Technical Specifications v2 191T7023Q0049.pdf
PDF 2 MB Posted
- Attached to
- X-Ray Room Roof Reconfiguration, Rome, Italy
- Solicitation number
- 191T7023Q0049
- Issued by
-
Department of State
About this file
This document provides the technical specifications for a federal contract solicitation to replace the roof and flooring of an X-ray room at the U.S. Embassy in Rome, Italy. The solicitation seeks offers for demolishing the existing roof and installing a new roofing system including insulation, waterproofing membrane, and concrete screed over structural decking. The work also includes installing a new steel staircase and parapet around the roof perimeter. Bidders must submit samples, drawings, and schedules for the roofing materials and steel components by the closing date. The period of performance is 40 calendar days from notice to proceed, and liquidated damages will be assessed for delays in completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BoQ v2 - 191T7023Q0049.pdf | ||
| Amendment 0001 - 191T7023Q0049.pdf | ||
| RFQ 191T7023Q0049.docx | DOCX document | |
| SF-1442 - 191T7023Q0049.doc | DOC document | |
| BoQ 191T7023Q0049.pdf | ||
| Technical Specifications 191T7023Q0049.pdf | ||
| Cover Letter - 191T7023Q0049.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Embassy of the United States of America
Rome, Italy
ROME
ROOF X-RAY ROOM
Facility Engineering Office
Summary
1. GENERALITY'
1.1. SUBJECT OF THE SCOPE OF WORK 4
1.2. GENERAL REQUIREMENTS OF THE SOW 4
1.3. OFFER AND ALL-INCLUSIVE PRICES 5
2. DESCRIPTION OF THE WORKS
BRIEF DESCRIPTION OF CURRENT STATE
WORKS FORESEEN IN THE PROJECT;
INTERFERENCES IN GENERAL
WORK IN GENERAL
CONSTRUCTION SITE SAFETY
3. PROCEDURE FOR EXECUTING THE WORKS
3.1. MATERIAL ACCEPTANCE RULES 12
3.2. GENERAL RULES 12
3.3. QUALITY OF MATERIALS 12
4. FLOORING
5. STEEL WORK
6. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND TRANSPORT ... 17
6.1. PROVISIONAL WORKS 17
6.2. RENTALS 17
6.3. TRANSPORTATION 17
8. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS
8.1. LAYING OF THE MATERIALS 18
9. SITE ORGANIZATION AND SAFETY
9.1. DAMAGE 20
10. SOLICITATION CHARACTERISTICS
10.1. CONTRACT PHASE 21
10.2. IMPLEMENTATION PHASE 21
10.3. CONCLUSION PHASE 22
10.4. PERFORMANCE TIME AND PENALTIES FOR DELAYS 22
10.5. SUBCONTRACTING AND PIECEWORK 22
10.6. MATERIAL EQUIVALENTS 23
10.7. WORK PROGRESS 23
10.8. PARKING 23
11. PRESENTATION OF OFFER
12. CATALOGUE CUTS
13. REGISTRY OF SUBMISSION
14. DRAWING
1. GENERALITY'
1.1. Subject of the scope of work
The object of this contract concerns the works relating to:
- the replacement of the roof flooring, including screeds, insulations and waterproofing, at the
X-ray Room.
The works object of the contract, described in this Scope of Work (hereinafter SOW), must be complete in all their parts, even for what is necessary not expressly mentioned, but in any case for the complete and workmanlike work, suitable for the meeting the anticipated need.
For a complete identification of the work, please refer to the technical conditions indicated in this SOW and to the drawings.
A complete maintenance booklet for each individual component must be delivered.
1.2. General requirements of the sow
All the works described in the descriptive and graphic documents must be carried out in the most scrupulous observance of the current Laws, rules and regulations, in any case, in a workmanlike manner.
It stand to reason that all the costs for the issue by the competent Authorities of any access permits or temporary occupation of the external area are borne by the Contractor (hereinafter the Contractor or Contractor).
All non-reusable removal materials, contemplated in this deed, will be transported to public landfills or eventually to places indicated by the Client at the care and expense of the
Contractor Contractor for which suitable transport documentation must be provided and delivery to authorized landfills without the expenses such as the work will not be compensated.
It also remains established that all costs relating to site inspections and surveys that the
Contractor deems most appropriate during the construction site or temporary site inspection are included and compensated for in the lump-sum prices referred to in this contract.
