Front Cover
International Boundary and Water Commission United States and Mexico United States Section
Technical Specifications Rio Grande Canalization Project Sunland Park Levee Repair El Paso County, TX and Doña Ana County, NM
RFP 191BWC22R0002
April 26, 2022
International Boundary and Water Commission United States Section Engineering Services Division El Paso, Texas
These Technical Specifications may be reprinted after Contract award using the awarded Contract number instead of the Solicitation number currently shown. The reprint shall have all changes indicated incorporated.
Reissuance of the awarded Technical Specifications with the Contract number will proceed without an amendment or modification.
Reissuance with the Contract number will NOT result in a new date being displayed on the Technical
Specifications.
PLEASE NOTE - Technical Specifications should be printed double sided.
Please conserve paper and print double sided.
All changes are highlighted. Changes in this April 14, 2022 version from the
March 4, 2022 version include:
Section 00.01.10 Table of Contents
Section 00.01.15 Table 1
Section 00.31.43 1.2.B., 1.2.D., and 1.4.
Section 01.42.00 1.6.
Section 01.45.00 Table 4
Section 01.57.00 1.3.B. and 1.3.C.
Section 01.57.19 1.3.C., 1.3.D., and 3.1.A.1.
Section 01.78.36 1.2.T. and 1.11.B.21. were deleted
Section 03.35.00 1.2.F. was deleted
Section 05.52.13 1.8.A.9. was deleted
Section 31.13.00 1.6.A. and 3.3.C.
Section 31.23.13 1.2.J. and 3.2.B.9. added
Section 31.23.16 1.6.G. was deleted
Section 31.23.23 1.2.T. and 1.6.G. were deleted
Section 33.05.39.41 1.6. and 3.3. were revised and 1.2.K. and 2.1.B.1.c. were deleted
Section 33.42.00 1.2.N.
Section 33.42.05 was deleted
Section 35.22.26 1.2.J. was delete and 1.6. was revised
Section 35.24.90 1.7.A. and 1.8.B.
Section 35.49.56 1.2.F. and 2.1.A.6. added
All changes are highlighted. Changes in this April 26, 2022 version from the
April 14, 2022 version include:
Section 00.31.21 1.4.B added
USIBWC Rio Grande Canalization Project
March 4, 2022 Division 00 USIBWC RFP 191BWC22R0002 Procurement and Contracting Requirements-Page 1
US International Boundary & Water Commission
International Boundary and Water Commission United States Section
TECHNICAL SPECIFICATIONS
DIVISION 00
PROCUREMENT AND CONTRACTING
REQUIREMENTS
Sunland Park Levee Repair US International Boundary & Water Commission Rio Grande Canalization Project
Procurement and Contracting
Requirements
Division 00
Division 00-Procurement and Contracting Requirements
Division 00 March 4, 2022 Procurement and Contracting Requirements-Page 2 USIBWC RFP 191BWC22R0002
This page intentionally left blank for double sided printing.
April 14, 2022 Table of Contents Governing USIBWC RFP 191BWC22R0002 00.01.10-Page 1
SECTION 00.01.10
TABLE OF CONTENTS GOVERNING
00.01.10 Table of Contents Governing 00.01.10-Table of Contents Governing
Table of Contents
DIVISIONS AND SECTIONS
Division 00-Procurement and Contracting Requirements
00.01.10-Table of Contents Governing
00.01.15-List of Contract Drawings
00.21.13-Instructions to Bidders
00.31.19-Existing Condition Information
00.31.21-Survey Information
00.31.24-Environmental Information
00.31.26-Existing Hazardous Material Information
00.31.32-Geotechnical Data
00.31.43-Permit Application
00.31.50-Other Project Information
00.60.00-USIBWC Forms and Standard Documents
00.70.00-Delivery of Data to USIBWC
00.70.13-Project Data
00.72.00-Order of Precedence
00.73.63-Security Requirements
Division 01-General Requirements
01.11.00-Summary of Work
01.22.00-Measurement and Payment
01.29.00-Payment Procedures
01.29.15-Certified Payroll
01.31.00-Project Coordination
01.31.75-Code of Business Ethics
01.32.16-Construction Progress Schedule
01.32.33-Photographic Documentation
01.33.00-Submittal Procedures
01.35.23-Safety
01.42.00-References
01.43.26-Testing and Inspection Agencies
01.45.00-Quality Control
01.51.00-Temporary Utilities
01.52.13-Field Offices and Sheds
01.55.26-Traffic Control and Project Signage
01.57.00-Temporary Controls for Work Areas
01.57.19-Temporary Environmental Controls
01.58.00-Project Identification
01.61.00-Common Product Requirements
01.61.16-Use of Recovered Materials and Biobased Products
01.71.13-Mobilization
01.74.19-Construction Waste Management and Disposal
01.77.19-Closeout Requirements
01.78.23-Operations and Maintenance Data
01.78.36-Warranties
01.78.39-Record Drawings
Table of Contents Governing April 14, 2022 00.01.10-Page 2 USIBWC RFP 191BWC22R0002
Division 02-Existing Conditions
02.01.00-Existing Conditions & Facilities
02.21.00-Surveys
02.21.13-Cultural Resources Surveys
02.22.13-Existing Conditions Assessment
Division 03-Concrete
03.11.00-Concrete Forming
03.15.00-Concrete Accessories
03.15.13-Waterstops
03.15.16-Concrete Joints
03.21.00-Reinforcing Steel
03.31.00-Cast-in-Place Concrete
03.35.00-Concrete Finishing
03.39.00-Concrete Curing
Division 05-Metal
05.05.13-Galvanizing
05.05.23-Welding
05.50.03-Miscellaneous Metalwork
05.52.13-Handrails
Division 10-Specialties
10.14.53-Traffic Signage
Division 13-Special Construction
13.34.23-Stoplog Storage Shed
Division 31-Earthwork
31.05.13-Geological Materials
31.05.16-Crushed Aggregate Base
31.05.19-Geotextile for Earthwork
31.11.00-Clearing and Grubbing
31.13.00-Clearing Saltcedar
31.14.00-Remove / Stockpile Existing Materials
31.23.13-Subgrade Preparation
31.23.16-Excavation
