19AJ2026Q0016 - Solicitation for Wall Floor and Conopy Repairs at the U.S. Embassy Baku.pdf
PDF 2 MB Posted
- Attached to
- Wall, Floor, and Canopy Repairs at the Consular Section of the U. S. Embassy Baku, Azerbaijan.
- Solicitation number
- 19AJ2026Q0016
- Issued by
-
Department of State US Embassy Baku
About this file
This is a Request for Quotes (RFQ) for construction repair services at the U.S. Embassy Baku, Azerbaijan. The solicitation number is 19AJ2026Q0016, issued July 23, 2026, with quotations due by August 10, 2026 at 6:00 PM local time. The contract will be awarded to the lowest-priced, acceptable, responsible quoter based on FAR 9.1 criteria including organizational experience, integrity, necessary equipment and facilities, and ability to comply with the performance period.
The scope of work encompasses wall, floor, and canopy repairs totaling approximately 240 square meters at the Consular Section exterior waiting area of the Chancery located at 111 Azadlig Avenue, Baku. Specific tasks include: exterior concrete wall repairs due to water damage and cracks with reinforcement using stainless steel; stairs repair with polymer-amended concrete and reinforcement; ramp flooring replacement with slip-resistant materials meeting ADA standards; floor replacement with new exterior flooring and tile baseboard installation; and canopy cover replacement with polycarbonate sheeting and new gutters with drainage integration. All work must be completed within 30 working days of notice to proceed. The contractor shall commence work within 10 calendar days of award. Contractor personnel must obtain security clearance before commencing work. The contract price shall include all labor, materials, equipment, services, overhead, profit, and cost of obtaining a Bank Letter Guarantee. General liability insurance is required at minimum USD 25,000 per occurrence and USD 65,000 cumulative. A performance and payment bond or letter of credit guarantee equal to 20 percent of contract price is required during performance and 10 percent during the guaranty period. The anticipated contract price range is USD 30,000 to USD 60,000. A mandatory site visit is scheduled for July 30, 2026 at 11:00 AM at the U.S. Embassy. Prospective quoters must be registered in the System for Award Management (SAM) prior to proposal submission and provide proof of SAM registration. The quotation submission shall include completed Standard Form 1442, Section A pricing, a performance schedule bar chart, and a Business Management/Technical Proposal demonstrating prior construction experience with references. The Government will not reimburse Value Added Tax (VAT) as the Embassy holds a tax exemption certificate with the host government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026.07.30_Questions and Answers_19AJ2026Q0016.pdf | ||
| Questions and Answers_19AJ2026Q0016.pdf | ||
| DS-4319 - Activity Risk Assessment 19AJ2026Q0016.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBU - CONTRACTING AND ACQUISITIONS
TABLE OF CONTENTS
SF-1442 COVER SHEET
A. PRICING
B. STATEMENT OF WORK
C. PACKAGING AND MARKING
D. INSPECTION AND ACCEPTANCE
E. DELIVERIES AND PERFORMANCE
F. CONTRACT ADMINISTRATION DATA
G. SPECIAL TERMS AND CONDITIONS
H. CLAUSES
I. LIST OF ATTACHMENTS
Attachment 1: Sample Letter of Bank Guaranty Attachment 2: Breakdown of Price by Divisions of Specifications
J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION
K. EVALUATION CRITERIA
L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS
SOLICITATION (Construction, Alteration, or Repair)
1. SOLICITATION NO.
19AJ2026Q0016
2. TYPE OF SOLICITATION
SEALED BID (IFB)
[x] NEGOTIATED (RFP)
3. DATE ISSUED
July 23, 2026
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
PR16090246
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
The U.S. Embassy Baku, 111 Azadliq Ave.
Baku, Azerbaijan
AZ1007
BAKUBIDBOX@STATE.GOV
9. FOR INFORMATION
CALL:
A. NAME
Vahid Movsumov
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) +994124883300
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
Wall, Floor, and Canopy Repairs at the Consular Section of the U.S. Embassy Baku, Azerbaijan, Price shall include all professional services, overheads, labor, material, equipment and services, and complete all works in accordance with the Statement of Work (SOW), and contract terms and conditions.
