COR.
2.9 Instructions
a) In all construction operations on the property, the following shall apply:
b) Check for asbestos before commencing any work. If asbestos is found, report it to the Embassy immediately.
c) Establish floor protection for all access and areas work related during all construction activities times.
d) Establish dust minimization measures for all demolition and installation areas.
e) Protect and isolate fire detection systems before starting construction activities and re-activate the system as necessary daily.
f) Disconnect and secure electrical, HVAC, and plumbing systems only when required during construction activities.
g) Only electrical work related to new systems added by the contractor is included. All existing lighting and power systems to be protected.
h) All required local government certifications, permits, or inspections are included, and the contractor shall be the sole responsible for it.
i) Keep and maintain all structural elements, solid walls and slabs, and any other elements as instructed by the U.S. Embassy.
j) Clean and remove unwanted materials daily and dispose waste from site.
k) Submit shop drawings, samples, technical sheets, and all required data for approval by the COR prior to the purchase or manufacture of any item in the construction process.
l) Submit warranties, manuals, and all post documentation required for the maintenance and operation of the facility before substantial completion.
m) The Contractor shall repair all damages on the existing landscape and other site features caused by construction activities to the original conditions at no cost to USG.
SECTION C - PACKAGING AND MARKING
Mark materials delivered to the site as follows:
[RESERVED]
SECTION D - INSPECTION AND ACCEPTANCE
The COR, or his/her authorized representatives, will inspect from time to time the services being performed and the supplies furnished to determine whether work is being performed in a satisfactory manner, and that all supplies are of acceptable quality and standards.
The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the Contracting Officer as a result of such inspection.
D.1 SUBSTANTIAL COMPLETION
(a) "Substantial Completion" means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:
(1) do not interfere with the intended occupancy or utilization of the work, and
(2) can be completed or corrected within the time period required for final completion.
(b) The "date of substantial completion" means the date determined by the Contracting Officer or authorized Government representative as of which substantial completion of the work has been achieved.
Use and Possession upon Substantial Completion - The Government shall have the right to take possession of and use the work upon substantial completion. Upon notice by the Contractor that the work is substantially complete (a Request for Substantial Completion) and an inspection by the Contracting Officer or an authorized Government representative (including any required tests), the Contracting Officer shall furnish the Contractor a Certificate of Substantial Completion. The certificate will be accompanied by a Schedule of Defects listing items of work remaining to be performed, completed, or corrected before final completion and acceptance.
Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use upon substantial completion shall not be deemed an acceptance of any work under the contract.
D.2 FINAL COMPLETION AND ACCEPTANCE
D.2.1 "Final completion and acceptance" means the stage in the progress of the work as determined by the Contracting Officer and confirmed in writing to the Contractor, at which all work required under the contract has been completed in a satisfactory manner, subject to the discovery of defects after final completion, and except for items specifically excluded in the notice of final acceptance.
D.2.2 The "date of final completion and acceptance" means the date determined by the Contracting Officer when final completion of the work has been achieved, as indicated by written notice to the Contractor.
D.2.3 FINAL INSPECTION AND TESTS. The Contractor shall give the Contracting Officer at least five (5) days advance written notice of the date when the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started not later than the date specified in the notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.
D.2.4 FINAL ACCEPTANCE. If the Contracting Officer is satisfied that the work under the contract is complete (with the exception of continuing obligations), the Contracting Officer shall issue to the Contractor a notice of final acceptance and make final payment upon:
• Satisfactory completion of all required tests,
• A final inspection that all items by the Contracting Officer listed in the Schedule of Defects have been completed or corrected and that the work is finally complete (subject to the discovery of defects after final completion), and
• Submittal by the Contractor of all documents and other items required upon completion of the work, including a final request for payment (Request for Final Acceptance).
SECTION E - DELIVERIES AND PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
The Contractor shall be required to:
(a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and,
(c) complete the entire work ready for use not later than seventy-five (75) calendar days.
The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay liquidated damages to the Government in the amount of $600AUD or 1% of project award total for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Default clause.
CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES
(a) The time for submission of the schedules referenced in FAR 52.236-15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect the due date for submission as " five (5) calendar days after receipt of an executed contract".
(b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contract will be submitted for approval.
(c) The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the performance schedule, and (3) as required by the Contracting Officer to achieve coordination with work by the Government and any separate contractors used by the Government. The Contractor shall submit a schedule, which sequences work so as to minimize disruption at the job site.
(d) All deliverables shall be in the English language and any system of dimensions (English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed due to delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. The
Contractor shall identify each deliverable as required by the contract.
(e) Acceptance of Schedule: When the Government has accepted any time schedule;
it shall be binding upon the Contractor. The completion date is fixed and may be extended only by a written contract modification signed by the Contracting Officer. Acceptance or approval of any schedule or revision thereof by the Government shall not:
(1) Extend the completion date or obligate the Government to do so,
(2) Constitute acceptance or approval of any delay, or
(3) Excuse the Contractor from or relieve the Contractor of its obligation to maintain the progress of the work and achieve final completion by the established completion date.
NOTICE OF DELAY
If the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are actually causing delays which the Contractor believes may result in late completion of the project, the Contractor shall notify the Contracting Officer. The Contractor’s notice shall state the effect, if any, of such change or other conditions upon the approved schedule, and shall state in what respects, if any, the relevant schedule, or the completion date should be revised. The Contractor shall give such notice promptly, not more than ten (10) days after the first event giving rise to the delay or prospective delay. Only the Contracting Officer may revise the approved time schedule.
NOTICE TO PROCEED
(a) After receiving and accepting any bonds or evidence of insurance, the Contracting Officer will provide the Contractor a Notice to Proceed. The Contractor must then prosecute the work, commencing and completing performance not later than the time period established in the contract.
(b) It is possible that the Contracting Officer may elect to issue the Notice to Proceed before receipt and acceptance of any bonds or evidence of insurance. Issuance of a Notice to Proceed by the Government before receipt of the required bonds or insurance certificates or policies shall not be a waiver of the requirement to furnish these documents.
WORKING HOURS
All work shall be performed during 0700 to 1800 Monday through Friday. Other hours, if requested by the Contractor, may be approved by the Contracting Officer's Representative (COR). The Contractor shall give 24 hours in advance to COR who will consider any deviation from the hours identified above. Changes in work hours, initiated by the Contractor, will not be a cause for a price increase.
PRECONSTRUCTION CONFERENCE
A preconstruction conference will be held 10 days after contract award at U.S. Embassy Canberra to discuss the schedule, submittals, notice to proceed, mobilization and other important issues that effect construction progress. See FAR 52.236-26, Preconstruction Conference.
DELIVERABLES - The following items shall be delivered under this contract:
Description Quantity Deliver Date Deliver To
Section G. Securities/Insurance 1 10 days after award CO Section E. Construction Schedule 1 10 days after award COR Section E. Preconstruction Conference 1 10 days after award COR Section G. Personnel Biographies 1 10 days after award COR
Section F. Payment Request 1 Last calendar day of each month COR
Section D. Request for Substantial Completion 1 15 days before inspection COR
Section D. Request for Final Acceptance 1 5 days before inspection COR
SECTION F – CONTRACT ADMINISTRATION DATA
652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)
(a) The Contracting Officer may designate in writing one or more Government employees, by name or position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative (COR).
Such designation(s) shall specify the scope and limitations of the authority so delegated;
provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer, and this authority is delegated in the designation.
(b) The COR for this contract is Facilities Management Project Coordinator.
Payment: The Contractor's attention is directed to Section H, 52.232-5, "Payments Under Fixed-Price Construction Contracts". The following elaborates on the information contained in that clause.
Requests for payment may be made no more frequently than monthly. Payment requests shall cover the value of labor and materials completed and in place, including a prorated portion of overhead and profit.
After receipt of the Contractor's request for payment, and on the basis of an inspection of the work, the Contracting Officer shall make a determination as to the amount, which is then due. If the Contracting Officer does not approve payment of the full amount applied for, less the retainage allowed by in 52.232-5, the Contracting Officer shall advise the Contractor as to the reasons.