31.23.23-Backfill
31.23.23.23-Flowable Backfill
31.35.23-Concrete Slope Drains
31.36.13-Gabions
31.81.00-Proof Rolling
Division 32-Exterior Improvements
32.05.33-Vegetation Establishment
32.12.19-Asphalt Paving Overlay Course
32.13.13-Concrete Paving, Sidewalks, and Curbs
32.15.00-Aggregate Road Surfacing
32.31.59-Boulders
32.31.80-Heavy Duty Vehicular Gate
32.31.90-Chicanes
32.32.00-Montoya Lateral Wasteway
32.91.19-Topsoil
April 14, 2022 Table of Contents Governing USIBWC RFP 191BWC22R0002 00.01.10-Page 3
32.92.19-Revegetation
Division 33-Utilities
33.05.39.41-Reinforced Concrete Pipe
33.42.00-Schultz Lateral
33.42.05-Montoya C Wasteway
Division 34-Transportation
34.71.13-Vehicle Guardrails
34.71.16-Crash Cushion Attenuators
Division 35-Waterway Construction
35.20.14-Stoplogs
35.22.26-Slide Gates
35.24.90-Montoya Intercepting Drain Excavation
35.41.00-Construction of Levee
35.42.37-Riprap
35.49.53-Country Club East Flood Protection
35.49.56-Country Club West Flood Protection
Technical Specification Tables
Table 1 - Index of Drawings
Table 2 - Encroachments
Table 3 - Properties Adjacent to Mislabeled Montoya Intercepting Drain
Table 4 - Quality Control Testing
Table 5 - Required Minimum Biobased Content
Table 6 - Required Minimum Recovered Content
Table 7 - Warranty Priority Code A
Table 8 - Warranty Priority Code B
Table 9 - Warranty Priority Code C
Table 10 - Permitted Surface Irregularities
Table 11 - Epoxy / Adhesive Requirements
Table 12 - ASTM C881 Minimum Requirements
Table 13 - Special Epoxy / Adhesive Requirements
Table 14 - Special Epoxy / Rod System Requirements
Table 15 - Nonshrink Grout Requirements
Table 16 - Expandable Waterstop Requirements
Table 17 - Minimum Concrete Cover Variation
Table 18 - Minimum Concrete Strength
Table 19 - Maximum Water-Cement Ratio
Table 20 - Deviations and Tolerances from Specified Lines, Grades, and Dimensions
Table 21 - Acceptance Criteria for Questionable Water Supplies
Table 22 - Chemical Limits for Mix Water
Table 23 - Coarse Aggregate Gradation Chart
Table 24 - Fine Aggregate Gradation Chart
Table 25 - Standard Deviation Modification Factor
Table 26 - Overdesign to Meet Compressive Strength Requirements (1)
Table 27 - Overdesign to Meet Compressive Strength Requirements (2)
Table 28 - Air Entrainment
Table 29 - Duration of Curing
Table 30 - Galvanizing Standards
Table 31 - Estimated Number of Signs
Table 32 - Sign Maintenance Materials Required
Table of Contents Governing April 14, 2022 00.01.10-Page 4 USIBWC RFP 191BWC22R0002
Table 33 - ASTM D4956 Sheeting Types
Table 34 - Gradation of Crushed Aggregate Base
Table 35 - Geotextile Requirements
Table 36 - Existing Stock[pile Locations
Table 37 - Compacted Lift Thickness and Required Core Height
Table 38 - Aggregate Surfacing Gradation Requirements
Table 39 - Coating System Weathering Requirements
Table 40 - Coating System Material Requirements
Table 41 - Gradation of Topsoil
Table 42 - Levee Plant Varieties and Seeding Rates
Table 43 - Floodplain Plant Varieties and Seeding Rates
Table 44 - Circular Pipe ASTM C76 & ASTM C655
Table 45 - Riprap (D50 of 6 inches)
Table 46 - Bedding Material Gradation Chart
Technical Specification Figures
Figure 1 - Doña Ana County Clerk Parcel Boundaries
Figure 2 - Fillable Form (not printed)
Figure 3 - Printed Fillable Form
Figure 4 - Sample Project Sign
Figure 5 - Fabrication Tolerances for Bars
Figure 6 - Miscellaneous Qualification: Fillet Weld Break Specimen
Figure 7 - Miscellaneous Qualification: Method of Rupturing Specimen
Figure 8 - Examples of Other Existing Signs
Figure 9 - Storage Container Example
Figure 10 - Example of Complete Vehicular Gate with Signs
Figure 11 - General Planting Depths
Figure 12 - Shrub Planting Depth
Figure 13 - Example of Dried, Cut Levee that Met these Specifications
Figure 14 - Example of Completed Levee recently Cut to Grade that Met these Specifications
Figure 15 - Example of Cut Levee that Did Not Meet these Specifications
Figure 16 - Example of Cut Levee that Did Not Meet these Specifications
Figure 17 - Example of Cut Levee that Did Not Meet these Specifications
--End of Section--file:///C:/00_Work/191BWC22R0002%20Sunland/23-Solicitation%20Files/Specs/Specs%20Amend%2006.docm%23_Toc100816216 file:///C:/00_Work/191BWC22R0002%20Sunland/23-Solicitation%20Files/Specs/Specs%20Amend%2006.docm%23_Toc100816217 file:///C:/00_Work/191BWC22R0002%20Sunland/23-Solicitation%20Files/Specs/Specs%20Amend%2006.docm%23_Toc100816218 file:///C:/00_Work/191BWC22R0002%20Sunland/23-Solicitation%20Files/Specs/Specs%20Amend%2006.docm%23_Toc100816219 file:///C:/00_Work/191BWC22R0002%20Sunland/23-Solicitation%20Files/Specs/Specs%20Amend%2006.docm%23_Toc100816221
April 14, 2022 List of Contract Drawings USIBWC RFP 191BWC22R0002 00.01.15-Page 1
SECTION 00.01.15
LIST OF CONTRACT DRAWINGS
00.01.15 List of Contract Drawings 00.01.15-List of Contract Drawings
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Measurement and Payment
1.3. Drawing Titles
1.4. Drawing Index
Part 2 - Products
2.1. Additional or Revised Drawings
Part 3 - Execution (Not Used)
--End of Section--
1.2. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.3. DRAWING TITLES
1.3.A. The Contract Drawings applicable to this Contract are entitled:
Sunland Park Levee Repair
El Paso County, TX and Doña Ana County, NM
1.4. DRAWING INDEX
1.4.A. The Contract Drawings include the drawings shown in Table 1.