SF-1442, Solicitation, Offer and Award Section A Pricing Section B Statement of Work Section C Parking and Marking Section D Inspection and Acceptance Section E Deliveries or Performance Section F Administrative Data Section G Special Requirements Section H Contract Clauses Section I List of Attachments Section J Quotation Information Section K Evaluation Criteria Section L Representations, Certification and Other Statements of Offerors or Quoters Attachments
11. The Contractor shall begin performance within __10__ calendar days and complete it within _30___ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section E))
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
10 days
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. The offers to perform the work required are due at the place specified in Item 8 by 6:00 pm local time August 10, 2026. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than __60___ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
https://ilmsariba.state.sbu/Buyer/Main/aw?awh=r&awssk=xi2j&dard=1
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within _____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Line Item Summary
Solicitation number:
19AJ2026Q0016
Contract number:
The U.S. Embassy Renovation of walls and replacement of floor tiles at Post 2
Date of solicitation July 23, 2026
Line No Description Quantity Unit Unit Price
Total Cost
001 Wall, floor, and canopy repairs at the Consular Section of the U.S. Embassy Baku, Azerbaijan. Price shall include all professional services, overheads, labor, material, equipment and services, cost of obtaining Bank Letter Guarantee and profit, to perform and complete all works in accordance with the Statement of Work (SOW), and contract terms and conditions.
1.00 LT
002 Defense Base Act (DBA) Insurance 1.00 LT
003 General Liability Insurance 1.00 LT
SECTION A - PRICING
A. PRICE
The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurances, overhead and profit.
Total Price (including all labor, materials, overhead and profit)
A.1 VALUE ADDED TAX
VALUE ADDED TAX (VAT). The Government will not reimburse the Contractor for VAT under this contract. The Contractor shall not include a line for VAT on Invoices as the U.S.
Embassy has a tax exemption certificate with the host government.
SECTION B - STATEMENT OF WORK
The character and scope of the work are set forth in the contract. The Contractor shall furnish and install all materials required by this contract.
In case of differences between small and large-scale drawings, the latter will govern. Where a portion of the work is drawn in detail and the remainder of the work is indicated in outline, the parts drawn in detail shall apply also to all other portions of the work.
SCOPE OF WORK
U.S. Embassy Baku, Azerbaijan Consular Section Canopy Repair Project – 2026
Project Description and Specifics:
The U.S. Embassy Azerbaijan is requesting the services of a company to repair the canopy located at the Consular Section exterior waiting area of the Chancery.
Purpose:
The purpose of this project is to repair the existing canopy in the exterior of the Consular Section Waiting Area to ensure proper drainage of the water, durability, and weather protection. The repair of the canopy structure will include replacement of the existing fabric cover for a translucent material such as polycarbonate, new gutters, and proper drainage to the existing water drain system.
Project Overview:
This project involves the following tasks:
1. Existing canopy cover replacement.
2. Adjust existing metal structure to the new cover if necessary.
3. Installation of new gutters.
Scope of Work:
1. Existing canopy (fabric) replacement
• Safely dismantle and remove the existing canopy (fabric), including all associated components.
• Adjust the structure to the new cover material.
• Paint the structure as necessary.
• Dispose of all removed materials in accordance with local regulations.
• Ensure the area is clean and free of debris before proceeding with installation of the new cover.
2. Installation of new canopy cover material:
• Provide canopy capable of withstanding loads as defined by the State Department without failure.
• Ensure the new cover is durable, weather-resistant, has the correct slope to direct the water to the new installed gutters and downspouts.
• Use high-quality materials to ensure longevity and safety.
• Provide monolithic polycarbonate sheet fabricated from an approved polycarbonate glazing (light transmitting) material identical to that tested with a CC1 fire rating.
• Ensure the material is securely fastened and sealed to prevent leaks.
3. Installation of new gutters and drainage system:
• Install new gutters along the edges of the canopy to collect rainwater.
• Connect the gutters to the existing drainage system to ensure proper water flow and prevent pooling.
• Test the drainage system to confirm functionality.
4. Submittals:
A. Drawings: Include plans, details, and attachments to other work.
Field Measurements: Verify dimensions of the area before installation and indicate measurements on Shop Drawings.