Prior to the start of work, the Contractor must provide the Client with:
within days 30 (thirty) calendar and consecutive days, including holidays and semi-holidays from the date of the Notice to Proceed:
a construction site and assembly project, complete in every detail and completion of the project responsible for the basis of the tender signed by Contractor technical staff responsible for the production of the modules themselves;
a detailed work schedule;
Upon delivery of the works, the Contractor will arrange at its own expense to organize and set up the site within the area dedicated to the works, being responsible for the custody of means and materials, as will be better specified in the following documents that the Contractor is required to draw up and send to the COR, before handing over the construction site, to the
CSE and to the Project Supervisor.
All charges relating to demolitions, removals of the relative areas of intervention must be considered included and compensated, including handling on site, any lifting and lowering, loading and transport to landfill of resulting materials and download charges.
All the charges relating to the preparation of all the temporary works, such as delimitations and anything else necessary for the safe execution of the works relating to the intervention in question, are also to be considered included and compensated in the lump sum prices.
Any material used (“gravel, scree…”) to make the site area suitable for vehicles is included.
With regard to removals and excavations, these must be carried out in an orderly manner and with the necessary precautions, in order to prevent any injury to workers and to avoid inconvenience or disturbance to the performance of activities within the area.
The production of dust must be limited, therefore the resulting materials must be, if necessary, covered and contained in "removable" containers until they are disposed of.
For the indications referring to the constructional and dimensional characteristics of the artefacts, reference must be made to the description of the works and to the current state of the places, which the Contractor must have compulsorily examined in the places concerned.
Finally, it should be noted that the unit prices applied to the various magisteriums must therefore include general expenses, any costs for design, assembly and assembly, Contractor profits, charges for labour, transport, freight and materials, etc.
1.3. Offer and all-inclusive prices
The works referred to in this deed are "lump sum contract". By accepting this contract, the
Contractor declares, to all intents and purposes, that in formulating the offer it has taken into account all the particular and general situations inherent in the contract covered by this deed and, in particular, that it has evaluated all the obligations and charges indicated or referred to even implicitly, also evaluating the new prices if present, with the relative analyses.
The Contractor agrees to carry out the works according to the conditions and methods established or referred to in this Deed, even implicitly.
In accepting this SOW, the Contractor declares to have taken full knowledge of the area subject to intervention and its nature, which lead to greater costs, to have normally examined the general, particular and contractual circumstances relating to the contract and the execution times and that you have taken all of this into account in your offer.
The Contractor acknowledges that the consideration for the contract, agreed in the manner and under the conditions all indicated or referred to implicitly in this deed, is inclusive of all the works and furniture required for the perfect execution of the contract itself in its entirety and functionality, including charges of all kinds.
With the lump sum prices of the estimate, it is intended to compensate the Contractor for any general and particular burden for undertaking the works to be fully functional and complete even in the non-mainstream parts and prescribed in these Specifications. Consequently, the estimated prices cannot be subject to changes due to incomplete or erroneous forecasts made by the Contractor in determining the offer during the tender. In the price the value of the offer, the Contractor must also include for all prices take into account the charges referred to in the
Administrative Conditions and in particular:
• on-site supplies of all materials;
• sources of energy and water supply;
• labor performance;
• rental of all necessary equipment of any kind;
• charges deriving from the general and particular conditions of these Regulations
(geotechnical tests and professional services, relating to checks, calculations, tests, documentation and certifications, static tests, technical tests - provisional, final test, etc.);
• contractual and tax expenses.
At the beginning of the works, the Contractor will take care and expenses to organize and set up its construction site on the areas granted, according to its instructions given by the Facility
Management, as per the timetable presented by the same Contractor, being responsible for the custody of vehicles and materials , as will be better specified on the POS (operational safety) that the Contractor will be required to prepare in advance of the construction site installation.
All charges relating to the construction site of the intervention areas (delimitations, shelters, walkways, systems, etc.) which will be implemented from time to time by the Contractor
Contractor must be considered included and compensated, even if not expressly provided for in these Specifications, but however necessary for the correct execution of the contract. All charges relating to the preparation of all temporary works, such as scaffolding, shoring and anything else necessary for the safe execution of the works relating to the intervention in question are included and compensated in the lump-sum prices.
