19-1-06 Quality Assurance Surveillance Plan.pdf
PDF 62 KB Posted
- Attached to
- Concrete Mounting Pads Federal contract opportunity
- Solicitation number
- W9098S22R0010
About this file
This quality assurance surveillance plan outlines monitoring requirements for a concrete work contract. The contractor will be observed daily to ensure all work is performed safely and in accordance with the timeline and scope of work. Materials will undergo random inspections to verify specifications are met. Upon completion, a final inspection will validate all work conforms to the contract's scope of work. The related federal solicitation seeks two concrete mounting pads for Rock Island Arsenal from offers due by May 11, 2022. The Department of the Army Materiel Command Contracting Command at Rock Island Arsenal will award the contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9098S22R0010 Amendment 0002 - Concrete Mounting Pad.pdf | ||
| W9098S22R0010 Amendment 0001 Concrete Mounting Pad.pdf | ||
| 19-1-06 B222 Mounting Pad Drawings for Forging Hammer - VENDOR.pdf | ||
| W9098S22R0010 Concrete Mounting Pad - Solicitation.pdf | ||
| Site Visit Information.pdf | ||
| 19-1-06 B222 Mounting Pad Drawings for Forging Hammer.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rock Island Arsenal Quality Assurance Surveillance Plan
Concrete Work (Concrete Mounting Pad)
TARA-IFF-19-1-06
DATE: 21-Mar-2022
Task Contract
Reference Freq Performance Standard
Acceptable Quality Level
Surveil Method
Surveil Date(s)
Perform Level Notes
Site Conference
Sheet 1 - Security Notes
Once
Each individual working at the site must receive this information for safety and accountability purposes.
May be updated if additional personnel come to the work site.
May be performed as part of the badging process.
100% Visual/ Roster
Work Roster Sheet 1 - Security Notes
Daily
Must be maintained for safety and security purposes. Must show who is at the work-site at any given time.
90% Written Roster
Project Timeline
Dictated by contract Once
To be provided within 1-week of award of the contract. Must show plan for completion prior to the date stated in the contract. May be adjusted during performance provided within project completion date.
100% Visual/ Written
Site Inspection
Sheet 1 - Security Notes
Daily
Observe work is being performed safely and in accordance with the contractor provided timeline and IAW the contracted Scope of Work
90% Visual
Materials Inspections
Sheet 1 - Notes 1-17 Random
Materials provided by the contractor may be inspected to ensure that they meet the contracted Scope of Work and minimum industry and design standards. (e.g. slump or temperature tests of incoming concrete)
100% Visual/ Measure
Rock Island Arsenal Quality Assurance Surveillance Plan
Concrete Work (Concrete Mounting Pad)
TARA-IFF-19-1-06
DATE: 21-Mar-2022
Task Contract
Reference Freq Performance Standard
Acceptable Quality Level
Surveil Method
Surveil Date(s)
Perform Level Notes
Final Inspection
Sheet 1 - Notes 1-17 Once
Verify that all work is completed IAW the contracted Scope of Work 100% Visual