Amendment_0001.pdf
PDF 325 KB Posted
- Attached to
- Lab Renovation, Building 26, Room B114 Federal contract opportunity
- Solicitation number
- 18-223-SOL-00027
About this file
Amendment 0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_D-3_U.S._Department_of_Labor_General_Decision_Number_AR180036,_dated_01052018_AR36.pdf | ||
| Attachment_D-1_Scope_of_Work.pdf | ||
| Solicitation_18-223-SOL-00027.pdf | ||
| Attachment_D-2_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
Regina R. Williams
This amendment provides the following information regarding the solicitation referenced in block 9A.
1. Provide a copy of the minutes and attendance record from the pre-proposal conference and site visit held at NCTR on April 5, 2018 at 10:00 a.m. (Attachment 1) .
2. Provide answers to questions (Attachment 2).
FDA/OO/OFBA/OAGS/DAP
FOB - REGINA WILLIAMS
3900 NCTR ROAD
BUILDING 50, RM 419
JEFFERSON AR 72079
ALL OFFERORS
FDA/OO/OFBA/OAGS/DAP
FOB - REGINA WILLIAMS
3900 NCTR ROAD
BUILDING 50, RM 419
JEFFERSON AR 72079
18-223-SOL-00027
1 1
04/17/2018
Attachment 1 Solicitation 18-223-SOL-00027
Lab Renovation, Building 26, Room B114 April 5, 2018
Minutes
Pre-proposal Conference/Site Visit Minutes and Attendance Record
The meeting opened at 10:00 a.m. Regina Williams asked attendees to sign-in. After everyone signed in, Ms. Williams welcomed the attendees to the Pre-proposal conference site visit.
Ms. Williams explained the purpose of the conference is to understand the Government’s requirement, proposal instructions, and conduct a site visit.
Ms. Williams introduce the Government personnel in attendance:
Regina Williams, Contracting Officer Maxwell Good, Contracting Officer Representative Roosevelt Walker, Contract Specialist
It was stressed that the Contracting Officer, Regina Williams, is the only individual with authority to bind the Government or to make any changes to the Request for Proposal (RFP) and that any remarks and/or explanations at the conference today will not qualify the terms and conditions of the solicitation.
Ms. Williams gave a basic overview of the RFP. The overview included: submission of questions, questions due date, reports and deliverables, proposal submission, proposal closing date/time, and performance period.
The meeting was turned over to the COR, Mr. Maxwell Good, who gave a brief synopsis of the general requirement of the building/room involved and Max conducted a tour of the work area.
The meeting adjourned at 11:40 a.m.
Questions & Answers Attachment 2
Solicitation 18 223 SOL 00027 Lab Renovation, Building 26, Room B114
1. Local vendors have stated that Insinkerator no longer manufactures a 1.5 HP garbage disposal and that they only make a 1 or a 2 HP unit. If the awarded contractor cannot find a 1.5 HP unit what size unit does NCTR want it replaced with?
Answer: Garbage above existing rated hp rating will be allowed.
2. Would NCTR have an issue if the legs on their stainless steel tables are adjustable with jack screws that can twist to adjust and level the height?
Answer: Legs of stainless steel tables must be able to be locked and secure after installation. Jack screws to assist in installation are acceptable.
3. The bottle racks in the example room are all stainless steel. Does NCTR want to reuse the existing bottle racks or use all new stainless steel racks? If Stainless Steel, how many bottle racks were in the room and what were their dimensions?
Answer: Existing bottle racks will be reused.
4. Photo 3 (elevation 5) of the drawings is showing two new sinks. Does NCTR want two new garbage disposals or just one?
Answer: There is one disposal required in this area. This makes a total of two in the project.
5. General Notes, Page A 102 (1) When patching the vertical chase with metal, what gauge of sheet metal shall we use and what color shall we paint that chase? Item (2) States to paint the lab SW 1102, are we to paint the metal chase that color as well?
Answer: The metal used to patch the chase shall be light gauge. 2o gauge will be acceptable. Color of chase and lab will be the same.
6. Elevation view 6, photo 4 states to remove electrical raceway and to provide spares.
Does this imply spare raceways? If so does NCTR want additional spare raceways (if so how many and is contractor to purchase them) or spare only this one?
Answer: The intent of this note is that the contractor will remove wiring to the panel.
The existing breaker that was serving the outlets is to be labeled “SPARE”.
7. Elevation view 6, photo 4 states to install 3 duplex outlets on each chase. Are these outlets to be recessed inside the chase or installed in a junction box and flush mounted to the chase?
Answer: Outlets are to be flush mounted.
8. Does NCTR have a spec and color match for the vinyl floor?
Answer: No. There will not be vinyl floor added.
Questions & Answers Attachment 2
Solicitation 18 223 SOL 00027 Lab Renovation, Building 26, Room B114
9. Elevation view 6, photo 4 states to wrap chase with SS back splash. Pg A103, upper left drawing, states that the back splash shall be seamless and sealed. Does NCTR want the chase back splash seamless with the SS counter top as one single piece or a separate piece sealed to the SS counter top with a type of sealant?
Answer: Chase backsplash should be seamless with the counter top.
10. Will NCTR specify what type of sealant will be authorized inside the facility?
Answer: Sealants used on counter tops and food preparation surfaces shall be food safe. There is no food grade requirement for sealants used in other areas.
11. How many garbage disposals and faucets are going back in new? It seems like 5 but I want to be sure. Looks like two on each side of the room and one in the middle.
Answer: There will be a total of two garbage disposals and three sinks total.
12. Regarding General note 4 on Page A 102, the note states to turn the vinyl down and seal it to floor. Is the contractor to add more vinyl to fill the gap where the cabinet was removed or leave that portion as exposed foundation/concrete?
Answer: The area where cabinets are removed will be left as concrete.
13. Where is the construction New Building/Renovations/Design for the FDA that you posted on 2/21/2018? It only states Lab Renovation, Building 26, Room B114 and does not have a link to the web site reference.
Answer: This requirement is not for construction New Building/Renovations/Design.
This requirement is for Lab Renovation, Building 26, Room B114 only. See Attachment D 2 Drawings posted on 3/30/18.
14. A sheet metal fabricator has asked about the type of and gauge (thickness) of stainless steel requested to go on the counter top. They recommended 316 but were not sure about either. Also, does the government wish to have some type of hard board or backer under the stainless steel counter? Please clarify the thickness and type of SS as well as the type of subsurface.
Answer: Countertops shall be constructed of 18 gauge type 304 stainless steel with a #4 finish.
Countertop edges shall be box marine type. Countertop backsplashes shall have 45 degree return and firmly attach to wall. Countertops shall be supported by an exterior grade plywood backer. Contractor shall field weld and polish joints. Sink bowls shall be fabricated with the same material as countertops.
THERE WILL BE NO FURTHER QUESTIONS ANSWERED AT THIS TIME