B. Samples for initial selection: Manufacturer’s color charts showing the full range of colors available for factory-finished cover materials.
Security:
Personnel.
The contractor’s personnel must obtain a security clearance before the work commences. The FAC team can escort the contractor if necessary. All the work will be performed outside.
Place of Performance:
This job will be performed at the Chancery. This property is located at 111 Azadlig Propekti, Baku.
Period of Performance:
The contractor shall complete the repairs within 30 working days. See deliverables section.
Special Considerations:
All the materials for this project must be approved by the COR before purchasing. Clearance must be granted before the work commences.
Proposed Project Schedule/Timeline:
Task Duration Start Date End Date
Initial Assessment and Planning 4 days [TBD] [TBD]
Design and drawings 4 days
Materials selection 1 day
Manufacture 10 days
Removal of existing cover 1 days
Installation of new cover 5 days
Quality assurance 2 days
Cleaning and material disposal 1 day
Total Estimated Duration: 28 days Supporting Drawings (Can also be sent separately as an attachment or uploaded into ProjNet .PDF, .DOCX, .DWG):
Supporting Photos: (Can also be sent separately as an attachment or uploaded into ProjNet .JPG):
Additional Supporting Documentation (Can also be sent separately as an attachment or uploaded into ProjNet.):
SCOPE OF WORK
U.S. Embassy Baku, Azerbaijan Wall and floor repairs Project at the Chancery – 2025
Project Description and Specifics:
The U.S. Embassy Azerbaijan is requesting the services of a company to perform repairs of an area of approximately 240 sq/mt. The project location will be at the Consular Section exterior waiting area at the Chancery and areas nearby.
Project Overview:
This project involves the following tasks:
1. Repair of exterior walls damaged by water infiltration and cracks.
2. Installation of new bricks or tiles and cap stone on specific walls.
3. Repair of cracked stairs and installation of new flooring.
4. Replacement of ramp flooring.
5. Removal of existing flooring and installation of new exterior floor.
6. Removal and installation of new railings that comply with POSHO requirements.
Scope of Work:
5. Exterior Concrete Walls Repairs Due to Water Damage and Cracks:
• Assessment:
o Conduct a site survey to determine the dimensions, location, and specific requirements for the walls.
o Evaluate soil conditions and existing structures to ensure proper foundation design.
o Identify any existing damage and assess the structural integrity of the walls.
• Repair Process:
o Remove damaged sections of the wall.
o Clean and prepare the surface for patching or reinforcement.
o Apply concrete repair materials to restore structural integrity. Repair materials should match the properties of the existing.
o Reinforce the repaired sections with stainless steel bars or mesh as needed.
• Finishing:
o Apply vapor permeable coatings to protect wall surfaces and also allowing them to breathe.
o Install new tiles or bricks on the wall to create an accent wall (identified on the drawings). Paint the wall to match the surrounding structures or design specifications. Use vapor permeable paint systems compatible with the underlying paint.
o Install new capstone on top of the wall to prevent future water damage.
6. Stairs Repair Due to Cracks
• Assessment:
o Inspect the stairs to determine the cause and extent of cracking (e.g., structural settlement, material fatigue).
• Repair Process:
o Remove existing flooring.
o Fill with polymer amended concrete repair compound.
o Reinforce the structure with additional support if necessary. Use only stainless steel for reinforcement.
• Technical Requirements:
o Use same exterior flooring materials used on the rest of the area.
o Ensure the repaired stairs meet safety standards, including proper tread depth and riser height.
• Special Considerations:
o Maintain access to alternative routes during repairs.
o Ensure the stairs are safe and usable after each workday.
7. Replacement of Ramp Flooring
• Assessment:
o Evaluate the current ramp flooring for wear, damage, and compliance with accessibility standards.
• Replacement Process:
o Remove coating material.
o Prepare the ramp surface by cleaning and leveling it.
o Install new slip-resistant flooring material suitable for ramps (same as the rest of the flooring).
o Seal and finish the flooring to ensure durability.
• Technical Requirements:
o Flooring must meet ADA (Americans with Disabilities Act) standards for slip resistance and accessibility.
o Use durable, weather-resistant materials for outdoor ramps.