2. DESCRIPTION OF THE WORKS
The design of the works has the purpose of replacing the old and damaged Roof flooring of the X-
Ray Room.
Picture 1 – The terrace in question
Picture 2 –Terrace in question
Picture 3 – Terrace in question
Picture 4 – other small terrace to be replace
Brief description of current state
Currently, the areas in question are in a very poor condition with evident signs of deterioration and broken in many points.
Works foreseen in the project;
More specifically, the works will concern:
• Fencing of construction site areas and preparation of storage area and temporary routes;
• Demolition of the existing Flooring including all the screed until reaching the structural slab,
• Installation of the Flooring, according to the stratigraphy below;
• Installation of a new steel stairs;
• Installation of a new railing protection;
All the existing systems and devices must be respected and preserved.
Picture 5 – stratigraphy for flooring
INTERFERENCES IN GENERAL
On the top of the Terrace, there are several channel, cables, devices or various interferences, of an electric, water, sewage type, each of which must be respected, and/or replaced or moved.
The interference item includes all manufacturing, materials and/or services necessary for the perfect functionality of the interference found.
WORK IN GENERAL
All works, civil, electrical, hydraulic, temporary safety of the sites, must be supported by plans and executive drawings for the construction site, which must be approved by the COR.
At the end of the work, the Contractor must provide files in original format (e.g. dwg, word, excel, etc.)
of the As-Builts.
CONSTRUCTION SITE SAFETY
The safety of the construction site, including all charges foreseen by the current legislation, will be an important aspect for the planned works. The item includes the following:
- Fencing of the construction site area, temporary walkways, construction site bathroom.
- All types of scaffolding possibly necessary for carrying out the planned works.
3. PROCEDURE FOR EXECUTING THE WORKS
3.1. Material acceptance rules
The materials required for the construction of the works, whatever their origin, will be of the best quality, and will be considered accepted only when, at the unquestionable judgment of the
COR, they correspond to those designated below in terms of nature, quality, durability, suitability and application. Except for special materials, all the works must come from quarries, factories, refineries, etc., deposits. chosen exclusively by the Contractor, which cannot make any exceptions.
3.2. General rules
The items below must establish the execution rules for the various works contemplated in the
Contract, as well as the technical specifications of the materials used.
By rule of thumb, in the execution, the Contractor will have to comply with the best rules of the art as well as with the following works. For the categories of works that are not found in this
SOW, and for which no special rules have been prescribed, in particular for any work to be carried out economically, the Contractor must follow the best procedures dictated by the technique and comply with the orders that for this purpose, the COR will issue.
Works which, for any reason, immediately or subsequently prove to be badly performed, must be redone at the Contractor's expense, without the need for a formal request from the COR; the possible presence on site of an overseer of the Principal cannot be invoked by the Contractor in discharge of its liability.
For the works on the networks and for the construction of artifacts and works of art, the
Contractor, having received the delivery, referring to the project cornerstones, will first carry out the tracing of the work by affixing the stakes and modifiers for the axis, for the sections and for the works of art; at his care and expense the pickets will be maintained until completion.
3.3. Quality of materials
All the works envisaged by this SOW can be performed in perfect working order and with materials that meet the technical specifications indicated and/or referred to in this SOW.
The quality of the material used in the execution of these works must meet, when not otherwise specified by Contractor rules or regulations, the requisites required by the laws in force and by the official standards of good construction techniques.
The Client, during construction and at any time, may take material samples from the manufactured articles used to verify their perfect correspondence with the approved types.
In this case, the Contractor will have to make an operating team available to the client to carry out the activities necessary for the execution of these checks, carried out with the help of a specific specialized Contractor. These charges will be charged to the Contractor, including any demolition and reconstruction of the works found to be non-compliant.
The Contractor must promptly report any defect or anomaly found on the materials supplied directly by the Principal. .