1.4.B. USIBWC acknowledges that the drawing shown in Table 1 do not cover all of the work required by these
Technical Specifications. The Solicitation will be amended with additional drawings prior to award.
Table 1 - Index of Drawings
SHEET NO. USIBWC NO. SHEET TITLE
G001 26885-000-01 Cover Sheet
G002 26886-000-0102 Sheet Index and General Notes
G003 26887-000-00 Abbreviations, Legend and Symbols
G004 & G005 26888-000-00 & 26889-000-00 East Levee Existing Utility Information
G006 26890-000-00 West Levee Existing Utility Information
G101 - G103 26891-000-00 to 26893-000-00 East Levee Survey Control - Existing ROW Line and Curve Tables
G104 - G106 26894-000-00 to 26896-000-00 East Levee Survey Control - Control Points and Monuments
G107 26897-000-00 West Levee Survey Control - Existing ROW Line and Curve Tables
26803-000-00 West Levee Survey Control - Existing ROW Line and Curve Tables
G108 26898-000-00 West Levee Survey Control - Existing Benchmarks, Control Points and Monument
26804-000-00 West Levee Survey Control - Existing Benchmarks, Control Points and Monument
G201 - G204 26899-000-00 to 26902-000-00 East Levee Horizontal Control New ℄ Alignment
G205 26903-000-00 West Levee Horizontal Control New ℄ Alignment
G301 26904-000-00 East Levee Project Layout Key Map Sta: 1511+19.16 to 1750+00
List of Contract Drawings April 14, 2022 00.01.15-Page 2 USIBWC RFP 191BWC22R0002
SHEET NO. USIBWC NO. SHEET TITLE
G302 26905-000-00 East Levee Project Layout Key Map Sta: 1750+00 to 1956+25.86
G303 26906-000-00 West Levee Project Layout Key Map Sta: 1666+52.65 to 1702+74.24
C-1 26496-001-00 to 26496-003-00 Control Map
C001 26497-000-00 Right of Way Control Map
26907-000-00 East Levee Photos
26908-000-00 West Levee Photos
C002 - C008 26909-000-00 to 26915-000-00 Right of Way Map
C101 - C104 26916-000-00 to 26919-000-00 Typical Sections
C105 26920-000-00 Typical Benching Details
C106 26921-000-00 Typical Riprap Benching Details
C201 - C245 26922-000-01 to 26966-000-00 East Levee Plan & Profiles
C246 26967-000-01 East Levee Plan & Profile Begin of Project
C247 26968-000-01 East Levee Plan & Profile W Borderland Rd Bridge
C248 26969-000-01 East Levee Plan & Profile Country Club Rd Bridge
C249 26970-000-01 East Levee Plan & Profile Sunland Park Rd Bridge
26743-000-00 Borderland Bridge Upstream Handrail
26744-000-00 Borderland Bridge Downstream Handrail
26745-000-00 Country Club Bridge East Upstream Handrail
26746-000-00 Country Club Bridge East Downstream Handrail
C261 - C264 26971-000-00 01 to 26974-
000-0001 West Levee Plan & Profile
C265 26975-000-0001 West Levee Plan & Profile Country Club Rd Bridge
26747-001-00 to 26747-002-00 Country Club Bridge West Upstream Handrail
26748-001-00 to 26748-002-00 Country Club Bridge West Downstream Handrail
C301 - C303 26976-000-01 to 26978-000-
Civil Details
C311 26979-000-01 East Levee Landside Ramp at Sta 1685+50
26749-000-00 Typical Handrail Details
26484-000-00 Racetrack Chicane
26485-000-00 Blocking Access at Borderland Bridge Area
26486-000-00 Borderland Chicane
26487-000-00 Blocking Access at Canutillo Lateral Area
26488-000-00 Blocking Access under Artcraft Bridge
26489-000-00 Blocking Access near La Union Combined Lateral
26490-000-00 Blocking Access at Racetrack Park
27264-000-00 Montoya Intercepting Drain Excavation
26498-000-00 Salt Cedar Clearing and Gravel Road at EOP
C321 26980-000-00 West Levee Country Club Bridge Intersection and Landside Ramp
26491-000-00 West Levee Country Club Bridge Landside Ramp
C322 26981-000-00 West Levee Country Club Bridge Joint Layout
C323 26982-000-0001 West Levee Concrete Driveway Plan
C324 26983-000-00 West Levee Concrete Driveway Cross Section
C501 - C651 26984-000-00 to 27234-000-00 East Levee Cross Sections
C681 - C691 27235-000-00 to 27245-000-00 West Levee Cross Sections
CS101 27246-000-00 Country Club Bridge East - Demolish Plan
CS102 27247-000-00 Country Club Bridge East - Stoplog Arrangement Layout
CS103 27248-000-00 Country Club Bridge East - Sectional Elevation View
CS104 27249-000-0001 Country Club Bridge West - Demolition Plan
April 14, 2022 List of Contract Drawings USIBWC RFP 191BWC22R0002 00.01.15-Page 3
SHEET NO. USIBWC NO. SHEET TITLE
CS105 27250-000-0001 Country Club Bridge West - Stoplog Arrangement Layout
CS106 27251-000-00 Country Club Bridge West - Cross Sectional Elevation View
26796-000-00 Montoya Lateral WW Plan & Profile
26797-000-00 Montoya Lateral WW Sections
26798-000-00 Montoya Lateral WW Sections & Details
26479-000-00 to 26481-000-00 Schultz Lateral Wasteway Plan & Profiles
26482-000-00 Schultz Lateral Wasteway New Inlet Structure
26483-000-00 Schultz Lateral Wasteway New Outlet Structure
S102 27252-000-00 Country Club Bridge East and West - Structural General Notes
S103 - S105 27253-000-00 to 27255-000-00 Country Club Bridge East - Section & Details
S106 27256-000-00 Country Club Bridge East - Barrier Railing & Transition
S113 - S115 27257-000-00 to 27259-000-00 Country Club Bridge West - Section & Details
S116 27260-000-00 Country Club Bridge West - Barrier Railing and Transition
26492-000-00 Country Club Bridge West Floodwall Repair
26492-000-00 Country Club Bridge West Floodwall Repair
CCCG-21 27261-000-00 TxDOT Concrete Curb and Curb and Gutter
PED-18 25262-001-03 to 25262-004-03 TxDOT Pedestrian Facilities Curb Ramps
PRD-13 25263-001-01 to 25263-003-01 TxDOT Pedestrian Handrail Details
GF(31)-19 26493-000-00 TxDOT Metal Beam Guard Fence TL-3 MASH Compliant