Under the authority of 52.232-27(a), the 14-day period identified in FAR 52.232-27(a)(1)(i)(A) is hereby changed to 30 days.
Attn: Canberra Accounts Payable cnbcustservice@state.gov
The Contractor shall show Good and Services Tax (GST) as a separate item on invoices submitted for payment.
mailto:cnbcustservice@state.gov
SECTION G - SPECIAL TERMS AND CONDITIONS
G.1.0 INSURANCE - The Contractor is required by FAR 52.228-5, "Insurance - Work on a Government Installation" to provide whatever insurance is legally necessary. The Contractor shall at its own expense provide and maintain during the entire performance period the following insurance amounts:
G.1.1 GENERAL LIABILITY (includes premises/operations, collapse hazard, products, completed operations, contractual, independent contractors, broad form property damage, personal injury):
(1) BODILY INJURY, ON OR OFF THE SITE, IN U.S. DOLLARS
Per Occurrence $10,000,000 AUD or USD Equivalent
Cumulative $10,000,000 AUD or USD Equivalent
(2) PROPERTY DAMAGE, ON OR OFF THE SITE, IN U.S. DOLLARS
Per Occurrence $10,000,000 AUD or USD Equivalent
Cumulative $10,000,000 AUD or USD Equivalent
G.1.2 The foregoing types and amounts of insurance are the minimums required. The Contractor shall obtain any other types of insurance required by local law or that are ordinarily or customarily obtained in the location of the work. The limit of such insurance shall be as provided by law or sufficient to meet normal and customary claims.
G.1.3 The Contractor agrees that the Government shall not be responsible for personal injuries or for damages to any property of the Contractor, its officers, agents, servants, and employees, or any other person, arising from and incident to the Contractor's performance of this contract. The Contractor shall hold harmless and indemnify the Government from any and all claims arising therefrom, except in the instance of gross negligence on the part of the Government.
G.1.4 The Contractor shall obtain adequate insurance for damage to, or theft of, materials and equipment in insurance coverage for loose transit to the site or in storage on or off the site.
G.1.5 The general liability policy required of the Contractor shall name "the United States of America, acting by and through the Department of State", as an additional insured with respect to operations performed under this contract.
G.2.0 DOCUMENT DESCRIPTIONS
G.2.1 SUPPLEMENTAL DOCUMENTS: The Contracting Officer shall furnish from time to time such detailed drawings and other information as is considered necessary, in the opinion of the Contracting Officer, to interpret, clarify, supplement, or correct inconsistencies, errors or omissions in the Contract documents, or to describe minor changes in the work not involving an increase in the contract price or extension of the contract time. The Contractor shall comply with the requirements of the supplemental documents, and unless prompt objection is made by the Contractor within 20 days, their issuance shall not provide for any claim for an increase in the Contract price or an extension of contract time.
G.2.1.1. RECORD DOCUMENTS. The Contractor shall maintain at the project site:
(1) a current marked set of Contract drawings and specifications indicating all interpretations and clarification, contract modifications, change orders, or any other departure from the contract requirements approved by the Contracting Officer; and,
(2) a complete set of record shop drawings, product data, samples and other submittals as approved by the Contracting Officer.
G.2.1.2 . "As-Built" Documents: After final completion of the work, but before final acceptance thereof, the Contractor shall provide:
(1) a complete set of "as-built" drawings, based upon the record set of drawings, marked to show the details of construction as actually accomplished; and,
(2) record shop drawings and other submittals, in the number and form as required by the specifications.
G.3.0 LAWS AND REGULATIONS - The Contractor shall, without additional expense to the Government, be responsible for complying with all laws, codes, ordinances, and regulations applicable to the performance of the work, including those of the host country, and with the lawful orders of any governmental authority having jurisdiction. Host country authorities may not enter the construction site without the permission of the Contracting Officer. Unless otherwise directed by the Contracting Officer, the Contractor shall comply with the more stringent of the requirements of such laws, regulations, and orders and of the contract. In the event of a conflict between the contract and such laws, regulations and orders, the Contractor shall promptly advise the Contracting Officer of the conflict and of the Contractor's proposed course of action for resolution by the Contracting Officer.