4. FLOORING
The new flooring shall have the following stratigraphy and features, from top to bottom:
FLOORING
The new flooring include:
• FLOORING in self-locking slabs such as LASTRA® 50x50 in a light color like white or
Botticino or similar, 3 cm thick, CE marked in accordance with UNI 1339 in double-layer vibro-compressed concrete, with ECOTOP "PHOTOCATALYTIC" (TX Active ®) finish, produced only with natural aggregates from Contractor with UNI EN ISO 9001 Quality
Certification and UNI EN ISO 14001 Environmental Certification. The flooring must respond to environmental performance in accordance with point 2.4.1.2 of the Ministerial Decree
11/10/2017 (CAM), with a recycled material content ≥5%, this specification must be accompanied by a product certification issued by a conformity assessment body which certifies the recycled content through the explanation of the balance of mass which consists in the verification of a self-declared environmental declaration, compliant with the ISO 14021 standard. With reference to point 2.2.6 of the D.M. 11/10/2017, the flooring must have an SRI index ≥29. The flooring must consist of two layers, of which the surface layer with a thickness of ≥ 4 mm and made with a mixture of quartz with a maximum particle size of 2 mm and with a minimum dosage of white photocatalytic cement type TX ACTIVE® of 400 Kg/m3. The product, with this finish and this colour, must have a certificate of reduction of NOx values in
60 minutes of more than 60%. The flooring is made up of elements measuring 50x50 cm.
The elements must be equipped with suitable interlocking spacers which facilitate installation and ensure that it is blocked. The indirect tensile strength must be ≥ 3.5 MPa. Resistance to climatic agents must be at least Class 2, marking B (water absorption % by mass <6%). The freeze/thaw resistance must be at least equal to Class 3 marking D (mass loss after freeze/thaw test ≤1.0 kg/m2). The resistance to abrasion must be at least equal to Class 4
(Li≤20mm), Marking I. To overcome architectural barriers, the flooring must have a BCRA friction coefficient (DM 236 of 164/06/89) equal to or higher to 0.70 and a value of the USRV coefficient > 60. With reference to the measurement of the slip limit angle, conducted according to DIN 51097, this angle must be ≥25°, i.e. Class C-Excellent. The density must not be less than 2200 kg/m3; The supports are included according to the height that COR will decide.
• BITUME MEMBRANE. Preparation of the laying surface of waterproof coverings with a coat of solvent-based bituminous PRIMER in quantities of no less than 300g/m;
• Two layers of bituminous waterproofing membrane modified with elastomeric resins for surfaces confined or under heavy protection in areas with high temperature ranges, reinforced with continuous thread non-woven polyester fabric, torch-applied with 10 cm overlapping in the longitudinal direction and 15 cm at the ends of the sheets, laid out on the laying surface after treatment with a bituminous primer on flat, curved and inclined surfaces.
Thickness 4+4mm. The lump sum item also includes the waterproofing of the perimeter curbs, as per the attached drawings for a height of no less than 30 cm.
• SCREED for heights between 4 cm and 10 cm.
The lump sum item includes all types of work to carry out the flooring, for example, transport, raising, lowering, stacking, protection of materials, finishes and so on.
The item also includes the profiling of the rainwater downspouts, using both new metal cages and cement mortar and anything else necessary to give the finished work in a workmanlike manner.
5. STEEL WORK
IRON PARAPETS
The roof will be protected with an iron parapet like the one in the figure below, in hot-dip galvanized steel, anchored to the roof curb by means of mechanical and/or chemical fishers. The parapet will be equipped with a handrail and will have a height of no less than 92 cm from the threshold of the curb.
The distance between the vertical elements must not exceed 10 cm.
Picture 6 – type of railing
STEEL LADDER
As regards access to the roof, the installation of a simple staircase in hot-dip galvanized steel was envisaged, with a minimum width of 70 cm, equipped with a handrail on both sides and with a slope derived from the distance of 1.5m from the wall of the building from the lowest step. The drawing must be submitted to the COR for approval.
Picture 7 – type of staircase
In the work in subject, it also included three steel stairs to connect the first Roof Terrace with the Top
Roof Terrace
6. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND
TRANSPORT
6.1. Provisional works
The main regulations concerning scaffolding and scaffolding, fixed metal scaffolding, mobile scaffolding, etc., are contained in Legislative Decree 81/08 and subsequent Legislative Decree No.
106 of 08/03/2009.
6.2. Rentals
The machines and tools given for hire must be in perfect working order and be equipped with all the accessories necessary for their operation. The maintenance of tools and machines is the exclusive responsibility of the Contractor so that they are in constant efficiency.
The lump sum price includes: transport from the place of origin to the construction site and vice versa, assembly and disassembly, labour, fuel, lubricants, consumables, electricity, scrap and everything for the necessary functioning of the means. They also include general expenses and the entrepreneur's profit in the freight rates.