GF(31)DAT-19 26494-000-00
TxDOT Metal Beam Guard Fence (Downstream Anchor Terminal) TL- 3 MASH Compliant
GF(31)TR TL2-19 26495-000-00
TxDOT Metal Beam Guard Fence Thrie-Beam Transition TL-2 MASH Compliant
25084-000-01 USIBWC Levee Ramp Details
26409-001-05 to 26409-003-05 USIBWC Gate Manufacture and Installation
26424-001-02 to 26424-005-02 USIBWC Notice Signs
26741-000-00 USIBWC Chicane Manufacture and Installation
PART 2 - PRODUCTS
2.1. ADDITIONAL OR REVISED DRAWINGS
2.1.A. Except as provided in these Technical Specifications for drawings to be furnished by Contractor, Contract
Drawings will be supplemented by additional or revised general and detail drawings as necessary or desirable as work progresses.
2.1.B. Additional or revised general and detail drawings will show dimensions and details necessary for construction purposes more completely than are shown on these Contract Drawings for features of work.
2.1.C. Perform work in accordance with additional general and detail drawings or revisions at applicable prices bid in schedule for such work.
PART 3 - EXECUTION
(Not Used)
List of Contract Drawings April 14, 2022 00.01.15-Page 4 USIBWC RFP 191BWC22R0002
March 4, 2022 Instructions to Bidders USIBWC RFP 191BWC22R0002 00.21.13-Page 1
SECTION 00.21.13
INSTRUCTIONS TO BIDDERS
00.21.13 Instructions to Bidders 00.21.13-Instructions to Bidders
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Reference Standards
1.3. Measurement and Payment
1.4. Definitions
1.5. Duty to Inquire
1.6. Investigation of Site Conditions
1.7. Bid Items
1.8. Specifications
1.9. Bid Submission
Part 2 - Products (Not Used)
Part 3 - Execution
3.1. Requests for Interpretation (Duty to Inquire)
--End of Section--
1.2. REFERENCE STANDARDS
1.2.A. Federal Acquisition Regulation (FAR)
1. FAR 52.236-3, Site Investigation and Conditions Affecting the Work
1.3. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. DEFINITIONS
1.4.A. Within this Section, the following terms are used interchangeably.
1. Bid - Offer - Proposal
2. Solicitation - Request for Proposal - RFP
3. Bidder - Offeror - Contractor
1.5. DUTY TO INQUIRE
1.5.A. Bidders shall review the full Solicitation and all Contract documents including, but not limited to, Technical Specifications, Contract Drawings, USIBWC provided data, referenced items, attachments, etc.
to determine the full scope of work required.
1.5.B. If during review of these items, the Bidder finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire. The Bidder shall also inquire about items that are open to interpretation.
1.5.C. The Bidder shall inquire about items as soon as they are discovered, whether before deadline for submission of bidder questions, whether after deadline for submission of bidder questions, whether after submission of bids, or whether after Contract award.
Instructions to Bidders March 4, 2022 00.21.13-Page 2 USIBWC RFP 191BWC22R0002
1.5.D. If the Bidder fails to inquire, they forfeit their right to any claim based upon said discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation. The Bidder shall be proceeding at their own risk based upon only their unilateral interpretation.
1.5.E. The Bidder shall take no advantage of any item of which they have a duty to inquire.
1.6. INVESTIGATION OF SITE CONDITIONS
1.6.A. The Bidder, as well as their subcontractors, is urged to visit the worksite and project area to become fully aware as to the existing conditions affecting the work to be performed under the Contract documents. A site visit will be announced during the Solicitation. Each Bidder shall attend at their own expense. The
Government will not pay for any site visits. This visit is intended to provide the potential Bidders the opportunity to observe site conditions and incorporate into their proposal any required work based on site conditions. The Bidder will have the opportunity to walk around during the site visit. Unless otherwise noted, no other opportunity will exist for visits to the site.
1.6.B. The Bidder shall be responsible for ensuring that all of its suppliers, manufactures and subcontractors have reviewed all applicable Contract documents relative to their work. The Bidder shall provide all labor, material, equipment, and services not provided by the Bidder’s suppliers, manufacturers, fabricators, and/or subcontractors but required for complete and operable facilities as described in the
Contract documents.
1.6.C. Bidder has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the SOW.
1.6.D. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of the Bidder's officers or agents before the execution of this Contract, unless that understanding or representation is expressly stated in the Contract documents.
1.6.E. Any failure of the Bidder to take the actions described and acknowledged in this Section will not relieve the Bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work.
1.7. BID ITEMS
1.7.A. The Contract Line Item Numbers (CLIN) that shall be bid upon are identified in Section B (bid schedule) of the Solicitation.
1.7.B. The Bidder shall include all work related costs within its bid unit prices even if not specifically listed in the bid schedule.
1.7.C. If an error exists on the bid schedule between the CLIN total cost provided and the resultant value of the
CLIN quantity multiplied by the bid unit price, the bid unit price provided shall govern.