8. Floor Replacement
• Assessment:
o Level the surface and create new slopes so the water is directed to the existing floor drains.
o Determine if the subfloor has been affected.
• Replacement Process:
o Remove all the flooring material in the area.
o Inspect and repair the subfloor if necessary.
o Install new flooring material as specified.
o Apply protective coatings or sealants to prevent future staining.
o Replacement and installation of new tile baseboard in the waiting area.
• Technical Requirements:
o Use flooring materials that are durable, easy to maintain, and appropriate for the space.
o Ensure proper installation techniques to avoid gaps, uneven surfaces, or future damage.
• Special Considerations:
o Match the new flooring to the existing design and color scheme.
o Minimize noise and dust during the replacement process.
Security:
Personnel.
The contractor’s personnel must obtain a security clearance before the work commences. The FAC team can escort the contractor if necessary. All the work will be performed outside.
Place of Performance:
This job will be performed at the Chancery. This property is located at 111 Azadlig Propekti, Baku.
Period of Performance:
The contractor shall complete the repairs within 30 working days. See deliverables section.
Special Considerations:
All the materials for this project must be approved by the COR before purchasing. Clearance must be granted before the work commences.
Proposed Project Schedule/Timeline:
Task Duration Start Date End Date
Initial Assessment and Planning 3 days [Insert Date] [Insert Date]
Wall Repairs 10 days [Insert Date] [Insert Date]
Stairs Repair 5 days [Insert Date] [Insert Date]
Ramp Flooring Replacement 2 days [Insert Date] [Insert Date]
Floor Replacement 8 days [Insert Date] [Insert Date]
Final Inspection and Cleanup 2 days [Insert Date] [Insert Date]
Total Estimated Duration: 30 days Supporting Drawings (Can also be sent separately as an attachment or uploaded into ProjNet .PDF, .DOCX, .DWG):
Wall and floor repair project at the Chancery- Drawing.PDF Supporting Photos: (Can also be sent separately as an attachment or uploaded into ProjNet .JPG):
Wall and floor repair project at the Chancery- Pics.PDF Additional Supporting Documentation (Can also be sent separately as an attachment or uploaded into ProjNet.):
SECTION C - PACKAGING AND MARKING
Mark materials delivered to the site as follows: RESERVED
SECTION D - INSPECTION AND ACCEPTANCE
The COR, or his/her authorized representatives, will inspect from time to time the services being performed and the supplies furnished to determine whether work is being performed in a satisfactory manner, and that all supplies are of acceptable quality and standards.
The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the Contracting Officer as a result of such inspection.
D.1 SUBSTANTIAL COMPLETION
(a) "Substantial Completion" means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:
(1) do not interfere with the intended occupancy or utilization of the work, and
(2) can be completed or corrected within the time period required for final completion.
(b) The "date of substantial completion" means the date determined by the Contracting Officer or authorized Government representative as of which substantial completion of the work has been achieved.
Use and Possession upon Substantial Completion - The Government shall have the right to take possession of and use the work upon substantial completion. Upon notice by the Contractor that the work is substantially complete (a Request for Substantial Completion) and an inspection by the Contracting Officer or an authorized Government representative (including any required tests), the Contracting Officer shall furnish the Contractor a Certificate of Substantial Completion. The certificate will be accompanied by a Schedule of Defects listing items of work remaining to be performed, completed, or corrected before final completion and acceptance.
Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use upon substantial completion shall not be deemed an acceptance of any work under the contract.
D.2 FINAL COMPLETION AND ACCEPTANCE
D.2.1 "Final completion and acceptance" means the stage in the progress of the work as determined by the Contracting Officer and confirmed in writing to the Contractor, at which all work required under the contract has been completed in a satisfactory manner, subject to the discovery of defects after final completion, and except for items specifically excluded in the notice of final acceptance.
D.2.2 The "date of final completion and acceptance" means the date determined by the Contracting Officer when final completion of the work has been achieved, as indicated by written notice to the Contractor.
D.2.3 FINAL INSPECTION AND TESTS. The Contractor shall give the Contracting Officer at least five (5) days advance written notice of the date when the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started not later than the date specified in the notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.