6.3. Transportation
If the size of the material to be transported is less or more than the payload of the vehicle requested for hire, no price reductions or inreasing are envisaged.
The supply of consumables and the driver's labor are included in the transport prices.
8. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS
8.1. Laying of the materials
The Contractor shall be follow what is include the Technical sheets of the materials that we use, after approval by COR.
9. SITE ORGANIZATION AND SAFETY
In addition to the provisions of the SOW, the following remains established:
1. upon delivery of the works, the Contractor must designate by name a technical assignment employed by or registered in a specific professional register with the task of directing the organization of the site and supervising the conditions of safety and use of the manpower, equipment and materials. Said technician is required to always be present on site .
2. The Contractor is required, during the preparation of the site, the execution of the works to observe the rules on accident prevention and occupational hygiene referred to in Presidential
Decree 27.04.1955, n.547, to Presidential Decree 07.01.1956, n.164, to Presidential Decree
03.19.1956, n.303, to Legislative Decree 81/2008 and subsequent amendments. mod. and supplement and subsequent provisions even if issued during the course of the works.
3. The Contractor has the obligation to comply with the "safety plan" or the one amended following the supplementary proposals formulated by him and to comply with the related implementing provisions that will be issued during the works by the "safety coordinator during the execution of the works"; the Contractor must also draw up and promote to the COR, in the manner established by the combined provisions of the aforementioned Legislative Decree 81/2008, an operational safety plan that takes into account the organisational, technical, procedural and technological reality of the Contractor itself. In the event of a temporary association of companies, the above applies to the agent Contractor or Contractor designated as group leader. In the event that the drafting of the safety and coordination plan is not envisaged, the
Contractor must draw up and deliver its own replacement safety plan to the COR within the terms established by the Rule. It should be noted that the amount of the charges deriving from the implementation of the provisions of the aforementioned construction site safety documents, expressly indicated in the specifications, are understood to be offset and included in the unit and/or bulk prices of the various items of the estimate. Having established that the percentage safety incidence of the safety charges of each individual estimate item is conventionally assumed to be equal to the ratio between the global work costs and the gross amount of the safety charges, the portion of the amount not to be subject to a discount will be equal to product of the aforementioned incidence by the gross amount booked.
4. The Contractor is obliged to adapt the working hours to the User's needs, with the obligation to obtain the information in advance.
5. The Contractor, through its manager, will have to keep a register updated on the construction site, to be shown for inspection by the Project Manager himself or someone on his behalf, such as in the work itself or to be noted on a daily basis materials and inflows on site to be used in the works, those used in the execution of the works themselves and those removed from the site, with the resultant of the materials stored there. He must keep the packing slips/supply of materials in absolute order in special catalogues/binders prepared for this purpose.
6. It is absolutely forbidden to access the site for Contractor personnel who, where requested, refuse to submit to personal checks or checks on things in tow. The contracting station declines any responsibility if the refusal referred to in this paragraph causes delays, hindrances or even the impossibility of executing the contract.
7. The Contractor must maintain discipline on construction sites and is obliged to observe and away from his agents and his agents, the regulations and provisions in general issued by the contracting station and by the competent authorities for the good order and discipline of the works. The Contractor must employ suitable persons for his agents, foremen and workers. The construction manager has the right to order the change of duties of the Contractor's personnel in cases of ineptitude and the removal of personnel from the works in cases of insubordination and bad faith. In any case, the Contractor remains liable for damages caused by the inexperience, negligence or bad faith of the personnel themselves.
8. To guarantee the execution of the works, maintain personal surveillance compliance in all construction sites, even if external to the places of work, on all the means used by the
Contractor, as well as in the production and material processing workshops. When this is established by the regulations, by the specifications and by the contract and when the contracting station, in warning of any regulatory or contractual requirement, signifies to the contracting party that it wants to make use of this right, the contracting station itself has the obligation to inform the station in good time Contractor of the start of processing of objects related to the works and to give it all the information it deems necessary for the exercise of supervision. He must also indicate, if requested, the establishments from which he intends to order the materials necessary for the execution of the contract.