1.7.D. If the bid schedule includes CLINs entitled Receiving Lines, No Cost Receiving Lines, No Cost
Receiving Lines for IBWC Use Only, Receiving Lines for Internal Use Only, or similarly, then the Bidder shall not provide a bid price for this CLIN. Receiving lines are used for USIBWC's computer system to make pay estimate processing easier. These are an administrative CLIN and have no value on the
Contract.
1.8. SPECIFICATIONS
1.8.A. The Government does not implicitly warrant performance specifications for complete accuracy or adequacy. Typical performance type specifications set forth an objective or standard to be achieved, and the successful Bidder is expected to exercise their ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.
March 4, 2022 Instructions to Bidders USIBWC RFP 191BWC22R0002 00.21.13-Page 3
1.8.B. When a particular product or manufacturer is identified by name, but permits substitution of ‘an approved equal,’ such a specification is ‘performance’ in nature and, as a result, carries no implied warranty.
1.9. BID SUBMISSION
1.9.A. Submission of a bid shall be conclusive evidence that the Bidder has reviewed, investigated, and acknowledged all items detailed in FAR 52.236-3 and listed below.
1. Conditions bearing upon transportation, disposal, handling, and storage of materials.
2. The availability of labor, water, electric power, and roads.
3. Uncertainties of weather and similar physical conditions at the site.
4. The conformation and conditions of the ground.
5. The character of equipment and facilities needed preliminary to and during work performance.
1.9.B. Submission of a bid shall be conclusive evidence that the Bidder has reviewed all Contract documents.
1.9.C. Submission of a bid shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, the character, quality, and scope of work to be performed, and the quantities of materials to be furnished.
1.9.D. Submission of a bid constitutes agreement that Bidder has provided written notice of all discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation discovered in the
Contract documents, that responses to these written notices are acceptable to Bidder, and that Contract documents are sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing required work.
1.9.E. Bidder has the sole responsibility to make such independent instigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in a accordance with the Contract documents. The
Government will not award a modification or additional funds for conditions that were observable but not considered by Bidder.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
3.1. REQUESTS FOR INTERPRETATION (DUTY TO INQUIRE)
3.1.A. Bidders shall submit requests for interpretation, questions, and other concerns about the Solicitation and
Contract documents including, but not limited to, Technical Specifications, Contract Drawings, USIBWC provided data, referenced items, attachments, etc. to the Contracting Officer identified on SF-1442.
3.1.B. Such requests shall be made even if the question and answer period identified in the Solicitation has passed.
3.1.C. Failure to request interpretation prior to providing a bid shall result in the Bidder being fully responsible for any cost or time impacts involved to perform the work required.
Instructions to Bidders March 4, 2022 00.21.13-Page 4 USIBWC RFP 191BWC22R0002
March 4, 2022 Existing Condition Information USIBWC RFP 191BWC22R0002 00.31.19-Page 1
SECTION 00.31.19
EXISTING CONDITION INFORMATION
00.31.19 Existing Condition Information 00.31.19-Existing Condition Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Measurement and Payment
1.4. General
1.5. Existing Structures
1.6. Existing Utilities
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 00.31.32-Geotechnical Data
1.2.B. Section 32.32.00-Montoya Lateral Wasteway
1.2.C. Section 33.42.00-Schultz Lateral
1.2.D. Section 35.49.53-Country Club East Flood Protection
1.3. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. GENERAL
1.4.A. Reports on the Existing Condition Information
1. Field assessment of existing conditions within the project limits was performed by Arcadis. The findings were and available in a report entitled “Sunland Park Levee Repair Design Documentation
Report, East Levee & West Levee Segment Downstream of Country Club Bridge," dated February 4, 2022.
2. A field assessment was also performed by S&B Infrastructure, Ltd. entitled "Design Report for
Upper Rio Grande Flood Control Project, Sunland Park Canutillo Levee Segment, from Borderland
Bridge to Courchesne Bridge," dated July 23, 2010. Since significant work has been performed on the levee since 2010, the information in this report may no longer be valid.
3. Prior work was completed on this levee reach under USIBWC Contract IBM10C0018. The drawings entitled "Design of Rehabilitation Improvements for the Rio Grande Canalization
Protective Levee System Sunland Park Package," were completed by S & B Infrastructure, Ltd. No as-built drawings exist for this previous work.
1.4.B. The existing floodgate on the eastside of the Country Club Bridge must be removed per Section 35.49.53.
The shop drawings for this floodgate from FloodBreak are dated June 10, 2011.
1.4.C. The existing slide gates on the Schultz Lateral and the Montoya Lateral Wasteways were installed in 2011 under IBM10C0018. The shop drawings and submittal details for these gates from Rodney Hunt
Company are dated June 6, 2011.
Existing Condition Information March 4, 2022 00.31.19-Page 2 USIBWC RFP 191BWC22R0002
1.4.D. Geotechnical investigations were performed as noted in Section 00.31.32.
1.5. EXISTING STRUCTURES
1.5.A. Both El Paso County Water Improvement District #1 (EPCWID1) and Elephant Butte Irrigation District
(EBID) have irrigation structures adjacent to and through this project. The existing structures along the levee include the following.
1. Montoya Lateral Siphon (42"x48" RBC) owned by EPCWID1
2. Montoya Lateral owned by EPCWID1
3. Montoya 'D' Lateral owned by EPCWID1
4. Montoya Lateral WW#36 (48" RCP) owned by EPCWID1
5. Montoya Intercepting Drain owned by EBID
6. Nemexas Siphon (72" RCP) owned by EBID
7. Schultz Lateral WW#35C (30" RCP) owned by EBID
1.5.B. All irrigation structures shall be protected in place unless otherwise noted in the Contract Documents.
1.5.C. There are existing concrete floodwalls at Borderland Bridge. These floodwalls were built under USIBWC contract IBM10C0018.
1.5.D. There are existing concrete floodwalls on both sides of Country Club Bridge. These floodwalls were built under USIBWC contract IBM10C0018.
1.6. EXISTING UTILITIES
Existing utilities at the project site are identified on the Contract Drawings with the best information available.