D.2.4 FINAL ACCEPTANCE. If the Contracting Officer is satisfied that the work under the contract is complete (with the exception of continuing obligations), the Contracting Officer shall issue to the Contractor a notice of final acceptance and make final payment upon:
• Satisfactory completion of all required tests,
• A final inspection that all items by the Contracting Officer listed in the Schedule of Defects have been completed or corrected and that the work is finally complete (subject to the discovery of defects after final completion), and
• Submittal by the Contractor of all documents and other items required upon completion of the work, including a final request for payment (Request for Final Acceptance).
SECTION E - DELIVERIES AND PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
The Contractor shall be required to:
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and, complete the entire work ready for use not later than 30 days after notice to proceed.
The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay liquidated damages to the Government in the amount of USD 240.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Default clause.
CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES
(a) The time for submission of the schedules referenced in FAR 52.236-15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect the due date for submission as 5 calendar days after receipt of an executed contract".
(b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contract will be submitted for approval.
(c) The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the performance schedule, and (3) as required by the Contracting Officer to achieve coordination with work by the Government and any separate contractors used by the Government. The Contractor shall submit a schedule, which sequences work so as to minimize disruption at the job site.
(d) All deliverables shall be in the English language and any system of dimensions (English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed due to delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. The Contractor shall identify each deliverable as required by the contract.
(e) Acceptance of Schedule: When the Government has accepted any time schedule;
it shall be binding upon the Contractor. The completion date is fixed and may be extended only by a written contract modification signed by the Contracting Officer. Acceptance or approval of any schedule or revision thereof by the Government shall not:
(1) Extend the completion date or obligate the Government to do so,
(2) Constitute acceptance or approval of any delay, or
(3) Excuse the Contractor from or relieve the Contractor of its obligation to maintain the progress of the work and achieve final completion by the established completion date.
NOTICE OF DELAY
If the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are actually causing delays which the Contractor believes may result in late completion of the project, the Contractor shall notify the Contracting Officer. The Contractor’s notice shall state the effect, if any, of such change or other conditions upon the approved schedule, and shall state in what respects, if any, the relevant schedule, or the completion date should be revised. The Contractor shall give such notice promptly, not more than ten (10) days after the first event giving rise to the delay or prospective delay. Only the Contracting Officer may revise the approved time schedule.
NOTICE TO PROCEED
(a) After receiving and accepting any bonds or evidence of insurance, the Contracting Officer will provide the Contractor a Notice to Proceed. The Contractor must then prosecute the work, commencing and completing performance not later than the time period established in the contract.
(b) It is possible that the Contracting Officer may elect to issue the Notice to Proceed before receipt and acceptance of any bonds or evidence of insurance. Issuance of a Notice to Proceed by the Government before receipt of the required bonds or insurance certificates or policies shall not be a waiver of the requirement to furnish these documents.
WORKING HOURS
All work shall be performed during09:00 to 17:00, Monday – Friday. . Other hours, if requested by the Contractor, may be approved by the Contracting Officer's Representative (COR). The Contractor shall give 24 hours in advance to COR who will consider any deviation from the hours identified above. Changes in work hours, initiated by the Contractor, will not be a cause for a price increase.
PRECONSTRUCTION CONFERENCE
A preconstruction conference will be held 10 days after contract award at the U.S. Embassy Baku, Azadlig Avenue 111 to discuss the schedule, submittals, notice to proceed, mobilization and other important issues that effect construction progress. See FAR 52.236-26, Preconstruction Conference.
DELIVERABLES - The following items shall be delivered under this contract:
Description Quantity Deliver Date Deliver To
Section G. Securities/Insurance 1 10 days after award CO Section E. Construction Schedule 1 10 days after award COR Section E. Preconstruction Conference 1 10 days after award COR Section G. Personnel Biographies 1 10 days after award COR
Section F. Payment Request 1 Last calendar day of each month COR
Section D. Request for Substantial Completion 1 15 days before inspection COR
Section D. Request for Final Acceptance 1 5 days before inspection COR
SECTION F – CONTRACT ADMINISTRATION DATA
652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)
(a) The Contracting Officer may designate in writing one or more Government employees, by name or position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative (COR).