9. The works must be carried out in a workmanlike manner and the materials to be used must be of the best quality available on the market, free from any general and special defect, meet all the other requirements indicated in the technical specifications and in the specifications as well as in the Decrees bearing the conditions mandatory general techniques. When it comes to national products, the Contractor is free to procure materials where he deems the best, provided that they have requirements where prescribed by the contract, unless in these general conditions, in the special chapter or in the price tariff, special requirements are prescribed on origins some materials. The Contractor must justify, with the presentation of suitable documents, the actual origin of the materials, and lend himself to subjecting them to all the tests that the project manager deems appropriate to ascertain their quality and resistance. The materials cannot be used if they have not been previously accepted by the construction manager who has the right to refuse those he does not recognize as suitable for the goodwill of the works. The rejected materials must be removed from the construction sites within the term established by the construction manager and at a convenient distance; failing the Contractor to comply with the relevant provision, the site manager has the right to do so directly, charging the
Contractor the related expense, which will be deducted from the first advance certificate.
Acceptance does not affect the right of the contracting station to refuse, at any time until testing, the works performed with materials that do not comply with the contractual conditions, materials to proceed, pursuant to art. 18 of DM 145/2000, in the case of construction defects.
When the Contractor presents concrete for and the relative samples, the contracting station may examine proposals to replace the quality of the materials and their origin, if prescribed, however reserving the full right to accept and reject said proposals. If, even without opposition from the site manager, the Contractor has on his own initiative used materials of a better prescribed excess weight and size, or of a more accurate quality or mastery, he is not entitled to any price increase, whatever the the advantages that can derive from the contracting station;
and in this case the accreditation of the Contractor is done as if the materials found the weight and dimensions, the qualities and the mastery established in the contract. Conversely, objects or materials of weight, characteristics and/if smaller than those prescribed, or of lower quality or less accurate workmanship are used, they will be counted by reducing in proportion to the lower weight, smaller dimensions and different quality and processing the corresponding prices.
All general and specific charges, in any case connected to the obligations listed above, are to be paid in full and at the expense of the Contractor, having taken them into account in determining the individual unit prices, by measure or as a whole of the tender specifications.
9.1. DAMAGE
1. The Contractor is responsible for all measures, including provisional works and all obligations to avoid the occurrence of damage to the works, the environment, people and things in the execution of the contract pursuant to art. 14 of the DM n. 145/2000.
2. No compensation is due for damage caused by force majeure to temporary works, scaffolding or site vehicles and equipment .
10. SOLICITATION CHARACTERISTICS
10.1. Contract phase
Within 15 calendar days of the date of award, the Contractor shall submit the following documentation to the Embassy’s Technical Office:
· A final and detailed work schedule of the various interventions and relative length of time required to carry out all the work requested in the contract.
· A final Safety Plan as set forth in the General chapter, finalized with the names of all actors and with the results of the discussions with the POSHO.
· A list of the names, complete with bio-data, of all the employees, as well as possible suppliers and sub-Contractors for specific work, who will require access to the work-site. Furthermore, the
Contractor shall submit a complete list of vehicles to be used during the project, indicating the make, model and license number.
· Designation of someone who will be in charge of the project on behalf of the Contractor and who will be fully authorized to discuss and decide together with the COR any variations during the course of the project, both concerning methodology of the work and the supplies.
· Designation of a Safety Manger who will address all safety issues and will monitor the daily operations.
· The register of submittals.
10.2. Implementation phase
· The implementation phase starts with the Notice to proceed (NTP).
· No work shall be performed before the submission of the shop drawings and relevant approval.
· No materials shall be installed prior the relevant submission and approval.
· Normal working hours are from 08:00-08:30 up to 17:30 during weekdays. Any work to be carried out after normal working hours or during the week-end shall be agreed upon in advance with the
COR in order to obtain all the necessary authorizations and approvals.
· Demolitions, perforations and other high noise operations shall be carried out no earlier than 09.30.
The quiet rule shall apply even during the time 12.30 to 15.30, during work days.
· The work-site shall be kept as clean as possible.
· Areas for storing material shall be agreed upon, together with the COR, based on logistical-operative criteria.
· Any temporary interruptions of utilities shall be scheduled at least 5 days in advance and shall be subject to approval from the COR.
· Tests on the correct operation of the systems and consignment of parts of completed work shall be carried out in the presence of the person designated by the Contractor and someone authorized by the Consulate. The Contractor shall be responsible for drawing up the necessary delivery reports for the work and systems carried out and shall be subject to verification and acceptance by the COR.