The Contractor is responsible for identifying and coordinating with all the utility owners to determine exact locations of these utilities and protect them during construction. See Section 02.01.00 for additional requirements when dealing with utilities.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
April 26, 2022 Survey Information USIBWC RFP 191BWC22R0002 00.31.21-Page 1
SECTION 00.31.21
SURVEY INFORMATION
00.31.21 Survey Information 00.31.21-Survey Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Measurement and Payment
1.4. Field Survey
1.5. Survey Control
1.6. Right-of-Way (ROW)
1.7. Cross Section Survey
1.8. Existing Utility Survey
1.9. Survey Control Maps
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 02.01.00-Existing Conditions & Facilities
1.3. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. FIELD SURVEY
1.4.A. Field survey was performed between November 2017 and February 2018, by Frank X. Spencer and
Associates who developed and provided the following, which were used as the basis of design.
1. Survey Control Maps of the Sunland Park Levees are included with the project drawings.
2. The document "FXSA Survey Report," dated March 3, 2022.
1.4.B. LiDAR survey was performed on March 4 and 5, 2020 by Wilson-Freese and Nichols JV for USIBWC.
1. A report detailing the data collected is entitled "Rio Grande Canalization Project - LiDAR and
Orthophotography Report," dated June 12, 2020.
2. No comparison between the LiDAR data and the project survey data has been made. The LiDAR data is provided for Contractor's use since it extends past the boundaries of the project survey. All drawings and project data are based upon the Frank X. Spencer survey noted above.
1.5. SURVEY CONTROL
1.5.A. The surveyor established horizontal and vertical controls based on New Mexico State Plane Coordinate
Grid System (NMSPC) NM Central Zone North American Datum of 1983 (NAD 83) in US survey feet, using GEOID 2012B, and North American Vertical Datum of 1988 (NAVD 88) in US survey feet, respectively.
1.5.B. The survey was based on existing monumentation which is referenced on the Survey Control Maps, mentioned in Paragraph 1.9. Data for these points was provided by USIBWC and were adjusted to ground distances.
Survey Information April 26, 2022 00.31.21-Page 2 USIBWC RFP 191BWC22R0002
1.6. RIGHT-OF-WAY (ROW)
The surveyor surveyed and located all existing ROW survey markers along the USIBWC right-of-way line. The surveyor installed new ROW markers, witness posts and pipes, as needed per the USIBWC survey guidelines.
1.7. CROSS SECTION SURVEY
The surveyor performed cross section survey along the project reach at a 100 feet interval to include, but not limited to, both east and west levee, distances to the ROW, any ramps that enter or exit the levee, and any ditches or canals that cross the levee or are immediately adjacent to the levee. The final topographic mappings, including a 3-dimensional surface, were provided in an AutoCAD file, survey point file, and a surface TIN file.
1.8. EXISTING UTILITY SURVEY
1.8.A. The surveyors surveyed and obtained x & y coordinates and elevations of existing surface features of visible structures and utilities. These locations are shown on the Plan and Profile sheets of the Contract
Drawings.
1. NOTE: It is the Contractor’s responsibility to verify locations of all existing utilities (shown and not shown) prior to construction.
2. Additionally, attention is called to Sections 02.01.00 for additional requirements and guidelines for utility surveys.
1.9. SURVEY CONTROL MAPS
The surveyor prepared the Survey Control Maps for the total length of the reach showing existing levee alignment, existing levee stationing, ROW, and survey control points per the USIBWC survey guidelines. The survey is presented at grid distance. Grid to ground conversation factor is included in construction drawings.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
March 4, 2022 Environmental Information USIBWC RFP 191BWC22R0002 00.31.24-Page 1
SECTION 00.31.24
ENVIRONMENTAL INFORMATION
00.31.24 Environmental Information 00.31.24-Environmental Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Reference Standards
1.4. Measurement and Payment
1.5. General
1.6. Preservation of Cultural and Natural Resources and the Environment
1.7. Other Considerations
1.8. Use of Geologic Materials on a Federally Funded Project
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 01.57.00-Temporary Controls for Work Areas
1.2.B. Section 01.57.19-Temporary Environmental Controls
1.2.C. Section 02.21.13-Cultural Resources Surveys
1.2.D. Section 31.13.00-Clearing Saltcedar
1.2.E. Section 35.24.90-Montoya Intercepting Drain Excavation
1.3. REFERENCE STANDARDS
1.3.A. United States Code (USC)
1. Clean Air Act, 42 USC 7401 et seq.
2. Clean Water Act (CWA), 33 USC 1251 et seq.
3. Endangered Species Act (ESA), 16 USC 1531 et seq.
4. Migratory Bird Treaty Act (MBTA), 16 USC 703 - 712
5. National Environmental Policy Act (NEPA), 42 USC 4321-4347
6. National Historic Preservation Act (NHPA), 54 USC 300101 et seq.
7. National Wildlife Refuge System Improvement Act of 1997, 16 USC 668dd
8. Native American Graves Protection and Repatriation Act (NAGPRA), 25 USC 3001 et. seq.
9. Refuge Recreation Act, 16 USC 460k - 460k-4
1.4. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
Environmental Information March 4, 2022 00.31.24-Page 2 USIBWC RFP 191BWC22R0002
1.5. GENERAL
1.5.A. The project’s Environmental Assessment (EA), entitled "Final Environmental Assessment, Flood Control
Improvements to the Rio Grande Canalization Project," dated December 2007, was prepared by
USIBWC. The Contractor shall review and comply with the requirements provided in the EA document.
1. This file can be downloaded at ibwc.gov/Files/Web/Final_EA_RGC_Levee_Raising.pdf.
1.5.B. "USIBWC Rio Grande Canalization Project, River Management Plan," dated December 8, 2016, was prepared by USIBWC. The Contractor shall review and comply with the requirements provided in this document.
1. This file can be downloaded at ibwc.gov/Files/USIBWC_RGCP_River_Management_Plan_FINAL_December_8_2016_reduced.p df.
1.5.C. "Final Biological Opinion for US International Boundary and Water Commission Long-Term River
Management of the Rio Grande Canalization Project, New Mexico," dated August 16, 2017, was prepared by USIBWC. The Contractor shall review and comply with the requirements provided in this document.