Such designation(s) shall specify the scope and limitations of the authority so delegated;
provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer, and this authority is delegated in the designation.
(b) The COR for this contract is Elchin Ismayilov, Maintenance Supervisor Engineer.
Payment: The Contractor's attention is directed to Section H, 52.232-5, "Payments Under Fixed-Price Construction Contracts". The following elaborates on the information contained in that clause.
Requests for payment, may be made no more frequently than monthly. Payment requests shall cover the value of labor and materials completed and in place, including a prorated portion of overhead and profit.
After receipt of the Contractor's request for payment, and on the basis of an inspection of the work, the Contracting Officer shall make a determination as to the amount, which is then due. If the Contracting Officer does not approve payment of the full amount applied for, less the retainage allowed by in 52.232-5, the Contracting Officer shall advise the Contractor as to the reasons.
Under the authority of 52.232-27(a), the 14 day period identified in FAR 52.232-27(a)(1)(i)(A) is hereby changed to 30 days.
[SECTION G - SPECIAL TERMS AND CONDITIONS
G.1.0 PERFORMANCE/PAYMENT PROTECTION -
G.2.0 INSURANCE - The Contractor is required by FAR 52.228-5, "Insurance - Work on a Government Installation" to provide whatever insurance is legally necessary. The Contractor shall at its own expense provide and maintain during the entire performance period the following insurance amounts:
G.2.1 GENERAL LIABILITY (includes premises/operations, collapse hazard, products, completed operations, contractual, independent contractors, broad form property damage, personal injury):
(1) BODILY INJURY, ON OR OFF THE SITE, IN U.S. DOLLARS
Per Occurrence USD 25,000.00
Cumulative USD 65,000.00
(2) PROPERTY DAMAGE, ON OR OFF THE SITE, IN U.S. DOLLARS
Per Occurrence USD 25,000.00
Cumulative USD 65,000.00
G.2.2 The foregoing types and amounts of insurance are the minimums required. The Contractor shall obtain any other types of insurance required by local law or that are ordinarily or customarily obtained in the location of the work. The limit of such insurance shall be as provided by law or sufficient to meet normal and customary claims.
G.2.3 The Contractor agrees that the Government shall not be responsible for personal injuries or for damages to any property of the Contractor, its officers, agents, servants, and employees, or any other person, arising from and incident to the Contractor's performance of this contract. The Contractor shall hold harmless and indemnify the Government from any and all claims arising therefrom, except in the instance of gross negligence on the part of the Government.
G.2.4 The Contractor shall obtain adequate insurance for damage to, or theft of, materials and equipment in insurance coverage for loose transit to the site or in storage on or off the site.
G.2.5 The general liability policy required of the Contractor shall name "the United States of America, acting by and through the Department of State", as an additional insured with respect to operations performed under this contract.
G.3.0 DOCUMENT DESCRIPTIONS
G.3.1 SUPPLEMENTAL DOCUMENTS: The Contracting Officer shall furnish from time to time such detailed drawings and other information as is considered necessary, in the opinion of the Contracting Officer, to interpret, clarify, supplement, or correct inconsistencies, errors or omissions in the Contract documents, or to describe minor changes in the work not involving an increase in the contract price or extension of the contract time. The Contractor shall comply with the requirements of the supplemental documents, and unless prompt objection is made by the Contractor within 20 days, their issuance shall not provide for any claim for an increase in the Contract price or an extension of contract time.
G.3.1.1. RECORD DOCUMENTS. The Contractor shall maintain at the project site:
(1) a current marked set of Contract drawings and specifications indicating all interpretations and clarification, contract modifications, change orders, or any other departure from the contract requirements approved by the Contracting Officer; and,
(2) a complete set of record shop drawings, product data, samples and other submittals as approved by the Contracting Officer.
G.3.1.2 . "As-Built" Documents: After final completion of the work, but before final acceptance thereof, the Contractor shall provide:
(1) a complete set of "as-built" drawings, based upon the record set of drawings, marked to show the details of construction as actually accomplished; and,
(2) record shop drawings and other submittals, in the number and form as required by the specifications.
