This document is a Statement of Work (SOW) for the repair and rehabilitation of the grit facilities at the South Bay International Wastewater Treatment Plant (SBIWTP) located in San Diego County, California. The key requirements include replacing 3 grit classifiers, 6 grit gallery pumps, 6 grit pump Variable Frequency Drives (VFDs), 2 primary channel air blowers, and 2 grit air blowers. The contractor shall also conduct an Arc Flash Study. The period of performance is 240 days from the Notice to Proceed. The work shall be performed during normal business hours, Monday through Friday, with exceptions for weekends, holidays, and other IBWC-indicated down days. The contractor shall provide all labor, materials, management, supervision, services, and coordination to fulfill the scope of work. The government may elect to purchase additional services for surge control system repairs at the Goat Canyon and Hollister Pump Stations. The contractor shall submit various project plans and documentation, including a phasing/work plan, construction schedule, quality control plan, and warranties. The government will perform pre-final and final inspections to ensure the work is completed to satisfactory standards.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SBIWTP

Repair to Grit Facility San Diego County, California

Statement of Work

Repair to Grit Facility

South Bay Intl. Wastewater Treatment Plant (SBIWTP) San Diego County, California

July 26, 2024

International Boundary and Water Commission (IBWC) United States and Mexico United States Section Headquarters, El Paso, Texas

SECTION I. BACKGROUND

The South Bay International Wastewater Treatment Plant (SBIWTP) is a plant located in San Diego County, CA. The plant treats sewage originating in Tijuana, Mexico and discharges it to the Pacific Ocean. Located at the San Diego Field Office, SBIWTP is part of the U.S. International Boundary and Water Commission (IBWC), a federal agency headquartered in El Paso, TX. SBIWTP has an immediate need to repair many components to their grit facilities. Existing aeration blowers and compressors have failed due to excessive wear and tear caused by sediment. Immediate repair & rehab within the grit facilities is needed to repair components past their life in order to maintain safe and reliable operations.

SECTION II. SCOPE OF WORK

The required work shall be performed in accordance with this Statement of Work, IBWC Form 245 (attached), and all applicable Federal, State and Local laws & regulations. The Contractor shall provide all labor, materials, management, supervision, services, and coordination required to fulfill the scope of work. The scope of work describes the need to replace (3) three grit classifiers, (6) six grit gallery pumps, (6) six grit pump Variable Frequency Drives (VFD), (2) two primary channel air blowers, and (2) two grit air blowers. Additionally, the scope of work includes a requirement to conduct a short-circuit Arc Flash Study.

It is the responsibility of the contractor to validate actual site conditions. Before installation begins, the Contractor may perform a physical survey of the actual site to verify, inspect, and obtain all information needed for the performance of work. The Contractor shall notify the Contracting Officer (CO) of any conditions that prevent the suitable completion of these services (if any). If the Contractor discovers such problems associated with the work after starting, he or she shall immediately notify the Contracting Officer Representative (COR), and obtain approval if work is to continue. It is the responsibility of the contractor to coordinate with SBIWTP personnel to ensure all local & state requirements are completed before completion of installation. This includes permits and approvals to ensure a turnkey installation.

SECTION III. LOCATION

South Bay International Wastewater Treatment Plant (SBIWTP) 2251 Dairy Mart. Rd San Ysidro, CA 92173

SECTION IV. PERIOD OF PERFORMANCE

The period of performance shall not exceed 240 days from the date of Notice to Proceed (NTP).

SECTION V. HOURS OF OPERATION

Contractor personnel shall perform the work during normal business hours, M-F 0800-1700 hrs, until completion. Exceptions to those hours will be weekends, holidays, and any other IBWC indicated down days. Schedule coordination will be conducted at contract award.

SECTION VI. SPECIFIC REQUIREMENTS

1. Grit Classifiers

a. 3x classifiers/separators

b. 3x motors

c. Grit Piping (Ductile Iron Glass lined)

1. Plug Valves with handwheel.

2. Fittings (Elbow, Cross, Tee, Reducer, Wye, Cap, Etc.)

3. Victaulic Couplings

4. Support Brackets, Clevis Hangers

2. Grit Gallery

a. 6x pumps

b. Grit Piping (Ductile Iron Glass lined) replace all suction & discharge pipe all the way to reducer 90 elbow at top (Next to field)

1. Plug Valves w/handwheel & chainwheel operators.

2. Fittings (Elbow, Cross, Tee, Reducer, Wye, Cap, Etc.)

3. Vitaulic Couplings

4. Support Brackets, Clevis Hangers

5. 6” Flow Meter Flange

c. 6x VFDs

3. Primary Channel Air Blowers

a. 2x Blowers

4. Grit Blowers

a. 2x Blowers

5. The Contractor shall include any incidentals such as pulley (sheaves), belts, etc. needed to complete the work.

6. All materials or equipment removed from the work site and not scheduled for reinstallation or turnover to the Government under terms of the contract shall be removed from the site for disposal by the Contractor at the earliest possible time after removal/demo. The Government reserves the right of first refusal on removed materials such as spare parts, pumps, etc.

7. The Contractor shall start up and test the new classifiers, grit pumps, blowers and VFDs in accordance with manufacturer recommendations.