1. This file can be downloaded at ibwc.gov/Files/IBWC_BO_2017_FINAL.pdf.
1.5.D. There are three habitat restoration areas on the floodplain of this project. The details are provided in the
Ideals-Ageiss, LLC report entitled "Riparian Habitat Restoration at Three Sites in New Mexico and
Texas: Country Club East, Sunland Park, and Anapra Bridge Restoration Sites," dated February 28, 2020.
1. This file can be downloaded at ibwc.gov/Files/Final_Restoration_Report_CCE_Sunland_Anapra_022820.pdf
2. Drawings associated with these sites are dated January 23, 2018 and are available in one of the report's appendices.
1.5.E. The saltcedar removal (Section 31.13.00) and work on the Montoya Intercepting Drain (Section 35.24.90) are related to "Final Environmental Assessment Aquatic Habitat Restoration in the Rio Grande
Canalization Project Sierra and Doña Ana Counties, New Mexico and El Paso County, Texas," dated
October 2021 and prepared by Gulf South Research Corporation.
1. This file can be downloaded at www.ibwc.gov/Files/FinalEA_Aquatic_Habitat_Restoration_RGCP_signed_508_VERSION.pdf.
1.5.F. Project related information can also be found in
1. "Updated Biological Assessment for Long-Term River Management of the Rio Grande Canalization
Project," dated March 20, 2017 and prepared by Ideals-Ageiss, LLC.
a. This file can be downloaded at ibwc.gov/Files/Updated_Biological_Assessment_RGCP_032017.pdf.
2. "Environmental Assessment for the Continued Implementation of the River Management Plan for the Rio Grande Canalization Project," dated December 6, 2019 and prepared by Ideals-Ageiss, LLC.
a. This file can be downloaded at ibwc.gov/Files/USIBWC-RMP-Final%20EA-signed121619.pdf.
3. "Finding of No Significant Impact Non-Native Plant Control and Re-Establishment of Riparian
Habitats along the Rio Grande," dated August 7, 2012 and prepared by FWS.
a. This file can be downloaded at www.ibwc.gov/Files/BLM_Final_wAppendices2.pdf.
https://ibwc.gov/Files/Web/Final_EA_RGC_Levee_Raising.pdf https://ibwc.gov/Files/USIBWC_RGCP_River_Management_Plan_FINAL_December_8_2016_reduced.pdf https://ibwc.gov/Files/USIBWC_RGCP_River_Management_Plan_FINAL_December_8_2016_reduced.pdf https://ibwc.gov/Files/IBWC_BO_2017_FINAL.pdf https://ibwc.gov/Files/Final_Restoration_Report_CCE_Sunland_Anapra_022820.pdf https://www.ibwc.gov/Files/FinalEA_Aquatic_Habitat_Restoration_RGCP_signed_508_VERSION.pdf https://ibwc.gov/Files/Updated_Biological_Assessment_RGCP_032017.pdf https://ibwc.gov/Files/USIBWC-RMP-Final%20EA-signed121619.pdf https://ibwc.gov/Files/USIBWC-RMP-Final%20EA-signed121619.pdf http://www.ibwc.gov/Files/BLM_Final_wAppendices2.pdf
March 4, 2022 Environmental Information USIBWC RFP 191BWC22R0002 00.31.24-Page 3
1.5.G. These documents list environmentally and culturally sensitive areas that need to be protected from any disturbances of construction activities. The environmentally and culturally sensitive areas that were identified on the document are identified below.
1. Biological Resources
Work should be scheduled to occur outside of the bird breeding season whenever possible.
Migratory birds may be present within the project area; birds, nests, and eggs are to be protected and avoided during construction. The breeding and nesting season is identified in Section 01.57.19. If work continues into the bird breeding/nesting season the areas proposed for disturbance shall be surveyed in order to avoid the inadvertent destruction of nests and eggs.
2. Natural Resources
Equipment cannot be parked, staged, or used under large, mature trees. Keeping equipment away from the large, mature trees will prevent incidental damage to the tree and prevent compression of the root ball.
1.5.H. Further details of environmental requirements are in Sections 01.57.00 and 01.57.19.
1.6. PRESERVATION OF CULTURAL AND NATURAL RESOURCES AND THE ENVIRONMENT
1.6.A. If the Contractor initiates changes to the Contract and USIBWC approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agencies.
1.6.B. Culturally Sensitive Areas
If a site, building, or location of historical, archaeological, educational, or scientific interest is discovered within the right of way, cease all work immediately, secure the site from further disturbance and possible vandalism, and notify USIBWC. The site, building, or location will be investigated and evaluated by
USIBWC.
1.7. OTHER CONSIDERATIONS
The Contractor is required to ensure that all Environmental Permits, Issues, and Comments (EPIC), which are included within the Contract documents are followed and implemented to ensure potential impacts are avoided.
1.8. USE OF GEOLOGIC MATERIALS ON A FEDERALLY FUNDED PROJECT
1.8.A. To ensure preservation of historical and archaeological data, prior to use of any soil, rock, or gravel including aggregate in concrete, the source must first be compliance confirmed by the COR to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA).
1.8.B. Take no action to use or alter the proposed location until written approval for site use is received from the
COR.
1.8.C. If the quarry or borrow site already provides materials for NMDOT, TxDOT, USACE, or other governmental agency, a copy of the environmental approvals from said agencies may be provided to the
COR.
1.8.D. Include permission for Government access to any geological source locations.