G.4.0 LAWS AND REGULATIONS - The Contractor shall, without additional expense to the Government, be responsible for complying with all laws, codes, ordinances, and regulations applicable to the performance of the work, including those of the host country, and with the lawful orders of any governmental authority having jurisdiction. Host country authorities may not enter the construction site without the permission of the Contracting Officer. Unless otherwise directed by the Contracting Officer, the Contractor shall comply with the more stringent of the requirements of such laws, regulations, and orders and of the contract. In the event of a conflict between the contract and such laws, regulations and orders, the Contractor shall promptly advise the Contracting Officer of the conflict and of the Contractor's proposed course of action for resolution by the Contracting Officer.
G.4.1 The Contractor shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters, to the extent that such compliance is not inconsistent with the requirements of this contract.
G.4.2 The Contractor shall give written assurance to the Contracting Officer that all subcontractors and others performing work on or for the project have obtained all requisite licenses and permits.
G.4.3 The Contractor shall submit proper documentation and evidence satisfactory to the Contracting Officer of compliance with this clause.
G.5.0 CONSTRUCTION PERSONNEL - The Contractor shall maintain discipline at the site and at all times take all reasonable precautions to prevent any unlawful, riotous, or disorderly conduct by or among those employed at the site. The Contractor shall ensure the preservation of peace and protection of persons and property in the neighborhood of the project against such action. The Contracting Officer may require, in writing that the Contractor remove from the work any employee that the Contracting Officer deems incompetent, careless, insubordinate or otherwise objectionable, or whose continued employment on the project is deemed by the Contracting Officer to be contrary to the Government's interests.
G.5.1 If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately give notice, including all relevant information, to the Contracting Officer.
G.5.2 After award, the Contractor has ten calendar days to submit to the Contracting Officer a list of workers and supervisors assigned to this project for the Government to conduct all necessary security checks. It is anticipated that security checks will take 30 days to perform.
For each individual, the list shall include:
• Completed OF-174 form
• Completed Release of Information with Cells for Social Networks data
• Copy of National ID
• Certificate of no Criminal Convictions (from ASAN Service)
Failure to provide any of the above information may be considered grounds for rejection and/or resubmittal of the application. Once the Government has completed the security screening and approved the applicants a badge will be provided to the individual for access to the site. This badge may be revoked at any time due to the falsification of data, or misconduct on site.
G.5.3 The Contractor shall provide an English speaking supervisor on site at all times. This position is considered as key personnel under this purchase order.
G.6.0 Materials and Equipment - All materials and equipment incorporated into the work shall be new and for the purpose intended, unless otherwise specified. All workmanship shall be of good quality and performed in a skillful manner that will withstand inspection by the Contracting Officer.
G.7.0 SPECIAL WARRANTIES
G.7.1 Any special warranties that may be required under the contract shall be subject to the stipulations set forth in 52.246-21, "Warranty of Construction", as long as they are not in conflict.
G.7.2 The Contractor shall obtain and furnish to the Government all information required to make any subcontractor's, manufacturer's, or supplier's guarantee or warranty legally binding and effective. The Contractor shall submit both the information and the guarantee or warranty to the Government in sufficient time to permit the Government to meet any time limit specified in the guarantee or warranty, but not later than completion and acceptance of all work under this contract.
G.8.0 EQUITABLE ADJUSTMENTS
Any circumstance for which the contract provides an equitable adjustment that causes a change within the meaning of paragraph (a) of the "Changes" clause shall be treated as a change under that clause; provided, that the Contractor gives the Contracting Officer prompt written notice (within 20 days) stating:
(a) the date, circumstances, and applicable contract clause authorizing an equitable adjustment and
(b) that the Contractor regards the event as a changed condition for which an equitable adjustment is allowed under the contract
The Contractor shall provide written notice of a differing site condition within 10 calendar days of occurrence following FAR 52.236-2, Differing Site Conditions.
G.9.0 ZONING APPROVALS AND PERMITS
The Government shall be responsible for:
- obtaining proper zoning or other land use control approval for the project
- obtaining the approval of the Contracting Drawings and Specifications
- paying fees due for the foregoing; and,
- for obtaining and paying for the initial building permits.