8. The Contractor shall ensure proper function and operation of the new classifiers, grit pumps, blowers and VFDs.

9. The Contractor shall provide manufacturer’s warranties, provide O&M manuals, and include shop drawings.

ADDITIONAL BID OPTION ITEMS:

At the time of contract award, the Government may elect to purchase (but not guaranteed) additional services for items described below:

Bid Option Item A: Surge Control System repair at the Goat Canyon Pump Station by replacing (2) two surge arrestors tanks, and any electrical wiring needed to accomplish the task. Surge arrestor tanks are horizontal, hydropneumatics pressure vessels, manufactured by Young Engineering and Manufacturing, Inc. SA-1 has a diameter of 6 ft-0 inches, a shell length of 8 ft-3 inches, an overall length of 11 ft-3 inches, a usable capacity of 280 cubic feet, a design flowrate of 2,435 gpm, a maximum design pressure of 100 psi, and a maximum working pressure of 40 psi. SA-2 has a diameter of 7 ft-0 inches, a shell length of 12 ft-4 inches, an overall length of 15 ft-11 inches, a capacity of 550 cubic feet, a design flowrate of 4,000 gpm, a maximum design pressure of 100 psi, and a maximum working pressure of 24 psi.

Bid Option Item B: Surge Control System repair at the Hollister Pump Station by replacing (2) two surge arrestors tanks, (1) one air compressor, and any additional accessories or electrical wiring needed to accomplish the task. The surge arrestor tanks are horizontal, steel, hydropneumatic pressure vessels, manufactured by Young Engineering and Manufacturing, Inc. SA-1 has a diameter of 6 ft-0 inches, a shell length of 8 ft-3 inches, an overall length of 11 ft-3 inches, a usable capacity of 280 cubic feet, a design flowrate of 3,680 gpm, a maximum design pressure of 125 psi, and a maximum working pressure of 33 psi. SA-2 has a diameter of 8 ft-6 inches, a shell length of 24 ft-4 inches, an overall length of 28 ft-8 inches, a capacity of 1500 cubic feet, a design flowrate of 16,950 gpm, a maximum design pressure of 125 psi, and a maximum working pressure of 30 psi. The compressor, which is manufactured by Ingersoll-Rand, Model 2475, is a two cylinder, splash lubricated air compressor driven by a 5 hp, 1760 rpm, 3 phase, 60 Hz, 230/460 volt motor, manufactured by Baldor Electric Company.

SECTION VII. EXISTING CONDITIONS

The contractor shall field verify all existing information. Some, but not all, existing conditions & specifications are provided below:

1. Grit Classifiers/Separators specifications:

· Manufacturer: Wemco Pump

· Type: 18in-FF Hydrogritter

· Classifier: 18-inch diameter screw type, fullflared tank

· Separator: Cyclone type, WEMCLONE-1500C

· Capacity: 500 GPM @ 8 PSIG

· Feed Chamber Size: 15 in.

· Reducer Type: Orbital

2. Grit Pumps specifications:

· Manufacturer: Discflo Pump

· Model No: 604-17

3. Please be noted, there are no redundancies at any of the previously mentioned grit operations.

SECTION VIII. WARRANTIES

1. Warranty of Labor. The Contractor shall provide standard warranty for labor or extended labor warranties offered to the general public in customary commercial practice. The minimum warranty should be one (1) year after project completion date. The Contractor shall respond to the CO or POC within twenty-four (24) hours for the repair of all warranty items.

2. Warranty of Materials. The Contractor shall provide manufacturer's standard performance guarantees or extended warranties offered to the general public in customary commercial practice such as warranties including minimum five (5) years wear warranty, two (2) years material and workmanship.

SECTION IX. DAMAGES/SAFETY

The Contractor shall conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work as required by OSHA. The Contractor shall provide protection to Government property to prevent damage during the period of time the property is under the control or in possession of the Contractor. Any damage caused by the Contractor during installation is the responsibility of the Contractor and must be reported to the Contracting Officer (within two (2) hours) along with all available facts relating to each instance of damage to Government property or injury to either Contractor or Government personnel.

SECTION X. SCHEDULING OF WORK

This contract may include work in multiple use type facilities. The facilities may or may not be occupied when work is in progress; however, all work must be coordinated through the CO to minimize interruption of service. It shall be the Contractor’s responsibility to take whatever measures are necessary to assure the protection of assets, furnishings, equipment, etc., and to perform the work to cause minimal disruption of ongoing activities in occupied areas. The Government will advise of any known phasing or work hour situations for each project. The Contractor may propose phasing plans as part of his or her proposal package as suited for the project.

1. When specifically requested by the Government, the work shall, so far as practicable, be phased in definite sections or areas and confined to limited areas that shall be completed before work in other areas is begun.

2. The Contractor shall schedule work concurrently on all active projects without extending performance periods due to insufficient resources.

SECTION XI. SUBMITTALS

Deliver all submittals (hard copy or electronic) for review to the CO within 14 calendar days after the Notice to Proceed (NTP), unless otherwise specified. Approval by the Government shall not absolve the Contractor from his/her responsibilities for specific performance of the item or items submitted. Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. The Government will have 5 business days for return of the submittals to the Contractor. Contractor shall submit ‘Submittals’ which are required for this project, which include:

· List of proposed key personnel

· Phasing/Work Plan

· Construction Progress Schedule (Gantt Chart), to include material lead times, and critical path

· Quality Control Plan

· Environmental protection plan

· Product Data

· Test Reports to include performance test, grit pump tests

· Final Acceptance test & operational test procedures

· Warranties

· O&M manuals

SECTION XII. COMPLETION INSPECTION

1. Pre-final inspection: The Government will perform the pre-final inspection to verify that the work is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

2. Final Inspection: The Contractor's personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from IBWC user groups, can also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor’s assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance FAR 52.246-12 Inspection of Construction.

END OF STATEMENT OF WORK