G.3.1 The Contractor shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters, to the extent that such compliance is not inconsistent with the requirements of this contract.
G.3.2 The Contractor shall give written assurance to the Contracting Officer that all subcontractors and others performing work on or for the project have obtained all requisite licenses and permits.
G.3.3 The Contractor shall submit proper documentation and evidence satisfactory to the Contracting Officer of compliance with this clause.
G.4.0 CONSTRUCTION PERSONNEL - The Contractor shall maintain discipline at the site and at all times take all reasonable precautions to prevent any unlawful, riotous, or disorderly conduct by or among those employed at the site. The Contractor shall ensure the preservation of peace and protection of persons and property in the neighborhood of the project against such action. The Contracting Officer may require, in writing that the Contractor remove from the work any employee that the Contracting Officer deems incompetent, careless, insubordinate or otherwise objectionable, or whose continued employment on the project is deemed by the Contracting Officer to be contrary to the Government's interests.
G.4.1 If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately give notice, including all relevant information, to the Contracting Officer.
G.4.2 After award, the Contractor has ten calendar days to submit to the Contracting Officer a list of workers and supervisors assigned to this project for the Government to conduct all necessary security checks. It is anticipated that security checks will take five (5) days to perform. For each individual, the list shall include:
Full Name Place and Date of Birth Current Address Identification number
Failure to provide any of the above information may be considered grounds for rejection and/or resubmittal of the application. Once the Government has completed the security screening and approved the applicants a badge will be provided to the individual for access to the site. This badge may be revoked at any time due to the falsification of data, or misconduct on site.
G.4.3 The Contractor shall provide an English speaking supervisor on site at all times. This position is considered as key personnel under this purchase order.
G.5.0 Materials and Equipment - All materials and equipment incorporated into the work shall be new and for the purpose intended, unless otherwise specified. All workmanship shall be of good quality and performed in a skillful manner that will withstand inspection by the Contracting Officer.
G.6.0 SPECIAL WARRANTIES
G.6.1 Any special warranties that may be required under the contract shall be subject to the stipulations set forth in 52.246-21, "Warranty of Construction", as long as they are not in conflict.
G.6.2 The Contractor shall obtain and furnish to the Government all information required to make any subcontractor's, manufacturer's, or supplier's guarantee or warranty legally binding and effective. The Contractor shall submit both the information and the guarantee or warranty to the Government in sufficient time to permit the Government to meet any time limit specified in the guarantee or warranty, but not later than completion and acceptance of all work under this contract.
G.7.0 EQUITABLE ADJUSTMENTS
Any circumstance for which the contract provides an equitable adjustment that causes a change within the meaning of paragraph (a) of the "Changes" clause shall be treated as a change under that clause; provided, that the Contractor gives the Contracting Officer prompt written notice (within 20 days) stating:
(a) the date, circumstances, and applicable contract clause authorizing an equitable adjustment and
(b) that the Contractor regards the event as a changed condition for which an equitable adjustment is allowed under the contract
The Contractor shall provide written notice of a differing site condition within 10 calendar days of occurrence following FAR 52.236-2, Differing Site Conditions.
G.9.0 ZONING APPROVALS AND PERMITS
The Government shall be responsible for:
- obtaining proper zoning or other land use control approval for the project
- obtaining the approval of the Contracting Drawings and Specifications
- paying fees due for the foregoing; and,
- for obtaining and paying for the initial building permits.
SECTION H - CLAUSES
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. In addition, the full text of a clause may be accessed electronically at: Acquisition.gov this address is subject to change.
If the Federal Acquisition Regulation (FAR) is not available at the location indicated above, use the Department of State Acquisition website at e-CFR to see the links to the FAR. You may also use an Internet “search engine” (for example, Google, Yahoo or Excite) to obtain the latest location of the most current FAR.