SECTION H - CLAUSES
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. In addition, the full text of a clause may be accessed electronically at: Acquisition.gov this address is subject to change.
If the Federal Acquisition Regulation (FAR) is not available at the location indicated above, use the Department of State Acquisition website at e-CFR to see the links to the FAR. You may also use an Internet “search engine” (for example, Google, Yahoo or Excite) to obtain the latest location of the most current FAR.
THE FOLLOWING FEDERAL ACQUISITION REGULATION CLAUSE(S) IS/ARE
INCORPORATED BY REFERENCE (48 CFR CH. 1):
CLAUSE TITLE AND DATE
52.202-1 DEFINITIONS (JUN 2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL
(JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT
2018)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE
(AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED
OR PROPOSED FOR DEBARMENT OR VOLUNTARILY EXCLUDED (JAN
2025)
SBU - CONTRACTING AND ACQUISITIONS
https://acquisition.gov/browse/index/far https://gov.ecfr.io/cgi-bin/text-idx?SID=d9a7851186785ba2b1896db79b1b6b29&mc=true&tpl=/ecfrbrowse/Title48/48tab_02.tpl
52.216-7 ALLOWABLE COST AND PAYMENT (AUG 2018)
52.222-1 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)
52.222-19 CHILD LABOR-COOPERATION WITH AUTHORITIES AND REMEDIES
(JAN 2025)
52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
52.225-5 TRADE AGREEMENTS (NOV 2023)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.225-14 INCONSISTENCY BETWEEN ENGLISH VERSION AND TRANSLATION
OF CONTRACT (FEB 2000)
52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING
WHILE DRIVING (MAY 2024)
52.228-3 WORKERS’ COMPENSATION INSURANCE (DEFENSE BASE ACT)
(JUL 2014)
52.228-4 WORKERS’ COMPENSATION AND WAR-HAZARD INSURANCE
OVERSEAS (APR 1984)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (FEB 2021)
52.228-13 ALTERNATIVE PAYMENT PROTECTION (JULY 2000)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020)
52.229-6 TAXES - FOREIGN FIXED-PRICE CONTRACTS (FEB 2013)
52.229-7 TAXES- FIXED PRICE CONTRACTS WITH FOREIGN GOVERNMENTS
(FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS
(MAY 2014)
52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)
52.232-11 EXTRAS (APR 1984)
52.232-18 AVAILABILITY OF FUNDS (APR 1984)
52.232-22 LIMITATION OF FUNDS (APR 1984)
52.232-25 PROMPT PAYMENT (JAN 2017)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD
MANAGEMENT (OCT 2018)
52.232-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER – OTHER THAN
SYSTEM FOR AWARD MANAGEMENT (JULY 2013)
52.233-1 DISPUTES (MAY 2014) ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
(APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-14 SUSPENSION OF WORK (APR 1984)
52.243-4 CHANGES (JUN 2007)
52.243-5 CHANGES AND CHANGED CONDITIONS (APR 1984)
52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES
(APR 2012)
52.245-9 USE AND CHARGES (APR 2012)
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
52.246-17 WARRANTY OF SUPPLIES OF A NONCOMPLEX NATURE (JUN
2003)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.246-26 REPORTING NONCONFORMING ITEMS (AUG 2024)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-
PRICE) (APR 2012)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.249-14 EXCUSABLE DELAYS (APR 1984)
I. FAR CLAUSES INCORPORATED IN FULL TEXT
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN
TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR
EQUIPMENT (NOV 2021)
(a) Definitions. As used in this clause— Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means–
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means–
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology;
or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 (50 U.S.C. 4817).
Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.
Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.
Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.
The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.
(c) Exceptions. This clause does not prohibit contractors from providing—
(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(d) Reporting requirement.
(1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause to the Contracting Officer, unless elsewhere in this contract are established procedures for reporting the information; in the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause
SBU - CONTRACTING AND ACQUISITIONS
https://www.acquisition.gov/far/part-4#FAR_4_2104 https://www.acquisition.gov/far/part-4#FAR_4_2104 https://dibnet.dod.mil/ https://dibnet.dod.mil/
(i) Within one business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known);
brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of…