10.3. Conclusion phase
· Once the project is completed a final inspection shall be carried out with representatives of the
Contractor and the Embassy, in order to verify that the project has been carried out correctly, that it is in compliance with the technical specifications and that the systems operate correctly.
· When the work has been completed and accepted by the COR, the Contractor shall submit the following documents to the COR:
· detailed “as-built” drawings showing the new constructions, both the architectural/structural aspects as well as all the systems. The drawings shall be submitted on paper and software in ".dwg" format.
· technical cards of the most important materials used in the project, with a list indicating the location of the vendors and local suppliers.
· certification of conformity and tests carried out by the manufacturers for materials, as well as guarantee of the correct installation of all the materials by the Contractor with regard to the project realization and law requirements.
10.4. Performance time and penalties for delays
The contract performance time and the methods with which these times will be calculated are fully described in the solicitation package and here listed for convenience.
The Registry of Submission, at the following of this document, shall, (but shall not be limited to), indicate the kind of material samples and the number of them for selection and approval by the COR.
Period of time the complete execution of the project, from mobilization to final cleaning:
40 solar days from the "Notice to proceed".
For this reason, It would be appropriate that the Contractor start with two different Team Work.
Penalties for delays in completing the project are those described in the tender documents.
10.5. Subcontracting and piecework
In the subcontracting authorization request and in the subcontracting agreement, the Contractor shall promptly indicate the operational scope of the subcontract, in terms of performance, and specify in unambiguously, in particular, the name of the subContractor, the description of the work or services to be subcontracted – indicating the relative quantities or dimensional parameters referred to each execution area and process phase and referring to the project - the individual areas the individual process phases in which the subcontracted work or services will be performed.
In any case, the Contractor remains responsible towards the contracting authority for the execution of the works subject to subcontracting, relieving the contracting authority itself from any claims of subContractors or from claims for damages made by third parties as a result of the execution of subcontracted works.
It should be noted that in the event of subcontracting of works, the Contractor will be solely responsible for the technical and professional suitability of the subContractor.
In addition, the expected times for the work covered by the contract, the subcontracting must be compatible and congruent with the work program of the main contract (Gantt Chart), by updating it, with the Contractor's commitment to produce the work program updated to the works manager before the start of the subcontracted works .
10.6. Material equivalents
The contractor shall verify and ensure that all the materials supplied are new and without defects and that their use and/or installation is carried out using the best techniques and fully respecting the instructions supplied by the manufacturers.
Special parts shall be manufactured solely by workshops that are highly qualified in that specific sector.
The makes indicated in this SOW (Scope of Work) are intended as a point of reference and therefore, the words or approved equivalent are implicit.
Therefore, the makes and products listed are deemed equivalent to each other. Different selections implemented by the Contractor shall be approved in advance by the COR, after submission of samples and technical cards.
10.7. Work progress
In general, the Contractor shall have the faculty of developing the work in the way he believes more convenient and shall hand it over completed within the terms of the contract, as long as, in the opinion of the COR, this is not detrimental to the outcome of the project and the interests of the
Administration.
The Administration reserves the right to request that a specific task must be carried out within a pre-determined period of time, or to dispose the order of the performance of the work in a way it deems more convenient, especially in relation to requirements depending on the performance of work and delivery of supplies excluded from the contract, without the Contractor having the possibility to refuse or ask for special compensation.
Before starting the work, the Contractor shall submit for the CORs approval a detailed operative schedule and costs, which he will follow during the performance of the contract, in concurrence with the schedule.
10.8. Parking
The parking is allowed inside the Residence. The Contractor's vehicles shall be allowed to park only for loading and unloading materials
11. PRESENTATION OF OFFER
12. CATALOGUE CUTS
13. REGISTRY OF SUBMISSION
FLOORING
Contractor shall submit the sample of the Photovoltaic TxActive and all the materials used for this project, per specification. Each material shall be submitted with its technical sheet for COR approval.
WATERPROOFING
Contractor shall submit nr. 3 sample of the WATERPROOFING LAYER used for this project, per specification. Each material shall be submitted with its technical sheet for COR approval.
STAIRCASE AND PARAPETS
Contractor shall submit the drawings with features for staircase and parapets for COR approval.
14. DRAWING