Questions and Responses-Global Hardware-19AQMM25B0123-5 Pages.docx

DOCX document 35 KB Posted

Attached to
Global Hardware
Solicitation number
19AQMM25B0123
Issued by

About this file

This is a Questions and Answers document for a Department of State RFI regarding Global Hardware (solicitation #19AQMM25B0123) containing 24 questions and responses about technical specifications and requirements for server and storage hardware solutions.

Key clarifications include: FIPS 140-2 certification is acceptable with proof of 140-3 submission to NIST; hardware must be Intel 16-core CPU based; overseas half-rack configurations require one JBOD with 16 disks per SAN; backup servers are not required for domestic sites; power requirements are 15AMP 100-120V single phase for overseas posts and 30AMP 200-240V single phase for domestic locations; hyperconverged infrastructure is only allowed for datacenters, not overseas installations; solutions must be VMware compatible though alternatives may be considered; and hardware components must be transferrable between sites for uniformity. The document indicates this RFI may or may not lead to a contract award, with questions due February 26 at 3:00 PM Eastern Time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Global Hardware (19AQMM25B0123) Questions and Responses

#
Question
Response
1
Under 2.2.2 Overseas Units – Complete Prebuilt Half-Rack:
1)Oracle RAC Server. How many Oracle RAC servers are required?
2)Backup Server. What type of backup software will reside on the server (example: Commvault, Veeam, NetBackup)? Does the customer need us to quote the backup software as well?
1 – The amount needed will vary from year to year.

2 - Multi functional sever that is ESXi compatible - backup software of DoS choice

2
Section 2.2.1 paragraph “o” states FIPS 140-3 certification of cryptographic modules as a requirement for all hardware/software in the solutions that leverages encryption.

While FIPS 140-3 represents the latest evolution in cryptographic security standards, customers should recognize that the majority of vendors have not yet completed the transition from FIPS 140-2 validation. The process of achieving FIPS 140-3 certification is complex, resource-intensive, and time-consuming, requiring vendors to undergo a rigorous evaluation under updated testing methodologies. As a result, many trusted cryptographic solutions that were previously validated under FIPS 140-2 remain in use and fully compliant with current security requirements. Since NIST has allowed FIPS 140-2 validations to remain active through September 2026, organizations can continue relying on these well-established modules without compromising security or regulatory compliance.

Insisting on immediate FIPS 140-3 validation could unnecessarily limit product choices and create procurement bottlenecks, as only a small percentage of vendors have completed the transition. Many industry-leading cryptographic libraries, hardware security modules (HSMs), and security appliances are still undergoing certification, meaning that organizations that demand FIPS 140-3 today may face delayed deployments, higher costs, and fewer or no available solutions. Rather than focusing solely on validation status, customers should evaluate the security posture of a product holistically—ensuring it adheres to best practices, meets their risk management needs, and has a clear roadmap for future compliance. Flexibility during this transition period allows for a smoother and more strategic adoption of FIPS 140-3 without disrupting current operations or security investments.

Would the Department of State consider easing this requirement and mandate FIPS 140-2 certification instead?

140-2 certified (must provide module certificate number) is acceptable for now but will need proof of 140-3 submittal to NIST.

3
2.2.2 ORAC Cluster – Customer is looking for older intel CPUs. We are shipping Gen 6 latest Intel CPU based servers. Are we allowed to propose alternate solution in addition to what Dept of State has asked for
CPUs must be Intel 16 core – the newest generation is acceptable
4
2.2.2.h –[Question] JBOD requirements. Need clarification if it’s 1 JBOD per system, or 1 JBOD for the 2 systems they requested.
Each rack has a single SAN and each SAN has a JBOD of 16 disks.
5
2.2.3 f. ii. (Large Site) vs 2.2.3 e. ii. (Small Medium sites) – Both ask for 5 nodes, but Large asks for “12 total rack units” and Small/Med asks for “10 total rack units”. Please confirm if both Large and Small/Med sites need back up server.
Backup server is not required for domestic sites.
6
2.2.3 f. ii. [Question] Is the 5 node cluster a typo and it is really supposed to be 6 nodes? 16 Core * 6 CPU = 96 Cores.
16 core per server is what is needed.
7
Is there a min/max rack height, width, depth & weight?