THE FOLLOWING FEDERAL ACQUISITION REGULATION CLAUSE(S) IS/ARE
INCORPORATED BY REFERENCE (48 CFR CH. 1):
CLAUSE TITLE AND DATE
52.202-1 DEFINITIONS (JUN 2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)
52.204-9
PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL
(JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE
(AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN
TELECOMMUNICATION AND VIDEO SURVEILLANCE SERVICES OR
EQUIPMENT (NOV 2021)
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED
https://acquisition.gov/browse/index/far https://gov.ecfr.io/cgi-bin/text-idx?SID=d9a7851186785ba2b1896db79b1b6b29&mc=true&tpl=/ecfrbrowse/Title48/48tab_02.tpl
OR PROPOSED FOR DEBARMENT OR VOLUNTARILY EXCLUDED (JAN
2025)
52.222-19 CHILD LABOR-COOPERATION WITH AUTHORITIES AND REMEDIES
(JAN 2025)
52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
52.225-5 TRADE AGREEMENTS (NOV 2023)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.225-14 INCONSISTENCY BETWEEN ENGLISH VERSION AND TRANSLATION
OF CONTRACT (FEB 2000)
52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING
WHILE DRIVING (MAY 2024)
52.228-3 WORKERS’ COMPENSATION INSURANCE (DEFENSE BASE ACT)
(JUL 2014)
52.229-6 TAXES - FOREIGN FIXED-PRICE CONTRACTS (FEB 2013)
52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)
52.232-1 PAYMENTS (AUG 1984)
52.232-7 PAYMENTS UNDER TIME-AND-MATERIALS AND MATERIALS
LABOR-HOUR CONTRACTS (NOV 2021)
52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)
52.232-10 PAYMENTS UNDER FIXED-PRICE ARCHITECT-ENGINEER
CONTRACTS (APR 2010)
52.232-11 EXTRAS (APR 1984)
52.232-18 AVAILABILITY OF FUNDS (APR 1984)
52.232-26 PROMPT PAYMENT FOR FIXED-PRICE ARCHITECT-ENGINEER
CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD
MANAGEMENT (OCT 2018)
52.233-1 DISPUTES (MAY 2014) ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.236-22 DESIGN WITHIN FUNDING LIMITATIONS (APR 1984)
52.236-23 RESPONSIBILITY OF THE ARCHITECT-ENGINEER CONTRACTOR
52.236-24 WORK OVERSIGHT IN ARCHITECT-ENGINEER CONTRACTS
52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT AND
VEGETATION (APR 1984)
52.242-14 SUSPENSION OF WORK (APR 1984)
52.243-1 CHANGES – FIXED PRICE (AUG 1987) Alternate III (APR 1984)
52.243-3 CHANGES – TIME-AND-MATERIAL OR LABOR-HOUR
(SEPT 2000)
52.246-4 INSPECTION OF SERVICES – FIXED-PRICE (AUG 1996)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.246-26 REPORTING NONCONFORMING ITEMS (AUG 2024)
52.249-7 TERMINATION (FIXED-PRICE ARCHITECT-ENGINEER)
(APR 1984)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.249-14 EXCUSABLE DELAYS (APR 1984)
I. FAR CLAUSES INCORPORATED IN FULL TEXT
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN
TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR
EQUIPMENT (NOV 2021)
(a) Definitions. As used in this clause— Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means–
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means–
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology;
or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 (50 U.S.C. 4817).
Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.
Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.
Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.
The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.
(c) Exceptions. This clause does not prohibit contractors from providing—
(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(d) Reporting requirement.
(1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause to the Contracting Officer, unless elsewhere in this contract are established procedures for reporting the information; in the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause
(i) Within one business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known);
brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: any further available information about mitigation actions undertaken or recommended.
https://www.acquisition.gov/far/part-4#FAR_4_2104 https://www.acquisition.gov/far/part-4#FAR_4_2104 https://dibnet.dod.mil/ https://dibnet.dod.mil/
In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services.
(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (b)(2), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services.
(End of clause)
52.213-4 TERMS AND CONDITIONS—SIMPLIFIED ACQUISITIONS (OTHER
THAN COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES)
(MAR 2026)
(a) The Contractor shall comply with the…