2. IBWC Form 245 Minimum Quals for Award.docx
DOCX document 54 KB Posted
- Solicitation number
- 191BWC24R0013
About this file
This document is the INTERNATIONAL BOUNDARY & WATER COMMISSION MINIMUM QUALIFICATIONS FOR AWARD form. It outlines the minimum experience requirements for contractors bidding on the federal contract opportunity to perform emergency replacement of components within the grit facilities at the South Bay International Wastewater Treatment Plant (SBIWTP) in San Diego County, CA.
The form requires contractors to answer 'yes' or 'no' to questions regarding their experience, including a minimum of 5 years on similar construction projects, experience as a prime contractor with the federal government, experience performing infrastructure improvements to wastewater treatment plants while operations were ongoing, and a minimum of 5 years installing specialty piping systems for wastewater treatment plants. Contractors must provide backup information using IBWC Form 245B to support any 'yes' answers, and a subcontractor's experience can be used to satisfy the requirements. The contracting officer may request additional information to determine responsibility under FAR 9.104-1, which must be provided within 24 hours. Failure to provide the required information will result in the contractor being found ineligible for award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1. SOW_Grit Rehab Repair_Amendment 1-rmk.docx | DOCX document | |
| 191BWC24R0013 0001.pdf | ||
| Grit Rehab RFI Tracker QAs.xlsx | XLSX spreadsheet | |
| Surge Tank OM and Drawings.pdf | ||
| Grit System Rehab Compiled As-Built Drawings.pdf | ||
| Grit Removal System OM Info specs.pdf | ||
| Primary Channel Air Blower OM Info.pdf | ||
| Grit Removal System Design Info specs.pdf | ||
| 1. SOW_Grit Rehab Repair.docx | DOCX document | |
| 4. WD CA20240001 07.26.2024.pdf | ||
| 3. IBWC Form 245B Backup Information.pdf | ||
| 191BWC24R0013 Grit Chamber Rehab.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTERNATIONAL BOUNDARY & WATER COMMISSION
MINIMUM QUALIFICATIONS FOR AWARD
(Individual, Partnership, Company, or Corporation)
Any 'No' answer disqualifies a Contractor from bidding on this Project.
Subcontractor experience can be used to answer questions 1 through 4.
| Answer the following questions: |
| YES |
| NO |
| 1 |
| Do you have a minimum of 5 years of experience on construction projects similar in magnitude, scope, and complexity to that described in the solicitation? |
Valid experience must have occurred within the last 15 years.
| 2 |
| Do you have experience as a prime contractor with the Federal Government on projects similar in both scope and magnitude to this project? |
Valid experience must have occurred within the last 10 years.
Contractor must have had a contract directly with a Federal agency.
| 3 |
| Do you have experience performing infrastructure improvements to wastewater treatment plants while the plants remained continuously operational? |
| 4 |
| Do you have a minimum of 5 years of experience installing specialty piping systems for wastewater treatment plants? |
| Notes: | Magnitude refers to dollar amount of work. |
| Scope refers to technical requirements of work. | |
| Complexity refers to difficulty of performing work due to many varied interrelated parts. | |
| Similar in magnitude refers to projects priced at 85% of your bid and above. | |
| Similar in scope refers to the same type of work with comparable or greater quantities. | |
| Concrete flatwork including, but not limited to, slabs, sidewalks, parking lots, curbs, and roads is NOT similar in scope to structural concrete. |
Complete IBWC Form 245B-Backup Information for each project which supports your 'yes' answers above.
If any 'yes' answer is based upon a subcontractor's experience, said subcontractor shall provide IBWC Form 245B-Backup Information to support the answer. Contractor shall also provide a signed statement explaining exactly what work they will perform along with a certification that said subcontractor will be used for this project and will not be substituted for another entity. D&B scores are only based upon the Contractor; a subcontractor cannot meet this requirement.
I certify that my answers to these questions are true and correct.
If additional backup information is required by the Contracting Officer to further aide in determining responsibility in accordance with the general standards under Federal Acquisition Regulation (FAR) 9.104-1, I certify I will be able to submit that information within twenty-four (24) hours of the request.
If backup information is not provided when requested by the Contracting Officer or if information fails to support the answer provided, the Bidder will be found to be ineligible for award.
Sign Date
Contractor's Representative Name Contractor's Representative Title
IBWC Form 245(COND) Updated 11/18/2022 Page 1 of 2 www.ibwc.gov image1.jpeg