The solution is geared toward a standard full or half rack. Minimizing weight is ideal.

8
What type of AC power inputs are available, 16A, 32A, 30A, 50A or 60A? Single or 3Phase? 208V, 400V, 415V, 480V?

Post is 15AMP 100-120V single and Domestic 30AMP 200-240V single

9
Is there a preference on PDU type? Basic, Metered or Switched?
The current Post solution uses a CS-FED-AP9562 for the PDU. This is 15AMP, 120V, basic.

Domestic solutions may have higher power and more advanced PDU.

10
2.2.2.h [Question] - JBOD requirements. Need clarification if it’s 1 JBOD per Oracle RAC system, or 1 JBOD for the 2 Oracle RAC systems they requested.
Each rack has a single SAN and each SAN has a JBOD of 16 disks.
11
2.2.3 [Question] - For Large Site, we assume 2.2.3.e. are the spec requirements 6 hypervisor servers , and 2.2.5. Are the spec requirements for the 3 SAN devices connected to the 6 hypervisor servers?
No. Those are independent.
12
2.2.3 [Question] - For Small/Medium Site, we assume 2.2.3.f. are the spec requirements 6 hypervisor servers , and 2.2.5. Are the spec requirements for the 3 SAN devices connected to the 6 hypervisor servers? Is this correct?
No. Those are independent.
13
2.2.4 [Question] - What are Converged Hardware requirements here? It looks like a total capacity requirement, are there specific quantity requirements?
No – quantities will be determined for individual procurements.
14
What SW defined storage solution are they using?
Need more information. If you are referring to object storage, CEPH and vSAN
15
Will the State Department grant an extension for the due date of the RFI?

No

16
Does the Overseas Half Rack require SAN storage in addition to the SAN storage? (for DOS)

The solution is self-contained in a single unit to support Oracle real application cluster database

17
For the 2.2.3 and 2.2.4 requirements, are the total node counts required for application performance or to meet vSAN data protection policies?

The architecture includes both concepts

18
Would a backup configuration using a system (physical or virtual) storing backups on a dedicated SAN/NAS be acceptable instead of a backup server with only local storage?

No – servers acting in a storage capacity are future proofed for different workloads

19
Does the platform need to be able to meet the requirement to be compatible with alternate hypervisors for future growth?

Anything needs to be able to work with a top tier hypervisor but is now geared toward VMWare certifications

20
will the customer also accept “hyper-converged” (HCI) hardware solutions as the requirements only list “converged” infrastructure?
Only hyperconverged hardware would be for datacenters. Overseas hardware cannot be hyper-converged nor does the architecture allow for it. Any solution should be 2N+1.
21
While FIPS 140-3 is the latest cryptographic security standard, NIST has yet to fully complete the transition and certification process for many vendors. As a result, most solutions are still validated under FIPS 140-2, which remains compliant with current security requirements until September 2026. Insisting on immediate FIPS 140-3 certification could limit options and delay deployments, as NIST's slow pace of certification means fewer solutions are available. Customers should focus on a product’s overall security posture, ensuring it meets their needs while being adaptable to future compliance. Given this, would it be possible to adjust the requirement to FIPS 140-2 for now?
140-2 certified (must provide module certificate number) is acceptable for now but will need proof of 140-3 submittal to NIST.
22
Please define "transferrable component". What is the overall intent of this statement?
Individual hardware needs to be able to be swapped to any other site. Looking for hardware uniformity to fit in rack.
23
Does the Govt anticipate making an award off the RFI or will there be a follow on RFP/RFQ based upon the information provided in the RFI responses?

To be determined. An RFI does not commit the Government to awarding a contract.

24
VMware is mentioned throughout the RFI. Will a VMWare alternative be considered or will the Govt be issuing a sole source procurement?
Solution is currently VMware. Alternate solution could be considered but would need to be certified by alternate vendor as to not void any vendor support.

2/28/2025