1.8.E. Full details of requirements for geological materials are in Section 02.21.13.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Environmental Information March 4, 2022 00.31.24-Page 4 USIBWC RFP 191BWC22R0002
March 4, 2022 Existing Hazardous Material Information USIBWC RFP 191BWC22R0002 00.31.26-Page 1
SECTION 00.31.26
EXISTING HAZARDOUS MATERIAL INFORMATION
00.31.26 Existing Hazardous Material Information 00.31.26-Existing Hazardous Material Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Measurement and Payment
1.4. General
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 00.31.24-Environmental Information
1.3. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. GENERAL
Based on the environmental report(s) identified in Section 00.31.24, there are no hazardous material or waste storage sites, disposal sites, or spill sites identified within the immediate project area.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Existing Hazardous Material Information March 4, 2022 00.31.26-Page 2 USIBWC RFP 191BWC22R0002
March 4, 2022 Geotechnical Data USIBWC RFP 191BWC22R0002 00.31.32-Page 1
SECTION 00.31.32
GEOTECHNICAL DATA
00.31.32 Geotechnical Data 00.31.32-Geotechnical Data
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Measurement and Payment
1.3. Geotechnical Reports
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.3. GEOTECHNICAL REPORTS
1.3.A. Geotechnical analysis for this project was performed by Kenall, Inc. and summarized in their report entitled, "Sunland Park Levee Forensic Geotechnical Investigation," dated July 29, 2016. The base report including all boring logs and laboratory test data is available.
1.3.B. Appendix B of Arcadis' report entitled “Sunland Park Levee Repair Design Documentation Report, East
Levee & West Levee Segment Downstream of Country Club Bridge," dated February 4, 2022 contains additional geotechnical information.
1.3.C. Prior geotechnical analysis was performed by Raba-Kistner Consultants, Inc. and summarized in their report entitled, "Final Technical Memorandum for Geotechnical Explorations of Levee System within the
Rio Grande Canalization Project- Canutillo Levee Segment," both Volumes I and II, dated December 22, 2008. Since significant work was been performed on the levee since then, the information in this report may no longer be valid.
1.3.D. The data and report are not intended as a representation or warranty of continuity of conditions between soil borings nor of groundwater levels at dates and times other than date and time when measured. The
USIBWC neither warrants or guarantees the results of any geotechnical or subsurface investigations as being representative of the site, beyond the actual location of the test specimen(s) nor assumes any responsibility for the manner in which this information may be used or the conclusions reached in utilizing the information contained in these documents. Additional test borings and other exploratory operations may be made by Contractor subsequent to award of the Contract.
1.3.E. Due to the site location adjacent to the Rio Grande, groundwater levels may fluctuate, sometimes to extreme levels, based upon time of year and amount of water in the river. Higher groundwater levels than those shown in the bore logs may occur causing changes in soil saturation and strength.
1.3.F. The worksite is adjacent to the Rio Grande and is located in an area where the river flowed in the past.
Fluvial deposits can change rapidly in type (sand, silt, clay, loam, gravel, rocks, etc.) both horizontally and vertically due to depositional characteristics and channel shifting. Rocks may be present even if not visible on the ground surface. Rocks larger than the borehole would not have been captured in any logging data.
1.3.G. The Contractor is charged with the duty to read and understand the geotechnical data provided, including any data referenced within. The Contractor shall consider all geotechnical information including
Geotechnical Data March 4, 2022 00.31.32-Page 2 USIBWC RFP 191BWC22R0002 geotechnical reports, bore logs, and site visits as a whole. The Contractor shall consider the limitations of any geotechnical tests performed including the auger size, borehole spacing and location, consistency of borehole data, as well as the frequency of testing, results of testing, and groundwater level at time. The
USIBWC will not be responsible for interpretations or conclusions drawn by the Contractor.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
April 14, 2022 Permit Application USIBWC RFP 191BWC22R0002 00.31.43-Page 1
SECTION 00.31.43
PERMIT APPLICATION
00.31.43 Permit Application 00.31.43-Permit Application
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Reference Standards
1.3. Measurement and Payment
1.4. General
1.5. Work in Waters of the United States
1.6. Responsibilities
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
--End of Section--
1.2. REFERENCE STANDARDS
1.2.A. Doña Ana County, NM
1. Doña Ana County Code Chapter 157, Design and Construction Standards
2. Doña Ana County Stormwater Management Ordinance
1.2.B. Environmental Protection Agency (EPA)
1. 20172022 Construction General Permit (as modified)
2. National Pollutant Discharge Elimination System (NPDES)
1.2.C. State of New Mexico
1. New Mexico Environmental Department application of Clean Water Act §401
1.2.D. Texas Commission on Environmental Quality (TCEQ)
1. Texas Pollution Discharge Elimination System (TPDES)
2. TPDES 2018 Construction General Permit TXR150000 dated January 28, 2022
1.2.E. US Army Corps of Engineers (USACE)
1. Section 404 of Clean Water Act, 33 USC 1251 et seq.
1.3. MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. GENERAL
Prior to the beginning of construction, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities, including, but not limited to, a specific or general stormwater permit prepared in accordance with the requirements of Stormwater
Pollution Prevention Plan (SWPPP) EPA's National Pollutant Discharge Elimination System (NPDES) 20172022
Construction General Permit (as modified), and Texas Pollution Discharge Elimination System (TPDES) 2018
General Permit TXR150000.
Permit Application April 14, 2022 00.31.43-Page 2 USIBWC RFP 191BWC22R0002
1.5. WORK IN WATERS OF THE UNITED STATES
1.5.A. The US Army Corps of Engineers (USACE) has determined that a Section 404 permit will not be required for work within the currently defined Temporary Construction Limits (TCL).
1.5.B. The Contractor must adhere to all agreements, mitigation plans, and standard best management practices required.
1.5.C. If Contractor initiated changes in the construction method result in impacts to waters of the US, the
Contractor shall have sole responsibility to obtain all required new or revised Section 404 permit and shall adhere to all agreements, mitigation plans, and standard best management practices required by these permits.
1.6. RESPONSIBILITIES
1.6.A. The Contractor shall be responsible for providing the proposed location of the project staging areas for compliance confirmation of the COR prior to installation of stormwater pollution prevention (SWPP) measures.
1.6.B. The Federal Government is not subject to local jurisdictions' building codes, nor is it required to obtain building permits from local jurisdictions for construction on real estate owned or controlled by the
USIBWC. However, borrow pits and other offsite locations are subject to local regulations. The
Contractor is responsible for researching and obtaining all necessary permits for offsite work.
1.6.C. The Contractor shall be responsible for obtaining all necessary permits and rights of entry for…